1. Topography Pollution control Raw Material Town Planning Ash Disposal TPP Water Land Area Storage Waste Storage Green Belt Port Transport Water Storage Climate Road Rail Essential Elements for Establishing Thermal Power Plant
2. Environment Clearance <500 MW Clearance from SPCB >500 MW Clearance from MoEF EIA Report to the MoEF 3 months monitoring & 1 month for modeling Executive Summary and Form I Presentation to the EIAA about the Project 1 Month TOR of EIA ( Public Hearing is a part of TOR) TOR and Public hearing to SPCB Changes to be made according to the TOR Consent for the Establishment 1 Month 15 days 1 Month 45 days Public Hearing Commencement of the Plant Five years period Environmental Clearance