MANEESH P
DEPT. OF APPLIED ECONOMICS
The basic transportation problem was developed in 1941 by F.I.
Hitchaxic. However it could be solved for optimally as an answer to
complex business problem only in 1951,when Geroge B. Dantzig
applied the concept of Linear Programming in solving the
Transportation models.
Transportation problems are primarily concerned with the optimal
(best possible) way in which a product produced at different factories
or plants (called supply origins) can be transported to a number of
warehouses (called demand destinations).
INTRODUCTION
Transportation problem is a special kind of LP
problem in which goods are transported from a set
of sources to a set of destinations subject to the
supply and demand of the source and the
destination respectively, such that the total cost of
transportation is minimized.
The objective in a transportation problem is:-To
fully satisfy the destination requirements within
the operating production capacity constraints at
the minimum possible cost.
Whenever there is a physical movement of goods from
the point of manufacture to the final consumers through
a variety of channels of distribution (wholesalers,
retailers, distributors etc.), there is a need to minimize
the cost of transportation so as to increase the profit on
sales. Transportation problems arise in all such cases.
.
It aims at providing assistance to the top
management in ascertaining how many units of a
particular product should be transported from each
supply origin to each demand destinations to that
the total prevailing demand for the company’s
product is satisfied, while at the same time the
total transportation costs are minimized
i.e.; The total supply available at the plants exactly matches
the total demand at the destinations. Hence, there is neither
excess supply nor excess demand.
Such type of problems where supply and demand are
exactly equal are known as Balanced Transportation
Problem.
Supply (from various sources) are written in the rows,
while a column is an expression for the demand of different
warehouses. In general, if a transportation problem has m
rows an n columns, then the problem is solvable if there are
exactly (m + n –1) basic variables
.UNBALANCED TRANSPORTATION PROBLEM :
A transportation problem is said to be unbalanced if the
supply and demand are not equal.
Two situations are possible:-
1. If Supply < demand, a dummy supply variable is
introduced in the equation to make it equal to demand.
2. If demand < supply, a dummy demand variable is
introduced in the equation to make it equal to supply.
Then before solving we must balance the demand & supply.
When supply exceeds demand, the excess supply is assumed to go to
inventory. A column of slack variables is added to the transportation
table which represents dummy destination with a requirement equal to
the amount of excess supply and the transportation cost equal to zero.
When demand exceeds supply, balance is restored by adding a dummy
origin. The row representing it is added with an assumed total
availability equal to the difference between total demand & supply and
with each cell having a zero unit cost.
Demand Less Than Supply
 Suppose that a plywood factory increases its rate of
production from 100 to 250 desks
 The firm is now able to supply a total of 850 desks each
period
 Warehouse requirements remain the same (700) so the
row and column totals do not balance
 We add a dummy column that will represent a fake
warehouse requiring 150 desks
 This is somewhat analogous to adding a slack variable
 We use the northwest corner rule and either vogel’s
approximation method or MODI to find the optimal
solution
FROM
TO
A B C TOTAL
AVAILABLE
I 5 4 3 250
II 8 4 3 300
III 9 7 5 300
WAREHOUSE
REQUIREMENTS
300 200 200 850
700
FROM
TO
A B C D TOTAL
AVAILABLE
I 5 4 3 0 250
II 8 4 3 0 300
III 9 7 5 0 300
WAREHOUSE
REQUIREMENTS
300 200 200 150
850= 850
FROM
TO
A B C D TOTAL
AVAILABLE
I
5 4 3 0
250
II
8 4 3 0
300
III
9 7 5 0
300
WAREHOUSE
REQUIREMENTS
300 200 200 150
(1)
(1)
(2)
(3) (0) (0) (0)
250
300-250=50
FROM
A B C D
TOTAL
AVAILABLE
II
8 4 3 0 300
III 9 7 5 0 300
WAREHOUSE
REQUIREMENTS
50 200 200 150
TO
(1)
(2)
(1) (3) (2) (0)
200
300-200=100
FROM
A C D
TOTAL
AVAILABLE
II 8 3 0 100
III 9 5 0 300
WAREHOUSE
REQUIREMENTS
50 200 150
TO
100 (5)
(4)
(1) (2) (0)
200-100=100
FROM
A C D
TOTAL
AVAILABLE
III 9 5 0 300
WAREHOUSE
REQUIREMENTS 50 100 150
TO
(4)
(9) (5) (0)
50
300-50=250
FROM
C D
TOTAL
AVAILABLE
III 5 0 250
WAREHOUSE
REQUIREMENTS 100 150
TO
(5)
(5) (0)
150
250-150=100
FROM
C
TOTAL
AVAILABLE
III 5 100
WAREHOUSE
REQUIREMENTS
100
TO
100
100-100=0
FROM
A B C D
I 5 4 3 0
II 8 4 3 0
III 9 7 5 0
TO
WAREHOUSE
REQUIREMENTS
TOTAL
AVAILABLE
300 200 200 150
250
300
300
250
200 100
50 100 150
m+n-1 = 3+4-1= 6
FROM
A B C D
I 5 4 3 0
II 8 4 3 0
III 9 7 5 0
TO
WAREHOUSE
REQUIREMENTS
TOTAL
AVAILABLE
300 200 200 150
250
300
300
250
200 100
50 100 150
u1
u2
U3
v1 v2 v3 v4
U1+V1=5
U2+V2=4
U2+V3=3
U3+V1=9
U3+V3=5
U3+V4=0
ASSUMING U3=0
0+V1=9
V1=9
0+V3=5
V3=5
0+V4=0
V4=0
U1+V1=5
U1+9=5
U1= 5-9 = -4
U2+V3=3
U2+5=3
U2= 3-5= -2
(V3=5)
U3+V4=0
U3+0=0
U3=0
U2+V2=4
-2+V2=4
V2= 4-(-2) = 6
(V4=0)
(U2= -2)
CIJTABLE
4 3 0
8 0
7
V1 V2 V3 V4
U1
U2
U3
-4
-2
0
0569
uI-VJ TABLE
2 1 -4
7 -2
7
V1 V2 V3 V4
U1
U2
U3
DIJ TABLE
2 2 4
1 2
0
V1 V2 V3 V4
U1
U2
U3
Total cost = 250*5+200*4+100*3+50*9+100*5+150*0
1250+800+300+450+500+0 = 3,300
Initial basic feasible solution
Here all the dij values are positive, therefore the solution is
optimal.
Demand Greater than Supply
 The second type of unbalanced condition
occurs when total demand is greater than
total supply
 In this case we need to add a dummy row
representing a fake factory
 The new factory will have a supply exactly
equal to the difference between total
demand and total real supply
FROM
A B C
PLANT
SUPPLY
W 6 4 9 200
X 10 5 8 175
Y 12 7 6 75
WAREHOUSE
DEMAND 250 100 150
450
TO
500
Totals do not
balance
FROM
A B C
PLANT
SUPPLY
W 6 4 9 200
X 10 5 8 175
Y 12 7 6 75
Z 0 0 0 50
WAREHOUSE
DEMAND 250 100 150
500
TO
500
FROM
A B C
PLANT
SUPPLY
W 6 4 9 200
X 10 5 8 175
Y 12 7 6 75
Z 0 0 0 50
WAREHOUSE
DEMAND 250 100 150
TO
200
0 100 75
50
75
CIJ TABLE
4 9
12 7
0 0
V1 V2 V3
U1
U2
U3
U4
-4
0
-2
-10
10 5 8
UI+VJ TABLE
1 4
8 3
-5 -2
V1 V2 V3
U1
U2
U3
U4
DIJ TABLE
3 5
4 4
5 2
V1 V2 V3
U1
U2
U3
U4
DIJ= CIJ-(UI+VJ)
Here, all the dij values are positive, therefore the
solution is optimal.
TC= 200*6+0*10+100*5+75*8+75*6+50*0
1200+500+600+450= 2750
CONCLUSION
In real-life problems, total demand is frequently not
equal to total supply
These unbalanced problems can be handled easily by
introducing dummy sources or dummy destinations
If total supply is greater than total demand, a dummy
destination (warehouse), with demand exactly equal to
the surplus, is created
If total demand is greater than total supply, we introduce
a dummy source (factory) with a supply equal to the
excess of demand over supply
Any units assigned to a dummy destination represent
excess capacity
Any units assigned to a dummy source represent unmet
demand
THANK YOU FOR YOUR
ATTENTION!!!

More Related Content

What's hot

Simplex method - Maximisation Case
Simplex method - Maximisation CaseSimplex method - Maximisation Case
Simplex method - Maximisation Case
Joseph Konnully
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical Method
Joseph Konnully
 
Simplex Method
Simplex MethodSimplex Method
Simplex Method
Sachin MK
 
99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems
varsha nihanth lade
 

What's hot (20)

Assignment Chapter - Q & A Compilation by Niraj Thapa
Assignment Chapter  - Q & A Compilation by Niraj ThapaAssignment Chapter  - Q & A Compilation by Niraj Thapa
Assignment Chapter - Q & A Compilation by Niraj Thapa
 
Assignment model
Assignment modelAssignment model
Assignment model
 
North west corner method
North west corner method North west corner method
North west corner method
 
NORTH WEST CORNER METHOD
NORTH WEST CORNER METHODNORTH WEST CORNER METHOD
NORTH WEST CORNER METHOD
 
Operation research and its application
Operation research and its applicationOperation research and its application
Operation research and its application
 
Simplex method - Maximisation Case
Simplex method - Maximisation CaseSimplex method - Maximisation Case
Simplex method - Maximisation Case
 
Modified distribution method (modi method)
Modified distribution method (modi method)Modified distribution method (modi method)
Modified distribution method (modi method)
 
MODI Method (Operations Research)
MODI Method (Operations Research) MODI Method (Operations Research)
MODI Method (Operations Research)
 
3. linear programming senstivity analysis
3. linear programming senstivity analysis3. linear programming senstivity analysis
3. linear programming senstivity analysis
 
Stepping Stone Method
Stepping Stone MethodStepping Stone Method
Stepping Stone Method
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical Method
 
Simplex Method
Simplex MethodSimplex Method
Simplex Method
 
Vogel’s Approximation Method (VAM)
Vogel’s Approximation Method (VAM)Vogel’s Approximation Method (VAM)
Vogel’s Approximation Method (VAM)
 
99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems
 
Transportation problem
Transportation problemTransportation problem
Transportation problem
 
Transportation model and assignment model
Transportation model and assignment modelTransportation model and assignment model
Transportation model and assignment model
 
LINEAR PROGRAMMING
LINEAR PROGRAMMINGLINEAR PROGRAMMING
LINEAR PROGRAMMING
 
Transportation problem ppt
Transportation problem pptTransportation problem ppt
Transportation problem ppt
 
Assignment Problem
Assignment ProblemAssignment Problem
Assignment Problem
 
Vam
VamVam
Vam
 

Similar to unbalanced transportation problem

Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation ppt
Deepika Bansal
 
Transportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete MathsTransportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete Maths
Krupesh Shah
 
transportation_model.ppt
transportation_model.ppttransportation_model.ppt
transportation_model.ppt
NanoSana
 
Heizer om10 mod_c
Heizer om10 mod_cHeizer om10 mod_c
Heizer om10 mod_c
ryaekle
 

Similar to unbalanced transportation problem (20)

Transportation problem
Transportation problemTransportation problem
Transportation problem
 
Transportation problem_Operation research
Transportation problem_Operation researchTransportation problem_Operation research
Transportation problem_Operation research
 
Chapter 5.TRANSPORTATION PROBLEM.pdf
Chapter 5.TRANSPORTATION PROBLEM.pdfChapter 5.TRANSPORTATION PROBLEM.pdf
Chapter 5.TRANSPORTATION PROBLEM.pdf
 
Chap 10
Chap 10Chap 10
Chap 10
 
QA CHAPTER III and IV(1)(1).pdf
QA CHAPTER III and IV(1)(1).pdfQA CHAPTER III and IV(1)(1).pdf
QA CHAPTER III and IV(1)(1).pdf
 
O.R UNIT 3.pdf
O.R UNIT 3.pdfO.R UNIT 3.pdf
O.R UNIT 3.pdf
 
Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation ppt
 
Transportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete MathsTransportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete Maths
 
Assign transportation
Assign transportationAssign transportation
Assign transportation
 
Transportation Problem
Transportation ProblemTransportation Problem
Transportation Problem
 
transportation_model.ppt
transportation_model.ppttransportation_model.ppt
transportation_model.ppt
 
transportation_model (4).ppt
transportation_model (4).ppttransportation_model (4).ppt
transportation_model (4).ppt
 
transportation_model.ppt
transportation_model.ppttransportation_model.ppt
transportation_model.ppt
 
Heizer om10 mod_c
Heizer om10 mod_cHeizer om10 mod_c
Heizer om10 mod_c
 
Top schools in ghaziabad
Top schools in ghaziabadTop schools in ghaziabad
Top schools in ghaziabad
 
DPB 10013 MICROECONOMICS (SUPPLY THEORY)
DPB 10013 MICROECONOMICS (SUPPLY THEORY)DPB 10013 MICROECONOMICS (SUPPLY THEORY)
DPB 10013 MICROECONOMICS (SUPPLY THEORY)
 
English mathematic VAM Method
English mathematic VAM MethodEnglish mathematic VAM Method
English mathematic VAM Method
 
Linear Programming.pptx
Linear Programming.pptxLinear Programming.pptx
Linear Programming.pptx
 
Trans shipment problem
Trans shipment problemTrans shipment problem
Trans shipment problem
 
transportation-model.ppt
transportation-model.ppttransportation-model.ppt
transportation-model.ppt
 

More from Madurai Kamaraj University (6)

Maneesh (economics)
Maneesh (economics)Maneesh (economics)
Maneesh (economics)
 
Maneesh p
Maneesh pManeesh p
Maneesh p
 
Heteroscedasticity
HeteroscedasticityHeteroscedasticity
Heteroscedasticity
 
Biodiversity value and threats
Biodiversity value and threatsBiodiversity value and threats
Biodiversity value and threats
 
technical analysis
technical analysistechnical analysis
technical analysis
 
monopolistic competition and international trade
monopolistic competition and international trademonopolistic competition and international trade
monopolistic competition and international trade
 

Recently uploaded

Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Benefits & Risk Of Stock Loans
Benefits & Risk Of Stock LoansBenefits & Risk Of Stock Loans
Benefits & Risk Of Stock Loans
 
Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...
Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...
Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...
 
✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...
✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...
✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
 
Q1 2024 Conference Call Presentation vF.pdf
Q1 2024 Conference Call Presentation vF.pdfQ1 2024 Conference Call Presentation vF.pdf
Q1 2024 Conference Call Presentation vF.pdf
 
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
 
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
 
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
 
Toronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdfToronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdf
 
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai MultipleDubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
 
Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...
Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...
Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...
 
Fixed exchange rate and flexible exchange rate.pptx
Fixed exchange rate and flexible exchange rate.pptxFixed exchange rate and flexible exchange rate.pptx
Fixed exchange rate and flexible exchange rate.pptx
 
Bhubaneswar🌹Kalpana Mesuem ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...
Bhubaneswar🌹Kalpana Mesuem  ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...Bhubaneswar🌹Kalpana Mesuem  ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...
Bhubaneswar🌹Kalpana Mesuem ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswa...
 
Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...
 
Solution Manual For Financial Statement Analysis, 13th Edition By Charles H. ...
Solution Manual For Financial Statement Analysis, 13th Edition By Charles H. ...Solution Manual For Financial Statement Analysis, 13th Edition By Charles H. ...
Solution Manual For Financial Statement Analysis, 13th Edition By Charles H. ...
 
Thane Call Girls , 07506202331 Kalyan Call Girls
Thane Call Girls , 07506202331 Kalyan Call GirlsThane Call Girls , 07506202331 Kalyan Call Girls
Thane Call Girls , 07506202331 Kalyan Call Girls
 
Female Russian Escorts Mumbai Call Girls-((ANdheri))9833754194-Jogeshawri Fre...
Female Russian Escorts Mumbai Call Girls-((ANdheri))9833754194-Jogeshawri Fre...Female Russian Escorts Mumbai Call Girls-((ANdheri))9833754194-Jogeshawri Fre...
Female Russian Escorts Mumbai Call Girls-((ANdheri))9833754194-Jogeshawri Fre...
 
Famous Kala Jadu, Black magic expert in Faisalabad and Kala ilam specialist i...
Famous Kala Jadu, Black magic expert in Faisalabad and Kala ilam specialist i...Famous Kala Jadu, Black magic expert in Faisalabad and Kala ilam specialist i...
Famous Kala Jadu, Black magic expert in Faisalabad and Kala ilam specialist i...
 
Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Tilak Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
 

unbalanced transportation problem

  • 1. MANEESH P DEPT. OF APPLIED ECONOMICS
  • 2. The basic transportation problem was developed in 1941 by F.I. Hitchaxic. However it could be solved for optimally as an answer to complex business problem only in 1951,when Geroge B. Dantzig applied the concept of Linear Programming in solving the Transportation models. Transportation problems are primarily concerned with the optimal (best possible) way in which a product produced at different factories or plants (called supply origins) can be transported to a number of warehouses (called demand destinations). INTRODUCTION
  • 3. Transportation problem is a special kind of LP problem in which goods are transported from a set of sources to a set of destinations subject to the supply and demand of the source and the destination respectively, such that the total cost of transportation is minimized. The objective in a transportation problem is:-To fully satisfy the destination requirements within the operating production capacity constraints at the minimum possible cost.
  • 4. Whenever there is a physical movement of goods from the point of manufacture to the final consumers through a variety of channels of distribution (wholesalers, retailers, distributors etc.), there is a need to minimize the cost of transportation so as to increase the profit on sales. Transportation problems arise in all such cases. .
  • 5. It aims at providing assistance to the top management in ascertaining how many units of a particular product should be transported from each supply origin to each demand destinations to that the total prevailing demand for the company’s product is satisfied, while at the same time the total transportation costs are minimized
  • 6. i.e.; The total supply available at the plants exactly matches the total demand at the destinations. Hence, there is neither excess supply nor excess demand. Such type of problems where supply and demand are exactly equal are known as Balanced Transportation Problem. Supply (from various sources) are written in the rows, while a column is an expression for the demand of different warehouses. In general, if a transportation problem has m rows an n columns, then the problem is solvable if there are exactly (m + n –1) basic variables
  • 7. .UNBALANCED TRANSPORTATION PROBLEM : A transportation problem is said to be unbalanced if the supply and demand are not equal. Two situations are possible:- 1. If Supply < demand, a dummy supply variable is introduced in the equation to make it equal to demand. 2. If demand < supply, a dummy demand variable is introduced in the equation to make it equal to supply.
  • 8. Then before solving we must balance the demand & supply. When supply exceeds demand, the excess supply is assumed to go to inventory. A column of slack variables is added to the transportation table which represents dummy destination with a requirement equal to the amount of excess supply and the transportation cost equal to zero. When demand exceeds supply, balance is restored by adding a dummy origin. The row representing it is added with an assumed total availability equal to the difference between total demand & supply and with each cell having a zero unit cost.
  • 9. Demand Less Than Supply  Suppose that a plywood factory increases its rate of production from 100 to 250 desks  The firm is now able to supply a total of 850 desks each period  Warehouse requirements remain the same (700) so the row and column totals do not balance  We add a dummy column that will represent a fake warehouse requiring 150 desks  This is somewhat analogous to adding a slack variable  We use the northwest corner rule and either vogel’s approximation method or MODI to find the optimal solution
  • 10. FROM TO A B C TOTAL AVAILABLE I 5 4 3 250 II 8 4 3 300 III 9 7 5 300 WAREHOUSE REQUIREMENTS 300 200 200 850 700
  • 11. FROM TO A B C D TOTAL AVAILABLE I 5 4 3 0 250 II 8 4 3 0 300 III 9 7 5 0 300 WAREHOUSE REQUIREMENTS 300 200 200 150 850= 850
  • 12. FROM TO A B C D TOTAL AVAILABLE I 5 4 3 0 250 II 8 4 3 0 300 III 9 7 5 0 300 WAREHOUSE REQUIREMENTS 300 200 200 150 (1) (1) (2) (3) (0) (0) (0) 250 300-250=50
  • 13. FROM A B C D TOTAL AVAILABLE II 8 4 3 0 300 III 9 7 5 0 300 WAREHOUSE REQUIREMENTS 50 200 200 150 TO (1) (2) (1) (3) (2) (0) 200 300-200=100
  • 14. FROM A C D TOTAL AVAILABLE II 8 3 0 100 III 9 5 0 300 WAREHOUSE REQUIREMENTS 50 200 150 TO 100 (5) (4) (1) (2) (0) 200-100=100
  • 15. FROM A C D TOTAL AVAILABLE III 9 5 0 300 WAREHOUSE REQUIREMENTS 50 100 150 TO (4) (9) (5) (0) 50 300-50=250
  • 16. FROM C D TOTAL AVAILABLE III 5 0 250 WAREHOUSE REQUIREMENTS 100 150 TO (5) (5) (0) 150 250-150=100
  • 18. FROM A B C D I 5 4 3 0 II 8 4 3 0 III 9 7 5 0 TO WAREHOUSE REQUIREMENTS TOTAL AVAILABLE 300 200 200 150 250 300 300 250 200 100 50 100 150 m+n-1 = 3+4-1= 6
  • 19. FROM A B C D I 5 4 3 0 II 8 4 3 0 III 9 7 5 0 TO WAREHOUSE REQUIREMENTS TOTAL AVAILABLE 300 200 200 150 250 300 300 250 200 100 50 100 150 u1 u2 U3 v1 v2 v3 v4
  • 20. U1+V1=5 U2+V2=4 U2+V3=3 U3+V1=9 U3+V3=5 U3+V4=0 ASSUMING U3=0 0+V1=9 V1=9 0+V3=5 V3=5 0+V4=0 V4=0 U1+V1=5 U1+9=5 U1= 5-9 = -4 U2+V3=3 U2+5=3 U2= 3-5= -2 (V3=5) U3+V4=0 U3+0=0 U3=0 U2+V2=4 -2+V2=4 V2= 4-(-2) = 6 (V4=0) (U2= -2)
  • 21. CIJTABLE 4 3 0 8 0 7 V1 V2 V3 V4 U1 U2 U3 -4 -2 0 0569
  • 22. uI-VJ TABLE 2 1 -4 7 -2 7 V1 V2 V3 V4 U1 U2 U3
  • 23. DIJ TABLE 2 2 4 1 2 0 V1 V2 V3 V4 U1 U2 U3
  • 24. Total cost = 250*5+200*4+100*3+50*9+100*5+150*0 1250+800+300+450+500+0 = 3,300 Initial basic feasible solution Here all the dij values are positive, therefore the solution is optimal.
  • 25. Demand Greater than Supply  The second type of unbalanced condition occurs when total demand is greater than total supply  In this case we need to add a dummy row representing a fake factory  The new factory will have a supply exactly equal to the difference between total demand and total real supply
  • 26. FROM A B C PLANT SUPPLY W 6 4 9 200 X 10 5 8 175 Y 12 7 6 75 WAREHOUSE DEMAND 250 100 150 450 TO 500 Totals do not balance
  • 27. FROM A B C PLANT SUPPLY W 6 4 9 200 X 10 5 8 175 Y 12 7 6 75 Z 0 0 0 50 WAREHOUSE DEMAND 250 100 150 500 TO 500
  • 28. FROM A B C PLANT SUPPLY W 6 4 9 200 X 10 5 8 175 Y 12 7 6 75 Z 0 0 0 50 WAREHOUSE DEMAND 250 100 150 TO 200 0 100 75 50 75
  • 29. CIJ TABLE 4 9 12 7 0 0 V1 V2 V3 U1 U2 U3 U4 -4 0 -2 -10 10 5 8
  • 30. UI+VJ TABLE 1 4 8 3 -5 -2 V1 V2 V3 U1 U2 U3 U4
  • 31. DIJ TABLE 3 5 4 4 5 2 V1 V2 V3 U1 U2 U3 U4 DIJ= CIJ-(UI+VJ)
  • 32. Here, all the dij values are positive, therefore the solution is optimal. TC= 200*6+0*10+100*5+75*8+75*6+50*0 1200+500+600+450= 2750
  • 33. CONCLUSION In real-life problems, total demand is frequently not equal to total supply These unbalanced problems can be handled easily by introducing dummy sources or dummy destinations If total supply is greater than total demand, a dummy destination (warehouse), with demand exactly equal to the surplus, is created If total demand is greater than total supply, we introduce a dummy source (factory) with a supply equal to the excess of demand over supply
  • 34. Any units assigned to a dummy destination represent excess capacity Any units assigned to a dummy source represent unmet demand
  • 35. THANK YOU FOR YOUR ATTENTION!!!