Planning
- 1. Sequence of fabrication Date
Sr. Truss Action plan Duration Start Finish Manpower Tools & M/C EngineerRemarks Notes Activity Remarks Notes
1 B5 Fixtures Mr Dalip 08148440515
Drg/ ok Drg. Observation3/6 seg. Rdy for GW<--
2 B4 Fixtures-> gateway Md Safi Area marking Insp done
GW Due+profile pipe
3 BB3 Bend truss Md Safi Sizing awtd??
4 Cross Fixtures Mr RopeshAdd/ arg. Indenting Ready for Inspection
5 V.Col Fit up/ SAW?? Mr Lalit BOQ/BOM Centre punch required
Slot hole not
6 Perlin continue process Mr Subram Sch of Sequenceacceptable
Tool & M/C
Manpower
Plan/ Gradation
Quantity X Time
Marking QC/Gway
Cutting QC/Gway
Grinding QC/Gway
Fit-Up QC/Gway
- 3. Sequence of execution planning
Sr. No. Name of truss Segments, components and fixture, D.0.Start D.O.Finish
1 Main truss grid 3 'B' Side