SlideShare a Scribd company logo
1 of 25
Download to read offline
September 2018
A SCARCE ASSET IN A TRUE
MINING DISTRICT
www.guygold.com 2
This presentation of Guyana Goldfields Inc. (the "Company") contains
statements that constitute "forward-looking statements." Such forward-looking
statements involve known and unknown risks, uncertainties and other factors
that may cause our actual results, performance or achievements, or
developments in our industry, to differ materially from the anticipated results,
performance or achievements expressed or implied by such forward-looking
statements. Forward looking statements are statements that are not historical
facts and are generally, but not always, identified by the words "expects,"
"aims," "plans," "anticipates," "believes," "intends," "estimates," "projects,"
"potential" and similar expressions, or that events or conditions "will," "would,"
"may," "could" or "should" occur. Information inferred from the interpretation of
drilling results and information concerning mineral resource and mineral reserve
estimates may also be deemed to be forward looking statements, as such
information constitutes a prediction of what might be found to be present when
and if a project is actually developed. Forward-looking statements this document
include statements regarding: the Company's expectations regarding drilling
and exploration activities on properties in which the Company has an interest;
and the Company's statements regarding estimates of reserves and resources
on properties in which the Company has an interest.
There can be no assurance that such statements will prove to be accurate.
Actual results and future events could differ materially from those anticipated in
such statements, and readers are cautioned not to place undue reliance on
these forward-looking statements that speak only as of their respective dates.
Important factors that could cause actual results to differ materially from the
Company's expectations include among others, risks related to fluctuations in
mineral prices; uncertainties related to raising sufficient financing to fund
planned work in a timely manner and on acceptable terms; changes in planned
work resulting from weather, logistical, technical or other factors; the possibility
that results of work will not fulfill expectations and realize the perceived potential
of the Company's properties; uncertainties involved in the estimation of
resources and reserves; the possibility that required permits may not be
obtained on a timely manner or at all; the possibility that capital and operating
costs may be higher than currently estimated and may preclude commercial
development or render operations uneconomic; the possibility that the estimated
recovery rates may not be achieved; risk of accidents, equipment breakdowns
and labour disputes or
other unanticipated difficulties or interruptions; the possibility of cost overrun or
unanticipated expenses in the work program; the risk of environmental
contamination or damage resulting from the Company's operations; risks
associated with title to mineral properties; and other risks and uncertainties
discussed appear elsewhere in the Company's documents filed from time to
time with the Toronto Stock Exchange and Canadian securities regulators.
These statements are based on a number of assumptions, including
assumptions regarding general market conditions, the availability of financing for
proposed transactions and programs on reasonable terms, the cost of
exploration and development and the ability of outside service providers to
deliver services in a satisfactory and timely manner. Forward-looking statements
are based on the beliefs, estimates and opinions of the Company's
management on the date the statements are made. Except as expressly
required by applicable securities laws, the Corporation undertakes no obligation
to update these forward-looking statements in the event that management's
beliefs, estimates or opinions, or other factors, should change.
This presentation uses the terms "Inferred Resource", "Indicated Resource",
“Measured Resource” and "Mineral Resource". The Company advises readers
that although these terms are recognized and required by Canadian securities
regulations (under National Instrument 43-101 "Standards of Disclosure for
Mineral Projects"), the US Securities and Exchange Commission does not
recognize these terms. Readers are cautioned not to assume that any part or all
of the mineral deposits in these categories will ever be converted into reserves.
In addition, "Inferred Resources" have a great amount of uncertainty as to their
existence, and economic and legal feasibility. It cannot be assumed that any
part of an Indicated or Inferred Mineral Resource will ever be upgraded to a
higher category. Under Canadian rules, estimates of Inferred Mineral Resources
may not form the basis of feasibility or pre-feasibility studies, or economic
studies except for a Preliminary Assessment as defined and permitted under
National Instrument 43-101. Readers are cautioned not to assume that part or
all of an Inferred Resource exists, or is economically or legally mineable. The
Mineral Resources stated in this presentation are not Mineral Reserves and, in
the absence of a current feasibility study, do not demonstrate economic viability.
The determination of Mineral Reserves can be affected by various factors
including environmental, permitting, legal, title, taxation, socio-political, and
marketing issues.
FORWARD LOOKING STATEMENT
www.guygold.com 3
 High grade Au producer with +16 years reserve life with upside
 Production growth of ~15% CAGR from 2018 to 2022
 +200,000 acre land package in highly prospective & underexplored greenstone belt
A Scarce Asset
 Cash position of US$62M vs. debt of US$50M as at June 30, 2018
 Post quarter end US$35mln gross proceeds to be realized from sale of SolGold shares
Strong Balance
Sheet
 Management changes: Rene Marion new Non-Executive Chairman & realignment of
organizational structure
 Phase 2 mill expansion on schedule for Q4 completion
 Mining rate showing Open pit contractor mobilized
Operational
Enhancements
 P/NAV multiple of 0.4x versus peer medium producer average of 1.0x
 GDX Index rebalance has resulted in significant multiple compression
Value Proposition
INVESTMENT HIGHLIGHTS
www.guygold.com
2.9 2.9
2.7
1.7
1.4 1.3 1.3
1.0 1.0 0.9 0.9 0.8
0.7 0.7 0.6
0.4
Guyana Torex SEMAFO Alacer OceanaGold IAMGOLD Alamos B2Gold Detour Eldorado SSR Mining New Gold Kinross Yamana Tahoe Centerra
Gold Equivalent Grade (g/t Au Eq.)
4
Aurora is a High Grade Gold Mine
Source: Company filings
Note: Gold equivalent grade shown for total reserves and resources (precious metals only).
www.guygold.com 5
2018 Guidance
2018 Guidance
Gold production 175,000-185,000
Cost of sales (production costs, royalty and depreciation) $905-955/oz
Cash cost¹, excluding royalty $535-585/oz
All-in sustaining cost¹ (“AISC”) $945-995/oz
• Production is weighted towards the second half of the year due to mine sequencing and
increased throughput with completion of the phase 1 expansion.
• 2018 mine plan is primarily made up of all hard rock ore from the central tonalite/diorite ore at
Rory’s Knoll and East Walcott deposits.
• Costs are based on an increased stripping rate during 2018, offset by the increased and more cost-
efficient production offered by the process plant expansion investments.
(1) This is a non-IFRS measure. Refer to non-IFRS Performance Measures section in the latest MD&A
www.guygold.com 6
Significant Cash Flow Generation
Source: Company Reports
2Q18 net cash position includes US$35mln of proceeds from sale of SolGold shares, which occurred September 4, 2018
‐30.0
‐20.0
‐10.0
0.0
10.0
20.0
30.0
40.0
50.0
3Q16 4Q16 1Q17 2Q17 3Q17 4Q17 1Q18 2Q18
(US$ mlns)
Net Cash Balance
www.guygold.com 7
Value Proposition
Source: Company Reports, Street Research
1. 2Q18 net cash position adjusted for subsequent events. GUY includes US$35mln of proceeds from sale of SolGold shares, which occurred September 4, 2018
($300.0)
($250.0)
($200.0)
($150.0)
($100.0)
($50.0)
‐‐
$50.0
$100.0
PG GUY ROXG TGZ AKG AR ALO SMF TMR LMC ASR TXG
(US$ mlns)
Net Cash Position as at June 30, 2018(1) 
www.guygold.com 8
Value Proposition
Source: Company Reports, Street Research
‐‐
0.1x
0.2x
0.3x
0.4x
0.5x
0.6x
0.7x
0.8x
0.9x
1.0x
SMF TXG TGZ ROXG ASR AKG PG AR TMR GUY LMC ALO
(P/NAV ratio)
Street Consensus P/NAV
www.guygold.com
0
200
400
600
800
1,000
1,200
 ‐
 50
 100
 150
 200
 250
 300
 350
2017 2018E 2019E 2020E 2021E 2022E
Costs (US$/oz)
Recovered Oz
Gold Recovered / Costs
Underground Open Pit Operating Cash Cost AISC
9
Lucrative Growth Profile
(1) 2018 Guidance of 175k‐185koz
(2) Gold Production from January 1 – August 31, 2018 of 96,950 ounces. Production is weighted towards the second half of the year due to mine sequencing and 
increased throughput with completion of the phase 1 expansion.
(1)(2)
97koz
YTD
www.guygold.com 10
SITE LAYOUT: Aurora Gold Mine
Rory’s Knoll
Walcott Hill
Mad Kiss
Aleck Hill
North Aleck Hill
www.guygold.com 11
Brownfields Exploration: Resource Growth Potential
Source: JDS, 2018
Open laterally 
and at Depth
www.guygold.com 12
Brownfields Exploration: Resource Additions at East Walcott
EWD099: 20m at 4.79g/t Au from 356m 
EWD094: 23m @ 6.80g/t Au from 102m
‐150mRL
0mRL
‐300mRL
‐450mRL
RORY’S KNOLL 
(Resource Extends to ‐
2000mRL)
EAST WALCOTT
(Open at Depth)
EWD‐27: 48m at 3.71g/t Au from 366m 
EWD094: 21.4m @ 10.85g/t Au from 130.35m
EWD094: 44.8m at 9.09g/t Au from 205.4m 
EWD095: 35.25m at 5.84g/t Au from 213.25m 
EWD097: 12.7m at 6.33g/t Au from 141m 
EWD099: 21.2m at 4.21g/t Au from 291m
EWD099: 14.2m at 3g/t Au from 378.8m
RKD‐51: 56m at 5.5g/t Au from 379m
EWD‐12: 37m at 7.49g/t Au from 300m
EWD‐60: 43m at 6.66g/t Au from 222m 
EWD‐19: 7.35m at 12.77g/t Au from 124m
EWD‐19: 20.05m at 9.94g/t Au from 134.95m
Rory’s Knoll 
Deposit
Interpreted High 
Grade Ore 
Shoots – East 
Walcott
Historical 
Exploration 
Drilling 
Intersections
2018 East Walcott 
Drilling Program
Current Open Pit 
Extent
Meters
0 150
www.guygold.com 13
Brownfields Exploration: Resource Additions at East Walcott
Meters
0 500
0mRL
‐500mRL
‐1000mRL
‐1500mRL
‐2000mRL
Current extent of 
exploration drilling 
in East Walcott
Approximate extent 
of current LOM Plan 
for Rory’s Knoll
SIGNIFICANT EXPLORATION 
POTENTIAL DOWN‐PLUNGE 
OF ORE SHOOTS
Rory’s Knoll 
Deposit
Interpreted High 
Grade Ore 
Shoots – East 
Walcott
Current Open 
Pit Extent
EAST WALCOTT
(Open at Depth)
RORY’S KNOLL 
(Resource Extends to ‐
2000mRL)
www.guygold.com 14
APPENDIX
www.guygold.com 15
Symbol: TSX: GUY
Total Shares Outstanding 173,530,802
Options 5,949,179 
Warrants 0
52 week: Hi/Lo C$5.42 / C$2.74
Market Cap (at C$ 2.97) C$510 million
Cash Balance (June 30, 2018) US$62 million
Debt  (June 30, 2018) US$50 million
Top 5 Shareholders Shares %
The Baupost Group 23.7M 13.7%
Van Eck 19.1M 11.0%
Wellington Management 11.2M 6.5%
Franklin Resources (Templeton) 9.0M 5.2%
CI Investments 7.4M 4.3%
CORPORATE SNAPSHOT
www.guygold.com 16
 Guyana is the only English speaking country in South America
 British common law and secure tenure - part of the Commonwealth
 Democratically elected government under parliamentary system
 Long history of significant gold production:
 Gold was the largest export of the country
 Royalty:
 5%: Gold price $1,000/oz or less
 8%: Gold price $1,000/oz +
 Corporate income tax:
 27.5% with no withholding tax on interest payments
MINING FRIENDLY JURISDICTION & GOVERNMENT
www.guygold.com 17
Road Access to 
Aurora
LOGISTICS & INFRASTRUCTURE
www.guygold.com 18
Focus on health and safety of our employees, the well-being of our
community and the protection of the natural environment
Hiring in the region, giving priority to local communities:
 96% are Guyanese nationals
 Scholarship and job/skills training
Supporting local communities
 Local sourcing of goods and services
 Business opportunities
 Participation in municipal development
 Sustainable development initiatives in community
CSR AND SUSTAINABLE DEVELOPMENT
www.guygold.com 19
MINERAL RESERVES
As at December 31, 2017
Category
Quantity
(kt)
Grade
(g/t Au)
Ounces
(k Oz)
Proven
OP Saprolite 108 0.73 3
OP Rock 4,569 2.75 404
Total Proven 4,677 2.70 406
Probable
OP Saprolite 2,291 1.77 130
OP Rock 12,959 2.81 1,172
UG Rock 23,120 3.04 2,262
Total Probable 38,370 2.89 3,565
Total P&P 43,047 2.87 3,971
1. The CIM definitions were followed for mineral reserves.
2. Mineral Reserves are based on a gold price of US$1,200 per ounce, an 8% royalty and an average
metallurgical recovery of 96.0% for saprolite and 94.0% for fresh rock material.
3. Open pit saprolite and rock reserves are reported at a cut-off grade of 0.44 g/t Au and 0.42 g/t Au
for vein and upper saprolite material respectively. Open pit rock reserves are reported at a cut-off
grade of 0.76 g/t Au and 0.64 g/t Au for vein and Rory’s Knoll rock material respectively.
4. Underground fresh rock reserves are reported at a cut-off grade of 1.5 g/t Au.
5. Mineral reserves are contained within mineral resources.
6. All figures have been rounded to reflect the relative accuracy of the estimates. Numbers may not
add due to rounding
7. The mineral reserve estimate was prepared by Tysen Hantelmann, P.Eng. and Gord Doerksen,
P.Eng of JDS Mining and both are a “qualified person” under National Instrument 43-101.
www.guygold.com 20
MINERAL RESOURCES
As at December 31, 2017
Category
Quantity
(kt)
Grade
(g/t Au)
Ounces
(k Oz)
Measured
OP Saprolite 108 0.73 3
OP Rock 4,728 2.91 442
Total Measured 4,836 2.86 445
Indicated
OP Saprolite 1,404 0.93 42
OP Rock 20,901 2.60 1,747
UG Rock 30,060 3.91 3,780
Total Indicated 52,365 3.31 5,569
Total M + I 57,201 3.27 6,014
Inferred
OP Saprolite 1,939 0.91 57
OP Rock 2,581 1.93 161
UG Rock 11,810 4.12 1,560
Total Inferred 16,330 3.39 1,777
1. The CIM definitions were followed for mineral resources.
2. Mineral resources are inclusive of mineral reserves. Mineral resources are not mineral reserves and do not have demonstrated economic viability.
3. All figures have been rounded to reflect the relative accuracy of the estimates. Number may not add due to rounding.
4. Open pit mineral resources are reported at a cut-off grade of 0.30 g/t for Saprolite and 0.40 g/t for Fresh rock respectively, and underground mineral resources are reported at a cut-off grade of 1.8 g/t. Cut-off
grades are based on a price of US$1,300 per ounce of gold and a gold recoveries of 97 percent for saprolite and 94.5 percent for fresh material.
5. Mineral resources have been adjusted using the 2017 EOY topography, to account for open pit mining to date, and include ore stockpile inventories as of EOY 2017.
6. The qualified person is not aware of any mining, metallurgical, infrastructure, permitting, or other factors that could materially affect the mineral resource estimates.
7. The mineral resource estimate for Rory’s Knoll was prepared under the supervision of Tim Maunula, of T. Maunula & Associates Consulting Ltd. Mr. Maunula is a “qualified person” under NI 43-101 and
is independent of the Company. The mineral resource estimate for the satellites was prepared under the supervision of Daniel Noone of Guyana Goldfields Inc. Mr. Noone is a “qualified person” under
National Instrument 43-101.
www.guygold.com 21
Annual LOM Production Profile
Units
Total/
Avg
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
OPEN PIT MINING
Open Pit Ore ktonnes 19,022 2,579 3,078 1,553 2,317 1,976 1,098 820 684 1,039 1,096 957 822 684 320
Au Grade Mined gpt 2.74 2.62 2.90 2.89 2.80 2.74 3.09 2.61 2.86 2.03 2.93 2.44 1.78 3.99 2.20
Au Mined from Open Pit kounces 1,675 217 287 144 208 174 109 69 63 68 103 75 47 88 23
Open Pit Waste ktonnes 169,376 22,071 22,472 24,067 19,416 8,880 8,465 8,640 8,943 8,705 8,622 8,984 9,577 9,755 779
Open Pit Material Moved ktonnes 188,397 24,650 25,550 25,620 21,733 10,855 9,562 9,460 9,627 9,745 9,717 9,942 10,399 10,439 1,098
Strip Ratio 8.9 8.6 7.3 15.5 8.4 4.5 7.7 10.5 13.1 8.4 7.9 9.4 11.7 14.3 2.4
UNDERGROUND MINING
Ore Mined - Rory's Knoll ktonnes 20,537 347 554 1,332 1,506 1,714 1,725 1,714 1,720 1,738 1,707 1,704 1,748 1,677 1,349
Au Grade Mined gpt 2.92 4.76 4.24 3.85 2.93 2.88 3.25 3.43 3.05 2.50 2.38 2.34 2.31 2.69 2.74
Au Mined from Rory's Knoll
UG koz 1,925 53 76 165 142 159 180 189 169 140 131 128 130 145 119
Ore Mined - Satellites koz 2,583 140 420 562 285 67 165 181 209 205 205 144
Au Grade Mined gpt 4.06 3.41 4.98 3.66 3.23 2.97 4.72 4.64 3.90 4.07 3.77 4.93
Au Mined from Satellites
UG koz 337 15 67 66 30 6 25 27 26 27 25 23
Total Au Mined koz 3,937 217 302 265 350 368 257 227 243 257 272 240 205 242 179 170 142
PROCESSING
Tonnes Milled ktonnes 43,047 2,355 2,738 2,745 2,738 2,738 2,738 2,745 2,738 2,738 2,738 2,745 2,738 2,738 2,738 2,745 2,337
Throughput Rate tpd 7,400 6,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 6,400
Mill Feed Average Grade gpt 2.87 2.91 3.12 3.30 3.48 3.70 3.01 2.87 3.12 2.95 3.07 2.70 2.37 2.83 2.14 2.15 2.11
Recovery % 94.8% 92.1% 95.4% 95.6% 95.8% 96.1% 95.2% 95.0% 95.4% 95.1% 95.3% 94.6% 93.9% 94.9% 93.3% 93.3% 93.1%
Total Au Recovered kounces 3,767 203 262 278 294 313 252 240 262 247 258 226 196 236 176 177 148
Source: Optimized Life of Mine Plan – Press Release February 20, 2018
www.guygold.com 22
Annual LOM Cost Profile
Units
Total/
Avg
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
FINANCIALS
Revenue $mlns 4,508 243 314 333 352 374 302 288 313 295 309 270 235 283 211 211 177
NSR Royalty (8%) $mlns 361 19 25 27 28 30 24 23 25 24 25 22 19 23 17 17 14
Site Operating Costs $mlns 1,989 92 100 118 141 121 126 129 130 135 137 138 139 146 119 113 108
Sustaining Capital $mlns 295 9 21 34 29 16 14 19 21 16 12 15 17 26 21 16 10
Deferred Stripping $mlns 138 36 28 37 11 5 2 4 6 - - 3 4 2 - - -
Expansion Capital $mlns
Mill Expansion $mlns 13 13 - - - - - - - - - - - - - - -
UG Mining $mlns 151 19 73 17 - - - - - - 20 21 - - - - -
Other $mlns 3 3 - - - - - - - - - - - - - - -
Total Capital Costs $mlns 599 79 122 88 41 20 16 22 27 16 32 40 21 28 21 16 10
Total Site Costs $mlns 2,950 190 247 232 210 171 166 174 182 175 193 200 178 196 157 147 132
AISC $mlns 3,002 170 188 229 223 185 180 188 196 188 187 192 191 210 171 160 145
Pre-tax Cash Flow $mlns 1,567 50 61 98 140 204 138 112 128 120 113 70 57 82 60 64 46
NPV (5%) (pre-tax) $mlns 1,142
Tax $mlns 348 1 7 6 24 50 33 30 35 33 32 20 14 23 14 16 11
NPV (5%) (after tax) $mlns 898
Operating Cash Cost¹ $/oz 531 455 385 425 483 389 501 540 498 551 532 614 710 618 679 645 732
Operating Cash Cost (incl
Royalty)¹ $/oz 627 551 481 521 579 485 597 636 594 647 628 710 806 714 775 740 828
AISC¹ $/oz 797 836 717 821 761 592 713 783 747 764 723 851 977 886 970 907 985
Source: Optimized Life of Mine Plan – Press Release February 20, 2018
www.guygold.com 23
BOARD & SENIOR OFFICERS
Alan Ferry
Director
 Geologist that has been Involved in the investment industry for over 28 years as a mining
analyst and a mining corporate finance specialist.
Patrick Sheridan Jr.
Founder, Director
 Over 25 years of experience in the mining industry
 Has actively explored in Guyana since 1996 and is the founder of Guyana Goldfields and lead the
discovery of the Aurora and Sulphur Rose deposits
Scott A. Caldwell
President & CEO
and Director
 Mining engineer with 35+ years experience building and operating gold and base metal mines worldwide
 Former President, CEO and Director of Allied Nevada Gold Corp. from 2006 - 2013
Michael Richings
Director
 40+ years of development and operational experience in the resource sector. Mr. Richings is currently
the Chairman of the Board for Vista Gold, where he also served as CEO from 2007 to 2012
Rene Marion
Non Executive
Chairman, Director
 25+ years of diversified management and senior technical experience with resource industry
expertise in operations, mineral exploration, and mine development, along with a successful
history of corporate development.
Wendy Kei
Director
 Chartered Professional Accountant and previously served as CFO of Dominion Diamond Corporation
(formerly Harry Winston).
Jean-Pierre Chauvin
Director
 40+ years of combined experience in mining operations and construction management.
David Beatty
Director
 25+ years of financial capital markets and resource management experience.
Ron Stewart
SVP, Technical
Services & Corp. Dev
 30 years of international experience in exploration, project development, operations and capital markets
Paul J. Murphy
Executive VP,
Finance & CFO
 Over 40 years of financial experience and former Head of PricewaterhouseCoopers LLP Western’s
World Mining Practice
www.guygold.com 24
Scientific and Technical Information
The compilation of the Optimized LOM Plan was completed by Tysen Hantelmann, P.Eng. and Gord Doerksen, P.Eng of JDS Mining. By
virtue of their education, membership to a recognized professional association and relevant work experience, Tysen Hantelmann and
Gord Doerksen are independent Qualified Persons as defined by National Instrument 43-101 and have reviewed, approved and verified
the technical content of this news release.
The mineral reserve estimates were prepared under the supervision of Tysen Hantelmann, P.Eng. and Gord Doerksen, P.Eng of JDS
Mining. Mr. Hantelmann and Mr. Doerksen are a “qualified person” under NI 43-101 and is independent of the Company. The mineral
resource estimate for Rory’s Knoll was prepared under the supervision of Tim Maunula, of T. Maunula & Associates Consulting. Mr.
Maunula is a “qualified person” under NI 43-101 and is independent of the Company. The mineral resource estimates for the satellite
deposits was prepared under the supervision of Danial Noone of Guyana Goldfields Inc. Daniel Noone is a “qualified person” under
National Instrument 43-101 and has also reviewed the contents of this press release.
Securities Laws
This presentation does not constitute an offer or solicitation to buy or sell any securities discussed herein in any jurisdiction where such
would be prohibited. This presentation is not an offer to sell, or a solicitation of an offer to purchase, any securities in the United States.
The securities referred to in this presentation will not be registered under the U.S. Securities Act of 1933 and may not be offered or sold in
the United States except pursuant to an exemption from the registration requirements of the U.S. Securities Act of 1933 and applicable
state securities laws.
The information contained in this presentation does not and is not intended to constitute a "valuation," "formal valuation," "appraisal,"
"prior valuation," or a "report, statement or opinion of an expert" for purposes of any securities legislation in Canada or otherwise.
Currency
Unless otherwise indicated, all dollar values herein are in United States dollars.
SCIENTIFIC, TECHNICAL AND SECURITIES INFORMATION
www.guygold.com 25
Jacqueline Wagenaar
VP, IR & Corporate Communications
Tel: (416) 628 5936 x.5295
Email: jwagenaar@guygold.com

More Related Content

What's hot

Equitas Resources Corp. - Corporate Presentation (August12)
Equitas Resources Corp. - Corporate Presentation (August12)Equitas Resources Corp. - Corporate Presentation (August12)
Equitas Resources Corp. - Corporate Presentation (August12)
Equitas Resources Corp
 

What's hot (20)

Guy february 2018 ir presentation final-v2
Guy february 2018 ir presentation final-v2Guy february 2018 ir presentation final-v2
Guy february 2018 ir presentation final-v2
 
Guy february 2018 ir presentation final
Guy february 2018 ir presentation finalGuy february 2018 ir presentation final
Guy february 2018 ir presentation final
 
Harte Gold Corporate Presentation - August 2020
Harte Gold Corporate Presentation - August 2020Harte Gold Corporate Presentation - August 2020
Harte Gold Corporate Presentation - August 2020
 
Largo corporate presentation july 2017
Largo corporate presentation july 2017Largo corporate presentation july 2017
Largo corporate presentation july 2017
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate Presentation
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate Presentation
 
February 2016 Corporate Presentation
February 2016 Corporate PresentationFebruary 2016 Corporate Presentation
February 2016 Corporate Presentation
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate Presentation
 
Corporate presentation september 2016 v final
Corporate presentation   september 2016 v finalCorporate presentation   september 2016 v final
Corporate presentation september 2016 v final
 
New Zealand Energy Corporate Presentation
New Zealand Energy Corporate PresentationNew Zealand Energy Corporate Presentation
New Zealand Energy Corporate Presentation
 
Equitas Resources Corp. - Corporate Presentation (August12)
Equitas Resources Corp. - Corporate Presentation (August12)Equitas Resources Corp. - Corporate Presentation (August12)
Equitas Resources Corp. - Corporate Presentation (August12)
 
New Zealand Energy Corporate Presentation
New Zealand Energy Corporate PresentationNew Zealand Energy Corporate Presentation
New Zealand Energy Corporate Presentation
 
Kemess Site Visit Presentation
Kemess Site Visit PresentationKemess Site Visit Presentation
Kemess Site Visit Presentation
 
Ami kemess lunch june 22 2017 final website
Ami kemess lunch   june 22 2017 final websiteAmi kemess lunch   june 22 2017 final website
Ami kemess lunch june 22 2017 final website
 
New Zealand Energy Corporate Presentation
New Zealand Energy Corporate PresentationNew Zealand Energy Corporate Presentation
New Zealand Energy Corporate Presentation
 
Rubicon Minerals January 2018 Corporate Presentation
Rubicon Minerals January 2018 Corporate PresentationRubicon Minerals January 2018 Corporate Presentation
Rubicon Minerals January 2018 Corporate Presentation
 
New Zealand Energy Corporate Presentation
New Zealand Energy Corporate PresentationNew Zealand Energy Corporate Presentation
New Zealand Energy Corporate Presentation
 
Alamos corporate presentation sept 19 2016 final
Alamos corporate presentation sept 19 2016 finalAlamos corporate presentation sept 19 2016 final
Alamos corporate presentation sept 19 2016 final
 
New Zealand Energy Corporate Presentation
New Zealand Energy Corporate PresentationNew Zealand Energy Corporate Presentation
New Zealand Energy Corporate Presentation
 
Osisko Gold Royalties - 2017 Denver Gold Forum
Osisko Gold Royalties - 2017 Denver Gold ForumOsisko Gold Royalties - 2017 Denver Gold Forum
Osisko Gold Royalties - 2017 Denver Gold Forum
 

Similar to Sep 2018 ir presentation

Guyana Goldfields August 2017 IR Presentation
Guyana Goldfields August 2017 IR PresentationGuyana Goldfields August 2017 IR Presentation
Guyana Goldfields August 2017 IR Presentation
guygold2016
 
Guy august-2016-ir-presentation-final-20160812132506
Guy august-2016-ir-presentation-final-20160812132506Guy august-2016-ir-presentation-final-20160812132506
Guy august-2016-ir-presentation-final-20160812132506
guygold2016
 
GUY January 2017 IR Presentation-first
GUY January 2017 IR Presentation-firstGUY January 2017 IR Presentation-first
GUY January 2017 IR Presentation-first
guygold2016
 
July 2014 Investor Presentation
July 2014 Investor PresentationJuly 2014 Investor Presentation
July 2014 Investor Presentation
jwagenaar734
 

Similar to Sep 2018 ir presentation (20)

Guyana Goldfields August 2017 IR Presentation
Guyana Goldfields August 2017 IR PresentationGuyana Goldfields August 2017 IR Presentation
Guyana Goldfields August 2017 IR Presentation
 
Guy august 2017 ir presentation final2
Guy august 2017 ir presentation final2Guy august 2017 ir presentation final2
Guy august 2017 ir presentation final2
 
Guy august-2016-ir-presentation-final-20160812132506
Guy august-2016-ir-presentation-final-20160812132506Guy august-2016-ir-presentation-final-20160812132506
Guy august-2016-ir-presentation-final-20160812132506
 
GUY January 2017 IR Presentation-first
GUY January 2017 IR Presentation-firstGUY January 2017 IR Presentation-first
GUY January 2017 IR Presentation-first
 
Guy january 2018 ir presentation 1
Guy january 2018 ir presentation 1Guy january 2018 ir presentation 1
Guy january 2018 ir presentation 1
 
Guy january 2018 ir presentation 2
Guy january 2018 ir presentation 2Guy january 2018 ir presentation 2
Guy january 2018 ir presentation 2
 
Guy january 2018 ir presentation 2
Guy january 2018 ir presentation 2Guy january 2018 ir presentation 2
Guy january 2018 ir presentation 2
 
Guy september 2017 ir presentation
Guy september 2017 ir presentationGuy september 2017 ir presentation
Guy september 2017 ir presentation
 
Guy october 2017 ir presentation
Guy october 2017 ir presentationGuy october 2017 ir presentation
Guy october 2017 ir presentation
 
Guy december 2017 ir presentation
Guy december 2017 ir presentationGuy december 2017 ir presentation
Guy december 2017 ir presentation
 
Guy november 2017 ir presentation
Guy november 2017 ir presentationGuy november 2017 ir presentation
Guy november 2017 ir presentation
 
Guy november 2017 ir presentation
Guy november 2017 ir presentationGuy november 2017 ir presentation
Guy november 2017 ir presentation
 
July 2014 Investor Presentation
July 2014 Investor PresentationJuly 2014 Investor Presentation
July 2014 Investor Presentation
 
Llg corporate presentation march 2017
Llg   corporate presentation march 2017Llg   corporate presentation march 2017
Llg corporate presentation march 2017
 
Llg corporate presentation december 2016
Llg   corporate presentation december 2016Llg   corporate presentation december 2016
Llg corporate presentation december 2016
 
Llg corporate presentation october 2016
Llg   corporate presentation october 2016Llg   corporate presentation october 2016
Llg corporate presentation october 2016
 
Llg corporate presentation october 2016
Llg   corporate presentation october 2016Llg   corporate presentation october 2016
Llg corporate presentation october 2016
 
Guy november 2017 ir presentation
Guy november 2017 ir presentationGuy november 2017 ir presentation
Guy november 2017 ir presentation
 
Guy november 2017 ir presentation
Guy november 2017 ir presentationGuy november 2017 ir presentation
Guy november 2017 ir presentation
 
Llg corporate presentation october 2016
Llg   corporate presentation october 2016Llg   corporate presentation october 2016
Llg corporate presentation october 2016
 

More from guygold2016 (6)

Guy june 2017 ir presentation
Guy june 2017 ir presentationGuy june 2017 ir presentation
Guy june 2017 ir presentation
 
Guyana Gold May 2017 IR Presentation
Guyana Gold May 2017 IR PresentationGuyana Gold May 2017 IR Presentation
Guyana Gold May 2017 IR Presentation
 
Guy april-2017-ir-presentation
Guy april-2017-ir-presentationGuy april-2017-ir-presentation
Guy april-2017-ir-presentation
 
Guyana Goldfields Inc. March 2017 IR Presentation
Guyana Goldfields Inc. March 2017 IR PresentationGuyana Goldfields Inc. March 2017 IR Presentation
Guyana Goldfields Inc. March 2017 IR Presentation
 
Guyana Goldfields February 2017 IR Presentation
Guyana Goldfields February  2017 IR Presentation Guyana Goldfields February  2017 IR Presentation
Guyana Goldfields February 2017 IR Presentation
 
Guy february-2017-ir-presentation-final.v
Guy february-2017-ir-presentation-final.vGuy february-2017-ir-presentation-final.v
Guy february-2017-ir-presentation-final.v
 

Recently uploaded

一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样
一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样
一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样
dyuozua
 
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
sovco
 
一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样
一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样
一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样
dyuozua
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
Probe Gold
 
一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样
一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样
一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样
dyuozua
 
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
xzxvi5zp
 
一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样
一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样
一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样
dyuozua
 
一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样
一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样
一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样
dyuozua
 
一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样
一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样
一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样
dyuozua
 
一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样
一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样
一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样
dyuozua
 
一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样
一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样
一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样
dyuozua
 
一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样
一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样
一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样
dyuozua
 

Recently uploaded (20)

Western Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 PresentationWestern Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 Presentation
 
一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样
一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样
一比一原版(Otago毕业证书)奥塔哥大学毕业证成绩单原件一模一样
 
SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024
 
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
 
一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样
一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样
一比一原版(MU毕业证书)梅努斯大学毕业证成绩单原件一模一样
 
Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
 
一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样
一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样
一比一原版(Waikato毕业证书)怀卡托大学毕业证成绩单原件一模一样
 
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
 
一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样
一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样
一比一原版(UoA毕业证书)奥克兰大学毕业证成绩单原件一模一样
 
一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样
一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样
一比一原版(UC毕业证书)坎特伯雷大学毕业证成绩单原件一模一样
 
一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样
一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样
一比一原版(VUW毕业证书)惠灵顿维多利亚大学毕业证成绩单原件一模一样
 
一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样
一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样
一比一原版(UCD毕业证书)都柏林大学毕业证成绩单原件一模一样
 
Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024
 
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
 
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdfITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
 
The Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results PresentationThe Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results Presentation
 
AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024
 
一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样
一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样
一比一原版(Mac毕业证书)麦克马斯特大学毕业证成绩单原件一模一样
 
一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样
一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样
一比一原版(Massey毕业证书)梅西大学毕业证成绩单原件一模一样
 

Sep 2018 ir presentation

  • 1. September 2018 A SCARCE ASSET IN A TRUE MINING DISTRICT
  • 2. www.guygold.com 2 This presentation of Guyana Goldfields Inc. (the "Company") contains statements that constitute "forward-looking statements." Such forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements, or developments in our industry, to differ materially from the anticipated results, performance or achievements expressed or implied by such forward-looking statements. Forward looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects," "aims," "plans," "anticipates," "believes," "intends," "estimates," "projects," "potential" and similar expressions, or that events or conditions "will," "would," "may," "could" or "should" occur. Information inferred from the interpretation of drilling results and information concerning mineral resource and mineral reserve estimates may also be deemed to be forward looking statements, as such information constitutes a prediction of what might be found to be present when and if a project is actually developed. Forward-looking statements this document include statements regarding: the Company's expectations regarding drilling and exploration activities on properties in which the Company has an interest; and the Company's statements regarding estimates of reserves and resources on properties in which the Company has an interest. There can be no assurance that such statements will prove to be accurate. Actual results and future events could differ materially from those anticipated in such statements, and readers are cautioned not to place undue reliance on these forward-looking statements that speak only as of their respective dates. Important factors that could cause actual results to differ materially from the Company's expectations include among others, risks related to fluctuations in mineral prices; uncertainties related to raising sufficient financing to fund planned work in a timely manner and on acceptable terms; changes in planned work resulting from weather, logistical, technical or other factors; the possibility that results of work will not fulfill expectations and realize the perceived potential of the Company's properties; uncertainties involved in the estimation of resources and reserves; the possibility that required permits may not be obtained on a timely manner or at all; the possibility that capital and operating costs may be higher than currently estimated and may preclude commercial development or render operations uneconomic; the possibility that the estimated recovery rates may not be achieved; risk of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of cost overrun or unanticipated expenses in the work program; the risk of environmental contamination or damage resulting from the Company's operations; risks associated with title to mineral properties; and other risks and uncertainties discussed appear elsewhere in the Company's documents filed from time to time with the Toronto Stock Exchange and Canadian securities regulators. These statements are based on a number of assumptions, including assumptions regarding general market conditions, the availability of financing for proposed transactions and programs on reasonable terms, the cost of exploration and development and the ability of outside service providers to deliver services in a satisfactory and timely manner. Forward-looking statements are based on the beliefs, estimates and opinions of the Company's management on the date the statements are made. Except as expressly required by applicable securities laws, the Corporation undertakes no obligation to update these forward-looking statements in the event that management's beliefs, estimates or opinions, or other factors, should change. This presentation uses the terms "Inferred Resource", "Indicated Resource", “Measured Resource” and "Mineral Resource". The Company advises readers that although these terms are recognized and required by Canadian securities regulations (under National Instrument 43-101 "Standards of Disclosure for Mineral Projects"), the US Securities and Exchange Commission does not recognize these terms. Readers are cautioned not to assume that any part or all of the mineral deposits in these categories will ever be converted into reserves. In addition, "Inferred Resources" have a great amount of uncertainty as to their existence, and economic and legal feasibility. It cannot be assumed that any part of an Indicated or Inferred Mineral Resource will ever be upgraded to a higher category. Under Canadian rules, estimates of Inferred Mineral Resources may not form the basis of feasibility or pre-feasibility studies, or economic studies except for a Preliminary Assessment as defined and permitted under National Instrument 43-101. Readers are cautioned not to assume that part or all of an Inferred Resource exists, or is economically or legally mineable. The Mineral Resources stated in this presentation are not Mineral Reserves and, in the absence of a current feasibility study, do not demonstrate economic viability. The determination of Mineral Reserves can be affected by various factors including environmental, permitting, legal, title, taxation, socio-political, and marketing issues. FORWARD LOOKING STATEMENT
  • 3. www.guygold.com 3  High grade Au producer with +16 years reserve life with upside  Production growth of ~15% CAGR from 2018 to 2022  +200,000 acre land package in highly prospective & underexplored greenstone belt A Scarce Asset  Cash position of US$62M vs. debt of US$50M as at June 30, 2018  Post quarter end US$35mln gross proceeds to be realized from sale of SolGold shares Strong Balance Sheet  Management changes: Rene Marion new Non-Executive Chairman & realignment of organizational structure  Phase 2 mill expansion on schedule for Q4 completion  Mining rate showing Open pit contractor mobilized Operational Enhancements  P/NAV multiple of 0.4x versus peer medium producer average of 1.0x  GDX Index rebalance has resulted in significant multiple compression Value Proposition INVESTMENT HIGHLIGHTS
  • 4. www.guygold.com 2.9 2.9 2.7 1.7 1.4 1.3 1.3 1.0 1.0 0.9 0.9 0.8 0.7 0.7 0.6 0.4 Guyana Torex SEMAFO Alacer OceanaGold IAMGOLD Alamos B2Gold Detour Eldorado SSR Mining New Gold Kinross Yamana Tahoe Centerra Gold Equivalent Grade (g/t Au Eq.) 4 Aurora is a High Grade Gold Mine Source: Company filings Note: Gold equivalent grade shown for total reserves and resources (precious metals only).
  • 5. www.guygold.com 5 2018 Guidance 2018 Guidance Gold production 175,000-185,000 Cost of sales (production costs, royalty and depreciation) $905-955/oz Cash cost¹, excluding royalty $535-585/oz All-in sustaining cost¹ (“AISC”) $945-995/oz • Production is weighted towards the second half of the year due to mine sequencing and increased throughput with completion of the phase 1 expansion. • 2018 mine plan is primarily made up of all hard rock ore from the central tonalite/diorite ore at Rory’s Knoll and East Walcott deposits. • Costs are based on an increased stripping rate during 2018, offset by the increased and more cost- efficient production offered by the process plant expansion investments. (1) This is a non-IFRS measure. Refer to non-IFRS Performance Measures section in the latest MD&A
  • 6. www.guygold.com 6 Significant Cash Flow Generation Source: Company Reports 2Q18 net cash position includes US$35mln of proceeds from sale of SolGold shares, which occurred September 4, 2018 ‐30.0 ‐20.0 ‐10.0 0.0 10.0 20.0 30.0 40.0 50.0 3Q16 4Q16 1Q17 2Q17 3Q17 4Q17 1Q18 2Q18 (US$ mlns) Net Cash Balance
  • 7. www.guygold.com 7 Value Proposition Source: Company Reports, Street Research 1. 2Q18 net cash position adjusted for subsequent events. GUY includes US$35mln of proceeds from sale of SolGold shares, which occurred September 4, 2018 ($300.0) ($250.0) ($200.0) ($150.0) ($100.0) ($50.0) ‐‐ $50.0 $100.0 PG GUY ROXG TGZ AKG AR ALO SMF TMR LMC ASR TXG (US$ mlns) Net Cash Position as at June 30, 2018(1) 
  • 8. www.guygold.com 8 Value Proposition Source: Company Reports, Street Research ‐‐ 0.1x 0.2x 0.3x 0.4x 0.5x 0.6x 0.7x 0.8x 0.9x 1.0x SMF TXG TGZ ROXG ASR AKG PG AR TMR GUY LMC ALO (P/NAV ratio) Street Consensus P/NAV
  • 9. www.guygold.com 0 200 400 600 800 1,000 1,200  ‐  50  100  150  200  250  300  350 2017 2018E 2019E 2020E 2021E 2022E Costs (US$/oz) Recovered Oz Gold Recovered / Costs Underground Open Pit Operating Cash Cost AISC 9 Lucrative Growth Profile (1) 2018 Guidance of 175k‐185koz (2) Gold Production from January 1 – August 31, 2018 of 96,950 ounces. Production is weighted towards the second half of the year due to mine sequencing and  increased throughput with completion of the phase 1 expansion. (1)(2) 97koz YTD
  • 10. www.guygold.com 10 SITE LAYOUT: Aurora Gold Mine Rory’s Knoll Walcott Hill Mad Kiss Aleck Hill North Aleck Hill
  • 11. www.guygold.com 11 Brownfields Exploration: Resource Growth Potential Source: JDS, 2018 Open laterally  and at Depth
  • 12. www.guygold.com 12 Brownfields Exploration: Resource Additions at East Walcott EWD099: 20m at 4.79g/t Au from 356m  EWD094: 23m @ 6.80g/t Au from 102m ‐150mRL 0mRL ‐300mRL ‐450mRL RORY’S KNOLL  (Resource Extends to ‐ 2000mRL) EAST WALCOTT (Open at Depth) EWD‐27: 48m at 3.71g/t Au from 366m  EWD094: 21.4m @ 10.85g/t Au from 130.35m EWD094: 44.8m at 9.09g/t Au from 205.4m  EWD095: 35.25m at 5.84g/t Au from 213.25m  EWD097: 12.7m at 6.33g/t Au from 141m  EWD099: 21.2m at 4.21g/t Au from 291m EWD099: 14.2m at 3g/t Au from 378.8m RKD‐51: 56m at 5.5g/t Au from 379m EWD‐12: 37m at 7.49g/t Au from 300m EWD‐60: 43m at 6.66g/t Au from 222m  EWD‐19: 7.35m at 12.77g/t Au from 124m EWD‐19: 20.05m at 9.94g/t Au from 134.95m Rory’s Knoll  Deposit Interpreted High  Grade Ore  Shoots – East  Walcott Historical  Exploration  Drilling  Intersections 2018 East Walcott  Drilling Program Current Open Pit  Extent Meters 0 150
  • 13. www.guygold.com 13 Brownfields Exploration: Resource Additions at East Walcott Meters 0 500 0mRL ‐500mRL ‐1000mRL ‐1500mRL ‐2000mRL Current extent of  exploration drilling  in East Walcott Approximate extent  of current LOM Plan  for Rory’s Knoll SIGNIFICANT EXPLORATION  POTENTIAL DOWN‐PLUNGE  OF ORE SHOOTS Rory’s Knoll  Deposit Interpreted High  Grade Ore  Shoots – East  Walcott Current Open  Pit Extent EAST WALCOTT (Open at Depth) RORY’S KNOLL  (Resource Extends to ‐ 2000mRL)
  • 15. www.guygold.com 15 Symbol: TSX: GUY Total Shares Outstanding 173,530,802 Options 5,949,179  Warrants 0 52 week: Hi/Lo C$5.42 / C$2.74 Market Cap (at C$ 2.97) C$510 million Cash Balance (June 30, 2018) US$62 million Debt  (June 30, 2018) US$50 million Top 5 Shareholders Shares % The Baupost Group 23.7M 13.7% Van Eck 19.1M 11.0% Wellington Management 11.2M 6.5% Franklin Resources (Templeton) 9.0M 5.2% CI Investments 7.4M 4.3% CORPORATE SNAPSHOT
  • 16. www.guygold.com 16  Guyana is the only English speaking country in South America  British common law and secure tenure - part of the Commonwealth  Democratically elected government under parliamentary system  Long history of significant gold production:  Gold was the largest export of the country  Royalty:  5%: Gold price $1,000/oz or less  8%: Gold price $1,000/oz +  Corporate income tax:  27.5% with no withholding tax on interest payments MINING FRIENDLY JURISDICTION & GOVERNMENT
  • 18. www.guygold.com 18 Focus on health and safety of our employees, the well-being of our community and the protection of the natural environment Hiring in the region, giving priority to local communities:  96% are Guyanese nationals  Scholarship and job/skills training Supporting local communities  Local sourcing of goods and services  Business opportunities  Participation in municipal development  Sustainable development initiatives in community CSR AND SUSTAINABLE DEVELOPMENT
  • 19. www.guygold.com 19 MINERAL RESERVES As at December 31, 2017 Category Quantity (kt) Grade (g/t Au) Ounces (k Oz) Proven OP Saprolite 108 0.73 3 OP Rock 4,569 2.75 404 Total Proven 4,677 2.70 406 Probable OP Saprolite 2,291 1.77 130 OP Rock 12,959 2.81 1,172 UG Rock 23,120 3.04 2,262 Total Probable 38,370 2.89 3,565 Total P&P 43,047 2.87 3,971 1. The CIM definitions were followed for mineral reserves. 2. Mineral Reserves are based on a gold price of US$1,200 per ounce, an 8% royalty and an average metallurgical recovery of 96.0% for saprolite and 94.0% for fresh rock material. 3. Open pit saprolite and rock reserves are reported at a cut-off grade of 0.44 g/t Au and 0.42 g/t Au for vein and upper saprolite material respectively. Open pit rock reserves are reported at a cut-off grade of 0.76 g/t Au and 0.64 g/t Au for vein and Rory’s Knoll rock material respectively. 4. Underground fresh rock reserves are reported at a cut-off grade of 1.5 g/t Au. 5. Mineral reserves are contained within mineral resources. 6. All figures have been rounded to reflect the relative accuracy of the estimates. Numbers may not add due to rounding 7. The mineral reserve estimate was prepared by Tysen Hantelmann, P.Eng. and Gord Doerksen, P.Eng of JDS Mining and both are a “qualified person” under National Instrument 43-101.
  • 20. www.guygold.com 20 MINERAL RESOURCES As at December 31, 2017 Category Quantity (kt) Grade (g/t Au) Ounces (k Oz) Measured OP Saprolite 108 0.73 3 OP Rock 4,728 2.91 442 Total Measured 4,836 2.86 445 Indicated OP Saprolite 1,404 0.93 42 OP Rock 20,901 2.60 1,747 UG Rock 30,060 3.91 3,780 Total Indicated 52,365 3.31 5,569 Total M + I 57,201 3.27 6,014 Inferred OP Saprolite 1,939 0.91 57 OP Rock 2,581 1.93 161 UG Rock 11,810 4.12 1,560 Total Inferred 16,330 3.39 1,777 1. The CIM definitions were followed for mineral resources. 2. Mineral resources are inclusive of mineral reserves. Mineral resources are not mineral reserves and do not have demonstrated economic viability. 3. All figures have been rounded to reflect the relative accuracy of the estimates. Number may not add due to rounding. 4. Open pit mineral resources are reported at a cut-off grade of 0.30 g/t for Saprolite and 0.40 g/t for Fresh rock respectively, and underground mineral resources are reported at a cut-off grade of 1.8 g/t. Cut-off grades are based on a price of US$1,300 per ounce of gold and a gold recoveries of 97 percent for saprolite and 94.5 percent for fresh material. 5. Mineral resources have been adjusted using the 2017 EOY topography, to account for open pit mining to date, and include ore stockpile inventories as of EOY 2017. 6. The qualified person is not aware of any mining, metallurgical, infrastructure, permitting, or other factors that could materially affect the mineral resource estimates. 7. The mineral resource estimate for Rory’s Knoll was prepared under the supervision of Tim Maunula, of T. Maunula & Associates Consulting Ltd. Mr. Maunula is a “qualified person” under NI 43-101 and is independent of the Company. The mineral resource estimate for the satellites was prepared under the supervision of Daniel Noone of Guyana Goldfields Inc. Mr. Noone is a “qualified person” under National Instrument 43-101.
  • 21. www.guygold.com 21 Annual LOM Production Profile Units Total/ Avg 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 OPEN PIT MINING Open Pit Ore ktonnes 19,022 2,579 3,078 1,553 2,317 1,976 1,098 820 684 1,039 1,096 957 822 684 320 Au Grade Mined gpt 2.74 2.62 2.90 2.89 2.80 2.74 3.09 2.61 2.86 2.03 2.93 2.44 1.78 3.99 2.20 Au Mined from Open Pit kounces 1,675 217 287 144 208 174 109 69 63 68 103 75 47 88 23 Open Pit Waste ktonnes 169,376 22,071 22,472 24,067 19,416 8,880 8,465 8,640 8,943 8,705 8,622 8,984 9,577 9,755 779 Open Pit Material Moved ktonnes 188,397 24,650 25,550 25,620 21,733 10,855 9,562 9,460 9,627 9,745 9,717 9,942 10,399 10,439 1,098 Strip Ratio 8.9 8.6 7.3 15.5 8.4 4.5 7.7 10.5 13.1 8.4 7.9 9.4 11.7 14.3 2.4 UNDERGROUND MINING Ore Mined - Rory's Knoll ktonnes 20,537 347 554 1,332 1,506 1,714 1,725 1,714 1,720 1,738 1,707 1,704 1,748 1,677 1,349 Au Grade Mined gpt 2.92 4.76 4.24 3.85 2.93 2.88 3.25 3.43 3.05 2.50 2.38 2.34 2.31 2.69 2.74 Au Mined from Rory's Knoll UG koz 1,925 53 76 165 142 159 180 189 169 140 131 128 130 145 119 Ore Mined - Satellites koz 2,583 140 420 562 285 67 165 181 209 205 205 144 Au Grade Mined gpt 4.06 3.41 4.98 3.66 3.23 2.97 4.72 4.64 3.90 4.07 3.77 4.93 Au Mined from Satellites UG koz 337 15 67 66 30 6 25 27 26 27 25 23 Total Au Mined koz 3,937 217 302 265 350 368 257 227 243 257 272 240 205 242 179 170 142 PROCESSING Tonnes Milled ktonnes 43,047 2,355 2,738 2,745 2,738 2,738 2,738 2,745 2,738 2,738 2,738 2,745 2,738 2,738 2,738 2,745 2,337 Throughput Rate tpd 7,400 6,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 7,500 6,400 Mill Feed Average Grade gpt 2.87 2.91 3.12 3.30 3.48 3.70 3.01 2.87 3.12 2.95 3.07 2.70 2.37 2.83 2.14 2.15 2.11 Recovery % 94.8% 92.1% 95.4% 95.6% 95.8% 96.1% 95.2% 95.0% 95.4% 95.1% 95.3% 94.6% 93.9% 94.9% 93.3% 93.3% 93.1% Total Au Recovered kounces 3,767 203 262 278 294 313 252 240 262 247 258 226 196 236 176 177 148 Source: Optimized Life of Mine Plan – Press Release February 20, 2018
  • 22. www.guygold.com 22 Annual LOM Cost Profile Units Total/ Avg 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 FINANCIALS Revenue $mlns 4,508 243 314 333 352 374 302 288 313 295 309 270 235 283 211 211 177 NSR Royalty (8%) $mlns 361 19 25 27 28 30 24 23 25 24 25 22 19 23 17 17 14 Site Operating Costs $mlns 1,989 92 100 118 141 121 126 129 130 135 137 138 139 146 119 113 108 Sustaining Capital $mlns 295 9 21 34 29 16 14 19 21 16 12 15 17 26 21 16 10 Deferred Stripping $mlns 138 36 28 37 11 5 2 4 6 - - 3 4 2 - - - Expansion Capital $mlns Mill Expansion $mlns 13 13 - - - - - - - - - - - - - - - UG Mining $mlns 151 19 73 17 - - - - - - 20 21 - - - - - Other $mlns 3 3 - - - - - - - - - - - - - - - Total Capital Costs $mlns 599 79 122 88 41 20 16 22 27 16 32 40 21 28 21 16 10 Total Site Costs $mlns 2,950 190 247 232 210 171 166 174 182 175 193 200 178 196 157 147 132 AISC $mlns 3,002 170 188 229 223 185 180 188 196 188 187 192 191 210 171 160 145 Pre-tax Cash Flow $mlns 1,567 50 61 98 140 204 138 112 128 120 113 70 57 82 60 64 46 NPV (5%) (pre-tax) $mlns 1,142 Tax $mlns 348 1 7 6 24 50 33 30 35 33 32 20 14 23 14 16 11 NPV (5%) (after tax) $mlns 898 Operating Cash Cost¹ $/oz 531 455 385 425 483 389 501 540 498 551 532 614 710 618 679 645 732 Operating Cash Cost (incl Royalty)¹ $/oz 627 551 481 521 579 485 597 636 594 647 628 710 806 714 775 740 828 AISC¹ $/oz 797 836 717 821 761 592 713 783 747 764 723 851 977 886 970 907 985 Source: Optimized Life of Mine Plan – Press Release February 20, 2018
  • 23. www.guygold.com 23 BOARD & SENIOR OFFICERS Alan Ferry Director  Geologist that has been Involved in the investment industry for over 28 years as a mining analyst and a mining corporate finance specialist. Patrick Sheridan Jr. Founder, Director  Over 25 years of experience in the mining industry  Has actively explored in Guyana since 1996 and is the founder of Guyana Goldfields and lead the discovery of the Aurora and Sulphur Rose deposits Scott A. Caldwell President & CEO and Director  Mining engineer with 35+ years experience building and operating gold and base metal mines worldwide  Former President, CEO and Director of Allied Nevada Gold Corp. from 2006 - 2013 Michael Richings Director  40+ years of development and operational experience in the resource sector. Mr. Richings is currently the Chairman of the Board for Vista Gold, where he also served as CEO from 2007 to 2012 Rene Marion Non Executive Chairman, Director  25+ years of diversified management and senior technical experience with resource industry expertise in operations, mineral exploration, and mine development, along with a successful history of corporate development. Wendy Kei Director  Chartered Professional Accountant and previously served as CFO of Dominion Diamond Corporation (formerly Harry Winston). Jean-Pierre Chauvin Director  40+ years of combined experience in mining operations and construction management. David Beatty Director  25+ years of financial capital markets and resource management experience. Ron Stewart SVP, Technical Services & Corp. Dev  30 years of international experience in exploration, project development, operations and capital markets Paul J. Murphy Executive VP, Finance & CFO  Over 40 years of financial experience and former Head of PricewaterhouseCoopers LLP Western’s World Mining Practice
  • 24. www.guygold.com 24 Scientific and Technical Information The compilation of the Optimized LOM Plan was completed by Tysen Hantelmann, P.Eng. and Gord Doerksen, P.Eng of JDS Mining. By virtue of their education, membership to a recognized professional association and relevant work experience, Tysen Hantelmann and Gord Doerksen are independent Qualified Persons as defined by National Instrument 43-101 and have reviewed, approved and verified the technical content of this news release. The mineral reserve estimates were prepared under the supervision of Tysen Hantelmann, P.Eng. and Gord Doerksen, P.Eng of JDS Mining. Mr. Hantelmann and Mr. Doerksen are a “qualified person” under NI 43-101 and is independent of the Company. The mineral resource estimate for Rory’s Knoll was prepared under the supervision of Tim Maunula, of T. Maunula & Associates Consulting. Mr. Maunula is a “qualified person” under NI 43-101 and is independent of the Company. The mineral resource estimates for the satellite deposits was prepared under the supervision of Danial Noone of Guyana Goldfields Inc. Daniel Noone is a “qualified person” under National Instrument 43-101 and has also reviewed the contents of this press release. Securities Laws This presentation does not constitute an offer or solicitation to buy or sell any securities discussed herein in any jurisdiction where such would be prohibited. This presentation is not an offer to sell, or a solicitation of an offer to purchase, any securities in the United States. The securities referred to in this presentation will not be registered under the U.S. Securities Act of 1933 and may not be offered or sold in the United States except pursuant to an exemption from the registration requirements of the U.S. Securities Act of 1933 and applicable state securities laws. The information contained in this presentation does not and is not intended to constitute a "valuation," "formal valuation," "appraisal," "prior valuation," or a "report, statement or opinion of an expert" for purposes of any securities legislation in Canada or otherwise. Currency Unless otherwise indicated, all dollar values herein are in United States dollars. SCIENTIFIC, TECHNICAL AND SECURITIES INFORMATION
  • 25. www.guygold.com 25 Jacqueline Wagenaar VP, IR & Corporate Communications Tel: (416) 628 5936 x.5295 Email: jwagenaar@guygold.com