SlideShare a Scribd company logo
1 of 25
Experimental Investigation on Energy
Efficiency of Electrical Utilities in
Process Industries through Standard
Energy Conservation Practices

Vyas Pareshkumar A,
Bhale Purnanad V.
1
INTRODUCTION
•
•

•
•
•
•
•

Surat textile cluster - @ 400 industries
Annual electricity consumption is 726 GWh,Gas consumption is 315
million SCM & Coal consumption is 2.3 million tones
i.e. 1.2 million TOE (tons of oil equivalents) of energy use.
Overall energy saving potential is 1.5 lakh TOE
Electrical and Thermal energy cost is 12 to 15 % of manufacturing
Cost.
Small And Medium Enterprise (SME’s) sector is characterised by
the use of outdated technologies.
As per BEE’s Study for SME Overall energy saving potential is @
72432 TOE i.e. 27.4 % of total energy consumption in SME’s
As an individual the SME’s may not have significant effect on
environment and resource use, but together they exert a substantial
effect.
2
Instruments used:
• Electrical Portable Load Manager ALM 10
• Hand held Ultrasonic flow meter
Focus area:
• Air compressor system
• Centrifugal pumping system
Energy Audit Activity:
• Pre audit meeting
• Familiarisation with manufacturing process and energy consuming
machineries
• Review of manuals,maintenace records
• Verification of calibration status of instruments, installation of
measuring instruments or other facilities
3
PROCESS DIAGRAM
Grey Cloth

Jet M/c

Rotary M/c

Loop M/c

(Raw Material)

(Dyeing)

(Printing Process)

(Drying & Color setting)

Stenter

(Heat setting)

Zero -Zero
Folding
Washing

Hydro
Packing

4
WATER DISTRIBUTION SYSTEM

Bore well

Overhead tank

Supply pump

Stenter M/c

Colour kitchen

Jet M/c

Rotary M/c

Drums ,zero-zero M/c

Printing M/c

Padding M/c

Office use
5
AIR DISTRIBUTION SYSTEM

Compressor 1

Stenter M/c

Compressor 2

Printing M/c

Rotary & Loop M/c

Compressor 3

Padding M/c

Jet M/c

Drum M/c
6
ENERGY AUDIT ACTIVITY

Air compressor & Centrifugal pumping system :
Following data are collected with measuring instruments and
calculations were made for Efficiency and Percentage air leakage.
•
•
•
•
•
•
•

Input voltage,current,power factor – Measured with portable load
analyser
Running hours – Installed Running hour meter
Tank volume - measured and compared with available data
Discharge air pressure – Measured with calibrated pressure gauge
Actual tank filling time – Measured with calibrated stop watch
Actual head – measured with calibrated pressure gauge
Actual discharge – measured with Ultrasonic flow meter

7
SNAPS

Modification of air distribution network & Installation of PID controller

8
Installation of Auto moisture drain & Setting of new discharge set points

9
AIR LEAKAGE TEST
T on Average on time (T)
min

=

38

T off Average Off Time (t)
min

=

28

% Air leakage

=

Annual cost of power for
comp. no 3 (Rs)

=

Unit rate× Annual power cons.

=

5.50 ×(674.3 × 26 × 12)

=

1157098

Annual power loss due to
leakages (Rs)

=

Annual power cost × % Air
leakage

=

666257

Power can be saved by
plugging leakage in %

=

75%
=

499693

=

1.2

Annual saving by leakage
prevention(Rs)

57.58

T/(T+ t) × 100

Power saved by plugging 75 %
leakage

Investment required in
plugging leakages (Rs)

=

50000

Payback in months

=

(Investment × 12) / savings

10
VOLUMETRIC EFFICIENCY MEASUREMENT
COMPRESSOR NO.

=

1

2

3

Hp

=

40

30

40

Motor RPM

=

1440

1440

1440

Voltage

=

410

412

414

Current

=

43

35

45

Power Factor

=

0.95

0.95

0.95

Power consumption per hour

=

[√3 x V x I x COSΦ]

=

29.01

23.73

30.65

Average working hrs

=

24

12

22

Compressor RPM

=

1440

1440

1440

4.4

2.94

5.4

1.076

1.076

1.076

Compressor
(m3/min)
Tank Volume (m3)

Capacity =
=

11
Air pressure (Kg/cm2)

=

6

Total air volume (m3)

=

(Tank Volume × Air Pressure)

=

6.456

7.532

4.304

Actual Tank filling time (Sec)

=

105

162

52

Actual air generation (m3/min)

=

(Total Air Volume ÷ Actual Tank Filling Time) × 60

=

3.69

=

(Total Air Volume ÷ Compressor Capacity) × 60

=

88.04

=

(Actual air generation ÷ Compressor Capacity) × 100

=

83.84

Required tank filling time (sec)
% Efficiency

Existing specific power =
consumption (m3/min per kWh)
=

7

2.79
153.71
94.89

4

4.97
47.82
91.97

Actual air generation ÷ power consumption per hour

0.127

0.118

0.162
12
Proposed
specific
power =
3
consumption. (m /min per kWh)

compressor capacity ÷ Power consumption per
hour

=

0.152

=

(100-eff/100) × power consumption per hr × avg.
working hrs

=

112.48

=

Power loss per day (kWh) × cost of power (Rs)

=

618.62

80.09

298.00

Annual power loss (Rs)

=

193011

24989

92975

Investment (Rs)

=

20000

0

0

Payback in months

=

(Investment (Rs) x 12 ) ÷ (Annual power loss (Rs))

=

1.24

Power loss per day (kWh)

Power loss per day ( Rs)

0.124

14.56

0

0.176

54.18

0
13
CENTRIFUGAL PUMPING SYSTEM
SNAPS :

OLD PUMP 1
OLD PUMP 2

OLD PUMP 3
NEW PUMP IN
SUMP SUMP
SUMP

OLD PUMP 1
NEW PUMP
OLD PUMP 2

Set up of old and new transfer and supply pump

14
Transfer pump
•
•
•
•
•
•
•
•
•
•
•
•
•
•

Pump No.
Rated motor efficiency
Hp
RPM
Measured voltage
Measured current
Existing pump running hours
Calculated input kW / hr
[√3 x V x I x cosΦ]
Pump input kW / hr
Actual head (m)
Measured flow (m3/hr)
PROPOSED FLOW(m3)=
AFTER UNIT / HR
AFTER WORKING HR

=
=
=
=
=
=
=

1
0.8
10
2800
409
14
2

2
0.8
10
2800
408
10.3
14

3
0.8
10
2800
407
10.2
24

=
9.8
7.2
7.1
= calculated input kW / hr × rated motor eff.
=
=
=
115
=
=

7.85
24
48

5.76
24
38

5.69
24
25

11
11
15
Present water discharge per day

= measured flow (m3/hr) × existing pump running
hrs
= 96

Existing pump efficiency (%)

532

600

= 0.4

0.431

0.286

Hydraulic power = Q (m3/s) × Total head, hd - hs (m) × Density (kg/m3) × g (m2/s) ÷ 1000
Electrical input power = Pump shaft power ÷ Motor efficiency
Pump shaft power = Hydraulic power ÷ Pump efficiency
Proposed
minimum
efficiency (%)

pump = 0.7

Existing overall efficiency (%)

= existing pump efficiency × rated motor efficiency
= 0.32

Proposed overall efficiency (%)

0.34

0.23

= Proposed minimum pump efficiency × Rated
motor efficiency
= 0.56

Existing specific power
consumption (m3/kW)

= (measured flow m3) ÷ calculated input kW / hr
= 4.89

5.27

3.51

16
Existing unit consumption = calculated input kW / hr × existing pump running hrs
per day
= 19.64
Total unit consumption

100.88

170.84

= 19.60 +100.94 +171.36 = 291.36

Afterunit consumption/day = after unit kW/hr × after pump running hrs
(single pump)
= 121
Saving in unit/day

= 291.36 – 121 = 170.36

Saving achieved per day = Saving in unit/day × Price per unit (Rs)
(Rs)
= 170.36 X 5.5

= 936.96

Annual Saving (Rs)

= 936.96 × 26 ×12 =
292332.70

Investment required (Rs)

= 35000

Payback in months

= (Investment required (Rs) × 12 ) ÷ Saving per year
= 1.44
17
RESULTS AND DISCUSSION

Air compressor system :
• Three nos. Air compressors
• PID controller is installed and different air pressure setting is set.
• Air distribution network rearranged.
• Automatic moisture drain valve installed
• Air leakages arrested.
Centrifugal Pumping system :
• Instead of Three nos 10 hp ; 24 meter head; Different discharge
capacity Transfer pump, One Single Energy efficient 10 hp;20 meter
head;100 m3/hr capacity pump installed.
• Instead of Two nos 10 hp ; 22 meter head; Different discharge
capacity Supply pump, One Single Energy efficient 3 hp;6 meter
head;100 m3/hr capacity pump installed.

18
Description

hp

m3/min

Air
compressor
#1

40

4.4

83.84

Air
compressor
#2

30

2.94

Air
compressor
#3

40

5.4

Energy-Saving
Measures

%
volumetric
efficiency

Annual
power loss
( Rs)

Investment
required (Rs)

7.62

193011

20000

1.24

94.89

7.08

24989

0

0

91.97

9.72

92975

0

0

Investment (Rs)

Specific
power
consumption
(kwh/m3)

Annual Savings
(Rs)

Simple Payback
Period (Months)

Pay back
period
(months)

Expected Lifetime
(operating hours)

Improve Efficiency
of Compressor #. 1

20000

193011

1.24

14400

Stop Air Leakages
in Department.

50000

499693

1.20

Req. Regular
Maintaince

Total

70000

692704

19
CENTRIFUGAL PUMPING SYSTEM
Transfer pump :

Descripti
on

hp

Head
(meter)

Flow
(m3/hr)

Current
(amp)

Input
kW/hr

% Efficiency % overall
Efficiency

Transfer
pump # 1

10

24

48

14

7.85

40.0

32

Transfer
pump # 2

10

24

38

10.3

5.76

43.1

34

Transfer
pump # 3

10

24

25

10.2

5.69

28.6

23

Energy saving
measure

Investment
(Rs)

Annual savings
(Rs)

Simple
Payback

Expected
lifetime
(operating hrs)

Replace Transfer
pump 1,2 and 3by
single Energy
efficient pump

35000

292332

1.44

14400

Total

35000

292332
20
Supply pump
Descripti
on

hp

Head
(meter)

Flow
(m3/hr)

Current
(amp)

Input
kW/hr

%
Efficiency

% overall
Efficiency

Supply
pump # 1

10

22

42

10.5

5.26

50

40

Supply
pump # 2

10

22

45

10.2

5.13

55

44

Energy saving
measure

Investment
(Rs)

Annual savings
(Rs)

Simple
Payback

Expected
lifetime
(operating hrs)

Replace supply
pump 1 and 2 by
single Energy
efficient pump

30000

230000

1.57

14400

Total

30000

230000

21
SUMMARY OF IMPLEMENTED RESULTS
Steps taken

Saving In
Units
(kWh /
Year

Actual
investment
(Rs)

Energy cost
saving per year
(Rs)

Pay back
(month)

Single Energy efficient
pump of 3 HP ; 6 meter
head ; 100 m3/hr discharge
capacity is installed (supply
pump)

41817

30000

230000

1.57

Single mono sub pump of
10 hp ;20 meter head ;100
m3/hr discharge capacity is
installed (transfer pump)

53152

35000

292332

1.44

PID controller is installed;
Different air pressure
setting is set for three
different compressors. Air
line network rearranged
(common header )
Automatic moisture drain
valve also installed

134400

180000

821338

2.67

Total

229369

245000

1343670

22
REFERENCES

[1]

http://www.business-standard.com/india/news/energy-effeciency-plan-for-sm
[2] Guide book for National Certification Examination for Energy Managers
and Auditors. “General aspects of energy management and audit.
www.beeindia.nic.in
[3] Kapur, Shilpi , Plannet Earth , Fiscal reforms, SMEs'hope , Date: 10
October 2011, http://www.teriin.org/index.php?
option=com_featurearticle&task
[4] Ali,Hasanbeigi ,China Energy Group,Energy Analysis Department,
Environmental Energy Technologies Division “energy- efficiency
improvement opportunities for the textile industry”,E.O. Lawrence
Berkeley National Laboratory,Washington, DC Resource Dynamics
Corporation
[5] Facts air distribution,”druckluft effizient’,07 compressed air
facts,www.druckluft-effizient.de.
[6] Kaya D, Phelan P, Chau D, Sarac HI. Energy conservation in
compressed-air systems. International Journal of Energy Research
2002;26:837–49.

23
[7] Galitsky C, Worrell E. Energy efficiency improvement and cost saving
opportunities for the vehicle assembly industry. Lawrence Berkeley
National Laboratory 2008 [LBNL-50939-Revision].
[8] U.S. DOE. Minimize compressed air leaks; 2010, Available online at:
http://www.energystar.gov/ia/business/industry/compressed_air3.pdf
[Accessed:24.09.11].
[9] Saidur R, Rahim NA, Hasanuzzaman M. A review on compressed-air
energy use and energy savings. Renewable and Sustainable Energy
Reviews 2010;14:1135–53
[10] PS (Plant Support). Compressed air ultrasonic leak detection guide;
2010,Available online at:
http://www.plantsupport.com/download/UCAGuide.pdf[Accessed
24.09.11].

24
It is never too late to practice energy
modesty and efficiency otherwise …
Year 1900

Year 1800

Year 2000

Year 2050

Year 2020

25

More Related Content

What's hot

Energy audit & conservation studies for industries
Energy audit & conservation studies for industriesEnergy audit & conservation studies for industries
Energy audit & conservation studies for industriesravindradatar
 
Energy conservation Opportunities - Offices
Energy conservation Opportunities - OfficesEnergy conservation Opportunities - Offices
Energy conservation Opportunities - Officesravindradatar
 
Energy management techniques
Energy management techniquesEnergy management techniques
Energy management techniquesJerin Antony
 
Total cost of ownership of transformers
Total cost of ownership of transformersTotal cost of ownership of transformers
Total cost of ownership of transformersLeonardo ENERGY
 
ongc project ppt
ongc project pptongc project ppt
ongc project pptAditya Oak
 
Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)ravindradatar
 
A case study on heat exchnage network
A case study on heat exchnage networkA case study on heat exchnage network
A case study on heat exchnage networkeSAT Journals
 
Method for-increasing-energy-efficiency-in-flexible-manufacturing
Method for-increasing-energy-efficiency-in-flexible-manufacturingMethod for-increasing-energy-efficiency-in-flexible-manufacturing
Method for-increasing-energy-efficiency-in-flexible-manufacturingafaq Shaheen
 
Analytics Project - Combined Cycle Power Plant
Analytics Project  - Combined Cycle Power PlantAnalytics Project  - Combined Cycle Power Plant
Analytics Project - Combined Cycle Power PlantJyothi Lakshmi
 
IRJET- Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...
IRJET-	 Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...IRJET-	 Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...
IRJET- Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...IRJET Journal
 
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...Global CCS Institute
 
OPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICS
OPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICSOPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICS
OPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICSijmech
 
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET Journal
 
final presentation of my INTERN
final presentation of my INTERNfinal presentation of my INTERN
final presentation of my INTERNShahina Supriti
 
Integrated Air Conditioning Unit for Automobiles
Integrated Air Conditioning Unit for AutomobilesIntegrated Air Conditioning Unit for Automobiles
Integrated Air Conditioning Unit for AutomobilesIJARTES
 
Sq 4.6 - fans and blowers (table format)
Sq   4.6 - fans and blowers (table format)Sq   4.6 - fans and blowers (table format)
Sq 4.6 - fans and blowers (table format)Murad Eltaher
 
A Study on Energy Audit of a Cold Storage
A Study on Energy Audit of a Cold StorageA Study on Energy Audit of a Cold Storage
A Study on Energy Audit of a Cold StorageIJERA Editor
 
Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...
Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...
Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...Antea Group
 

What's hot (20)

Energy audit & conservation studies for industries
Energy audit & conservation studies for industriesEnergy audit & conservation studies for industries
Energy audit & conservation studies for industries
 
Energy conservation Opportunities - Offices
Energy conservation Opportunities - OfficesEnergy conservation Opportunities - Offices
Energy conservation Opportunities - Offices
 
Energy management techniques
Energy management techniquesEnergy management techniques
Energy management techniques
 
Total cost of ownership of transformers
Total cost of ownership of transformersTotal cost of ownership of transformers
Total cost of ownership of transformers
 
ongc project ppt
ongc project pptongc project ppt
ongc project ppt
 
Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)
 
A case study on heat exchnage network
A case study on heat exchnage networkA case study on heat exchnage network
A case study on heat exchnage network
 
Power Cycles
Power CyclesPower Cycles
Power Cycles
 
Method for-increasing-energy-efficiency-in-flexible-manufacturing
Method for-increasing-energy-efficiency-in-flexible-manufacturingMethod for-increasing-energy-efficiency-in-flexible-manufacturing
Method for-increasing-energy-efficiency-in-flexible-manufacturing
 
energy audits
energy auditsenergy audits
energy audits
 
Analytics Project - Combined Cycle Power Plant
Analytics Project  - Combined Cycle Power PlantAnalytics Project  - Combined Cycle Power Plant
Analytics Project - Combined Cycle Power Plant
 
IRJET- Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...
IRJET-	 Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...IRJET-	 Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...
IRJET- Energy and Exergy Analysis of Multiple Extraction Cum Condensing Stea...
 
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
 
OPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICS
OPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICSOPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICS
OPTIMIZATION OF AN OPEN CYCLE GAS TURBINE POWER PLANT USING EXERGOECONOMICS
 
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration PlantIRJET-Detailed Energy Audit in a Captive Cogeneration Plant
IRJET-Detailed Energy Audit in a Captive Cogeneration Plant
 
final presentation of my INTERN
final presentation of my INTERNfinal presentation of my INTERN
final presentation of my INTERN
 
Integrated Air Conditioning Unit for Automobiles
Integrated Air Conditioning Unit for AutomobilesIntegrated Air Conditioning Unit for Automobiles
Integrated Air Conditioning Unit for Automobiles
 
Sq 4.6 - fans and blowers (table format)
Sq   4.6 - fans and blowers (table format)Sq   4.6 - fans and blowers (table format)
Sq 4.6 - fans and blowers (table format)
 
A Study on Energy Audit of a Cold Storage
A Study on Energy Audit of a Cold StorageA Study on Energy Audit of a Cold Storage
A Study on Energy Audit of a Cold Storage
 
Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...
Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...
Overview of a Strategy to Exempt Multiple Process Heaters from the “Boiler MA...
 

Viewers also liked

Viewers also liked (7)

Sales kit Brochure
Sales kit Brochure Sales kit Brochure
Sales kit Brochure
 
Interface result set
Interface result setInterface result set
Interface result set
 
374 sagar
374 sagar374 sagar
374 sagar
 
Talents Affinity - Fuel your company with Talents Innovation
Talents Affinity - Fuel your company with Talents InnovationTalents Affinity - Fuel your company with Talents Innovation
Talents Affinity - Fuel your company with Talents Innovation
 
Metro Rail and the City
Metro Rail and the CityMetro Rail and the City
Metro Rail and the City
 
Todd Snyder's Provisionalization Technique طريقة لصنع التعويض المؤقت
Todd Snyder's Provisionalization Technique طريقة لصنع التعويض المؤقت Todd Snyder's Provisionalization Technique طريقة لصنع التعويض المؤقت
Todd Snyder's Provisionalization Technique طريقة لصنع التعويض المؤقت
 
Ingilis dili 3 bos_feteliyeva gunay ikram
Ingilis dili 3 bos_feteliyeva gunay ikramIngilis dili 3 bos_feteliyeva gunay ikram
Ingilis dili 3 bos_feteliyeva gunay ikram
 

Similar to 106 pareshkumar

Industrial energy-saving
Industrial energy-savingIndustrial energy-saving
Industrial energy-savingsachindesai055
 
Analysis and optimization of mechanical utility system
Analysis and optimization of mechanical utility systemAnalysis and optimization of mechanical utility system
Analysis and optimization of mechanical utility systemeSAT Journals
 
OPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDY
OPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDYOPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDY
OPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDYvishal laddha
 
Electricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use EfficiencyElectricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use Efficiencyeecfncci
 
Electricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiencyElectricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiencyeecfncci
 
Analysis and Optimization of Mechanical Utility System
Analysis and Optimization of Mechanical Utility SystemAnalysis and Optimization of Mechanical Utility System
Analysis and Optimization of Mechanical Utility SystemDeeptej Kolambkar
 
Manufacturing cost estimation
Manufacturing cost estimationManufacturing cost estimation
Manufacturing cost estimationvineethgoud6
 
Energy Savings with Variable Frequency Drives
Energy Savings with Variable Frequency DrivesEnergy Savings with Variable Frequency Drives
Energy Savings with Variable Frequency DrivesAzizah Kassim
 
SIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial Motor
SIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial MotorSIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial Motor
SIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial MotorColin Koh (許国仁)
 
Benefit of Variable Speed Unit.pptx
Benefit of Variable Speed Unit.pptxBenefit of Variable Speed Unit.pptx
Benefit of Variable Speed Unit.pptxAmirulHadi17
 
EPC+Energy audit of reliance infrastructure
EPC+Energy audit of reliance infrastructureEPC+Energy audit of reliance infrastructure
EPC+Energy audit of reliance infrastructureNisheeth Srivastava
 
How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%Schneider Electric
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Ray Beebe
 
CENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdfCENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdfeldoctol
 
CENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdfCENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdfeldoctol
 
Energy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and managementEnergy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and managementkiranpatilsjce
 

Similar to 106 pareshkumar (20)

Industrial energy-saving
Industrial energy-savingIndustrial energy-saving
Industrial energy-saving
 
Analysis and optimization of mechanical utility system
Analysis and optimization of mechanical utility systemAnalysis and optimization of mechanical utility system
Analysis and optimization of mechanical utility system
 
OPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDY
OPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDYOPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDY
OPTIMIZATION OF COMPRESSED AIR IN THERMAL POWER PLANT-A NOVEL STUDY
 
Electricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use EfficiencyElectricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use Efficiency
 
Electricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiencyElectricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiency
 
Air Compressors
Air CompressorsAir Compressors
Air Compressors
 
Analysis and Optimization of Mechanical Utility System
Analysis and Optimization of Mechanical Utility SystemAnalysis and Optimization of Mechanical Utility System
Analysis and Optimization of Mechanical Utility System
 
Manufacturing cost estimation
Manufacturing cost estimationManufacturing cost estimation
Manufacturing cost estimation
 
LEAKAGE MANAGEMENT SOLUTIONS
LEAKAGE MANAGEMENT SOLUTIONSLEAKAGE MANAGEMENT SOLUTIONS
LEAKAGE MANAGEMENT SOLUTIONS
 
Energy Savings with Variable Frequency Drives
Energy Savings with Variable Frequency DrivesEnergy Savings with Variable Frequency Drives
Energy Savings with Variable Frequency Drives
 
SIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial Motor
SIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial MotorSIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial Motor
SIMTech SMC 2013 Manufacturing Energy Efficiency : Industrial Motor
 
Benefit of Variable Speed Unit.pptx
Benefit of Variable Speed Unit.pptxBenefit of Variable Speed Unit.pptx
Benefit of Variable Speed Unit.pptx
 
EPC+Energy audit of reliance infrastructure
EPC+Energy audit of reliance infrastructureEPC+Energy audit of reliance infrastructure
EPC+Energy audit of reliance infrastructure
 
DG
DGDG
DG
 
How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014
 
Bombas Centrifugas
Bombas Centrifugas Bombas Centrifugas
Bombas Centrifugas
 
CENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdfCENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdf
 
CENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdfCENTRIFUGAL PUMPS.pdf
CENTRIFUGAL PUMPS.pdf
 
Energy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and managementEnergy auditing, monitoring& targeting, and management
Energy auditing, monitoring& targeting, and management
 

More from 4th International Conference on Advances in Energy Research (ICAER) 2013

More from 4th International Conference on Advances in Energy Research (ICAER) 2013 (20)

329 Kandavel
329 Kandavel329 Kandavel
329 Kandavel
 
260 prashant
260 prashant260 prashant
260 prashant
 
236 rakhi
236 rakhi236 rakhi
236 rakhi
 
103 sudhir
103 sudhir103 sudhir
103 sudhir
 
84 padmini
84 padmini84 padmini
84 padmini
 
360 j. deshpande
360 j. deshpande360 j. deshpande
360 j. deshpande
 
195 b.m. sudaroli
195 b.m. sudaroli195 b.m. sudaroli
195 b.m. sudaroli
 
178 dp & ts
178 dp & ts178 dp & ts
178 dp & ts
 
90 a. kaur
90 a. kaur90 a. kaur
90 a. kaur
 
215 k rahul sharma
215 k rahul sharma215 k rahul sharma
215 k rahul sharma
 
36 sarang
36 sarang36 sarang
36 sarang
 
001 pvthakre
001 pvthakre001 pvthakre
001 pvthakre
 
51 murthy
51 murthy51 murthy
51 murthy
 
302 swapan
302 swapan302 swapan
302 swapan
 
28 saket
28 saket28 saket
28 saket
 
212 aparna
212 aparna212 aparna
212 aparna
 
315 devendra
315 devendra315 devendra
315 devendra
 
303 piyush
303 piyush303 piyush
303 piyush
 
275 pattanaik
275 pattanaik275 pattanaik
275 pattanaik
 
131 sorate
131 sorate131 sorate
131 sorate
 

Recently uploaded

Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 

Recently uploaded (20)

Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 

106 pareshkumar

  • 1. Experimental Investigation on Energy Efficiency of Electrical Utilities in Process Industries through Standard Energy Conservation Practices Vyas Pareshkumar A, Bhale Purnanad V. 1
  • 2. INTRODUCTION • • • • • • • Surat textile cluster - @ 400 industries Annual electricity consumption is 726 GWh,Gas consumption is 315 million SCM & Coal consumption is 2.3 million tones i.e. 1.2 million TOE (tons of oil equivalents) of energy use. Overall energy saving potential is 1.5 lakh TOE Electrical and Thermal energy cost is 12 to 15 % of manufacturing Cost. Small And Medium Enterprise (SME’s) sector is characterised by the use of outdated technologies. As per BEE’s Study for SME Overall energy saving potential is @ 72432 TOE i.e. 27.4 % of total energy consumption in SME’s As an individual the SME’s may not have significant effect on environment and resource use, but together they exert a substantial effect. 2
  • 3. Instruments used: • Electrical Portable Load Manager ALM 10 • Hand held Ultrasonic flow meter Focus area: • Air compressor system • Centrifugal pumping system Energy Audit Activity: • Pre audit meeting • Familiarisation with manufacturing process and energy consuming machineries • Review of manuals,maintenace records • Verification of calibration status of instruments, installation of measuring instruments or other facilities 3
  • 4. PROCESS DIAGRAM Grey Cloth Jet M/c Rotary M/c Loop M/c (Raw Material) (Dyeing) (Printing Process) (Drying & Color setting) Stenter (Heat setting) Zero -Zero Folding Washing Hydro Packing 4
  • 5. WATER DISTRIBUTION SYSTEM Bore well Overhead tank Supply pump Stenter M/c Colour kitchen Jet M/c Rotary M/c Drums ,zero-zero M/c Printing M/c Padding M/c Office use 5
  • 6. AIR DISTRIBUTION SYSTEM Compressor 1 Stenter M/c Compressor 2 Printing M/c Rotary & Loop M/c Compressor 3 Padding M/c Jet M/c Drum M/c 6
  • 7. ENERGY AUDIT ACTIVITY Air compressor & Centrifugal pumping system : Following data are collected with measuring instruments and calculations were made for Efficiency and Percentage air leakage. • • • • • • • Input voltage,current,power factor – Measured with portable load analyser Running hours – Installed Running hour meter Tank volume - measured and compared with available data Discharge air pressure – Measured with calibrated pressure gauge Actual tank filling time – Measured with calibrated stop watch Actual head – measured with calibrated pressure gauge Actual discharge – measured with Ultrasonic flow meter 7
  • 8. SNAPS Modification of air distribution network & Installation of PID controller 8
  • 9. Installation of Auto moisture drain & Setting of new discharge set points 9
  • 10. AIR LEAKAGE TEST T on Average on time (T) min = 38 T off Average Off Time (t) min = 28 % Air leakage = Annual cost of power for comp. no 3 (Rs) = Unit rate× Annual power cons. = 5.50 ×(674.3 × 26 × 12) = 1157098 Annual power loss due to leakages (Rs) = Annual power cost × % Air leakage = 666257 Power can be saved by plugging leakage in % = 75% = 499693 = 1.2 Annual saving by leakage prevention(Rs) 57.58 T/(T+ t) × 100 Power saved by plugging 75 % leakage Investment required in plugging leakages (Rs) = 50000 Payback in months = (Investment × 12) / savings 10
  • 11. VOLUMETRIC EFFICIENCY MEASUREMENT COMPRESSOR NO. = 1 2 3 Hp = 40 30 40 Motor RPM = 1440 1440 1440 Voltage = 410 412 414 Current = 43 35 45 Power Factor = 0.95 0.95 0.95 Power consumption per hour = [√3 x V x I x COSΦ] = 29.01 23.73 30.65 Average working hrs = 24 12 22 Compressor RPM = 1440 1440 1440 4.4 2.94 5.4 1.076 1.076 1.076 Compressor (m3/min) Tank Volume (m3) Capacity = = 11
  • 12. Air pressure (Kg/cm2) = 6 Total air volume (m3) = (Tank Volume × Air Pressure) = 6.456 7.532 4.304 Actual Tank filling time (Sec) = 105 162 52 Actual air generation (m3/min) = (Total Air Volume ÷ Actual Tank Filling Time) × 60 = 3.69 = (Total Air Volume ÷ Compressor Capacity) × 60 = 88.04 = (Actual air generation ÷ Compressor Capacity) × 100 = 83.84 Required tank filling time (sec) % Efficiency Existing specific power = consumption (m3/min per kWh) = 7 2.79 153.71 94.89 4 4.97 47.82 91.97 Actual air generation ÷ power consumption per hour 0.127 0.118 0.162 12
  • 13. Proposed specific power = 3 consumption. (m /min per kWh) compressor capacity ÷ Power consumption per hour = 0.152 = (100-eff/100) × power consumption per hr × avg. working hrs = 112.48 = Power loss per day (kWh) × cost of power (Rs) = 618.62 80.09 298.00 Annual power loss (Rs) = 193011 24989 92975 Investment (Rs) = 20000 0 0 Payback in months = (Investment (Rs) x 12 ) ÷ (Annual power loss (Rs)) = 1.24 Power loss per day (kWh) Power loss per day ( Rs) 0.124 14.56 0 0.176 54.18 0 13
  • 14. CENTRIFUGAL PUMPING SYSTEM SNAPS : OLD PUMP 1 OLD PUMP 2 OLD PUMP 3 NEW PUMP IN SUMP SUMP SUMP OLD PUMP 1 NEW PUMP OLD PUMP 2 Set up of old and new transfer and supply pump 14
  • 15. Transfer pump • • • • • • • • • • • • • • Pump No. Rated motor efficiency Hp RPM Measured voltage Measured current Existing pump running hours Calculated input kW / hr [√3 x V x I x cosΦ] Pump input kW / hr Actual head (m) Measured flow (m3/hr) PROPOSED FLOW(m3)= AFTER UNIT / HR AFTER WORKING HR = = = = = = = 1 0.8 10 2800 409 14 2 2 0.8 10 2800 408 10.3 14 3 0.8 10 2800 407 10.2 24 = 9.8 7.2 7.1 = calculated input kW / hr × rated motor eff. = = = 115 = = 7.85 24 48 5.76 24 38 5.69 24 25 11 11 15
  • 16. Present water discharge per day = measured flow (m3/hr) × existing pump running hrs = 96 Existing pump efficiency (%) 532 600 = 0.4 0.431 0.286 Hydraulic power = Q (m3/s) × Total head, hd - hs (m) × Density (kg/m3) × g (m2/s) ÷ 1000 Electrical input power = Pump shaft power ÷ Motor efficiency Pump shaft power = Hydraulic power ÷ Pump efficiency Proposed minimum efficiency (%) pump = 0.7 Existing overall efficiency (%) = existing pump efficiency × rated motor efficiency = 0.32 Proposed overall efficiency (%) 0.34 0.23 = Proposed minimum pump efficiency × Rated motor efficiency = 0.56 Existing specific power consumption (m3/kW) = (measured flow m3) ÷ calculated input kW / hr = 4.89 5.27 3.51 16
  • 17. Existing unit consumption = calculated input kW / hr × existing pump running hrs per day = 19.64 Total unit consumption 100.88 170.84 = 19.60 +100.94 +171.36 = 291.36 Afterunit consumption/day = after unit kW/hr × after pump running hrs (single pump) = 121 Saving in unit/day = 291.36 – 121 = 170.36 Saving achieved per day = Saving in unit/day × Price per unit (Rs) (Rs) = 170.36 X 5.5 = 936.96 Annual Saving (Rs) = 936.96 × 26 ×12 = 292332.70 Investment required (Rs) = 35000 Payback in months = (Investment required (Rs) × 12 ) ÷ Saving per year = 1.44 17
  • 18. RESULTS AND DISCUSSION Air compressor system : • Three nos. Air compressors • PID controller is installed and different air pressure setting is set. • Air distribution network rearranged. • Automatic moisture drain valve installed • Air leakages arrested. Centrifugal Pumping system : • Instead of Three nos 10 hp ; 24 meter head; Different discharge capacity Transfer pump, One Single Energy efficient 10 hp;20 meter head;100 m3/hr capacity pump installed. • Instead of Two nos 10 hp ; 22 meter head; Different discharge capacity Supply pump, One Single Energy efficient 3 hp;6 meter head;100 m3/hr capacity pump installed. 18
  • 19. Description hp m3/min Air compressor #1 40 4.4 83.84 Air compressor #2 30 2.94 Air compressor #3 40 5.4 Energy-Saving Measures % volumetric efficiency Annual power loss ( Rs) Investment required (Rs) 7.62 193011 20000 1.24 94.89 7.08 24989 0 0 91.97 9.72 92975 0 0 Investment (Rs) Specific power consumption (kwh/m3) Annual Savings (Rs) Simple Payback Period (Months) Pay back period (months) Expected Lifetime (operating hours) Improve Efficiency of Compressor #. 1 20000 193011 1.24 14400 Stop Air Leakages in Department. 50000 499693 1.20 Req. Regular Maintaince Total 70000 692704 19
  • 20. CENTRIFUGAL PUMPING SYSTEM Transfer pump : Descripti on hp Head (meter) Flow (m3/hr) Current (amp) Input kW/hr % Efficiency % overall Efficiency Transfer pump # 1 10 24 48 14 7.85 40.0 32 Transfer pump # 2 10 24 38 10.3 5.76 43.1 34 Transfer pump # 3 10 24 25 10.2 5.69 28.6 23 Energy saving measure Investment (Rs) Annual savings (Rs) Simple Payback Expected lifetime (operating hrs) Replace Transfer pump 1,2 and 3by single Energy efficient pump 35000 292332 1.44 14400 Total 35000 292332 20
  • 21. Supply pump Descripti on hp Head (meter) Flow (m3/hr) Current (amp) Input kW/hr % Efficiency % overall Efficiency Supply pump # 1 10 22 42 10.5 5.26 50 40 Supply pump # 2 10 22 45 10.2 5.13 55 44 Energy saving measure Investment (Rs) Annual savings (Rs) Simple Payback Expected lifetime (operating hrs) Replace supply pump 1 and 2 by single Energy efficient pump 30000 230000 1.57 14400 Total 30000 230000 21
  • 22. SUMMARY OF IMPLEMENTED RESULTS Steps taken Saving In Units (kWh / Year Actual investment (Rs) Energy cost saving per year (Rs) Pay back (month) Single Energy efficient pump of 3 HP ; 6 meter head ; 100 m3/hr discharge capacity is installed (supply pump) 41817 30000 230000 1.57 Single mono sub pump of 10 hp ;20 meter head ;100 m3/hr discharge capacity is installed (transfer pump) 53152 35000 292332 1.44 PID controller is installed; Different air pressure setting is set for three different compressors. Air line network rearranged (common header ) Automatic moisture drain valve also installed 134400 180000 821338 2.67 Total 229369 245000 1343670 22
  • 23. REFERENCES [1] http://www.business-standard.com/india/news/energy-effeciency-plan-for-sm [2] Guide book for National Certification Examination for Energy Managers and Auditors. “General aspects of energy management and audit. www.beeindia.nic.in [3] Kapur, Shilpi , Plannet Earth , Fiscal reforms, SMEs'hope , Date: 10 October 2011, http://www.teriin.org/index.php? option=com_featurearticle&task [4] Ali,Hasanbeigi ,China Energy Group,Energy Analysis Department, Environmental Energy Technologies Division “energy- efficiency improvement opportunities for the textile industry”,E.O. Lawrence Berkeley National Laboratory,Washington, DC Resource Dynamics Corporation [5] Facts air distribution,”druckluft effizient’,07 compressed air facts,www.druckluft-effizient.de. [6] Kaya D, Phelan P, Chau D, Sarac HI. Energy conservation in compressed-air systems. International Journal of Energy Research 2002;26:837–49. 23
  • 24. [7] Galitsky C, Worrell E. Energy efficiency improvement and cost saving opportunities for the vehicle assembly industry. Lawrence Berkeley National Laboratory 2008 [LBNL-50939-Revision]. [8] U.S. DOE. Minimize compressed air leaks; 2010, Available online at: http://www.energystar.gov/ia/business/industry/compressed_air3.pdf [Accessed:24.09.11]. [9] Saidur R, Rahim NA, Hasanuzzaman M. A review on compressed-air energy use and energy savings. Renewable and Sustainable Energy Reviews 2010;14:1135–53 [10] PS (Plant Support). Compressed air ultrasonic leak detection guide; 2010,Available online at: http://www.plantsupport.com/download/UCAGuide.pdf[Accessed 24.09.11]. 24
  • 25. It is never too late to practice energy modesty and efficiency otherwise … Year 1900 Year 1800 Year 2000 Year 2050 Year 2020 25