The document is calculating the takt time for a production system. It is given that the total time per shift is 490 minutes, there is one shift, workers get two 14-minute breaks and a 25-minute lunch, and the daily demand is 214 units. The takt time is the number of minutes allocated per production cycle to meet customer demand.