SlideShare a Scribd company logo
1 of 11
Download to read offline
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
Minnova Corp. Issues an Updated Preliminary Economic Assessment 
for its Maverick Gold Project 
Toronto, Ontario – Minnova Corp. (TSXV: MCI, ("Minnova” of “the Company”) is pleased to announce it 
has filed its Updated Preliminary Economic Assessment ("PEA") Technical Report titled "NI 43-101 
UPDATED PRELIMINARY ECONOMIC ASSESSMENT OPEN PIT AND UNDERGROUND MINING, AND ON-SITE 
MILLING AT THE MAVERICK GOLD PROJECT, INCLUDING MINING OF THE PL GOLD DEPOSIT AND THE 
NOKOMIS GOLD DEPOSIT, Sherridan, Manitoba" on SEDAR at www.sedar.com. The Updated PEA was 
prepared by ACA Howe International Limited (“Howe”) based on the mineral resource estimates (see 
April 17, 2014 news release) prepared by P&E Mining Consultants Inc. and Howe on Minnova’s 100% 
owned Maverick Gold Project. Prior to June 2014 Minnova was called Auriga Gold Corp. ("Auriga Gold"). 
Prior to this release the PL Property and PL Mine were known as the Puffy Lake Property and Puffy Lake 
Mine. Currencies reported below are in Canadian dollars unless otherwise specified. 
Highlights from the Base Case study, which uses a long term gold price of US$1,250 per ounce gold and 
USD:CAD exchange rate of $1.05, include: 
 Pre-tax Net Present Value ("NPV") at a 5% discount rate of $97.7 million and an Internal Rate of 
Return ("IRR") of 59%; 
 After-tax NPV at a 5% discount rate of $83.3 million and IRR of 55%; 
 After-tax payback of 1.5 years after plant start-up; 
 11 year mine life, mining and processing 2.5 million tonnes, averaging 6.53 grams per tonne 
("g/t") gold, and producing 483,000 ounces of gold; 
 Open pit production amounts to 558,000 tonnes at an average diluted grade of 4.41 g/t 
gold at a LOM strip ratio of 6:1; 
 Underground production amounts to 1.98 million tonnes an average diluted grade of 7.26 
g/t gold; 
 Total payable gold production of 483,000 ounces with an average Life of Mine (“LOM”) cash 
cost of US$798 per ounce and average AISC of US$1003 per ounce; 
 Years 2 to 5 mill feed planned at 900 tpd to produce an average of 52,522 ounces a year 
at an average cash cost of US$849 per ounce and average AISC of US$991 per ounce; 
 Years 6 to 10 mill throughput planned at 600 tpd to produce an average of 49,100 ounces 
a year at cash cost of US$770 per ounce and AISC of US$896 per ounce; 
 Pre-production (years -1 and 1) capital cost of $26.3 million including a 19% for contingency, 
environmental bonds and initial working capital; 
 In Year 1, the projected $12.7 million capital expenditure is partially offset by income of 
$6.6 million; 
 Sustaining Capital and Closure Costs of $29.5 million over LOM; 
Gorden Glenn, President & CEO of Minnova commented, "We are very pleased with the results of this 
Updated Preliminary Economic Assessment. It confirms the Maverick Gold Project (“MGP”) as a robust 
project with a low pre-production capital cost, low operating and All In Sustaining Cost’s (“AISC”) and a 
quick payback of 1.5 years from the start of production on a +10 year mine life.
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
Our focus on upgrading the PL and Nokomis resources (see our April 17, 2014 press release) and 
introducing new innovative underground mining techniques to the mine plan have resulted in a higher 
overall life of mine gold production, higher average annual production, lower cash operating costs, 
lower AISC and lower strip ratio over our initial January 2012 Preliminary Economic Assessment 
(“January 2012 PEA”). 
Importantly the project’s NPV has remained largely unchanged despite using a lower, more 
conservative, long-term gold price of US$1,250/oz vs $1,400/oz used in the January 2012 PEA. While the 
initial capital costs have increased modestly they are more defensible incorporating significant 
contingency, environmental permitting and bonding, and working capital considerations, which were 
not fully factored into the January 2012 PEA. The completion of this updated PEA marks another 
significant milestone for Minnova and we can now move forward with our plans for a test underground 
stope program to validate the SAMSTM underground mining method, finalize and update all required 
operating permits and complete a Feasibility Study by the end of 2014. Upon completion of the 
Feasibility Study we anticipate we could be initiating construction/rehabilitation of the mine and mill 
infrastructure in early 2015 toward achieving initial production in the second half of 2015.” 
UPDATED MAVERICK GOLD PROJECT DEVELOPMENT PLAN 
The Maverick Gold Project updated development plan includes the following: 
Pre-production Year -1 (starts July 1, 2014) 
• Complete an initial underground test mining program at the PL underground mine; 
 Finalize all environmental and operating permits 
• By the end of 2014 complete a Feasibility Study (“FS”) 
Development and Production Years 1 - 11 (starts July 1, 2015) 
 Assuming positive FS, starting in January 2015 initiate the refurbishment and reactivation of the 
existing PL mill and underground mine; 
• Sequential development of five open pits on the PL Deposit and another on the Nokomis 
Deposit; 
Closure and Rehabilitation 
• Progressive mine closure activity and planning; 
 Mine closure in year 11 to be followed by and a post-closure monitoring program. 
Forecast Gold Production 
Howe estimates total mill feed to be 2.53 million tonnes at an average diluted grade of 6.58g/t. Of this 
approximately 1.98 million tonnes at an average diluted grade of 7.26 g/t would be sourced from 
underground mine on the PL deposit and 0.59 million tonnes would be sourced from shallow open pits 
at an average diluted grade of 4.17 g/t Au. 
At full production from open pits and underground (900 tpd) in years 2 through 5 average annual 
production is estimated at approximately 52,500 ounces and will drop to an average of 49,000 ounces
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
during years 6 through 10 when the pits are depleted (underground only) and mill throughput drops to 
600tpd. Years 1 and 11 are partial years. 
Total recoverable gold production over the LOM is estimated at 483,000 ounces for an average annual 
production rate of approximately 48,100 ounces of gold. The project development schedule is shown in 
Figure 1. 
Figure 1: Summary of Projected Annual Gold Production, Cash Operating Costs and AISC 
Preliminary Economic Assessment 
The Maverick Gold Project was assessed using a discounted cashflow approach with a Base Case long-term 
gold price of US$1,250/oz and a USD:CAD exchange rate of 1.05. 
The results of the economic analysis, summarized in Table 1 and Table 2, support advancing the project 
and completing a FS by the end of 2014. Undiscounted after-tax cashflow amounts to $125.7 million and 
returns a robust IRR of 55%. 
Table1: Results of the Economic Analysis 
Pre-tax After-tax 
IRR 59% 55% 
Undiscounted NPV ($M) $146.20 $125.70 
NPV (5%) ($M) $97.70 $83.80 
NPV (8%) ($M) $77.50 $66.40 
Payback 3 yrs from start of development 
1.5 yrs from start of production 
$ oz 
$200 oz 
$400 oz 
$600 oz 
$800 oz 
$1,000 oz 
$1,200 oz 
$1,400 oz 
$1,600 oz 
$1,800 oz 
oz 
10,000 oz 
20,000 oz 
30,000 oz 
40,000 oz 
50,000 oz 
60,000 oz 
70,000 oz 
1 2 3 4 5 6 7 8 9 10 11 
Open Pits (LHS) Underground (LHS) Total Cash Costs (RHS) AISC (RHS)
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
Table 2: Results of the Cashflow Analysis 
Undiscounted 
LOM Total 
(000's) 
Discounted at 
5% (000's) 
Discounted at 
8% (000's) 
IRR (%) 
Gross Sales $629,632 $475,868 $408,206 
Less royalties $18,291 $13,785 $11,807 
Less selling expenses $2,900 $2,191 $1,880 
Net Sales Revenue $608,441 $459,890 $394,519 
Mining costs $306,573 $221,457 $185,021 
Processing costs $67,399 $48,613 $40,602 
G&A costs $32,461 $23,311 $19,424 
Total cash operating costs $406,434 $293,381 $245,048 
Net cash operating margin $202,006 $144,609 $120,247 
Initial capital $26,299 $24,471 $23,481 
Sustaining capital $29,504 $24,722 $22,430 
Net cash flow before tax $146,203 $97,713 $77,535 59% 
Taxation payable $20,463 $13,845 $11,103 
Net cash flow after tax $125,739 $83,867 $66,432 55%
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
Resources 
Together the PL and Nokomis gold deposits support mineral resources amenable to open pit and 
underground mining that include Measured and Indicated mineral resources totalling 327,900 ounces of 
gold and Inferred mineral resources of 438,600 ounces of gold. See mineral resource summary in Table 3 
and Table 4 below. 
Table 3: PL Deposit Mineral Resource Estimate as of April 17, 2014 
Class 
Au Cut-off 
g/t 
Tonnes Au g/t 
Contained 
Au oz 
In-Pit 
Measured 0.6 123,000 4.41 17,400 
Indicated 0.6 445,000 4.40 63,000 
M+I 0.6 568,000 4.40 80,400 
Inferred 0.6 45,000 4.87 7,000 
Out-of-Pit 
Measured 2.5 27,000 5.12 4,500 
Indicated 2.5 1,057,000 5.95 202,300 
M+I 2.5 1,084,000 5.93 206,800 
Inferred 2.5 2,135,000 6.01 412,500 
Total 
Measured 0.6/2.5 150,000 4.54 21,900 
Indicated 0.6/2.5 1,502,000 5.49 265,300 
M+I 0.6/2.5 1,652,000 5.41 287,200 
Inferred 0.6/2.5 2,180,000 5.99 419,500 
Notes PL Deposit: 
1. The volume of the historical mined areas was depleted from the resource estimate. 
Table 4: Nokomis Mineral Resource Estimate Statement as of April 17, 2014 
Class 
Reporting 
Cut-off g/t 
Au 
Tonnes Grade g/t Au Contained Au oz 
Indicated 0.6 371,000 3.41 41,000 
Inferred 0.6 247,000 2.41 19,000 
Notes PL and Nokomis Deposits: 
1. The quantity and grade of reported Inferred resources in this estimation are uncertain in nature and there has been 
insufficient exploration to define these Inferred resources as an Indicated or Measured mineral resource and it is 
uncertain if further exploration will result in upgrading them to an Indicated or Measured mineral resource category. 
2. The PL updated NI 43-101 compliant mineral resource estimate has been prepared by Mr. Eugene Puritch, P.Eng. of 
P&E Mining Consultants Inc.. The Nokomis NI 43-101 compliant mineral resource was prepared by Leon McGarry, 
B.Sc., P.Geo., of ACA Howe International Limited. 
3. The NI 43-101 compliant mineral resources in this press release were estimated using the Canadian Institute of 
Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and 
Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council. 
4. Grade capping of 30g/t Au was utilized on composites at the PL Deposit and grade capping of 50g/t Au was utilized 
on raw assays at the Nokomis Deposit.
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
5. Bulk densities of 2.72 t/m3 and 2.89t/m3, respectively were used for tonnage calculations at the PL Deposit and 
Nokomis Deposits, respectively. 
6. At the PL gold deposit open pit resources are reported within an optimized pit shell. 
7. A gold price of US$1,300/oz and an exchange rate of US$0.97US=C$1.00 was utilized in the Au cut-off grade 
calculations of 0.6 g/t open pit and 2.5 g/t underground. Open pit mining costs were C$3.75/t for mineralized 
material and C$3.00/t for waste rock while underground mining costs were C$75/t. Process costs were C$17/t and 
G&A was C$6/t. Process recovery used was 95%. 
8. Tonnes and ounces have been rounded to reflect the relative accuracy of the mineral resource estimate; therefore 
numbers may not total correctly. 
9. Mineral Resource tonnes quoted are not diluted. 
10. Mineral resources are not mineral reserves and by definition do not demonstrate economic viability. This mineral 
resource estimate includes inferred mineral resources that are normally considered too speculative geologically to 
have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is 
also no certainty that these inferred mineral resources will be converted to the measured and indicated resource 
categories through further drilling, or into mineral reserves, once economic considerations are applied. 
11. 1 troy ounce equals 31.10348 grams. 
Mining Model Construction 
The mine plan developed for the Updated PEA considers the re-opening of the PL underground mine 
and the development of five new open pits on the PL gold property and another on the Nokomis gold 
property. 
The relative contribution of open pit and underground feed to the mill has been optimized to so as to 
generate the highest value early in the mine life. This is done to accelerate capital payback and maximize 
cash flow and hence deliver the highest Net Present Value. The defining variables used for this work are 
summarized in Table 5 and Table 6 below. 
Table 5: Parameters used to create the financial model for the Maverick Gold Project (PL and Nokomis 
Gold Deposits) 
Parameter Unit Values 
Au price US$/oz 1,250 
Exchange rate USD:CAD 1.05 
Au recovery % 90 
Au payable % 99 
Selling costs (Au refining, transportation and insurance) US$/payable oz 6
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
Table 6: Maverick Gold Project Estimated Unit Operating Costs 
Item Unit Operating Costs 
Open pit mining costs: 
Mining cost $7.50 / t potentially economic mineralization 
Definition drilling and grade control 
assays 
$3.00 / t potentially economic mineralization 
Overburden Stripping $1.88 / t overburden 
Waste rock stripping cost $6.00 / t waste rock 
Muskeg removal allowance $2.0 M 
Underground development and mining costs: 
Typical lateral development cost $5,100 / m for drift and ramp development 
Production stoping cost $50.00 / t potentially economic mineralization 
Underground mine indirect operating 
costs 
$38.00 / t potentially economic mineralization 
Underground haul to mill $2.00 / t potentially economic mineralization 
Processing cost yrs 1-5; $22.24 /t, yr 6; $26.00 /t, yrs 7-11: $29.79 /t processed 
Tailings management cost yrs 1-5; $1.00 /t, yr 6; $1.27 /t, yrs 7-11: $1.50 /t processed 
General and Administration cost yrs 1-5; $10.51 /t, yr 6; $13.34 /t, yrs 7-11: $15.77 /t processed 
Production royalties 3% at PL deposit, 2% at Nokomis deposit (2.92% overall) 
Projected corporate taxes 15% federal & 10% provincial. 
Figure 2: Image showing the PL deposit open pits 1 through 5 and underground block model. 
Open pit mining would be done using conventional open pit equipment and technologies. Underground 
mining would be done using Minrail Inc.’s Shallow Angle Mining System (SAMSTM) which would first be 
demonstrated in a test stope. The SAMSTM is designed to underground mine flat dipping zones. It uses
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
back-mounted rails and suspended interchangeable drilling, blasting and mucking modules. Stopes 
would paste backfilled once mined out. 
The mines would operate 350 days/year on a two 10 hour shifts per day basis with four rotating crews. 
The mill would operate on a two 12 hour shifts per day basis with four rotating crews. 
The Nokomis satellite deposit, located less than 8 kilometres to the northeast, will be incorporated into 
the mine plan in year 3 enabling mill feed to be sustained at 900tpd for years 2 through 5. In years 6 
through 11 mine output will consist of underground mineralization only and the mill feed rate will drop 
to 600tpd. 
Figure 3: Nokomis pit, facing east-northeast 
SAMSTM represents an innovated new technology that is designed to ensure and enhance operator 
safety while improving productivity. The electric-powered modules have multiple braking systems 
including a failsafe braking system. Minrail has reviewed its safety devices with mine safety regulators 
in Ontario and Quebec and reports that the SAMSTM system meets rigorous mine safety requirements 
in those jurisdictions. The proposed test stoping program at the PL underground mine would be 
reviewed with Manitoba health and safety regulatory authorities prior to the test. 
Figure 4: Driving the stope centre raise using SAMSTM
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
Processing 
The existing process plant has a name plate capacity of 1,000 tonnes per day and has been on care and 
maintenance since April 1989. It is proposed to rehabilitate and use the existing PL mill for processing. It 
is anticipated that, although process modifications and equipment additions may be indicated by future 
testwork, the historical flowsheet will be satisfactory. 
The initial throughput rate for this study is 900 t/d which will yield a nominal grind (K80) of 
approximately 110 microns utilizing the existing conventional crushing and grinding circuits. Based on 
planned tonnage and grade and assuming continuous stable operation, an overall gold recovery of 90% 
is projected. This recovery estimate would be confirmed by testwork on samples representing the 
current mining plan. 
Infrastructure 
The Maverick Gold Project is accessible by all-weather road and there is a commercial rail line within 7 
kilometers for the property for delivery of bulk supplies. Power would be provided Manitoba Hydro 
which requires modest extensions and upgrades of existing transmission lines to the site. A back-up 
power supply would be provided from diesel generators already located at site. Manitoba Hydro is a 
reliable, low cost source of power. 
As described in the Updated PEA report Minnova plan to conduct a fish population survey of the Ragged 
TMA this summer. This PEA assumes that the Ragged TMA would continue to be utilized for tailings 
management. 
Capital Costs 
The initial capital requirement in years -1 and 1 for the Project is estimated to be US$26.3M, as detailed 
in Table 7. This amount includes 19% for contingency, environmental bonds and initial working capital. 
Year 1, the projected $12.7 million capital expenditure is partially offset by income of $6.6 million. 
Table 7: Maverick Gold Project Pre-production Capital Cost Estimate as of July 9, 2014 
Item 
Pre-production Production Total 
($k) ($k) ($k) 
Yr -1 Yr 1 Yrs 2-11 
Months 1-12 Months 1-7 Months 8-12 
Months 13 - 
EML 
Mill running 
Test stoping $4,342 $4,342 
Feasibility study and supporting 
studies 
$415 $415 
Mill rehabilitation and commissioning $6,245 $3,898 $280 $10,423 
Infrastructure $1,550 $475 $2,999 $5,024
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
Underground mine $3,390 $0 $15,575 $18,965 
Paste backfill plant $5,000 $5,000 
Open Pits including muskeg removal $314 $2,250 $2,564 
Environmental projects $540 $100 $0 $100 $740 
Mine closure $500 $0 $5,300 $5,800 
Working Capital $2,000 -$2,000 $0 
Sub Total $13,092 $8,677 $2,000 $29,504 $53,273 
Contingency $530 $2,000 $2,530 
Total $13,622 $12,677 $29,504 $55,803 
Cumulative Capital $13,622 $26,299 $55,803 
The Project has a total sustaining capital requirement of $29.5M. Closure costs amount to $5.8M. Start-up 
capital contingency plus closure bond and working capital amounts to $4.5M. 
Financial Analysis and Sensitivities 
Using a gold price of $1,250/oz, the study yields a pre-tax NPV8% of $77.5 million and IRR of 59%. After-tax 
NPV8% amounts to $66.4 million and an IRR of 55%. The results of the sensitivity analysis for the 
Base Case are shown in Table 8 and indicate that the project is most sensitive to changes in gold price 
and head grade, and least sensitive to changes in capital cost. 
It must be noted that all economic results reported in a PEA are preliminary in nature and as such may 
vary considerably from actual results. The project does not currently have any mineral reserves as the 
declaration of reserves requires at least a pre-feasibility study to be completed. 
Table 8: Results of Sensitivity Analysis of the Base Case 
Parameter 
After-Tax NPV (8%) ($M) 
Variation of Parameter Relative to Base Case 
-40% -30% -20% -10% 0% 10% 20% 30% 40% 
Head Grade -$43 -$16 $12 $39 $66 $94 $121 $149 $176 
Gold Price -$44 -$16 $11 $39 $66 $94 $122 $149 $177 
Operating Costs $140 $122 $103 $85 $66 $48 $30 $11 -$7 
Capital Costs $77 $74 $72 $69 $66 $64 $61 $59 $56 
Qualified Persons 
The PEA was conducted under the overall review of David Orava, M. Eng., P. Eng. of ACA Howe 
International Ltd. of Toronto Ontario with the following Qualified Persons contributing to their 
respective sections: 
Alfred Hayden P.Eng., Senior Associate Metallurgical Engineer, ACA Howe International Ltd. 
David Burga P.Geo., Geologist, P&E Mining Consultants Inc. 
Eugene Puritch P.Eng., President, P&E Mining Consultants Inc. 
Felix Lee P.Geo., Senior Geologist, ACA Howe International Ltd. 
Leon McGarry P.Geo., Project Geologist, ACA Howe International Ltd. 
William Douglas Roy, M.A.Sc. P.Eng., Senior Associate Mining Engineer, ACA Howe International Ltd. 
Yungang Wu P.Geo., Geologist, P&E Mining Consultants Inc.
` 
Minnova Corp. Office: +1 647 985 2785 
MCI:TSXV 365 Bay Street, Suite 400 
www.minnovacorp.ca Toronto, Ontario M5H 2V1 
MINN VA 
CORP. 
O 
The foregoing Qualified Persons have verified that the data from the PEA is fairly and accurately 
disclosed in this news release. 
About Minnova Corp. 
Minnova Corp. is an emerging Canadian gold producer focused on re-starting the PL Mine and expanding 
gold resources on its PL and Nokomis gold deposits (collectively the "Maverick Gold Project"). The 
Company has completed an Updated PEA which supports average annual production of 48,100 ounces 
over a +10 year mine life. Work to date strongly supports advancing the project toward production with 
an initial program of underground test mining and completion of a Feasibility Study to bring the PL Mine 
back into production. The PL Mine includes a 1,000 tpd flotation mill with a replacement value in excess 
of $50 million, over 7,000 meters of developed underground ramp to 135 metres depth, is fully road 
accessible and close to existing mining infrastructure. The Maverick Gold Project is located in the Flin 
Flon Greenstone Belt of Central Manitoba. To view current images of the property and mill, please see 
www.minnovacorp.ca/s/photogallery.asp 
For more information please contact: 
Minnova Corp. 
Gorden Glenn 
Chairman, President and CEO 
gglenn@minnovacorp.ca 
Phone: +1 (647) 985 2785 
info@minnovacorp.ca 
http://www.minnovacorp.ca 
CHF Investor Relations 
Cathy Hume 
CEO 
Tel: +1 (416) 868 1079 ext.231 
Email: cathy@chfir.com 
www.chfir.com 
Renmark Financial Communications Inc. 
Barry Mire: bmire@renmarkfinancial.com 
Laurence A. Lachance: llachance@renmarkfinancial.com 
Tel.: +1 (416) 644 2020 or 
+1 (514) 939 3989 
www.renmarkfinancial.com 
This news release contains "forward-looking information" within the meaning of applicable Canadian securities 
legislation. Forward-looking information includes, but is not limited to, information regarding the Company 
including management’s assessment of future plans and operations, that may involve risks associated with mining 
exploration and development, volatility of prices, currency fluctuations, imprecision of resource estimates, 
environmental and permitting risks, access to labour and services, competition from other companies and ability to 
access sufficient capital. As a consequence, actual results may differ materially from those anticipated in the 
forward looking statements. A feasibility study has not been completed and there is no certainty the disclosed 
targets will be achieved nor that the proposed operations will be economically viable. Although Minnova has 
attempted to identify important factors that could cause actual results to differ materially from those contained in 
forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or 
intended. There can be no assurance that such information will prove to be accurate, as actual results and future 
events could differ materially from those anticipated in such information. Accordingly, readers should not place 
undue reliance on forward-looking information. Minnova does not undertake to update any forward-looking 
information, except in accordance with applicable securities laws. 
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX 
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

More Related Content

What's hot

Corporate Presentation - January 2017
Corporate Presentation - January 2017Corporate Presentation - January 2017
Corporate Presentation - January 2017GranColombiaGold
 
Claude Resources Inc. 2011 Third Quarter Report
Claude Resources Inc. 2011 Third Quarter ReportClaude Resources Inc. 2011 Third Quarter Report
Claude Resources Inc. 2011 Third Quarter ReportClaude Resources Inc.
 
Barclays select screen march 2015
Barclays select screen   march 2015Barclays select screen   march 2015
Barclays select screen march 2015RoyalGold
 
Bmo presentation feb 2015 final screen
Bmo presentation   feb 2015 final screenBmo presentation   feb 2015 final screen
Bmo presentation feb 2015 final screenRoyalGold
 
Investor Presentation Aug-Sept 2012
Investor Presentation Aug-Sept 2012Investor Presentation Aug-Sept 2012
Investor Presentation Aug-Sept 2012Sagegold
 
Presentation march - final
Presentation   march - finalPresentation   march - final
Presentation march - finalFirstQuantum
 
Morgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentation
Morgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentationMorgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentation
Morgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentationRoyalGold
 
PVA BMO Investor Presentation a2013
PVA BMO Investor Presentation a2013PVA BMO Investor Presentation a2013
PVA BMO Investor Presentation a2013PennVirginiaCorp
 
Avion Presentation Aug 2010
Avion Presentation Aug 2010Avion Presentation Aug 2010
Avion Presentation Aug 2010Avion Gold Corp
 
Goldman presentation nov 2014 final screen
Goldman presentation nov 2014 final screenGoldman presentation nov 2014 final screen
Goldman presentation nov 2014 final screenRoyalGold
 
Investor Presentation - March 2015
Investor Presentation - March 2015Investor Presentation - March 2015
Investor Presentation - March 2015RowanCompanies
 
Pmd -investor_presentation__jan_2012__final
Pmd  -investor_presentation__jan_2012__finalPmd  -investor_presentation__jan_2012__final
Pmd -investor_presentation__jan_2012__finalPetroMagdalena
 
Sage april 2013__investor_presentation
Sage april 2013__investor_presentationSage april 2013__investor_presentation
Sage april 2013__investor_presentationSagegold
 
Royal Gold's Fourth Quarter and Year End Fiscal 2014 Results
Royal Gold's Fourth Quarter and Year End Fiscal 2014 ResultsRoyal Gold's Fourth Quarter and Year End Fiscal 2014 Results
Royal Gold's Fourth Quarter and Year End Fiscal 2014 ResultsRoyalGold
 

What's hot (20)

17 06 07 nbf conference - toronto
17 06 07   nbf conference - toronto17 06 07   nbf conference - toronto
17 06 07 nbf conference - toronto
 
Corporate Presentation - January 2017
Corporate Presentation - January 2017Corporate Presentation - January 2017
Corporate Presentation - January 2017
 
EDW Presentation
EDW PresentationEDW Presentation
EDW Presentation
 
Nap investor presentation november 2011
Nap investor presentation november 2011Nap investor presentation november 2011
Nap investor presentation november 2011
 
Claude Resources Inc. 2011 Third Quarter Report
Claude Resources Inc. 2011 Third Quarter ReportClaude Resources Inc. 2011 Third Quarter Report
Claude Resources Inc. 2011 Third Quarter Report
 
NAP Investor Presentation June 2014
NAP Investor Presentation June 2014NAP Investor Presentation June 2014
NAP Investor Presentation June 2014
 
Barclays select screen march 2015
Barclays select screen   march 2015Barclays select screen   march 2015
Barclays select screen march 2015
 
Bmo presentation feb 2015 final screen
Bmo presentation   feb 2015 final screenBmo presentation   feb 2015 final screen
Bmo presentation feb 2015 final screen
 
Investor Presentation Aug-Sept 2012
Investor Presentation Aug-Sept 2012Investor Presentation Aug-Sept 2012
Investor Presentation Aug-Sept 2012
 
Presentation march - final
Presentation   march - finalPresentation   march - final
Presentation march - final
 
Investor Presentation November 2014
Investor Presentation November 2014Investor Presentation November 2014
Investor Presentation November 2014
 
Morgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentation
Morgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentationMorgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentation
Morgan Stanley Metals & Mining Corporate Access Day - Royal Gold presentation
 
PVA BMO Investor Presentation a2013
PVA BMO Investor Presentation a2013PVA BMO Investor Presentation a2013
PVA BMO Investor Presentation a2013
 
Avion Presentation Aug 2010
Avion Presentation Aug 2010Avion Presentation Aug 2010
Avion Presentation Aug 2010
 
Goldman presentation nov 2014 final screen
Goldman presentation nov 2014 final screenGoldman presentation nov 2014 final screen
Goldman presentation nov 2014 final screen
 
Investor Presentation - March 2015
Investor Presentation - March 2015Investor Presentation - March 2015
Investor Presentation - March 2015
 
Pmd -investor_presentation__jan_2012__final
Pmd  -investor_presentation__jan_2012__finalPmd  -investor_presentation__jan_2012__final
Pmd -investor_presentation__jan_2012__final
 
Sage april 2013__investor_presentation
Sage april 2013__investor_presentationSage april 2013__investor_presentation
Sage april 2013__investor_presentation
 
Royal Gold's Fourth Quarter and Year End Fiscal 2014 Results
Royal Gold's Fourth Quarter and Year End Fiscal 2014 ResultsRoyal Gold's Fourth Quarter and Year End Fiscal 2014 Results
Royal Gold's Fourth Quarter and Year End Fiscal 2014 Results
 
Marketing July 2015
Marketing July 2015Marketing July 2015
Marketing July 2015
 

Similar to Maverick Gold Project Updated Preliminary Economic Assessment July 9 2014

Cowen and Company 5th Annual Global Metals, Mining & Materials Conference
Cowen and Company 5th Annual Global Metals, Mining & Materials ConferenceCowen and Company 5th Annual Global Metals, Mining & Materials Conference
Cowen and Company 5th Annual Global Metals, Mining & Materials ConferenceRoyalGold
 
Capstone Mining 2014 First Quarter Production Results
Capstone Mining 2014 First Quarter Production ResultsCapstone Mining 2014 First Quarter Production Results
Capstone Mining 2014 First Quarter Production Resultsracialyesterday85
 
Bank of America Merrill Lynch Conference - May 18, 2017
Bank of America Merrill Lynch Conference - May 18, 2017Bank of America Merrill Lynch Conference - May 18, 2017
Bank of America Merrill Lynch Conference - May 18, 2017SemafoCorporate
 
Royal gold slides final october 30 2014
Royal gold slides   final october 30 2014Royal gold slides   final october 30 2014
Royal gold slides final october 30 2014RoyalGold
 
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014Symposium
 
DGF 2014 Presentation
DGF 2014 PresentationDGF 2014 Presentation
DGF 2014 PresentationRichmontIR
 
2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...
2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...
2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...Symposium
 
Raymond James Texas Gold Investor Forum - October 2014
Raymond James Texas Gold Investor Forum - October 2014Raymond James Texas Gold Investor Forum - October 2014
Raymond James Texas Gold Investor Forum - October 2014RoyalGold
 
2016 Annual General Meeting Presentation
2016 Annual General Meeting Presentation2016 Annual General Meeting Presentation
2016 Annual General Meeting PresentationAdnet Communications
 
Investor Presentation - September 2014
Investor Presentation - September 2014Investor Presentation - September 2014
Investor Presentation - September 2014Sagegold
 
Sage May 2014 investor presentation
Sage May 2014 investor presentationSage May 2014 investor presentation
Sage May 2014 investor presentationSagegold
 
Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...
Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...
Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...Symposium
 
Mci drill results may 4 2017 final
Mci drill results may 4 2017 finalMci drill results may 4 2017 final
Mci drill results may 4 2017 finalGorden Glenn
 
Cibc whistler conf jan 2015 final
Cibc whistler conf   jan 2015 finalCibc whistler conf   jan 2015 final
Cibc whistler conf jan 2015 finalRoyalGold
 
Td securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-finalTd securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-finalSemafoCorporate
 
Investor Presentation October 2014
Investor Presentation October 2014Investor Presentation October 2014
Investor Presentation October 2014Sagegold
 

Similar to Maverick Gold Project Updated Preliminary Economic Assessment July 9 2014 (20)

Cowen and Company 5th Annual Global Metals, Mining & Materials Conference
Cowen and Company 5th Annual Global Metals, Mining & Materials ConferenceCowen and Company 5th Annual Global Metals, Mining & Materials Conference
Cowen and Company 5th Annual Global Metals, Mining & Materials Conference
 
Capstone Mining 2014 First Quarter Production Results
Capstone Mining 2014 First Quarter Production ResultsCapstone Mining 2014 First Quarter Production Results
Capstone Mining 2014 First Quarter Production Results
 
Bank of America Merrill Lynch Conference - May 18, 2017
Bank of America Merrill Lynch Conference - May 18, 2017Bank of America Merrill Lynch Conference - May 18, 2017
Bank of America Merrill Lynch Conference - May 18, 2017
 
Royal gold slides final october 30 2014
Royal gold slides   final october 30 2014Royal gold slides   final october 30 2014
Royal gold slides final october 30 2014
 
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
 
DGF 2014 Presentation
DGF 2014 PresentationDGF 2014 Presentation
DGF 2014 Presentation
 
DGF 2014 Presentation
DGF 2014 PresentationDGF 2014 Presentation
DGF 2014 Presentation
 
2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...
2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...
2015 Broken Hill Resources Investment Symposium - Southern Gold (ASX:SAU) - S...
 
Denver Gold Forum 2015
Denver Gold Forum 2015Denver Gold Forum 2015
Denver Gold Forum 2015
 
Raymond James Texas Gold Investor Forum - October 2014
Raymond James Texas Gold Investor Forum - October 2014Raymond James Texas Gold Investor Forum - October 2014
Raymond James Texas Gold Investor Forum - October 2014
 
2016 Annual General Meeting Presentation
2016 Annual General Meeting Presentation2016 Annual General Meeting Presentation
2016 Annual General Meeting Presentation
 
2016 Annual General Meeting
2016 Annual General Meeting2016 Annual General Meeting
2016 Annual General Meeting
 
Investor Presentation - September 2014
Investor Presentation - September 2014Investor Presentation - September 2014
Investor Presentation - September 2014
 
Sage May 2014 investor presentation
Sage May 2014 investor presentationSage May 2014 investor presentation
Sage May 2014 investor presentation
 
Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...
Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...
Investor Presentation | Millennium Materials (ASX:MOY) | Gold Investment Symp...
 
Mci drill results may 4 2017 final
Mci drill results may 4 2017 finalMci drill results may 4 2017 final
Mci drill results may 4 2017 final
 
Cibc whistler conf jan 2015 final
Cibc whistler conf   jan 2015 finalCibc whistler conf   jan 2015 final
Cibc whistler conf jan 2015 final
 
Presentation - November 2015
Presentation - November 2015Presentation - November 2015
Presentation - November 2015
 
Td securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-finalTd securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-final
 
Investor Presentation October 2014
Investor Presentation October 2014Investor Presentation October 2014
Investor Presentation October 2014
 

Recently uploaded

Call Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our Escorts
Call Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our EscortsCall Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our Escorts
Call Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our Escortsindian call girls near you
 
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts PodanurTop Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanurdharasingh5698
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girladitipandeya
 
VIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our Escorts
VIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our EscortsVIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our Escorts
VIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our Escortssonatiwari757
 
Malad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls ServiceMalad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls ServicePooja Nehwal
 
Russian Call Girls Kolkata Indira 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls Kolkata Indira 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls Kolkata Indira 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls Kolkata Indira 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
Corporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdfCorporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdfProbe Gold
 
Q3 FY24 Earnings Conference Call Presentation
Q3 FY24 Earnings Conference Call PresentationQ3 FY24 Earnings Conference Call Presentation
Q3 FY24 Earnings Conference Call PresentationSysco_Investors
 
Call Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service Available
Call Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service AvailableCall Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service Available
Call Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service AvailableSheetaleventcompany
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girladitipandeya
 
BDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort ServiceBDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort ServiceDelhi Call girls
 
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rishra 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Roomdivyansh0kumar0
 

Recently uploaded (20)

Call Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our Escorts
Call Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our EscortsCall Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our Escorts
Call Girls in Friends Colony 9711199171 Delhi Enjoy Call Girls With Our Escorts
 
Call Girls 🫤 East Of Kailash ➡️ 9999965857 ➡️ Delhi 🫦 Russian Escorts FULL ...
Call Girls 🫤 East Of Kailash ➡️ 9999965857  ➡️ Delhi 🫦  Russian Escorts FULL ...Call Girls 🫤 East Of Kailash ➡️ 9999965857  ➡️ Delhi 🫦  Russian Escorts FULL ...
Call Girls 🫤 East Of Kailash ➡️ 9999965857 ➡️ Delhi 🫦 Russian Escorts FULL ...
 
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts PodanurTop Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Miyapur high-profile Call Girl
 
Call Girls In Vasant Kunj 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Vasant Kunj 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In Vasant Kunj 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Vasant Kunj 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
Call Girls Service Green Park @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Green Park @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Green Park @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Green Park @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
VIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our Escorts
VIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our EscortsVIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our Escorts
VIP Amritsar Call Girl 7001035870 Enjoy Call Girls With Our Escorts
 
Malad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls ServiceMalad Escorts, (Pooja 09892124323), Malad Call Girls Service
Malad Escorts, (Pooja 09892124323), Malad Call Girls Service
 
Russian Call Girls Kolkata Indira 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls Kolkata Indira 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls Kolkata Indira 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls Kolkata Indira 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
Russian Call Girls Rohini Sector 3 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 3 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...Russian Call Girls Rohini Sector 3 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 3 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
 
Russian Call Girls Rohini Sector 22 💓 Delhi 9999965857 @Sabina Modi VVIP MODE...
Russian Call Girls Rohini Sector 22 💓 Delhi 9999965857 @Sabina Modi VVIP MODE...Russian Call Girls Rohini Sector 22 💓 Delhi 9999965857 @Sabina Modi VVIP MODE...
Russian Call Girls Rohini Sector 22 💓 Delhi 9999965857 @Sabina Modi VVIP MODE...
 
(👉゚9999965857 ゚)👉 VIP Call Girls Greater Noida 👉 Delhi 👈 : 9999 Cash Payment...
(👉゚9999965857 ゚)👉 VIP Call Girls Greater Noida  👉 Delhi 👈 : 9999 Cash Payment...(👉゚9999965857 ゚)👉 VIP Call Girls Greater Noida  👉 Delhi 👈 : 9999 Cash Payment...
(👉゚9999965857 ゚)👉 VIP Call Girls Greater Noida 👉 Delhi 👈 : 9999 Cash Payment...
 
Call Girls 🫤 Mukherjee Nagar ➡️ 9999965857 ➡️ Delhi 🫦 Russian Escorts FULL ...
Call Girls 🫤 Mukherjee Nagar ➡️ 9999965857  ➡️ Delhi 🫦  Russian Escorts FULL ...Call Girls 🫤 Mukherjee Nagar ➡️ 9999965857  ➡️ Delhi 🫦  Russian Escorts FULL ...
Call Girls 🫤 Mukherjee Nagar ➡️ 9999965857 ➡️ Delhi 🫦 Russian Escorts FULL ...
 
Corporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdfCorporate Presentation Probe May 2024.pdf
Corporate Presentation Probe May 2024.pdf
 
Q3 FY24 Earnings Conference Call Presentation
Q3 FY24 Earnings Conference Call PresentationQ3 FY24 Earnings Conference Call Presentation
Q3 FY24 Earnings Conference Call Presentation
 
Call Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service Available
Call Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service AvailableCall Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service Available
Call Girls Chandigarh Just Call 8868886958 Top Class Call Girl Service Available
 
Call Girls In South Delhi 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In South Delhi 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In South Delhi 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In South Delhi 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Abids high-profile Call Girl
 
BDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort ServiceBDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Hari Nagar Delhi >༒8448380779 Escort Service
 
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rishra 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rishra 👉 8250192130 Available With Room
 

Maverick Gold Project Updated Preliminary Economic Assessment July 9 2014

  • 1. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O Minnova Corp. Issues an Updated Preliminary Economic Assessment for its Maverick Gold Project Toronto, Ontario – Minnova Corp. (TSXV: MCI, ("Minnova” of “the Company”) is pleased to announce it has filed its Updated Preliminary Economic Assessment ("PEA") Technical Report titled "NI 43-101 UPDATED PRELIMINARY ECONOMIC ASSESSMENT OPEN PIT AND UNDERGROUND MINING, AND ON-SITE MILLING AT THE MAVERICK GOLD PROJECT, INCLUDING MINING OF THE PL GOLD DEPOSIT AND THE NOKOMIS GOLD DEPOSIT, Sherridan, Manitoba" on SEDAR at www.sedar.com. The Updated PEA was prepared by ACA Howe International Limited (“Howe”) based on the mineral resource estimates (see April 17, 2014 news release) prepared by P&E Mining Consultants Inc. and Howe on Minnova’s 100% owned Maverick Gold Project. Prior to June 2014 Minnova was called Auriga Gold Corp. ("Auriga Gold"). Prior to this release the PL Property and PL Mine were known as the Puffy Lake Property and Puffy Lake Mine. Currencies reported below are in Canadian dollars unless otherwise specified. Highlights from the Base Case study, which uses a long term gold price of US$1,250 per ounce gold and USD:CAD exchange rate of $1.05, include:  Pre-tax Net Present Value ("NPV") at a 5% discount rate of $97.7 million and an Internal Rate of Return ("IRR") of 59%;  After-tax NPV at a 5% discount rate of $83.3 million and IRR of 55%;  After-tax payback of 1.5 years after plant start-up;  11 year mine life, mining and processing 2.5 million tonnes, averaging 6.53 grams per tonne ("g/t") gold, and producing 483,000 ounces of gold;  Open pit production amounts to 558,000 tonnes at an average diluted grade of 4.41 g/t gold at a LOM strip ratio of 6:1;  Underground production amounts to 1.98 million tonnes an average diluted grade of 7.26 g/t gold;  Total payable gold production of 483,000 ounces with an average Life of Mine (“LOM”) cash cost of US$798 per ounce and average AISC of US$1003 per ounce;  Years 2 to 5 mill feed planned at 900 tpd to produce an average of 52,522 ounces a year at an average cash cost of US$849 per ounce and average AISC of US$991 per ounce;  Years 6 to 10 mill throughput planned at 600 tpd to produce an average of 49,100 ounces a year at cash cost of US$770 per ounce and AISC of US$896 per ounce;  Pre-production (years -1 and 1) capital cost of $26.3 million including a 19% for contingency, environmental bonds and initial working capital;  In Year 1, the projected $12.7 million capital expenditure is partially offset by income of $6.6 million;  Sustaining Capital and Closure Costs of $29.5 million over LOM; Gorden Glenn, President & CEO of Minnova commented, "We are very pleased with the results of this Updated Preliminary Economic Assessment. It confirms the Maverick Gold Project (“MGP”) as a robust project with a low pre-production capital cost, low operating and All In Sustaining Cost’s (“AISC”) and a quick payback of 1.5 years from the start of production on a +10 year mine life.
  • 2. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O Our focus on upgrading the PL and Nokomis resources (see our April 17, 2014 press release) and introducing new innovative underground mining techniques to the mine plan have resulted in a higher overall life of mine gold production, higher average annual production, lower cash operating costs, lower AISC and lower strip ratio over our initial January 2012 Preliminary Economic Assessment (“January 2012 PEA”). Importantly the project’s NPV has remained largely unchanged despite using a lower, more conservative, long-term gold price of US$1,250/oz vs $1,400/oz used in the January 2012 PEA. While the initial capital costs have increased modestly they are more defensible incorporating significant contingency, environmental permitting and bonding, and working capital considerations, which were not fully factored into the January 2012 PEA. The completion of this updated PEA marks another significant milestone for Minnova and we can now move forward with our plans for a test underground stope program to validate the SAMSTM underground mining method, finalize and update all required operating permits and complete a Feasibility Study by the end of 2014. Upon completion of the Feasibility Study we anticipate we could be initiating construction/rehabilitation of the mine and mill infrastructure in early 2015 toward achieving initial production in the second half of 2015.” UPDATED MAVERICK GOLD PROJECT DEVELOPMENT PLAN The Maverick Gold Project updated development plan includes the following: Pre-production Year -1 (starts July 1, 2014) • Complete an initial underground test mining program at the PL underground mine;  Finalize all environmental and operating permits • By the end of 2014 complete a Feasibility Study (“FS”) Development and Production Years 1 - 11 (starts July 1, 2015)  Assuming positive FS, starting in January 2015 initiate the refurbishment and reactivation of the existing PL mill and underground mine; • Sequential development of five open pits on the PL Deposit and another on the Nokomis Deposit; Closure and Rehabilitation • Progressive mine closure activity and planning;  Mine closure in year 11 to be followed by and a post-closure monitoring program. Forecast Gold Production Howe estimates total mill feed to be 2.53 million tonnes at an average diluted grade of 6.58g/t. Of this approximately 1.98 million tonnes at an average diluted grade of 7.26 g/t would be sourced from underground mine on the PL deposit and 0.59 million tonnes would be sourced from shallow open pits at an average diluted grade of 4.17 g/t Au. At full production from open pits and underground (900 tpd) in years 2 through 5 average annual production is estimated at approximately 52,500 ounces and will drop to an average of 49,000 ounces
  • 3. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O during years 6 through 10 when the pits are depleted (underground only) and mill throughput drops to 600tpd. Years 1 and 11 are partial years. Total recoverable gold production over the LOM is estimated at 483,000 ounces for an average annual production rate of approximately 48,100 ounces of gold. The project development schedule is shown in Figure 1. Figure 1: Summary of Projected Annual Gold Production, Cash Operating Costs and AISC Preliminary Economic Assessment The Maverick Gold Project was assessed using a discounted cashflow approach with a Base Case long-term gold price of US$1,250/oz and a USD:CAD exchange rate of 1.05. The results of the economic analysis, summarized in Table 1 and Table 2, support advancing the project and completing a FS by the end of 2014. Undiscounted after-tax cashflow amounts to $125.7 million and returns a robust IRR of 55%. Table1: Results of the Economic Analysis Pre-tax After-tax IRR 59% 55% Undiscounted NPV ($M) $146.20 $125.70 NPV (5%) ($M) $97.70 $83.80 NPV (8%) ($M) $77.50 $66.40 Payback 3 yrs from start of development 1.5 yrs from start of production $ oz $200 oz $400 oz $600 oz $800 oz $1,000 oz $1,200 oz $1,400 oz $1,600 oz $1,800 oz oz 10,000 oz 20,000 oz 30,000 oz 40,000 oz 50,000 oz 60,000 oz 70,000 oz 1 2 3 4 5 6 7 8 9 10 11 Open Pits (LHS) Underground (LHS) Total Cash Costs (RHS) AISC (RHS)
  • 4. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O Table 2: Results of the Cashflow Analysis Undiscounted LOM Total (000's) Discounted at 5% (000's) Discounted at 8% (000's) IRR (%) Gross Sales $629,632 $475,868 $408,206 Less royalties $18,291 $13,785 $11,807 Less selling expenses $2,900 $2,191 $1,880 Net Sales Revenue $608,441 $459,890 $394,519 Mining costs $306,573 $221,457 $185,021 Processing costs $67,399 $48,613 $40,602 G&A costs $32,461 $23,311 $19,424 Total cash operating costs $406,434 $293,381 $245,048 Net cash operating margin $202,006 $144,609 $120,247 Initial capital $26,299 $24,471 $23,481 Sustaining capital $29,504 $24,722 $22,430 Net cash flow before tax $146,203 $97,713 $77,535 59% Taxation payable $20,463 $13,845 $11,103 Net cash flow after tax $125,739 $83,867 $66,432 55%
  • 5. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O Resources Together the PL and Nokomis gold deposits support mineral resources amenable to open pit and underground mining that include Measured and Indicated mineral resources totalling 327,900 ounces of gold and Inferred mineral resources of 438,600 ounces of gold. See mineral resource summary in Table 3 and Table 4 below. Table 3: PL Deposit Mineral Resource Estimate as of April 17, 2014 Class Au Cut-off g/t Tonnes Au g/t Contained Au oz In-Pit Measured 0.6 123,000 4.41 17,400 Indicated 0.6 445,000 4.40 63,000 M+I 0.6 568,000 4.40 80,400 Inferred 0.6 45,000 4.87 7,000 Out-of-Pit Measured 2.5 27,000 5.12 4,500 Indicated 2.5 1,057,000 5.95 202,300 M+I 2.5 1,084,000 5.93 206,800 Inferred 2.5 2,135,000 6.01 412,500 Total Measured 0.6/2.5 150,000 4.54 21,900 Indicated 0.6/2.5 1,502,000 5.49 265,300 M+I 0.6/2.5 1,652,000 5.41 287,200 Inferred 0.6/2.5 2,180,000 5.99 419,500 Notes PL Deposit: 1. The volume of the historical mined areas was depleted from the resource estimate. Table 4: Nokomis Mineral Resource Estimate Statement as of April 17, 2014 Class Reporting Cut-off g/t Au Tonnes Grade g/t Au Contained Au oz Indicated 0.6 371,000 3.41 41,000 Inferred 0.6 247,000 2.41 19,000 Notes PL and Nokomis Deposits: 1. The quantity and grade of reported Inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred resources as an Indicated or Measured mineral resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured mineral resource category. 2. The PL updated NI 43-101 compliant mineral resource estimate has been prepared by Mr. Eugene Puritch, P.Eng. of P&E Mining Consultants Inc.. The Nokomis NI 43-101 compliant mineral resource was prepared by Leon McGarry, B.Sc., P.Geo., of ACA Howe International Limited. 3. The NI 43-101 compliant mineral resources in this press release were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council. 4. Grade capping of 30g/t Au was utilized on composites at the PL Deposit and grade capping of 50g/t Au was utilized on raw assays at the Nokomis Deposit.
  • 6. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O 5. Bulk densities of 2.72 t/m3 and 2.89t/m3, respectively were used for tonnage calculations at the PL Deposit and Nokomis Deposits, respectively. 6. At the PL gold deposit open pit resources are reported within an optimized pit shell. 7. A gold price of US$1,300/oz and an exchange rate of US$0.97US=C$1.00 was utilized in the Au cut-off grade calculations of 0.6 g/t open pit and 2.5 g/t underground. Open pit mining costs were C$3.75/t for mineralized material and C$3.00/t for waste rock while underground mining costs were C$75/t. Process costs were C$17/t and G&A was C$6/t. Process recovery used was 95%. 8. Tonnes and ounces have been rounded to reflect the relative accuracy of the mineral resource estimate; therefore numbers may not total correctly. 9. Mineral Resource tonnes quoted are not diluted. 10. Mineral resources are not mineral reserves and by definition do not demonstrate economic viability. This mineral resource estimate includes inferred mineral resources that are normally considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is also no certainty that these inferred mineral resources will be converted to the measured and indicated resource categories through further drilling, or into mineral reserves, once economic considerations are applied. 11. 1 troy ounce equals 31.10348 grams. Mining Model Construction The mine plan developed for the Updated PEA considers the re-opening of the PL underground mine and the development of five new open pits on the PL gold property and another on the Nokomis gold property. The relative contribution of open pit and underground feed to the mill has been optimized to so as to generate the highest value early in the mine life. This is done to accelerate capital payback and maximize cash flow and hence deliver the highest Net Present Value. The defining variables used for this work are summarized in Table 5 and Table 6 below. Table 5: Parameters used to create the financial model for the Maverick Gold Project (PL and Nokomis Gold Deposits) Parameter Unit Values Au price US$/oz 1,250 Exchange rate USD:CAD 1.05 Au recovery % 90 Au payable % 99 Selling costs (Au refining, transportation and insurance) US$/payable oz 6
  • 7. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O Table 6: Maverick Gold Project Estimated Unit Operating Costs Item Unit Operating Costs Open pit mining costs: Mining cost $7.50 / t potentially economic mineralization Definition drilling and grade control assays $3.00 / t potentially economic mineralization Overburden Stripping $1.88 / t overburden Waste rock stripping cost $6.00 / t waste rock Muskeg removal allowance $2.0 M Underground development and mining costs: Typical lateral development cost $5,100 / m for drift and ramp development Production stoping cost $50.00 / t potentially economic mineralization Underground mine indirect operating costs $38.00 / t potentially economic mineralization Underground haul to mill $2.00 / t potentially economic mineralization Processing cost yrs 1-5; $22.24 /t, yr 6; $26.00 /t, yrs 7-11: $29.79 /t processed Tailings management cost yrs 1-5; $1.00 /t, yr 6; $1.27 /t, yrs 7-11: $1.50 /t processed General and Administration cost yrs 1-5; $10.51 /t, yr 6; $13.34 /t, yrs 7-11: $15.77 /t processed Production royalties 3% at PL deposit, 2% at Nokomis deposit (2.92% overall) Projected corporate taxes 15% federal & 10% provincial. Figure 2: Image showing the PL deposit open pits 1 through 5 and underground block model. Open pit mining would be done using conventional open pit equipment and technologies. Underground mining would be done using Minrail Inc.’s Shallow Angle Mining System (SAMSTM) which would first be demonstrated in a test stope. The SAMSTM is designed to underground mine flat dipping zones. It uses
  • 8. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O back-mounted rails and suspended interchangeable drilling, blasting and mucking modules. Stopes would paste backfilled once mined out. The mines would operate 350 days/year on a two 10 hour shifts per day basis with four rotating crews. The mill would operate on a two 12 hour shifts per day basis with four rotating crews. The Nokomis satellite deposit, located less than 8 kilometres to the northeast, will be incorporated into the mine plan in year 3 enabling mill feed to be sustained at 900tpd for years 2 through 5. In years 6 through 11 mine output will consist of underground mineralization only and the mill feed rate will drop to 600tpd. Figure 3: Nokomis pit, facing east-northeast SAMSTM represents an innovated new technology that is designed to ensure and enhance operator safety while improving productivity. The electric-powered modules have multiple braking systems including a failsafe braking system. Minrail has reviewed its safety devices with mine safety regulators in Ontario and Quebec and reports that the SAMSTM system meets rigorous mine safety requirements in those jurisdictions. The proposed test stoping program at the PL underground mine would be reviewed with Manitoba health and safety regulatory authorities prior to the test. Figure 4: Driving the stope centre raise using SAMSTM
  • 9. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O Processing The existing process plant has a name plate capacity of 1,000 tonnes per day and has been on care and maintenance since April 1989. It is proposed to rehabilitate and use the existing PL mill for processing. It is anticipated that, although process modifications and equipment additions may be indicated by future testwork, the historical flowsheet will be satisfactory. The initial throughput rate for this study is 900 t/d which will yield a nominal grind (K80) of approximately 110 microns utilizing the existing conventional crushing and grinding circuits. Based on planned tonnage and grade and assuming continuous stable operation, an overall gold recovery of 90% is projected. This recovery estimate would be confirmed by testwork on samples representing the current mining plan. Infrastructure The Maverick Gold Project is accessible by all-weather road and there is a commercial rail line within 7 kilometers for the property for delivery of bulk supplies. Power would be provided Manitoba Hydro which requires modest extensions and upgrades of existing transmission lines to the site. A back-up power supply would be provided from diesel generators already located at site. Manitoba Hydro is a reliable, low cost source of power. As described in the Updated PEA report Minnova plan to conduct a fish population survey of the Ragged TMA this summer. This PEA assumes that the Ragged TMA would continue to be utilized for tailings management. Capital Costs The initial capital requirement in years -1 and 1 for the Project is estimated to be US$26.3M, as detailed in Table 7. This amount includes 19% for contingency, environmental bonds and initial working capital. Year 1, the projected $12.7 million capital expenditure is partially offset by income of $6.6 million. Table 7: Maverick Gold Project Pre-production Capital Cost Estimate as of July 9, 2014 Item Pre-production Production Total ($k) ($k) ($k) Yr -1 Yr 1 Yrs 2-11 Months 1-12 Months 1-7 Months 8-12 Months 13 - EML Mill running Test stoping $4,342 $4,342 Feasibility study and supporting studies $415 $415 Mill rehabilitation and commissioning $6,245 $3,898 $280 $10,423 Infrastructure $1,550 $475 $2,999 $5,024
  • 10. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O Underground mine $3,390 $0 $15,575 $18,965 Paste backfill plant $5,000 $5,000 Open Pits including muskeg removal $314 $2,250 $2,564 Environmental projects $540 $100 $0 $100 $740 Mine closure $500 $0 $5,300 $5,800 Working Capital $2,000 -$2,000 $0 Sub Total $13,092 $8,677 $2,000 $29,504 $53,273 Contingency $530 $2,000 $2,530 Total $13,622 $12,677 $29,504 $55,803 Cumulative Capital $13,622 $26,299 $55,803 The Project has a total sustaining capital requirement of $29.5M. Closure costs amount to $5.8M. Start-up capital contingency plus closure bond and working capital amounts to $4.5M. Financial Analysis and Sensitivities Using a gold price of $1,250/oz, the study yields a pre-tax NPV8% of $77.5 million and IRR of 59%. After-tax NPV8% amounts to $66.4 million and an IRR of 55%. The results of the sensitivity analysis for the Base Case are shown in Table 8 and indicate that the project is most sensitive to changes in gold price and head grade, and least sensitive to changes in capital cost. It must be noted that all economic results reported in a PEA are preliminary in nature and as such may vary considerably from actual results. The project does not currently have any mineral reserves as the declaration of reserves requires at least a pre-feasibility study to be completed. Table 8: Results of Sensitivity Analysis of the Base Case Parameter After-Tax NPV (8%) ($M) Variation of Parameter Relative to Base Case -40% -30% -20% -10% 0% 10% 20% 30% 40% Head Grade -$43 -$16 $12 $39 $66 $94 $121 $149 $176 Gold Price -$44 -$16 $11 $39 $66 $94 $122 $149 $177 Operating Costs $140 $122 $103 $85 $66 $48 $30 $11 -$7 Capital Costs $77 $74 $72 $69 $66 $64 $61 $59 $56 Qualified Persons The PEA was conducted under the overall review of David Orava, M. Eng., P. Eng. of ACA Howe International Ltd. of Toronto Ontario with the following Qualified Persons contributing to their respective sections: Alfred Hayden P.Eng., Senior Associate Metallurgical Engineer, ACA Howe International Ltd. David Burga P.Geo., Geologist, P&E Mining Consultants Inc. Eugene Puritch P.Eng., President, P&E Mining Consultants Inc. Felix Lee P.Geo., Senior Geologist, ACA Howe International Ltd. Leon McGarry P.Geo., Project Geologist, ACA Howe International Ltd. William Douglas Roy, M.A.Sc. P.Eng., Senior Associate Mining Engineer, ACA Howe International Ltd. Yungang Wu P.Geo., Geologist, P&E Mining Consultants Inc.
  • 11. ` Minnova Corp. Office: +1 647 985 2785 MCI:TSXV 365 Bay Street, Suite 400 www.minnovacorp.ca Toronto, Ontario M5H 2V1 MINN VA CORP. O The foregoing Qualified Persons have verified that the data from the PEA is fairly and accurately disclosed in this news release. About Minnova Corp. Minnova Corp. is an emerging Canadian gold producer focused on re-starting the PL Mine and expanding gold resources on its PL and Nokomis gold deposits (collectively the "Maverick Gold Project"). The Company has completed an Updated PEA which supports average annual production of 48,100 ounces over a +10 year mine life. Work to date strongly supports advancing the project toward production with an initial program of underground test mining and completion of a Feasibility Study to bring the PL Mine back into production. The PL Mine includes a 1,000 tpd flotation mill with a replacement value in excess of $50 million, over 7,000 meters of developed underground ramp to 135 metres depth, is fully road accessible and close to existing mining infrastructure. The Maverick Gold Project is located in the Flin Flon Greenstone Belt of Central Manitoba. To view current images of the property and mill, please see www.minnovacorp.ca/s/photogallery.asp For more information please contact: Minnova Corp. Gorden Glenn Chairman, President and CEO gglenn@minnovacorp.ca Phone: +1 (647) 985 2785 info@minnovacorp.ca http://www.minnovacorp.ca CHF Investor Relations Cathy Hume CEO Tel: +1 (416) 868 1079 ext.231 Email: cathy@chfir.com www.chfir.com Renmark Financial Communications Inc. Barry Mire: bmire@renmarkfinancial.com Laurence A. Lachance: llachance@renmarkfinancial.com Tel.: +1 (416) 644 2020 or +1 (514) 939 3989 www.renmarkfinancial.com This news release contains "forward-looking information" within the meaning of applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, information regarding the Company including management’s assessment of future plans and operations, that may involve risks associated with mining exploration and development, volatility of prices, currency fluctuations, imprecision of resource estimates, environmental and permitting risks, access to labour and services, competition from other companies and ability to access sufficient capital. As a consequence, actual results may differ materially from those anticipated in the forward looking statements. A feasibility study has not been completed and there is no certainty the disclosed targets will be achieved nor that the proposed operations will be economically viable. Although Minnova has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. Minnova does not undertake to update any forward-looking information, except in accordance with applicable securities laws. Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.