SlideShare a Scribd company logo
1 of 60
Download to read offline
Achieving better value, timeliness and accountability through
                      Public-Private Partnerships




                   2nd Annual
                Federal Canada
       Innovation in Infrastructure Finance
                      Forum

PPP Canada
October 30, 2012
What is PPP Canada?
•    A Federal Crown Corporation
•    Reports to Parliament through the Minister of Finance
•    Led by an accomplished private sector Board of Directors
•    Partial Agent of the Crown

                          Mandate

•  To act as a source of expertise and advice on public-private
   partnership matters.
•  To assess public private partnership opportunities at the federal
   level in accordance with criteria established by the Treasury Board.
•  To advise on the execution of public-private partnership projects at
   the federal level.
•  Manage the $1.2 billion P3 Canada Fund

                                                                          2
PPP Canada Value Proposition

 What and who we       •  Knowledge and networks to capital
      know                market participants and private and public
                          sector P3 practitioners


Project experience     •  Practical and technical project experience


Providing incentives   •  P3 Canada Fund
   and support         •  Project Development Fund




                                                                       3
Growing and Supporting a Pipeline of Federal P3s




                   Supporting P3
    Implementing                     Building
                   business case
      Federal                      institutional
                    development
       Screen                      frameworks




                                                   4
Definition
P3s are a long-term performance-based approach for procuring public
infrastructure where the private sector assumes a major share of the
responsibility in terms of risk and financing for the delivery and the
performance of the infrastructure, from design and structural planning, to
long-term maintenance.


 •  Integration of roles (Design, Build, Finance, Operate, Maintain);
 •  The provision of capital assets and associated services to meet a defined
    output specification (i.e., define what is required rather than how it is to be
    done);
 •  A transfer of risk to the private sector anchored with private sector capital
    at risk;
 •  Entered into by a competitive process.

                                                                                      5
What is Not a P3
The following types of contractual arrangements ARE NOTARE NOT
The following types of contractual arrangements examples of
P3 arrangements:
examples of P3 arrangements:
   –    privatization;
   –    joint ventures with the private sector;
   –    co-ownership with another public sector body;
   –    arrangements for the divestiture of federal assets where the private
        partner will become the new owner;
   –    design-build contracts;
   –    service-only contracts
   –    Sale/lease-back contracts; and
   –    lease-purchase contracts.

                                                                           6
How do P3s Work?

Contractual relationship between public sector and private
sector


Payments based on performance



Private sector puts money at risk


                                                             7
The Federal Screen
• The purpose of the P3 Screen isis to raise the level of
    The purpose of the P3 Screen to raise the level of
  awareness and consideration of P3s inin the federal
    awareness and consideration of P3s the federal
  investment planning process.
    investment planning process.
•  It is a consistent and systematic approach for assessing
    the P3 suitability of capital investments.
•  The screen supports the efficient use of analytical
    resources by ensuring that investments with limited P3
    suitability do not needlessly consider the P3 option.




                                                              8
What Types of Projects?

Larger, more complex projects


Outcomes / outputs can be specified and are stable


Market interest / capacity

User fees not a driver or necessity for P3s but can broaden
scope

                                                              9
PPP Canada’s Screening Matrix
•  The P3 Screening Matrix identifies whether an investment
   presents the right mix of traits to succeed as a P3.
•  It asks the user to consider 14 questions on a scale of
   indicators from 1 to 5.
•  The user considers the question in the context of their
   proposed investment and identifies the best indicator that
   best aligns with their assessment.
•  The user also provides a complete rationale for their rating.
•  The user’s scores will be modified by a weighting factor
   that reflects the relative importance of that criterion in
   determining P3 suitability.
                                                               10
Interpreting Screening Results


Green
           •  Indicates that the P3 option should be included in
              the Procurement Option Analysis or Business
              Case to be developed for the investment




Yellow
           •  Indicates that the investment presents a mix of
              favorable and unfavorable indicators for P3
              delivery




 Red       •  Indicates the P3 option should not be retained for
              further analysis


                                                                   11
A Word on the Screening Result

 The accuracy of these results is a function of the degree of
   definition and the current state of planning around the
investment – clearer definition and greater understanding of
    the investment will provide better screening results.
  There is no one overwhelming indicator of P3 suitability.




                                                            12
My Asset has P3 Potential: What Now?

Assessing P3 potential is only the first step in a larger analytical process that
concludes with a recommendation on the optimal approach to procurement.


A positive screening outcome signals that the P3 option must be included the
broader Options Analysis for the investment.


Life-cycle options analysis is a long-standing requirement of Treasury Board
policy.


PPP Canada is developing tools and methodologies for supporting these
subsequent phases of analysis as well as the procurement phase.

                                                                                    13
100, Queen Street, Suite 630
Ottawa, Ontario K1P 1J9
Canada

Telephone: (613) 947-9480
Fax: (613) 947-2289
Toll Free Telephone: 877-947-9480

Email: info@p3canada.ca
Website: www.p3canada.ca
Budget 2011 and Federal Public-Private
Partnerships


            Office of the Comptroller General
            Treasury Board of Canada Secretariat
            October 30th 2012
Overview

•  Budget 2011 Screening requirements.
•  Government of Canada real property asset
   portfolio and policy context.
•  Implementation of Budget 2011 and next steps.




                                                   2
Budget 2011 – P3 Screen for Large
  Investments in Infrastructure
•  Mandatory P3 screening requirement when
   capital costs of the asset are $100M or more and
   the lifespan is at least 20 years.
•  If the screen identifies a P3 as a viable option,
   the department is required to develop a P3
   proposal in addition to other options.
•  Departments to screen in consultation with PPP
   Canada.




                                                       3
Government of Canada Real Property
     Portfolio
•  Complex portfolio across large geographical area.
•  Assets include a very broad range of resources
   ranging from land, office buildings, special purpose
   buildings (eg. laboratories) and engineering works and
   infrastructure (eg. bridges, roads).
•  Total value of assets: approx. $57 Billion (2011).
•  Current issues :
    –  Aging assets (particularly buildings and
       infrastructure, such as roads and bridges).
    –  Need to optimize scarce capital dollars.
    –  Need to use private sector innovation and
       financing.                                       4
Government of Canada Real Property
  Inventory
Buildings                     Properties
•  29,929 domestic            •  21,252 properties
•  1,917 abroad               •  40.7M (ha) domestic
•  82% Crown owned            •  1,100 (ha) abroad
•  Major Custodians:          •  95% Crown owned
    –  National Defence       •  Major Custodians:
                                  −  Parks Canada
    –  Parks Canada
                                     Agency
    –  RCMP                       −  National Defence
    –  Public Works and           −  Agriculture and
       Government Services           Agri-Food
    –  Fisheries and Oceans       −  Transport Canada
                                                        5
Treasury Board Policy Instruments

    •    Relevant Treasury Board policies include:
            •  Policy Framework for the Management of Assets and
               Acquired Services
            •  Policy on Management of Real Property
            •  Policy on Management of Projects
            •  Policy on Investment Planning

    •    These policies govern the management of assets
         throughout their life cycle.


                                                                   6
6
Key Policy Principles

•    Assets are only held to support a department’s
     delivery of program
•    Value for money
•    Stewardship
•    Management strategies developed based on life
     cycle management principles
•    Management decisions encourage innovation




                                                      7
Treasury Board Policies and P3

–  P3s are a new tool for managing government
   infrastructure.
–  TBS released a guideline for implementing
   Budget 2011 P3 requirements.
–  TBS is working on further measures relating
   to the requirement to screen investments for
   their P3 viability.
–  References are made to PPP Canada’s
   Screening Matrix.



                                                  8
Federal P3s Going Forward

•  Recent P3 agreements include:
   –  Royal Canadian Mounted Police ‘E’ division
      headquarters – 76,000m2 facility housing 2,700+
      employees in British Columbia.
   –  Communications Security Establishment long term
      accommodation facility in Ottawa - 72,000m2 facility
      housing 2,000+ employees.
•  Federal government is exploring new P3
   opportunities:
   –  Detroit River International Crossing Project Bridge
   –  Champlain Bridge - Montreal



                                                             9
Potential Benefits of P3s

–  Risk transfer
–  Private financing
–  Upfront planning / Integration of life cycle phases
   into a single contract
–  Innovation / output-based specifications
–  Performance-based payments
–  Quality of the asset at the end of its life cycle
–  Cost, schedule and scope certainty



                                                       10
Conclusions

•  Given today’s fiscal climate and the challenges
   of managing a large and complex infrastructure
   portfolio, the Government of Canada is looking
   to alternative and innovative solutions.
•  Treasury Board Secretariat is working closely
   with PPP Canada in ensuring value for money
   through P3s.




                                                     11
Defence & Security
Infrastructure Panel
2nd Annual Innovation in Infrastructure
Finance Forum




Moderator:
             Brian Budden, Senior Vice President, Plenary Group

Panel:
             James Paul, President & CEO, Defence Construction Canada
             Wayne Sutherland, Director of Major Capital Projects, RCMP
             Rick Taylor, President, Balfour Beatty Capital


October 30th, 2012
Outline
RCMP E

CSEC – Driving Collaboration

Military Housing

Potential Canadian Applications




                                  2
RCMP E Project Overview




»  Project Scope
 !    Design-Build-Finance-Maintain of a 76,000 m2 purpose-built facility to house the RCMP E
      Division Headquarters in the City of Surrey
 !    Project includes Facilities Management for the full 25 year term
»  Project Approvals Process
 !    2003 Preliminary Project Approval, allowing for planning and land acquisition
 !    2005Purchase of Green Timbers site
 !    2007 Revised Preliminary Project Approval to proceed with P3-DBFM assuming value for
      money
 !    2008 Request for Qualifications and short list of top three consortia
 !    2009 Request for Proposal and formal evaluation
 !    2010 Effective Project Approval allowing for contract award and financial close



                                                                                                3
RCMP E Project Overview




»  Security Issues and Other Challenges
 !    Security Clearances for the key personnel on all three proponents in the RFP stage
 !    Physical Security requirements for spaces within the functional program
 !    Dealing with sanitized drawings and room names
 !    Dealing with security concerns without being prescriptive
»  Procurement Process
 !    Designed to identify optimal balance between quality and cost through all phases of the Project
      (design, construction, services and maintenance)
 !    RFP stipulated a maximum price, carefully established to ensure VfM within existing budget
      limits and clearly communicated expectations to the Proponents
 !    Flexible request for proposals that enabled dialogue with proponents on optimal balance of
      public and private communications
 !    Agreed upon independent fairness monitor overseeing all collaborative meetings and RFI’s


                                                                                                        4
RCMP E Project Overview




»  Lessons Learned
 !    The phased approach and additional upfront capital contributions by Canada allowed for the
      possibility of greater competition and facilitated greater financing options to Proponents
 !    Establishing an affordability ceiling likely improved an already highly competitive process that
      required each Proponent’s proposal to balance quality and cost while demonstrating how it most
      closely met the requirements of the Project Agreement
 !    Implement a process for the flow of information in advance of receiving RFIs, i.e. identify the
      individuals to have input into responses based on area of expertise and determine who will
      provide any oversight function (e.g. legal, technical, etc.)
 !    Prior to initial internal circulation of the TB submission, concurrence as to the appropriate
      legislative authority as well as the approvals being sought should be obtained from the
      Department of Justice legal counsel representing TBS, the department and client department
 !    Each Project Agreement and its related Schedules are project specific. Care should be taken to
      ensure that the Project Agreement is written to reflect the performance requirements of that
      particular project as well as reflects any pertinent legislative requirements

                                                                                                         5
RCMP E Project Overview




»  Current Status
  !    Early Access to the Data Center and telecommunication closets in Sept 2012
  !    Construction 98 % complete; scheduled Substantial Completion in December 2012
  !    Ongoing work on deficiencies and commissioning
  !    Work ongoing with all proponents as part of the move in schedule
  !    Move in to be completed by April 2013 less than 3 years after commencement of construction




                                                                                                    6
Outline
RCMP E

CSEC – Driving Collaboration

Military Housing

Potential Canadian Applications




                                  7
Communications Services Establishment Canada




Project Description:
»  The Project entails the design, financing, construction and           Size          $867 million
   subsequent operations of an approximately 775,000 ft2 facility
   (the “Facility”) over a 42-month construction period. Located on a    Financial
                                                                                       January 2011
   Crown-owned (approximately 36-hectare) greenfield site in             Close
   Ottawa, Canada. To meet CSEC’s program requirements, the
   Facility will consist of a mix of general office space, special       Substantial
   purpose spaces and a data centre and will include an                                July 2014
                                                                         Completion
   approximately 800-stall parking garage. The Facility will be LEED
   Gold certified.
                                                                         Team
                                                                                       PCL, HDR Architects/WZMH, Honeywell/HP
»  At the completion of construction, the Plenary Properties team will   Members
   be responsible for providing full-scope facilities management
   services (including both hard and soft services) as well as a
                                                                                       30-year IT Service Commitment, Security
   bundle of commodity IT services (such as email, printing and          Challenges
                                                                                       Requirements, Debtholder Restrictions
   computing).

                                                                                                                                 8
CSEC LTAP Timeline
         Collaboration, Innovation, and Flexibility
                      Project Management Team

                                                                                                                        Partnerships
                                                                                       Fasken
              »  Through the collaborative                                            Martineau
                                                                                     DuMoulin LLP
                                                                                                                       British Columbia


                 approach CSEC/DCC was able to
                 receive three different yet                  Fairness
                                                              Monitor
                                                                                             Deloitte Touche
                                                 1/2010                               10/2010 Tohmatsu LLP
                                                                             Building-in-
                 extremely viable RFP Issuedinnovative
                                                and            7/2010            Use
                                                                                    Selection of
                                                                            Environmental                       IT/NET


                                                                                                          The Result
                                                           Technical Bids       Preferred Proponent
                                                                             Psychologist

                 proposals that met the needs of9/2010
                                        9/2009                              all              11/2010
                                     RFQ Issued
                                            Communications                                                                                                           7/2014
                 stakeholders andSecurity
                             6/2009
                                                  continued           Financial Bids       TB Approval
                                                                                                                                                            Building Occupancy Date
                 collaboration is achieving amazingFlexible, adaptable workspace
                                                                      1. 
                                             Establishment
                       Preliminary Project                                                            1/2011
                                                Canada
                            Approval              PMO                                            Contract Award
                 outcomes.                                                                                         Defence

                                                                                  LTAP
                                                                             2.  Collaborative space Authority
                                                                                                                Construction
                                                                                                     Canada every turn
                                                                                                          at
                                                                                                 Contract
                                                KWC
                                               Architect

                                                                             3.  Ubiquitous IT
                                              Functional
                                               program
              1/2008               1/2009                  1/2010                       1/2011                    1/2012                        1/2013    1/2014

August 2007                                                                                         Wood Banani                          Various                          December 2014
               11/2007 - 11/2008
                Business Case
                                        1/2009 - 1/2010
                                                    Department of
                                        Development of                       4.  30+ Parizeau Inc. of performance
                                                                                      years
                                                                                      Bouthillette
                                                                                                          2/2011 - 6/2014
                                                                                                        Construction Period
                                                                                                                                        specialists

                                                   National Defence
                                         Output Specs
                                                     Infrastructure         FoTenn

                                                                             5.  On budget and on schedule
                                                                           Consulting
                                                                              Inc.
                                                                                                                                                 P3
                                                                                                                                               Advisors
                                                                                                                             CSP
                                                                                                                            Security
                                                                                                                           Consulting
                                                                                                     The Attain               Inc.                         Consultant
                                                                                                       Group
                                                                         Watson MacEwen
                                                                            Architects                                                                    Federal Government

                                                                                                                                                          LTAP – Owner’s Advocate
                                                                                                                     Marshall &
                                                                                                                      Murray
                                                                                                                        Inc.


                                                                                                                                                                                      9
Outline
RCMP E

CSEC – Driving Collaboration

Military Housing

Potential Canadian Applications




                                  10
ADF Single LEAP 2




»  33.5 year DBFM project for 3,015 accommodation        »  Following construction phase of approx. 3 years
   units at 14 military bases across all Australian         Plenary Living will provide a range of hard and soft
   mainland States                                          FM services over a 30 year term including:
»  Contract value +$1bn. Government counterparty is        !    Preventative and reactive maintenance
   the Australian Department of Defence                    !    Concierge services and accommodation
                                                                management
»  Key project objective the provision of comfortable
   housing for single Military Personnel as a critical     !    Housekeeping services (cleaning, waste
                                                                management and linen/laundry services)
   element to the attraction and retention of high
   calibre Servicemen/women.                               !    Utilities management
                                                           !    Pest control
                                                           !    Grounds maintenance
                                                           !    Lifecycle




                                                                                                               11
U.S. Military Housing Background




»  Why did they take the P3 route? (These “Before” photos told a powerful story)

»  In the early 1990s, U.S. DoD determined the following:
  !    Over 60% of DoD owned family housing was inadequate (180,000 of 300,000 units)
  !    If addressed using traditional funding, would require $20B and take 30 years
  !    Housing was not a core competency of the military services
  !    Quality of life was affecting ability to attract and retain service members
»  Recognized private sector development and management expertise, benefits of
   competition, and ability to attract private financing
»  Resulted in landmark legislation in 1996 Defense Authorization Bill

                                                                                        12
U.S. Military Housing P3 Program
»  Pilot projects initially, but expanded to 100% of domestic military bases




                                                    Map represents Balfour Beatty portfolio only
                                                                                                   13
U.S. Military Housing Basic Deal Points
»  50 year DBFOM; some with 25 year renewal options

»  Demand risk assumed by private sector
  !  Focus on customer service and on more than just housing

»  Most financed through capital markets

»  Varied financial participation by DoD
  !  equity, subordinate debt, limited loan guarantees

»  GMP Construction Contracts typical

»  Joint review/approval of O&M budgets

»  Lifecycle addressed through Recapitalization Account
  !  Different risk profile than traditional P3
  !  Demand risk motivates private sector to perform
  !  Limited ability to influence revenue (rental income) changes
  !  No specific hand back requirements

                                                                    14
Outline
RCMP E

CSEC – Driving Collaboration

Military Housing

Potential Canadian Applications




                                  15
Potential Canadian Applications
»  Future defence accommodation projects
»  Base housing (following Australia's LEAP programs)
»  Planes/vehicles (following the UK's refueling aircraft PFI)
»  Research facilities and labs
»  Ports, including major redevelopment projects
»  Data centres

»  Satellite infrastructure




                                                                 16
UNCLASSIFIED

                                                                                                                       1




        A world-class workplace for a world-class workforce


                     !
Federal!Canada!Infrastructure!Finance!Forum!
             30!October!2012!




                       A world-class workplace for a world-class workforce!
                       Un milieu moderne à l appui d un effectif moderne !


                                                                                  Conceptual Rendering – Aerial View
UNCLASSIFIED

                                                                                                                                2


       Long;Term!Accommoda>on!
       (LTA)!Project!:!
      •     2000!Employees!
      •     2014!Occupancy!Date!

      Design!Build!Finance!Maintain!
      (DBFM)!contract!for!30!years!
"
      includes:!
      "Design"and"Construc1on"of"72,000rm2"
       LTAP"facility""
         !  includes"a"4000m2"Data"Centre,"
             4500m2"PurposeABuilt"
             Engineering"Facility,"Top"Secret"
             Knowledge"Centre""
         !  Separate"and"secure"Shipping"
             and"Receiving"Building""
         !  Visitor"Centre"for"unclassified"
             visits"
         !  Power"Genera1on"Facility"to"
             accommodate"excep1onal"
             power"requirements"
         !  Parking"Structures"etc…"
         !  LEED"Gold"Accredita1on"
             required"


            A world-class workplace for a world-class workforce!
            Un milieu moderne à l appui d un effectif moderne !

                                                                              A world-class workplace for a world-class workforce
UNCLASSIFIED

                                                                                                                         3




                                          IT!Infrastructure!!
                                                       (What!is!included)!
 •  Data!Centres!
          –  Design,!build!and!operate!
          –  Space!management!
 •  Cooling!
          –  Provision!and!maintenance!
 •  Power!
          –  Provision!and!maintenance!
          –  Not!power!usage!cost!
 •  Flexibility!
          –  All!technical!services!that!support!the!office!
             automa>on!environment!!
A world-class workplace for a world-class workforce!
Un milieu moderne à l appui d un effectif moderne !

                                                                       A world-class workplace for a world-class workforce
UNCLASSIFIED

                                                                                                                         4


IT!Infrastructure!
   Specifics!
!
Network"
       –    Telephony"
       –    Network"
       –    Network"Security"
       –    Remote"Access"
•  End"User"
       –  Compu1ng"&"
          Engineering"
       –  Prin1ng"
       –  EAmail"
•  IT"Tools"&"Processes"
       –  Professionally"managed"
          data"centre"
       –  IT"Help"Desk"
•  Development"&"Test"
   Environment"
•  Technical"Infrastructure"
   A world-class workplace for a world-class workforce!
      Un milieu moderne à l appui d un effectif moderne !

                                                                       A world-class workplace for a world-class workforce
UNCLASSIFIED

                                                                                                                       5



                                               Mi>ga>ng!30!years…!
                                                           !
•  Key!Performance!Indicators!
    –  Availability"schedule"
    –  Deduc1ons"
    "
•  IT!Joint!Technical!Review""
    –  capacity"requirements,"technical"requirements,"hardware,"soYware""&"innova1on"
    –  Deduc1ons"applicable"for"missing"performance"indicators"
    –  IT"Unavailability"Event"deduc1ons"
    "
•  Benchmarking!
    –  First"benchmark"3rd"anniversary"of"Service"Commencement"Date"
    –  Every"5th"anniversary"of"the"last"benchmark"date"for"IT"Services"
    –  Provisions"established"so"that"original"prices"are"based"on"reasonableness"and"
       due"diligence"
    –  Crown"rights"of"audit"rela1ng"to"costs,"overheads"and"margins"of"IT"provider"
       guaranteed."

   A world-class workplace for a world-class workforce!
   Un milieu moderne à l appui d un effectif moderne !

                                                                     A world-class workplace for a world-class workforce
PUBLIC PRIVATE
PARTNERSHIPS

OPPORTUNITIES IN IT PROCUREMENT

-A PRIVATE SECTOR PERSPECTIVE




Sherry Casey
Vice President, Industry Sales
HP Enterprise Services
October 30, 2012
© 2011 Hewlett-Packard Development Company, L.P.
The information contained herein is subject to change without notice.
THE P3 AND IT - A POINT OF INFLECTION
& REFLECTION



2
TRADITIONAL IM/IT PROCUREMENTS
ARE NO LONGER ADEQUATE

Service delivery organization's business challenges are increasingly
relying on the IM/IT infrastructure for:
 •    Enterprise solutions, horizontal integrated services across levels of
      government
 •    Protection against cyber security attacks, privacy violations
 •    Promoting “Open Government” initiatives
 •    Standardized, streamlined and more affordable IM/IT
 •    Self service delivery models, mobile solutions
 •    Services anywhere and anytime
 •    Greater use of social media in support of service delivery & democracy
 •    Desire for adaptable, scalable, responsive solutions
P3’S LEVERAGE STRATEGIC
BUSINESS VALUE OVER
TRADITIONAL OUTSOURCING
1.  Capability based, highly collaborative, iterative procurements - can be
    quickly refined into “contractible” frameworks

2.  Strong Executive Governance for a shared commitment for relentless
    focus on horizontal business outcomes and timely problem resolution

3.  Financing requirements, penalty structures & duration of agreements
    catapults requirements to industrial strength, proven suppliers

4.  Government funding cycle constraints for capital & operational funding are
    removed, flow of government payment streams can be normalized

5.  Risk transfer to private sector with rewards for continued long term
    performance drives improved agility and business outcome focus

6.  Business outcome focus also builds-in supplier motivation for innovation
    and continuous improvement once base infrastructure in place
CONSIDERATIONS UNIQUE TO
IM/IT P3 VERSUS TRADITIONAL
BRICK & MORTAR P3

1.      Special IM/IT terms and conditions
        (Protection of IP, nature of commercial business software & applications, desire to
      appropriately limit liability plus others)

2.     IM/IT infrastructure is constantly evolving and P3 supplier cannot
       dictate or control the technology roadmaps for implemented solutions
3.      Usually dealing with an installed base of products and solutions
4.     Usually difficult to have accurate picture of the assets as not visible &
       asset management is often weak
5.     High level of interdependency between various IM/IT infrastructure
       elements to be understood & managed, etc

  5
TRANSFERABLE PRECURSORS FOR
SUCCESS, LESSONS LEARNED & BODY
OF BEST PRACTICES EXISTS
 What is known about complex IM/IT procurement is readily
   transferable to the P3 procurement
 A few examples:
 –  Criticality of the relationship between suppliers and clients
 –  IM/IT supplier should have a front seat early in the procurement; discussions
    and continually throughout the P3 duration – communication is key
 –  Significant due diligence within IM/IT companies is to be expected with regard
   to financing and internal approvals in pursing these types of ventures
 –  A certain amount of flexibility within the contracting framework is required and
   a willingness to address constraints for mutual resolution
 –  Strong governance and executive leadership is paramount
 –  Change management, focus on innovation
IN CONCLUSION




7
MGS – New Data Centre


Pioneering risk allocation in government data
centre projects in Canada. Setting the stage for IT
risk transfer.

                                          October 2012
Project Overview

!  New Government of Ontario data centre
!  Located in Guelph, Ontario
!  225,000 ft2
!  First Canadian data centre to be procured as an Alternative Financing and
   Procurement (“AFP”)
!  Reached Financial Close in 2008, delivered on time and on budget in 2010
!  Critical environment for the government
!  Tier IV highly redundant– only PPP data centre
   in the world to reach this classification
!  Green Design: certified LEED Gold certified
   despite massive energy requirements




                                                                               2
Partnership Overview




Debt funding




                                 Jan$




                                        3
Risk Allocation
!  Design/construction, financial and operations risks were largely transferred to
   Plenary Properties.
!  Specifications were prescriptive in performance outcomes:
    "  Specifications set standards not methods

    "  We were able to innovate within these parameters

    "  Tier IV was a critical in the design philosophy – this set the higher standard

!  Key construction risks included price certainty, scheduling and delays,
   permitting, M&E, financing, commissioning and transition to new facility.




                                                                                        4
Risk Allocation
!  Key operational term risks include facilities maintenance (including lifecycle
   renewal), meeting Tier IV operational standards, facility availability, power
   supply, energy and labour costs.
!  Key risks retained by the government were: planning, changes in law, pre-
   existing site contamination, public-sector initiated scope-change, force majeure
   (shared risk).
!  The Ontario government provides client side IT – i.e. all servers, hardware etc.
   that run within the critical environment




                                                                                      5
Project Cost and Payment

!  $352 million net present value (“NPV”) over 32 years
!  The AFP approach saved the taxpayer an estimated $64.2 million (14.3%)
   over the 30 year life of the facility
!  $50 million substantial completion payment to reduce the cost of private
   financing
!  Annual availability stream payable each year for 30 years (paid on a monthly
   basis), including partial inflation indexation at an estimated 2 per cent per
   year, subject to certain adjustments for benchmarking, market testing and
   inflation changes.
!  Severe abatements for performance failures




                                                                                   6
Summary
!  DBFM ensured an integrated approach to the whole life delivery of the critical
   environment
!  Risk transfer can be substantial and managed by the private sector
!  Level of IT transfer can be determined by the client to meet their specific
   requirements
!  Significant value for money realized for the client




                                                                                    7

More Related Content

Viewers also liked

Viewers also liked (6)

Dozvillya studentskoyi molodi
Dozvillya studentskoyi molodiDozvillya studentskoyi molodi
Dozvillya studentskoyi molodi
 
Public Lecture Presentation Slides (4.5.2013)
Public Lecture Presentation Slides (4.5.2013)Public Lecture Presentation Slides (4.5.2013)
Public Lecture Presentation Slides (4.5.2013)
 
1ª rotulo marwa
1ª rotulo marwa 1ª rotulo marwa
1ª rotulo marwa
 
Conectores y buses externos (powerpoint)
Conectores y buses externos (powerpoint)Conectores y buses externos (powerpoint)
Conectores y buses externos (powerpoint)
 
Base de participantes
Base de participantesBase de participantes
Base de participantes
 
Test
TestTest
Test
 

Similar to 2nd annual canadian innovation in infra fin 2011

OECD, 7th Meeting on Public-Private Partnerships - Greg SMITH
OECD, 7th Meeting on Public-Private Partnerships - Greg SMITHOECD, 7th Meeting on Public-Private Partnerships - Greg SMITH
OECD, 7th Meeting on Public-Private Partnerships - Greg SMITHOECD Governance
 
Capacity building for PPP projects
Capacity building for PPP projectsCapacity building for PPP projects
Capacity building for PPP projectsgeoffrey-cip
 
private finance initiative (PFI)
private finance initiative (PFI)private finance initiative (PFI)
private finance initiative (PFI)zyra Nia
 
Capacity Building for PPP projects
Capacity Building for PPP projects Capacity Building for PPP projects
Capacity Building for PPP projects admin-cip
 
Towards an integrated governance framework for infrastructure - Ian Hawkeswor...
Towards an integrated governance framework for infrastructure - Ian Hawkeswor...Towards an integrated governance framework for infrastructure - Ian Hawkeswor...
Towards an integrated governance framework for infrastructure - Ian Hawkeswor...OECD Governance
 
Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...
Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...
Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...OECD Governance
 
PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...
PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...
PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...Global Infrastructure Basel Foundation
 
2019 ASEAN PPP Summit MPG Opening
2019 ASEAN PPP Summit MPG Opening2019 ASEAN PPP Summit MPG Opening
2019 ASEAN PPP Summit MPG OpeningLuca Bernardinetti
 
Lindgren Combined 18may10
Lindgren Combined 18may10Lindgren Combined 18may10
Lindgren Combined 18may10Jaylindgren
 
introduction to public private partnership
introduction to public private partnershipintroduction to public private partnership
introduction to public private partnershipHayJirenyaa
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesLou Milrad
 
Deloitte Report: Transforming India Unleash your potential
Deloitte Report: Transforming India Unleash your potentialDeloitte Report: Transforming India Unleash your potential
Deloitte Report: Transforming India Unleash your potentialaakash malhotra
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnershipDivyajit Kumar
 
Let there be Light... in Nigeria using PPPs
Let there be Light... in Nigeria using PPPsLet there be Light... in Nigeria using PPPs
Let there be Light... in Nigeria using PPPsDamilola Olaniyan
 
Infra ppp corporate presentation jun2015en
Infra ppp corporate presentation jun2015enInfra ppp corporate presentation jun2015en
Infra ppp corporate presentation jun2015enJose de la Maza Alba
 
PPP around the World: Learning from the experience
PPP around the World: Learning from the experiencePPP around the World: Learning from the experience
PPP around the World: Learning from the experienceAndre Dantas
 
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdf
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdfRPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdf
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdfOECD Environment
 
SMART Infrastructure Business and Policy Dialogue Event: A private sector per...
SMART Infrastructure Business and Policy Dialogue Event: A private sector per...SMART Infrastructure Business and Policy Dialogue Event: A private sector per...
SMART Infrastructure Business and Policy Dialogue Event: A private sector per...SMART Infrastructure Facility
 

Similar to 2nd annual canadian innovation in infra fin 2011 (20)

OECD, 7th Meeting on Public-Private Partnerships - Greg SMITH
OECD, 7th Meeting on Public-Private Partnerships - Greg SMITHOECD, 7th Meeting on Public-Private Partnerships - Greg SMITH
OECD, 7th Meeting on Public-Private Partnerships - Greg SMITH
 
Capacity building for PPP projects
Capacity building for PPP projectsCapacity building for PPP projects
Capacity building for PPP projects
 
private finance initiative (PFI)
private finance initiative (PFI)private finance initiative (PFI)
private finance initiative (PFI)
 
Capacity Building for PPP projects
Capacity Building for PPP projects Capacity Building for PPP projects
Capacity Building for PPP projects
 
Towards an integrated governance framework for infrastructure - Ian Hawkeswor...
Towards an integrated governance framework for infrastructure - Ian Hawkeswor...Towards an integrated governance framework for infrastructure - Ian Hawkeswor...
Towards an integrated governance framework for infrastructure - Ian Hawkeswor...
 
Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...
Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...
Towards and Integrated Governance Framework for Infrastructure by Ian Hawkesw...
 
PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...
PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...
PWC - Catalysing Institutional Investment in Climate-Resilient Infrastructure...
 
Project Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS KenyaProject Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS Kenya
 
2019 ASEAN PPP Summit MPG Opening
2019 ASEAN PPP Summit MPG Opening2019 ASEAN PPP Summit MPG Opening
2019 ASEAN PPP Summit MPG Opening
 
Lindgren Combined 18may10
Lindgren Combined 18may10Lindgren Combined 18may10
Lindgren Combined 18may10
 
introduction to public private partnership
introduction to public private partnershipintroduction to public private partnership
introduction to public private partnership
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal Issues
 
Public Private Partnerships in the caribbean webinar presentation part 2
Public Private Partnerships in the caribbean webinar presentation part 2Public Private Partnerships in the caribbean webinar presentation part 2
Public Private Partnerships in the caribbean webinar presentation part 2
 
Deloitte Report: Transforming India Unleash your potential
Deloitte Report: Transforming India Unleash your potentialDeloitte Report: Transforming India Unleash your potential
Deloitte Report: Transforming India Unleash your potential
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnership
 
Let there be Light... in Nigeria using PPPs
Let there be Light... in Nigeria using PPPsLet there be Light... in Nigeria using PPPs
Let there be Light... in Nigeria using PPPs
 
Infra ppp corporate presentation jun2015en
Infra ppp corporate presentation jun2015enInfra ppp corporate presentation jun2015en
Infra ppp corporate presentation jun2015en
 
PPP around the World: Learning from the experience
PPP around the World: Learning from the experiencePPP around the World: Learning from the experience
PPP around the World: Learning from the experience
 
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdf
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdfRPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdf
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdf
 
SMART Infrastructure Business and Policy Dialogue Event: A private sector per...
SMART Infrastructure Business and Policy Dialogue Event: A private sector per...SMART Infrastructure Business and Policy Dialogue Event: A private sector per...
SMART Infrastructure Business and Policy Dialogue Event: A private sector per...
 

2nd annual canadian innovation in infra fin 2011

  • 1. Achieving better value, timeliness and accountability through Public-Private Partnerships 2nd Annual Federal Canada Innovation in Infrastructure Finance Forum PPP Canada October 30, 2012
  • 2. What is PPP Canada? •  A Federal Crown Corporation •  Reports to Parliament through the Minister of Finance •  Led by an accomplished private sector Board of Directors •  Partial Agent of the Crown Mandate •  To act as a source of expertise and advice on public-private partnership matters. •  To assess public private partnership opportunities at the federal level in accordance with criteria established by the Treasury Board. •  To advise on the execution of public-private partnership projects at the federal level. •  Manage the $1.2 billion P3 Canada Fund 2
  • 3. PPP Canada Value Proposition What and who we •  Knowledge and networks to capital know market participants and private and public sector P3 practitioners Project experience •  Practical and technical project experience Providing incentives •  P3 Canada Fund and support •  Project Development Fund 3
  • 4. Growing and Supporting a Pipeline of Federal P3s Supporting P3 Implementing Building business case Federal institutional development Screen frameworks 4
  • 5. Definition P3s are a long-term performance-based approach for procuring public infrastructure where the private sector assumes a major share of the responsibility in terms of risk and financing for the delivery and the performance of the infrastructure, from design and structural planning, to long-term maintenance. •  Integration of roles (Design, Build, Finance, Operate, Maintain); •  The provision of capital assets and associated services to meet a defined output specification (i.e., define what is required rather than how it is to be done); •  A transfer of risk to the private sector anchored with private sector capital at risk; •  Entered into by a competitive process. 5
  • 6. What is Not a P3 The following types of contractual arrangements ARE NOTARE NOT The following types of contractual arrangements examples of P3 arrangements: examples of P3 arrangements: –  privatization; –  joint ventures with the private sector; –  co-ownership with another public sector body; –  arrangements for the divestiture of federal assets where the private partner will become the new owner; –  design-build contracts; –  service-only contracts –  Sale/lease-back contracts; and –  lease-purchase contracts. 6
  • 7. How do P3s Work? Contractual relationship between public sector and private sector Payments based on performance Private sector puts money at risk 7
  • 8. The Federal Screen • The purpose of the P3 Screen isis to raise the level of The purpose of the P3 Screen to raise the level of awareness and consideration of P3s inin the federal awareness and consideration of P3s the federal investment planning process. investment planning process. •  It is a consistent and systematic approach for assessing the P3 suitability of capital investments. •  The screen supports the efficient use of analytical resources by ensuring that investments with limited P3 suitability do not needlessly consider the P3 option. 8
  • 9. What Types of Projects? Larger, more complex projects Outcomes / outputs can be specified and are stable Market interest / capacity User fees not a driver or necessity for P3s but can broaden scope 9
  • 10. PPP Canada’s Screening Matrix •  The P3 Screening Matrix identifies whether an investment presents the right mix of traits to succeed as a P3. •  It asks the user to consider 14 questions on a scale of indicators from 1 to 5. •  The user considers the question in the context of their proposed investment and identifies the best indicator that best aligns with their assessment. •  The user also provides a complete rationale for their rating. •  The user’s scores will be modified by a weighting factor that reflects the relative importance of that criterion in determining P3 suitability. 10
  • 11. Interpreting Screening Results Green •  Indicates that the P3 option should be included in the Procurement Option Analysis or Business Case to be developed for the investment Yellow •  Indicates that the investment presents a mix of favorable and unfavorable indicators for P3 delivery Red •  Indicates the P3 option should not be retained for further analysis 11
  • 12. A Word on the Screening Result The accuracy of these results is a function of the degree of definition and the current state of planning around the investment – clearer definition and greater understanding of the investment will provide better screening results. There is no one overwhelming indicator of P3 suitability. 12
  • 13. My Asset has P3 Potential: What Now? Assessing P3 potential is only the first step in a larger analytical process that concludes with a recommendation on the optimal approach to procurement. A positive screening outcome signals that the P3 option must be included the broader Options Analysis for the investment. Life-cycle options analysis is a long-standing requirement of Treasury Board policy. PPP Canada is developing tools and methodologies for supporting these subsequent phases of analysis as well as the procurement phase. 13
  • 14. 100, Queen Street, Suite 630 Ottawa, Ontario K1P 1J9 Canada Telephone: (613) 947-9480 Fax: (613) 947-2289 Toll Free Telephone: 877-947-9480 Email: info@p3canada.ca Website: www.p3canada.ca
  • 15. Budget 2011 and Federal Public-Private Partnerships Office of the Comptroller General Treasury Board of Canada Secretariat October 30th 2012
  • 16. Overview •  Budget 2011 Screening requirements. •  Government of Canada real property asset portfolio and policy context. •  Implementation of Budget 2011 and next steps. 2
  • 17. Budget 2011 – P3 Screen for Large Investments in Infrastructure •  Mandatory P3 screening requirement when capital costs of the asset are $100M or more and the lifespan is at least 20 years. •  If the screen identifies a P3 as a viable option, the department is required to develop a P3 proposal in addition to other options. •  Departments to screen in consultation with PPP Canada. 3
  • 18. Government of Canada Real Property Portfolio •  Complex portfolio across large geographical area. •  Assets include a very broad range of resources ranging from land, office buildings, special purpose buildings (eg. laboratories) and engineering works and infrastructure (eg. bridges, roads). •  Total value of assets: approx. $57 Billion (2011). •  Current issues : –  Aging assets (particularly buildings and infrastructure, such as roads and bridges). –  Need to optimize scarce capital dollars. –  Need to use private sector innovation and financing. 4
  • 19. Government of Canada Real Property Inventory Buildings Properties •  29,929 domestic •  21,252 properties •  1,917 abroad •  40.7M (ha) domestic •  82% Crown owned •  1,100 (ha) abroad •  Major Custodians: •  95% Crown owned –  National Defence •  Major Custodians: −  Parks Canada –  Parks Canada Agency –  RCMP −  National Defence –  Public Works and −  Agriculture and Government Services Agri-Food –  Fisheries and Oceans −  Transport Canada 5
  • 20. Treasury Board Policy Instruments •  Relevant Treasury Board policies include: •  Policy Framework for the Management of Assets and Acquired Services •  Policy on Management of Real Property •  Policy on Management of Projects •  Policy on Investment Planning •  These policies govern the management of assets throughout their life cycle. 6 6
  • 21. Key Policy Principles •  Assets are only held to support a department’s delivery of program •  Value for money •  Stewardship •  Management strategies developed based on life cycle management principles •  Management decisions encourage innovation 7
  • 22. Treasury Board Policies and P3 –  P3s are a new tool for managing government infrastructure. –  TBS released a guideline for implementing Budget 2011 P3 requirements. –  TBS is working on further measures relating to the requirement to screen investments for their P3 viability. –  References are made to PPP Canada’s Screening Matrix. 8
  • 23. Federal P3s Going Forward •  Recent P3 agreements include: –  Royal Canadian Mounted Police ‘E’ division headquarters – 76,000m2 facility housing 2,700+ employees in British Columbia. –  Communications Security Establishment long term accommodation facility in Ottawa - 72,000m2 facility housing 2,000+ employees. •  Federal government is exploring new P3 opportunities: –  Detroit River International Crossing Project Bridge –  Champlain Bridge - Montreal 9
  • 24. Potential Benefits of P3s –  Risk transfer –  Private financing –  Upfront planning / Integration of life cycle phases into a single contract –  Innovation / output-based specifications –  Performance-based payments –  Quality of the asset at the end of its life cycle –  Cost, schedule and scope certainty 10
  • 25. Conclusions •  Given today’s fiscal climate and the challenges of managing a large and complex infrastructure portfolio, the Government of Canada is looking to alternative and innovative solutions. •  Treasury Board Secretariat is working closely with PPP Canada in ensuring value for money through P3s. 11
  • 26. Defence & Security Infrastructure Panel 2nd Annual Innovation in Infrastructure Finance Forum Moderator: Brian Budden, Senior Vice President, Plenary Group Panel: James Paul, President & CEO, Defence Construction Canada Wayne Sutherland, Director of Major Capital Projects, RCMP Rick Taylor, President, Balfour Beatty Capital October 30th, 2012
  • 27. Outline RCMP E CSEC – Driving Collaboration Military Housing Potential Canadian Applications 2
  • 28. RCMP E Project Overview »  Project Scope !  Design-Build-Finance-Maintain of a 76,000 m2 purpose-built facility to house the RCMP E Division Headquarters in the City of Surrey !  Project includes Facilities Management for the full 25 year term »  Project Approvals Process !  2003 Preliminary Project Approval, allowing for planning and land acquisition !  2005Purchase of Green Timbers site !  2007 Revised Preliminary Project Approval to proceed with P3-DBFM assuming value for money !  2008 Request for Qualifications and short list of top three consortia !  2009 Request for Proposal and formal evaluation !  2010 Effective Project Approval allowing for contract award and financial close 3
  • 29. RCMP E Project Overview »  Security Issues and Other Challenges !  Security Clearances for the key personnel on all three proponents in the RFP stage !  Physical Security requirements for spaces within the functional program !  Dealing with sanitized drawings and room names !  Dealing with security concerns without being prescriptive »  Procurement Process !  Designed to identify optimal balance between quality and cost through all phases of the Project (design, construction, services and maintenance) !  RFP stipulated a maximum price, carefully established to ensure VfM within existing budget limits and clearly communicated expectations to the Proponents !  Flexible request for proposals that enabled dialogue with proponents on optimal balance of public and private communications !  Agreed upon independent fairness monitor overseeing all collaborative meetings and RFI’s 4
  • 30. RCMP E Project Overview »  Lessons Learned !  The phased approach and additional upfront capital contributions by Canada allowed for the possibility of greater competition and facilitated greater financing options to Proponents !  Establishing an affordability ceiling likely improved an already highly competitive process that required each Proponent’s proposal to balance quality and cost while demonstrating how it most closely met the requirements of the Project Agreement !  Implement a process for the flow of information in advance of receiving RFIs, i.e. identify the individuals to have input into responses based on area of expertise and determine who will provide any oversight function (e.g. legal, technical, etc.) !  Prior to initial internal circulation of the TB submission, concurrence as to the appropriate legislative authority as well as the approvals being sought should be obtained from the Department of Justice legal counsel representing TBS, the department and client department !  Each Project Agreement and its related Schedules are project specific. Care should be taken to ensure that the Project Agreement is written to reflect the performance requirements of that particular project as well as reflects any pertinent legislative requirements 5
  • 31. RCMP E Project Overview »  Current Status !  Early Access to the Data Center and telecommunication closets in Sept 2012 !  Construction 98 % complete; scheduled Substantial Completion in December 2012 !  Ongoing work on deficiencies and commissioning !  Work ongoing with all proponents as part of the move in schedule !  Move in to be completed by April 2013 less than 3 years after commencement of construction 6
  • 32. Outline RCMP E CSEC – Driving Collaboration Military Housing Potential Canadian Applications 7
  • 33. Communications Services Establishment Canada Project Description: »  The Project entails the design, financing, construction and Size $867 million subsequent operations of an approximately 775,000 ft2 facility (the “Facility”) over a 42-month construction period. Located on a Financial January 2011 Crown-owned (approximately 36-hectare) greenfield site in Close Ottawa, Canada. To meet CSEC’s program requirements, the Facility will consist of a mix of general office space, special Substantial purpose spaces and a data centre and will include an July 2014 Completion approximately 800-stall parking garage. The Facility will be LEED Gold certified. Team PCL, HDR Architects/WZMH, Honeywell/HP »  At the completion of construction, the Plenary Properties team will Members be responsible for providing full-scope facilities management services (including both hard and soft services) as well as a 30-year IT Service Commitment, Security bundle of commodity IT services (such as email, printing and Challenges Requirements, Debtholder Restrictions computing). 8
  • 34. CSEC LTAP Timeline Collaboration, Innovation, and Flexibility Project Management Team Partnerships Fasken »  Through the collaborative Martineau DuMoulin LLP British Columbia approach CSEC/DCC was able to receive three different yet Fairness Monitor Deloitte Touche 1/2010 10/2010 Tohmatsu LLP Building-in- extremely viable RFP Issuedinnovative and 7/2010 Use Selection of Environmental IT/NET The Result Technical Bids Preferred Proponent Psychologist proposals that met the needs of9/2010 9/2009 all 11/2010 RFQ Issued Communications 7/2014 stakeholders andSecurity 6/2009 continued Financial Bids TB Approval Building Occupancy Date collaboration is achieving amazingFlexible, adaptable workspace 1.  Establishment Preliminary Project 1/2011 Canada Approval PMO Contract Award outcomes. Defence LTAP 2.  Collaborative space Authority Construction Canada every turn at Contract KWC Architect 3.  Ubiquitous IT Functional program 1/2008 1/2009 1/2010 1/2011 1/2012 1/2013 1/2014 August 2007 Wood Banani Various December 2014 11/2007 - 11/2008 Business Case 1/2009 - 1/2010 Department of Development of 4.  30+ Parizeau Inc. of performance years Bouthillette 2/2011 - 6/2014 Construction Period specialists National Defence Output Specs Infrastructure FoTenn 5.  On budget and on schedule Consulting Inc. P3 Advisors CSP Security Consulting The Attain Inc. Consultant Group Watson MacEwen Architects Federal Government LTAP – Owner’s Advocate Marshall & Murray Inc. 9
  • 35. Outline RCMP E CSEC – Driving Collaboration Military Housing Potential Canadian Applications 10
  • 36. ADF Single LEAP 2 »  33.5 year DBFM project for 3,015 accommodation »  Following construction phase of approx. 3 years units at 14 military bases across all Australian Plenary Living will provide a range of hard and soft mainland States FM services over a 30 year term including: »  Contract value +$1bn. Government counterparty is !  Preventative and reactive maintenance the Australian Department of Defence !  Concierge services and accommodation management »  Key project objective the provision of comfortable housing for single Military Personnel as a critical !  Housekeeping services (cleaning, waste management and linen/laundry services) element to the attraction and retention of high calibre Servicemen/women. !  Utilities management !  Pest control !  Grounds maintenance !  Lifecycle 11
  • 37. U.S. Military Housing Background »  Why did they take the P3 route? (These “Before” photos told a powerful story) »  In the early 1990s, U.S. DoD determined the following: !  Over 60% of DoD owned family housing was inadequate (180,000 of 300,000 units) !  If addressed using traditional funding, would require $20B and take 30 years !  Housing was not a core competency of the military services !  Quality of life was affecting ability to attract and retain service members »  Recognized private sector development and management expertise, benefits of competition, and ability to attract private financing »  Resulted in landmark legislation in 1996 Defense Authorization Bill 12
  • 38. U.S. Military Housing P3 Program »  Pilot projects initially, but expanded to 100% of domestic military bases Map represents Balfour Beatty portfolio only 13
  • 39. U.S. Military Housing Basic Deal Points »  50 year DBFOM; some with 25 year renewal options »  Demand risk assumed by private sector !  Focus on customer service and on more than just housing »  Most financed through capital markets »  Varied financial participation by DoD !  equity, subordinate debt, limited loan guarantees »  GMP Construction Contracts typical »  Joint review/approval of O&M budgets »  Lifecycle addressed through Recapitalization Account !  Different risk profile than traditional P3 !  Demand risk motivates private sector to perform !  Limited ability to influence revenue (rental income) changes !  No specific hand back requirements 14
  • 40. Outline RCMP E CSEC – Driving Collaboration Military Housing Potential Canadian Applications 15
  • 41. Potential Canadian Applications »  Future defence accommodation projects »  Base housing (following Australia's LEAP programs) »  Planes/vehicles (following the UK's refueling aircraft PFI) »  Research facilities and labs »  Ports, including major redevelopment projects »  Data centres »  Satellite infrastructure 16
  • 42. UNCLASSIFIED 1 A world-class workplace for a world-class workforce ! Federal!Canada!Infrastructure!Finance!Forum! 30!October!2012! A world-class workplace for a world-class workforce! Un milieu moderne à l appui d un effectif moderne ! Conceptual Rendering – Aerial View
  • 43. UNCLASSIFIED 2 Long;Term!Accommoda>on! (LTA)!Project!:! •  2000!Employees! •  2014!Occupancy!Date! Design!Build!Finance!Maintain! (DBFM)!contract!for!30!years! " includes:!   "Design"and"Construc1on"of"72,000rm2" LTAP"facility"" !  includes"a"4000m2"Data"Centre," 4500m2"PurposeABuilt" Engineering"Facility,"Top"Secret" Knowledge"Centre"" !  Separate"and"secure"Shipping" and"Receiving"Building"" !  Visitor"Centre"for"unclassified" visits" !  Power"Genera1on"Facility"to" accommodate"excep1onal" power"requirements" !  Parking"Structures"etc…" !  LEED"Gold"Accredita1on" required" A world-class workplace for a world-class workforce! Un milieu moderne à l appui d un effectif moderne ! A world-class workplace for a world-class workforce
  • 44. UNCLASSIFIED 3 IT!Infrastructure!! (What!is!included)! •  Data!Centres! –  Design,!build!and!operate! –  Space!management! •  Cooling! –  Provision!and!maintenance! •  Power! –  Provision!and!maintenance! –  Not!power!usage!cost! •  Flexibility! –  All!technical!services!that!support!the!office! automa>on!environment!! A world-class workplace for a world-class workforce! Un milieu moderne à l appui d un effectif moderne ! A world-class workplace for a world-class workforce
  • 45. UNCLASSIFIED 4 IT!Infrastructure! Specifics! ! Network" –  Telephony" –  Network" –  Network"Security" –  Remote"Access" •  End"User" –  Compu1ng"&" Engineering" –  Prin1ng" –  EAmail" •  IT"Tools"&"Processes" –  Professionally"managed" data"centre" –  IT"Help"Desk" •  Development"&"Test" Environment" •  Technical"Infrastructure" A world-class workplace for a world-class workforce! Un milieu moderne à l appui d un effectif moderne ! A world-class workplace for a world-class workforce
  • 46. UNCLASSIFIED 5 Mi>ga>ng!30!years…! ! •  Key!Performance!Indicators! –  Availability"schedule" –  Deduc1ons" " •  IT!Joint!Technical!Review"" –  capacity"requirements,"technical"requirements,"hardware,"soYware""&"innova1on" –  Deduc1ons"applicable"for"missing"performance"indicators" –  IT"Unavailability"Event"deduc1ons" " •  Benchmarking! –  First"benchmark"3rd"anniversary"of"Service"Commencement"Date" –  Every"5th"anniversary"of"the"last"benchmark"date"for"IT"Services" –  Provisions"established"so"that"original"prices"are"based"on"reasonableness"and" due"diligence" –  Crown"rights"of"audit"rela1ng"to"costs,"overheads"and"margins"of"IT"provider" guaranteed." A world-class workplace for a world-class workforce! Un milieu moderne à l appui d un effectif moderne ! A world-class workplace for a world-class workforce
  • 47. PUBLIC PRIVATE PARTNERSHIPS OPPORTUNITIES IN IT PROCUREMENT -A PRIVATE SECTOR PERSPECTIVE Sherry Casey Vice President, Industry Sales HP Enterprise Services October 30, 2012 © 2011 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice.
  • 48. THE P3 AND IT - A POINT OF INFLECTION & REFLECTION 2
  • 49. TRADITIONAL IM/IT PROCUREMENTS ARE NO LONGER ADEQUATE Service delivery organization's business challenges are increasingly relying on the IM/IT infrastructure for: •  Enterprise solutions, horizontal integrated services across levels of government •  Protection against cyber security attacks, privacy violations •  Promoting “Open Government” initiatives •  Standardized, streamlined and more affordable IM/IT •  Self service delivery models, mobile solutions •  Services anywhere and anytime •  Greater use of social media in support of service delivery & democracy •  Desire for adaptable, scalable, responsive solutions
  • 50. P3’S LEVERAGE STRATEGIC BUSINESS VALUE OVER TRADITIONAL OUTSOURCING 1.  Capability based, highly collaborative, iterative procurements - can be quickly refined into “contractible” frameworks 2.  Strong Executive Governance for a shared commitment for relentless focus on horizontal business outcomes and timely problem resolution 3.  Financing requirements, penalty structures & duration of agreements catapults requirements to industrial strength, proven suppliers 4.  Government funding cycle constraints for capital & operational funding are removed, flow of government payment streams can be normalized 5.  Risk transfer to private sector with rewards for continued long term performance drives improved agility and business outcome focus 6.  Business outcome focus also builds-in supplier motivation for innovation and continuous improvement once base infrastructure in place
  • 51. CONSIDERATIONS UNIQUE TO IM/IT P3 VERSUS TRADITIONAL BRICK & MORTAR P3 1.  Special IM/IT terms and conditions (Protection of IP, nature of commercial business software & applications, desire to appropriately limit liability plus others) 2.  IM/IT infrastructure is constantly evolving and P3 supplier cannot dictate or control the technology roadmaps for implemented solutions 3.  Usually dealing with an installed base of products and solutions 4.  Usually difficult to have accurate picture of the assets as not visible & asset management is often weak 5.  High level of interdependency between various IM/IT infrastructure elements to be understood & managed, etc 5
  • 52. TRANSFERABLE PRECURSORS FOR SUCCESS, LESSONS LEARNED & BODY OF BEST PRACTICES EXISTS What is known about complex IM/IT procurement is readily transferable to the P3 procurement A few examples: –  Criticality of the relationship between suppliers and clients –  IM/IT supplier should have a front seat early in the procurement; discussions and continually throughout the P3 duration – communication is key –  Significant due diligence within IM/IT companies is to be expected with regard to financing and internal approvals in pursing these types of ventures –  A certain amount of flexibility within the contracting framework is required and a willingness to address constraints for mutual resolution –  Strong governance and executive leadership is paramount –  Change management, focus on innovation
  • 54. MGS – New Data Centre Pioneering risk allocation in government data centre projects in Canada. Setting the stage for IT risk transfer. October 2012
  • 55. Project Overview !  New Government of Ontario data centre !  Located in Guelph, Ontario !  225,000 ft2 !  First Canadian data centre to be procured as an Alternative Financing and Procurement (“AFP”) !  Reached Financial Close in 2008, delivered on time and on budget in 2010 !  Critical environment for the government !  Tier IV highly redundant– only PPP data centre in the world to reach this classification !  Green Design: certified LEED Gold certified despite massive energy requirements 2
  • 57. Risk Allocation !  Design/construction, financial and operations risks were largely transferred to Plenary Properties. !  Specifications were prescriptive in performance outcomes: "  Specifications set standards not methods "  We were able to innovate within these parameters "  Tier IV was a critical in the design philosophy – this set the higher standard !  Key construction risks included price certainty, scheduling and delays, permitting, M&E, financing, commissioning and transition to new facility. 4
  • 58. Risk Allocation !  Key operational term risks include facilities maintenance (including lifecycle renewal), meeting Tier IV operational standards, facility availability, power supply, energy and labour costs. !  Key risks retained by the government were: planning, changes in law, pre- existing site contamination, public-sector initiated scope-change, force majeure (shared risk). !  The Ontario government provides client side IT – i.e. all servers, hardware etc. that run within the critical environment 5
  • 59. Project Cost and Payment !  $352 million net present value (“NPV”) over 32 years !  The AFP approach saved the taxpayer an estimated $64.2 million (14.3%) over the 30 year life of the facility !  $50 million substantial completion payment to reduce the cost of private financing !  Annual availability stream payable each year for 30 years (paid on a monthly basis), including partial inflation indexation at an estimated 2 per cent per year, subject to certain adjustments for benchmarking, market testing and inflation changes. !  Severe abatements for performance failures 6
  • 60. Summary !  DBFM ensured an integrated approach to the whole life delivery of the critical environment !  Risk transfer can be substantial and managed by the private sector !  Level of IT transfer can be determined by the client to meet their specific requirements !  Significant value for money realized for the client 7