SlideShare a Scribd company logo
1 of 29
Download to read offline
Hypersonic Airplane Space Tether 
Orbital Launch -- HASTOL 
NASA Institute for Advanced Concepts 
3rd Annual Meeting 
NASA Ames Research Center, San Jose, CA 
June 6, 2001 
John E. Grant 
The Boeing Company, 5301 Bolsa Ave., Huntington Beach, CA92647-2099 
Phone 714-372-5391 john.e.grant@boeing.com www.boeing.com 
NIAC Subcontract No. 07600-040
HASTOL Phase II Study Team 
The Boeing Company 
John Grant, Phantom Works, Huntington Beach, CA 
Kimberly Harris, Phantom Works, Huntington Beach, CA 
Jim Martin, Phantom Works, Huntington Beach, CA 
Dan Nowlan, Phantom Works, Huntington Beach, CA 
Karl Oittinen, Expendable Launch Systems, Huntington Beach, CA 
Don Johnson, Phantom Works, St. Louis, MO 
Steve Hollowell, Phantom Works, Long Beach, CA 
Mike Bangham, Space and Communications, Huntsville, AL 
Beth Fleming, Space and Communications, Huntsville, AL 
John Blumer, Space and Communications, Huntsville, AL 
Ben Donahue, Space and Communications, Huntsville, AL 
Brian Tillotson, Space and Communications, Seattle, WA 
Tethers Unlimited, Inc. 
Rob Hoyt, Seattle, WA 
Bob Forward, Seattle, WA 
HASTOL Contract funded by NASA Institute for Advanced Concepts 
Dr. Robert Cassanova, Atlanta, Georgia
HASTOL Concept of Operation
HASTOL Phase I Results Showed 
Concept Feasibility 
• Top -Level Requirements Developed; Top-Level Trades 
Conducted to Define Basic Design Approaches 
• Selected Hypersonic Aircraft Concept (DF-9) 
• Validated Overlap of Tether Tip and Hypersonic Aircraft 
Velocity and Geometry Envelopes for Capture 
– Defined Aircraft Apogee Altitude/Velocity Envelope 
– Tether Tip Can Withstand Thermal Loads as it Dips into 
the Atmosphere 
• Tether Boost Facility Concept Defined 
• Rotovator Tether Concept Selected 
• Simplified Grapple Concept Identified
HASTOL Phase II Study Approach 
Phase I R esults 
• R otovator concept 
• Technology Readiness Level 2 systems (hypersonic airplane, tether control station, tether, grapple assem bly, payload accommodation assembly) 
• T rade study results: discovery that rendezvous point can be achieved by existing airplane (X-43) w ithout overheating tether tip 
• Selected concepts 
- DF-9 hypersonic vehicle 
- R endezvous point at Mach 10, 100-km altitude 
- HoytetherTM w ith Spectra2000TM m aterial and PBO tip m aterial 
Hypersonic Airplane Space Tether O rbital Launch (HASTOL) S tudy Program, Phase II 
Task 1 M ission Opportunities Definition 
• Develop contact plan 
• Conduct kick-off w ith potential customers and N IAC 
• Meet with customers to assess potential m issions 
and near-term applications 
• Identify opportunities to integrate into NASA 
programs 
Task 2 System Requirements Definition 
• Derive preliminary system requirements for each of 
the HASTOL systems 
• Determine payload characteristics, traffic rate, 
guidance and control, g-force limitations, initial and life 
cycle costs, and system interface requirements 
• Identify, define, allocate, and trade m ajor system 
requirements 
Task 3 Conceptual Design 
• Integrate into system architecture 
• C onduct trade studies 
• D evelop ROM cost estimate 
Task 4 System Analysis 
• C onduct m odeling and simulations 
• C onduct preliminary technical assessment 
- Identify high-risk areas 
- D evelop m itigation plans 
Task 5 Technology Development Planning 
• Identify technology needs 
• Develop technology development roadmap 
- F light test plan 
- Laboratory tests 
Candidate 
list of 
mission 
needs 
Phase II D eliverables 
• Final Phase II program review 
• Phase II final report 
– System requirements 
– Complete system design concept to TRL 3 
– Areas of development work needed 
– Technology roadmap 
– Cost models 
• Phase III customer funding commitment 
– Analyze key technical issues 
✔ GN&C 
✔ Payload transfer operations 
✔ Tether design and dynamics 
✔ Material selection 
✔ Simulation results
Markets Drive Requirements 
• Current & Emerging Markets 
– GEO Comsats 
– US Civil Satellites 
– US Military Satellites 
– Small-Vehicle Tourism 
– Mission Requirements at IOC 
• Future Markets 
– Human Exploration & Development of Space 
– Solar Power Satellites 
– Large-Vehicle Tourism 
– Mission Requirements for Extended 
Operation Capability
Total Existing Markets 
• Dominated by GEO Comsats => size HASTOL for that market 
– GEO destination matches HASTOL well 
– Aggressive pricing required 
• Other markets offer targets of opportunity, not core business 
– Extra revenue 
– Protection from non-US competition allows higher prices 
GEO Comsats 
100 
300 
500 
700 
900 
2000 
4000 
6000 
8000 
10000 
14000 
2010 
2015 
2020 
12 
10 
8 
6 
4 
2 
0 
number 
mass (lb) year 
• Total 2010 Market 
– ~33 Launches / yr 
– $1.5 B / yr revenue 
– 50% revenue capture?
Surveys Show Space Adventure Travel 
Is Large And Elastic Market 
Market likely stronger than data suggest 
•Survey data several years old 
•Economy has grown since then 
•Wealth more concentrated in top strata 
•Upper strata include more young & 
adventurous people than in the past 
Annual Passengers 
1K 10K 100K 1M 
100 1K 10K 100K 1M 10M 
Annual Passengers 
Seat Price 
Ivan Bekey, Economically Viable Public Space Travel, Space 
Energy and Transportation, vol 4, No 1,2, 1999.
Tourism Market Projection
Comsat and Passenger Flights Drive 
IOC Mission Requirements 
• Payload mass: 5500 kg 
• Release orbits: GTO + assured safe re-entry orbit 
• Release orbit insertion error to GTO: < Ariane 5 and Delta 4 error 
• Passenger orbit insertion error: not to exceed safe entry limits 
• Epoch: 2015 to 2025 
• Mission reliability: 98% for comsats, 99% for passengers 
• Mission safety: 
– 99% chance that comsat payloads will be undamaged 
– 99.99% chance that passengers will survive 
• Orbital debris produced: zero 
• Collision avoidance: “shall not endanger any tracked operational 
spacecraft”
Extended Operational Capability 
Mission Requirements 
HEDS and SPS Drive Requirements 
• Payload mass: 36,000 kg 
• Release orbits: GTO + transfer orbit to Earth-Moon L1 
• Release orbit insertion error: < Saturn V error 
• Rate: 1000 SPS flights / yr, 15 HEDS flights / yr 
• Epoch: 2020 to 2030 
• Mission reliability: 98% for HEDS & SPS 
• Mission safety: 99% chance that HEDS & SPS payloads will 
be undamaged 
• Orbital debris produced: zero (incl. lunar downmass)
HASTOL Phase I Hypersonic Aircraft Concept: 
Boeing-NASA/LaRC DF-9 Dual-Fuel Aerospaceplane 
Takeoff Wt: 270 MT (590,000 lb) 
Payload: 14 MT (30,000 lb) 
Length: 64 m (209 ft) 
Apogee: 100 km 
Speed at Apogee: 3.6 km/sec 
(approx. Mach 12) 
4.1 km/sec 
(inertial) 
Turboramjets up to Mach 4.5 
Ram-, Scramjets above Mach 4.5 
Linear Rocket for Pop-Up Maneuver
Variation with Rendezvous Velocity 
• Determined System Design for Hypersonic Airplane 
Apogee Velocities of Mach 10-19 
HASTOL Tether Facility Parameter Variations with Initial Payload Parameter Variations - 600 km - TCS 10X 
Fixed Parameters 
Tether length 600km 
TCS Mass 150 Mg (10X payload mass) 
Payload Mass 15 Mg 
Tether Safety Factor 3.0 along entire length 
Rendezvous Facility Mass Ratio Tip Altitude GTO 
Run Velocity Altitude Accel CM Peri CM Apo Tip Vel TCS Tether Total Perigee Apogee Apogee 
(Mach) (m/s) (km) (n.mi.) (gees) (km) (km) (m/s) (ratio) (ratio) (ratio) (km) (km) (X Geo) 
3111 19.0 5791 113 61 0.88 549 1314 1977 10 16 26 80 186 1.00 
3007 18.0 5486 110 60 1.18 540 1012 2229 10 28 38 88 80 1.44 
3010 17.0 5182 110 60 1.55 522 835 2502 10 51 61 97 80 2.76 
3015 16.0 4877 110 60 1.96 512 701 2780 10 94 104 102 80 13.51 
3032 15.0 4572 110 80 2.40 509 612 3064 10 175 185 106 80 -8.66 
3031 14.0 4267 110 60 2.86 511 559 3353 10 331 341 108 80 -2.49 
3030 13.0 3962 110 60 3.33 517 531 3645 10 638 648 109 80 -1.68 
3027 12.0 3658 110 60 3.82 524 524 3941 10 1253 1263 109 85 -1.31 
3029 11.0 3353 110 60 4.33 533 533 4241 10 2515 2525 110 97 -1.09 
3028 10.0 3048 110 60 4.87 542 542 4541 10 5108 5118 110 103 -0.95
Broad Range of Mission Profiles and 
Propulsion Systems Considered 
Vertical Launch, Downrange Land Vertical Launch, Flyback Rocket 
Burnout at Mach 17, 150 km 
Vertical 
Takeoff 
Gliding 
Entry 
Horizontal 
Landing 
Rocket 
Burnout a t Mach 17 , 15 0 km 
Vertical 
Takeo ff 
G lid ing 
Entry w ith 
Turn 
F lyback 
Horizontal 
Landing 
Air Launched Rocket Air-Turborocket Turboramjet Booster and Rocket 
Burnout at Mach 17, 150 km 
Gliding 
Entry with 
Turn 
Horizontal 
Landing 
Rocket 
Horizontal 
Takeoff 
Launch 
Uprange 
Cruise 
Turn 
Airplane 
Cruiseback 
Burnout at Mach 17, 150 km 
Gliding 
Entry with 
Turn 
Horizontal 
Landing 
Air- Rocket 
turborocket 
Horizontal 
Takeoff 
Launch 
Uprange 
Cruise 
Turn 
Airplane 
Cruiseback 
Switch at 
Mach 6 
Burnout at Mach 17, 150 km 
Gliding 
Entry with 
Turn 
Horizontal 
Landing 
RBCC 
rocket 
Mach 10 
Switch 
Horizontal 
Takeoff 
Launch 
Uprange 
Cruise 
Turn 
Airplane 
Cruiseback 
RBCC 
airbreathing 
Launch at 
Mach 4 
Burnout at Mach 17, 150 km 
RBCC Rocket 
High-Speed 
Turn 
Horizontal 
Takeoff 
MAGLEV 
Rocket 
Gliding 
Entry with 
Turn 
Mach 4 
Flyback 
Horizontal 
Landing 
Uprange 
Acceleration 
Mach 10 
Switch 
Burnout at Mach 17, 150 km 
Gliding 
Entry with 
Turn 
Horizontal 
Horizontal Landing 
Takeoff 
MAGLEV 
Turboramjet 
Uprange 
Cruise 
Turn 
Turboramjet 
Cruiseback 
Air Launched RBCC Single Stage Airbreather (RBCC)
HASTOL Phase II Hypersonic Aircraft Concept: 
Air Launched Turbo-Rocket 
Takeoff Wt: 177 MT (390,883 lb) 
Payload: 7 MT (15,000 lb) 
Payload bay: 3 m dia x 9.1 m (10 ft x 30 ft) 
Apogee: 150 km 
Air- Rocket 
turborocket 
Launch 
Speed at Apogee: 5.2 km/sec 
(approx. Mach 17) 
5.7 km/sec 
(inertial) 
Air-turborocket to Mach 6 
Linear Rocket above Mach 6 
138’ 11’’ 
54’ 2’’ 17’ 5’’ 
Burnout at Mach 17, 150 km 
Gliding 
Entry with 
Turn 
Horizontal 
Landing 
Horizontal 
Takeoff 
Uprange 
Cruise 
Turn 
Airplane 
Cruiseback 
Switch at 
Mach 6
HASTOL Tether Facility Design 
Mass Ratios: 
• Control Station 10x payload 
• Tether 58.8x 
• Grapple 0.12 
• TOTAL: ~ 69 x payload 
Tether Length: 630 km 
Orbit: 
• 582x805 km ->569x499 
Maximum Total ΔV ~ 5 km/s 
Capability to toss payload 
to 107,542 km 
Tosses to GTO by releasing 
off-vertical 
System Masses Tether Characteristics 
Tether mass 323,311 kg Tether Length 636,300 m 
CS Active Mass 51,510 kg Tether mass ratio 58.78 
CS Ballast Mass 3490 kg Tether tip velocity at catch 2,517 m/s 
Grapple mass 650 kg Tether tip velocity at toss 2,481 m/s 
Total Facility Mass 378,961 kg Tether angular rate 0.00583 rad/s 
Gravity at Control Station 0.73 g 
Total Launch Mass 375,471 kg Gravity at payload 1.48 g 
Rendezvous acceleration 1.50 g 
Payload Mass 5,500 kg 
Joined 
System 
Pre-Catch Post-Toss 
Positions & Velocities Payload Tether Post-catch Tether Payload 
resonance ratio 41 20 1 26.0 
perigee altitude km -4603 582 576 569 1001 
apogee altitude km 150 805 650 499 107542 
perigee radius km 1775 6960 6954 6948 7379 
apogee radius km 6528 7183 7028 6877 113921 
perigee velocity m/s 18789 7627 7591 7555 10073 
apogee velocity m/s 5110 7390 7511 7632 652 
CM dist. From Station m 204469 210647 204469 
CM dist. To Grapple m 431831 425653 431831 
²V to Reboost m/s 72 
²V to Correct Apogee m/s -484 
²V to Correct Precess. m/s 416 
²V To Circularize m/s 1218 
Basic Orbital Parameters 
semi-major axis km 4152 7072 6991 6912 60650 
eccentricity 0.6 0.016 0.005 -0.005 0.878 
inclination rad 0 0 0 0 0 
semi-latus rectum km 2792 7070 6991 6912 13861 
sp. mech. energy m2/s2 -4.80E+07 -2.82E+07 -2.85E+07 -2.88E+07 -3.29E+06 
vis-viva energy m2/s2 -9.60E+07 -5.64E+07 -5.70E+07 -5.77E+07 -6.57E+06 
period sec 2662 5918 5817 5720 148647 
period min 44.4 98.6 97.0 95.3 2477.5 
station rotation period sec 1077.8 1077.8 1077.8 
rotation ratio 5.5 5.4 5.3 
2.00E+01 
1.00E+01 
0.00E+00 
-1.00E+01 
-2.00E+01 
630000 598500 567000 535500 504000 472500 441000 409500 378000 346500 315000 283500 252000 220500 189000 157500 126000 94500 63000 31500 0 
Distance From Control Station 
Radius 
(mm)
Boost Facility Concept 
Control Station w/ 
Power Expansion Modules 
Power Expansion Module w/ PV arrays 
Tether Expansion Module 
Tether Length/Dia 
Grapple Assembly 
not to scale
Operational HASTOL Control Station 
Initial Subsystem Mass Allocations 
Subsystems Mass, kg. 
Thermal Control 1,970 
Cabling/Harnesses 1,380 
Structure 4,730 
Electrical Power (EPS) & Tether Power 9,060 
Command & Data Handling (C&DH) and Communication 200 
Attitude Determination & Control (ADCS) and Guidance & 
590 
Navigation (GN&C) 
Tether Deployment and Control (TDCS) 1,380 
Docking 
Ballast 
390 
35,300 
Control Station mass ≈ 55,000 kg
Phase I Results Show Feasibility of 
Payload Capture 
• Tether-Payload Rendezvous Capability 
is a Key Enabling Technology 
• TUI Developed Methods for Extending 
Rendezvous Window 
– Works in Simulation 
– Validation Experiments Needed
Relative Position of Grapple and Payload 
Relative Position of Grapple 
70000 
60000 
50000 
40000 
30000 
20000 
10000 
0 
-10000 
1,000 Km Tether Case, 4,100 m/s Rendezvous; Hypersonic A/C Coordinate System 
Before Grapple After Grapple 
Time Before Grapple 
60 Seconds 
Time After Grapple 
30 Seconds 
10 Seconds 
20 
Hypersonic Aircraft Pop-Up Apogee is at 
335,000 Feet; 13,450 Ft/Sec (Mach 15.2) 
-4000 -3000 -2000 -1000 0 1000 2000 3000 4000 
Horizontal Distance - Ft 
Vertical Distance - Ft 
60 Seconds 
10 
30 
Aft Forward
Relative Position of Grapple and Payload 
Relative Position of Grapple 
2000 
1600 
1200 
800 
400 
0 
-400 
Time Before Grapple 
Time After Grapple 
5 Seconds 5 Seconds 
1 Second 1 Second 
Distances 
26 Ft, 1680 Ft 
6 Ft, 420 Ft 
1 Ft, 17 Ft 
0 Ft, 0 Ft 
-2000 -1600 -1200 -800 -400 0 400 800 1200 1600 2000 
Horizontal Distance - Ft 
Vertical Distance - Ft 
1,000 Km Tether Case, 4,100 m/s Rendezvous; Hypersonic A/C Coordinate System 
10 Seconds 
10 Seconds 
Hypersonic Aircraft Pop-Up Apogee is at 
335,000 Feet; 13,450 Ft/Sec (Mach 15.2) 
Aft Forward
Visual 6-DOF Simulation Validates 
Rendezvous and Capture Scenario
R&C Scenario 
Timeline/Sequence of Events 
Time 
(sec) 
0 
5 
15 
30 
45 
58 
60 
65 
120 
Event 
Start R&C scenario 
Initiate guidance predictions 
Issue P/L bay door discrete 
Issue P/L rotation mechanism commands 
P/L rotation complete 
Issue grapple assembly release discrete 
Nominal capture point 
End grapple assembly freefall 
End R&C scenario
Possible Follow-on Projects and Tasks 
• Ground-Based Rendezvous and Capture Demo 
• Detailed rendezvous and capture simulation and analysis. 
• More detailed design of operational grapple 
• Detailed design of demo hardware 
• Sub-Scale Electrodynamic Tether Dynamics Experiments 
• Secondary payload 
• 4-5 km long ED tether; assess tether dynamics, survivability 
• Sub-scale tether system to capture and toss payloads 
• Four phase program: 
• Design 
• Fabrication and ground testing 
• Flight experiment 
• 1st, tether is in circular orbit just a little higher than payload and 
hanging. Then, tether and payload rendezvous and capture (low relative 
speed). Tether then uses thrust to start rotating and throw payload. 
• 2nd, tether is in a higher elliptic orbit and rotating slowly. It rendezvous 
with payload (moderate relative speed), rotates, and tosses. 
• 3rd, demo at maximum rotation. 
• Limited operation system for paying customers.
Aggressive Development Plan Leads to a 
2015 IOC
Remaining Phase II Tasks 
• Complete Boost Facility Concept Definition 
• Complete Operational System Deployment Concept 
• Define Grapple Requirements Using Rendezvous and 
Capture Simulation 
• Define Grapple Concept 
• Complete Survivability and Collision Avoidance 
Analyses 
• Complete Follow-on Program Plans 
• Estimate System Cost
Tether Systems Have the Potential 
to Enable Low Cost Access to Space 
• Concept feasibility study already completed. 
• Key targets for technical risk reduction have been 
identified. 
• Tether experiments have already flown in space. 
• Near term experiments further reduce potential system 
risks. 
• Phase II analyses reveal near term demonstrations 
and flight experiments required for full scale system 
development. 
• Commercial development path will probably be 
required. 
Modest near term government investment is 
encouraged to fund demos and experiments.

More Related Content

What's hot

What's hot (7)

GNSS and Positioning for the Future - Kai Borre
GNSS and Positioning for the Future - Kai BorreGNSS and Positioning for the Future - Kai Borre
GNSS and Positioning for the Future - Kai Borre
 
Space future
Space futureSpace future
Space future
 
Gslv
GslvGslv
Gslv
 
GPS II F12
GPS II F12GPS II F12
GPS II F12
 
Space Launch System (SLS)
Space Launch System (SLS)Space Launch System (SLS)
Space Launch System (SLS)
 
The Future of Solar System Exploration
The Future of Solar System ExplorationThe Future of Solar System Exploration
The Future of Solar System Exploration
 
Development of Navigation and Automated Flight Control System Solutions for M...
Development of Navigation and Automated Flight Control System Solutions for M...Development of Navigation and Automated Flight Control System Solutions for M...
Development of Navigation and Automated Flight Control System Solutions for M...
 

Viewers also liked

Viewers also liked (7)

Hypersonic vehicle
Hypersonic vehicleHypersonic vehicle
Hypersonic vehicle
 
Scramjet
ScramjetScramjet
Scramjet
 
HYPERSONIC VEHICLES
HYPERSONIC VEHICLESHYPERSONIC VEHICLES
HYPERSONIC VEHICLES
 
Physics of shock waves
Physics of shock wavesPhysics of shock waves
Physics of shock waves
 
Gas dynamics and jet propulsion – presentationof problemsanswers
Gas dynamics and jet propulsion – presentationof problemsanswersGas dynamics and jet propulsion – presentationof problemsanswers
Gas dynamics and jet propulsion – presentationof problemsanswers
 
Scranjet Engine
Scranjet EngineScranjet Engine
Scranjet Engine
 
High Speed Aerodynamics
High Speed AerodynamicsHigh Speed Aerodynamics
High Speed Aerodynamics
 

Similar to Hastol jun01

Investor space ops-presentation_2_dec2017
Investor  space ops-presentation_2_dec2017Investor  space ops-presentation_2_dec2017
Investor space ops-presentation_2_dec2017BillPannell1
 
Embry Riddle Final
Embry Riddle FinalEmbry Riddle Final
Embry Riddle Finaljschrell
 
Project LEON Overview 2015
Project LEON Overview 2015Project LEON Overview 2015
Project LEON Overview 2015Patrick Brown
 
Tether boostfacilitiesjun01
Tether boostfacilitiesjun01Tether boostfacilitiesjun01
Tether boostfacilitiesjun01Clifford Stone
 
Conceptual design and architecture of turkish communication satellite turksat...
Conceptual design and architecture of turkish communication satellite turksat...Conceptual design and architecture of turkish communication satellite turksat...
Conceptual design and architecture of turkish communication satellite turksat...Atılay Mayadağ
 
Fast forward project
Fast forward projectFast forward project
Fast forward projectWJ
 
GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...
GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...
GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...IdeaValley Sergio Cabral Cavalcanti
 
Sonobuoy Aerial Decelerator System
Sonobuoy Aerial Decelerator SystemSonobuoy Aerial Decelerator System
Sonobuoy Aerial Decelerator SystemJosh Benedictos
 
Airships as an Earth and Space Science Platform - Jason Rhodes
Airships as an Earth and Space Science Platform - Jason RhodesAirships as an Earth and Space Science Platform - Jason Rhodes
Airships as an Earth and Space Science Platform - Jason RhodesAdvanced-Concepts-Team
 
Space Shuttle Debris
Space Shuttle DebrisSpace Shuttle Debris
Space Shuttle DebrisEvan Wayton
 
LEO final presentation 2012
LEO final presentation 2012LEO final presentation 2012
LEO final presentation 2012Dmitry Tseitlin
 
Long_Alexandra-8900_final
Long_Alexandra-8900_finalLong_Alexandra-8900_final
Long_Alexandra-8900_finalAlexandra Long
 
The Pegasus Mission - The Making of Pegasus II
The Pegasus Mission - The Making of Pegasus IIThe Pegasus Mission - The Making of Pegasus II
The Pegasus Mission - The Making of Pegasus IIMatt Long
 
Olympuskpres20111118
Olympuskpres20111118Olympuskpres20111118
Olympuskpres20111118cargouav
 

Similar to Hastol jun01 (20)

Visits tomarsjun02
Visits tomarsjun02Visits tomarsjun02
Visits tomarsjun02
 
Investor space ops-presentation_2_dec2017
Investor  space ops-presentation_2_dec2017Investor  space ops-presentation_2_dec2017
Investor space ops-presentation_2_dec2017
 
Embry Riddle Final
Embry Riddle FinalEmbry Riddle Final
Embry Riddle Final
 
Project LEON Overview 2015
Project LEON Overview 2015Project LEON Overview 2015
Project LEON Overview 2015
 
Tether boostfacilitiesjun01
Tether boostfacilitiesjun01Tether boostfacilitiesjun01
Tether boostfacilitiesjun01
 
Conceptual design and architecture of turkish communication satellite turksat...
Conceptual design and architecture of turkish communication satellite turksat...Conceptual design and architecture of turkish communication satellite turksat...
Conceptual design and architecture of turkish communication satellite turksat...
 
AAS National Conference 2008: Kris Zacny
AAS National Conference 2008: Kris ZacnyAAS National Conference 2008: Kris Zacny
AAS National Conference 2008: Kris Zacny
 
Fast forward project
Fast forward projectFast forward project
Fast forward project
 
SpaceMETA - The Micro Launch Market 2016 - GLXP
SpaceMETA - The Micro Launch Market 2016 - GLXPSpaceMETA - The Micro Launch Market 2016 - GLXP
SpaceMETA - The Micro Launch Market 2016 - GLXP
 
Ssc10 iv-2
Ssc10 iv-2Ssc10 iv-2
Ssc10 iv-2
 
GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...
GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...
GLXP XPrize Tokyo - SpaceMETA - Sergio Cabral Cavalcanti - 2015 - Brasil Luna...
 
Sonobuoy Aerial Decelerator System
Sonobuoy Aerial Decelerator SystemSonobuoy Aerial Decelerator System
Sonobuoy Aerial Decelerator System
 
Airships as an Earth and Space Science Platform - Jason Rhodes
Airships as an Earth and Space Science Platform - Jason RhodesAirships as an Earth and Space Science Platform - Jason Rhodes
Airships as an Earth and Space Science Platform - Jason Rhodes
 
Space Shuttle Debris
Space Shuttle DebrisSpace Shuttle Debris
Space Shuttle Debris
 
Leo final presentation
Leo final presentationLeo final presentation
Leo final presentation
 
LEO final presentation 2012
LEO final presentation 2012LEO final presentation 2012
LEO final presentation 2012
 
X-69
X-69X-69
X-69
 
Long_Alexandra-8900_final
Long_Alexandra-8900_finalLong_Alexandra-8900_final
Long_Alexandra-8900_final
 
The Pegasus Mission - The Making of Pegasus II
The Pegasus Mission - The Making of Pegasus IIThe Pegasus Mission - The Making of Pegasus II
The Pegasus Mission - The Making of Pegasus II
 
Olympuskpres20111118
Olympuskpres20111118Olympuskpres20111118
Olympuskpres20111118
 

More from Clifford Stone (20)

Zubrin nov99
Zubrin nov99Zubrin nov99
Zubrin nov99
 
Xray telescopeconcept
Xray telescopeconceptXray telescopeconcept
Xray telescopeconcept
 
Xray interferometry
Xray interferometryXray interferometry
Xray interferometry
 
Wpafb blue bookdocuments
Wpafb blue bookdocumentsWpafb blue bookdocuments
Wpafb blue bookdocuments
 
What gov knows_about_ufos
What gov knows_about_ufosWhat gov knows_about_ufos
What gov knows_about_ufos
 
Welcome oct02
Welcome oct02Welcome oct02
Welcome oct02
 
Weather jun02
Weather jun02Weather jun02
Weather jun02
 
Wassersug richard[1]
Wassersug richard[1]Wassersug richard[1]
Wassersug richard[1]
 
Washington, d.c., jul 26 27, 1952
Washington, d.c., jul 26 27, 1952Washington, d.c., jul 26 27, 1952
Washington, d.c., jul 26 27, 1952
 
Wash dc jul 19 to 20 1952
Wash dc jul 19 to 20 1952Wash dc jul 19 to 20 1952
Wash dc jul 19 to 20 1952
 
Vol4ch03
Vol4ch03Vol4ch03
Vol4ch03
 
Vol4ch02
Vol4ch02Vol4ch02
Vol4ch02
 
Vol4ch01
Vol4ch01Vol4ch01
Vol4ch01
 
Vol3ch16
Vol3ch16Vol3ch16
Vol3ch16
 
Vol3ch14
Vol3ch14Vol3ch14
Vol3ch14
 
Vol3ch13
Vol3ch13Vol3ch13
Vol3ch13
 
Vol3ch12
Vol3ch12Vol3ch12
Vol3ch12
 
Vol3ch11
Vol3ch11Vol3ch11
Vol3ch11
 
Vol3ch10
Vol3ch10Vol3ch10
Vol3ch10
 
Vol3ch09
Vol3ch09Vol3ch09
Vol3ch09
 

Hastol jun01

  • 1. Hypersonic Airplane Space Tether Orbital Launch -- HASTOL NASA Institute for Advanced Concepts 3rd Annual Meeting NASA Ames Research Center, San Jose, CA June 6, 2001 John E. Grant The Boeing Company, 5301 Bolsa Ave., Huntington Beach, CA92647-2099 Phone 714-372-5391 john.e.grant@boeing.com www.boeing.com NIAC Subcontract No. 07600-040
  • 2. HASTOL Phase II Study Team The Boeing Company John Grant, Phantom Works, Huntington Beach, CA Kimberly Harris, Phantom Works, Huntington Beach, CA Jim Martin, Phantom Works, Huntington Beach, CA Dan Nowlan, Phantom Works, Huntington Beach, CA Karl Oittinen, Expendable Launch Systems, Huntington Beach, CA Don Johnson, Phantom Works, St. Louis, MO Steve Hollowell, Phantom Works, Long Beach, CA Mike Bangham, Space and Communications, Huntsville, AL Beth Fleming, Space and Communications, Huntsville, AL John Blumer, Space and Communications, Huntsville, AL Ben Donahue, Space and Communications, Huntsville, AL Brian Tillotson, Space and Communications, Seattle, WA Tethers Unlimited, Inc. Rob Hoyt, Seattle, WA Bob Forward, Seattle, WA HASTOL Contract funded by NASA Institute for Advanced Concepts Dr. Robert Cassanova, Atlanta, Georgia
  • 3. HASTOL Concept of Operation
  • 4. HASTOL Phase I Results Showed Concept Feasibility • Top -Level Requirements Developed; Top-Level Trades Conducted to Define Basic Design Approaches • Selected Hypersonic Aircraft Concept (DF-9) • Validated Overlap of Tether Tip and Hypersonic Aircraft Velocity and Geometry Envelopes for Capture – Defined Aircraft Apogee Altitude/Velocity Envelope – Tether Tip Can Withstand Thermal Loads as it Dips into the Atmosphere • Tether Boost Facility Concept Defined • Rotovator Tether Concept Selected • Simplified Grapple Concept Identified
  • 5. HASTOL Phase II Study Approach Phase I R esults • R otovator concept • Technology Readiness Level 2 systems (hypersonic airplane, tether control station, tether, grapple assem bly, payload accommodation assembly) • T rade study results: discovery that rendezvous point can be achieved by existing airplane (X-43) w ithout overheating tether tip • Selected concepts - DF-9 hypersonic vehicle - R endezvous point at Mach 10, 100-km altitude - HoytetherTM w ith Spectra2000TM m aterial and PBO tip m aterial Hypersonic Airplane Space Tether O rbital Launch (HASTOL) S tudy Program, Phase II Task 1 M ission Opportunities Definition • Develop contact plan • Conduct kick-off w ith potential customers and N IAC • Meet with customers to assess potential m issions and near-term applications • Identify opportunities to integrate into NASA programs Task 2 System Requirements Definition • Derive preliminary system requirements for each of the HASTOL systems • Determine payload characteristics, traffic rate, guidance and control, g-force limitations, initial and life cycle costs, and system interface requirements • Identify, define, allocate, and trade m ajor system requirements Task 3 Conceptual Design • Integrate into system architecture • C onduct trade studies • D evelop ROM cost estimate Task 4 System Analysis • C onduct m odeling and simulations • C onduct preliminary technical assessment - Identify high-risk areas - D evelop m itigation plans Task 5 Technology Development Planning • Identify technology needs • Develop technology development roadmap - F light test plan - Laboratory tests Candidate list of mission needs Phase II D eliverables • Final Phase II program review • Phase II final report – System requirements – Complete system design concept to TRL 3 – Areas of development work needed – Technology roadmap – Cost models • Phase III customer funding commitment – Analyze key technical issues ✔ GN&C ✔ Payload transfer operations ✔ Tether design and dynamics ✔ Material selection ✔ Simulation results
  • 6. Markets Drive Requirements • Current & Emerging Markets – GEO Comsats – US Civil Satellites – US Military Satellites – Small-Vehicle Tourism – Mission Requirements at IOC • Future Markets – Human Exploration & Development of Space – Solar Power Satellites – Large-Vehicle Tourism – Mission Requirements for Extended Operation Capability
  • 7. Total Existing Markets • Dominated by GEO Comsats => size HASTOL for that market – GEO destination matches HASTOL well – Aggressive pricing required • Other markets offer targets of opportunity, not core business – Extra revenue – Protection from non-US competition allows higher prices GEO Comsats 100 300 500 700 900 2000 4000 6000 8000 10000 14000 2010 2015 2020 12 10 8 6 4 2 0 number mass (lb) year • Total 2010 Market – ~33 Launches / yr – $1.5 B / yr revenue – 50% revenue capture?
  • 8. Surveys Show Space Adventure Travel Is Large And Elastic Market Market likely stronger than data suggest •Survey data several years old •Economy has grown since then •Wealth more concentrated in top strata •Upper strata include more young & adventurous people than in the past Annual Passengers 1K 10K 100K 1M 100 1K 10K 100K 1M 10M Annual Passengers Seat Price Ivan Bekey, Economically Viable Public Space Travel, Space Energy and Transportation, vol 4, No 1,2, 1999.
  • 10. Comsat and Passenger Flights Drive IOC Mission Requirements • Payload mass: 5500 kg • Release orbits: GTO + assured safe re-entry orbit • Release orbit insertion error to GTO: < Ariane 5 and Delta 4 error • Passenger orbit insertion error: not to exceed safe entry limits • Epoch: 2015 to 2025 • Mission reliability: 98% for comsats, 99% for passengers • Mission safety: – 99% chance that comsat payloads will be undamaged – 99.99% chance that passengers will survive • Orbital debris produced: zero • Collision avoidance: “shall not endanger any tracked operational spacecraft”
  • 11. Extended Operational Capability Mission Requirements HEDS and SPS Drive Requirements • Payload mass: 36,000 kg • Release orbits: GTO + transfer orbit to Earth-Moon L1 • Release orbit insertion error: < Saturn V error • Rate: 1000 SPS flights / yr, 15 HEDS flights / yr • Epoch: 2020 to 2030 • Mission reliability: 98% for HEDS & SPS • Mission safety: 99% chance that HEDS & SPS payloads will be undamaged • Orbital debris produced: zero (incl. lunar downmass)
  • 12. HASTOL Phase I Hypersonic Aircraft Concept: Boeing-NASA/LaRC DF-9 Dual-Fuel Aerospaceplane Takeoff Wt: 270 MT (590,000 lb) Payload: 14 MT (30,000 lb) Length: 64 m (209 ft) Apogee: 100 km Speed at Apogee: 3.6 km/sec (approx. Mach 12) 4.1 km/sec (inertial) Turboramjets up to Mach 4.5 Ram-, Scramjets above Mach 4.5 Linear Rocket for Pop-Up Maneuver
  • 13. Variation with Rendezvous Velocity • Determined System Design for Hypersonic Airplane Apogee Velocities of Mach 10-19 HASTOL Tether Facility Parameter Variations with Initial Payload Parameter Variations - 600 km - TCS 10X Fixed Parameters Tether length 600km TCS Mass 150 Mg (10X payload mass) Payload Mass 15 Mg Tether Safety Factor 3.0 along entire length Rendezvous Facility Mass Ratio Tip Altitude GTO Run Velocity Altitude Accel CM Peri CM Apo Tip Vel TCS Tether Total Perigee Apogee Apogee (Mach) (m/s) (km) (n.mi.) (gees) (km) (km) (m/s) (ratio) (ratio) (ratio) (km) (km) (X Geo) 3111 19.0 5791 113 61 0.88 549 1314 1977 10 16 26 80 186 1.00 3007 18.0 5486 110 60 1.18 540 1012 2229 10 28 38 88 80 1.44 3010 17.0 5182 110 60 1.55 522 835 2502 10 51 61 97 80 2.76 3015 16.0 4877 110 60 1.96 512 701 2780 10 94 104 102 80 13.51 3032 15.0 4572 110 80 2.40 509 612 3064 10 175 185 106 80 -8.66 3031 14.0 4267 110 60 2.86 511 559 3353 10 331 341 108 80 -2.49 3030 13.0 3962 110 60 3.33 517 531 3645 10 638 648 109 80 -1.68 3027 12.0 3658 110 60 3.82 524 524 3941 10 1253 1263 109 85 -1.31 3029 11.0 3353 110 60 4.33 533 533 4241 10 2515 2525 110 97 -1.09 3028 10.0 3048 110 60 4.87 542 542 4541 10 5108 5118 110 103 -0.95
  • 14. Broad Range of Mission Profiles and Propulsion Systems Considered Vertical Launch, Downrange Land Vertical Launch, Flyback Rocket Burnout at Mach 17, 150 km Vertical Takeoff Gliding Entry Horizontal Landing Rocket Burnout a t Mach 17 , 15 0 km Vertical Takeo ff G lid ing Entry w ith Turn F lyback Horizontal Landing Air Launched Rocket Air-Turborocket Turboramjet Booster and Rocket Burnout at Mach 17, 150 km Gliding Entry with Turn Horizontal Landing Rocket Horizontal Takeoff Launch Uprange Cruise Turn Airplane Cruiseback Burnout at Mach 17, 150 km Gliding Entry with Turn Horizontal Landing Air- Rocket turborocket Horizontal Takeoff Launch Uprange Cruise Turn Airplane Cruiseback Switch at Mach 6 Burnout at Mach 17, 150 km Gliding Entry with Turn Horizontal Landing RBCC rocket Mach 10 Switch Horizontal Takeoff Launch Uprange Cruise Turn Airplane Cruiseback RBCC airbreathing Launch at Mach 4 Burnout at Mach 17, 150 km RBCC Rocket High-Speed Turn Horizontal Takeoff MAGLEV Rocket Gliding Entry with Turn Mach 4 Flyback Horizontal Landing Uprange Acceleration Mach 10 Switch Burnout at Mach 17, 150 km Gliding Entry with Turn Horizontal Horizontal Landing Takeoff MAGLEV Turboramjet Uprange Cruise Turn Turboramjet Cruiseback Air Launched RBCC Single Stage Airbreather (RBCC)
  • 15. HASTOL Phase II Hypersonic Aircraft Concept: Air Launched Turbo-Rocket Takeoff Wt: 177 MT (390,883 lb) Payload: 7 MT (15,000 lb) Payload bay: 3 m dia x 9.1 m (10 ft x 30 ft) Apogee: 150 km Air- Rocket turborocket Launch Speed at Apogee: 5.2 km/sec (approx. Mach 17) 5.7 km/sec (inertial) Air-turborocket to Mach 6 Linear Rocket above Mach 6 138’ 11’’ 54’ 2’’ 17’ 5’’ Burnout at Mach 17, 150 km Gliding Entry with Turn Horizontal Landing Horizontal Takeoff Uprange Cruise Turn Airplane Cruiseback Switch at Mach 6
  • 16. HASTOL Tether Facility Design Mass Ratios: • Control Station 10x payload • Tether 58.8x • Grapple 0.12 • TOTAL: ~ 69 x payload Tether Length: 630 km Orbit: • 582x805 km ->569x499 Maximum Total ΔV ~ 5 km/s Capability to toss payload to 107,542 km Tosses to GTO by releasing off-vertical System Masses Tether Characteristics Tether mass 323,311 kg Tether Length 636,300 m CS Active Mass 51,510 kg Tether mass ratio 58.78 CS Ballast Mass 3490 kg Tether tip velocity at catch 2,517 m/s Grapple mass 650 kg Tether tip velocity at toss 2,481 m/s Total Facility Mass 378,961 kg Tether angular rate 0.00583 rad/s Gravity at Control Station 0.73 g Total Launch Mass 375,471 kg Gravity at payload 1.48 g Rendezvous acceleration 1.50 g Payload Mass 5,500 kg Joined System Pre-Catch Post-Toss Positions & Velocities Payload Tether Post-catch Tether Payload resonance ratio 41 20 1 26.0 perigee altitude km -4603 582 576 569 1001 apogee altitude km 150 805 650 499 107542 perigee radius km 1775 6960 6954 6948 7379 apogee radius km 6528 7183 7028 6877 113921 perigee velocity m/s 18789 7627 7591 7555 10073 apogee velocity m/s 5110 7390 7511 7632 652 CM dist. From Station m 204469 210647 204469 CM dist. To Grapple m 431831 425653 431831 ²V to Reboost m/s 72 ²V to Correct Apogee m/s -484 ²V to Correct Precess. m/s 416 ²V To Circularize m/s 1218 Basic Orbital Parameters semi-major axis km 4152 7072 6991 6912 60650 eccentricity 0.6 0.016 0.005 -0.005 0.878 inclination rad 0 0 0 0 0 semi-latus rectum km 2792 7070 6991 6912 13861 sp. mech. energy m2/s2 -4.80E+07 -2.82E+07 -2.85E+07 -2.88E+07 -3.29E+06 vis-viva energy m2/s2 -9.60E+07 -5.64E+07 -5.70E+07 -5.77E+07 -6.57E+06 period sec 2662 5918 5817 5720 148647 period min 44.4 98.6 97.0 95.3 2477.5 station rotation period sec 1077.8 1077.8 1077.8 rotation ratio 5.5 5.4 5.3 2.00E+01 1.00E+01 0.00E+00 -1.00E+01 -2.00E+01 630000 598500 567000 535500 504000 472500 441000 409500 378000 346500 315000 283500 252000 220500 189000 157500 126000 94500 63000 31500 0 Distance From Control Station Radius (mm)
  • 17. Boost Facility Concept Control Station w/ Power Expansion Modules Power Expansion Module w/ PV arrays Tether Expansion Module Tether Length/Dia Grapple Assembly not to scale
  • 18. Operational HASTOL Control Station Initial Subsystem Mass Allocations Subsystems Mass, kg. Thermal Control 1,970 Cabling/Harnesses 1,380 Structure 4,730 Electrical Power (EPS) & Tether Power 9,060 Command & Data Handling (C&DH) and Communication 200 Attitude Determination & Control (ADCS) and Guidance & 590 Navigation (GN&C) Tether Deployment and Control (TDCS) 1,380 Docking Ballast 390 35,300 Control Station mass ≈ 55,000 kg
  • 19. Phase I Results Show Feasibility of Payload Capture • Tether-Payload Rendezvous Capability is a Key Enabling Technology • TUI Developed Methods for Extending Rendezvous Window – Works in Simulation – Validation Experiments Needed
  • 20. Relative Position of Grapple and Payload Relative Position of Grapple 70000 60000 50000 40000 30000 20000 10000 0 -10000 1,000 Km Tether Case, 4,100 m/s Rendezvous; Hypersonic A/C Coordinate System Before Grapple After Grapple Time Before Grapple 60 Seconds Time After Grapple 30 Seconds 10 Seconds 20 Hypersonic Aircraft Pop-Up Apogee is at 335,000 Feet; 13,450 Ft/Sec (Mach 15.2) -4000 -3000 -2000 -1000 0 1000 2000 3000 4000 Horizontal Distance - Ft Vertical Distance - Ft 60 Seconds 10 30 Aft Forward
  • 21. Relative Position of Grapple and Payload Relative Position of Grapple 2000 1600 1200 800 400 0 -400 Time Before Grapple Time After Grapple 5 Seconds 5 Seconds 1 Second 1 Second Distances 26 Ft, 1680 Ft 6 Ft, 420 Ft 1 Ft, 17 Ft 0 Ft, 0 Ft -2000 -1600 -1200 -800 -400 0 400 800 1200 1600 2000 Horizontal Distance - Ft Vertical Distance - Ft 1,000 Km Tether Case, 4,100 m/s Rendezvous; Hypersonic A/C Coordinate System 10 Seconds 10 Seconds Hypersonic Aircraft Pop-Up Apogee is at 335,000 Feet; 13,450 Ft/Sec (Mach 15.2) Aft Forward
  • 22. Visual 6-DOF Simulation Validates Rendezvous and Capture Scenario
  • 23. R&C Scenario Timeline/Sequence of Events Time (sec) 0 5 15 30 45 58 60 65 120 Event Start R&C scenario Initiate guidance predictions Issue P/L bay door discrete Issue P/L rotation mechanism commands P/L rotation complete Issue grapple assembly release discrete Nominal capture point End grapple assembly freefall End R&C scenario
  • 24.
  • 25.
  • 26. Possible Follow-on Projects and Tasks • Ground-Based Rendezvous and Capture Demo • Detailed rendezvous and capture simulation and analysis. • More detailed design of operational grapple • Detailed design of demo hardware • Sub-Scale Electrodynamic Tether Dynamics Experiments • Secondary payload • 4-5 km long ED tether; assess tether dynamics, survivability • Sub-scale tether system to capture and toss payloads • Four phase program: • Design • Fabrication and ground testing • Flight experiment • 1st, tether is in circular orbit just a little higher than payload and hanging. Then, tether and payload rendezvous and capture (low relative speed). Tether then uses thrust to start rotating and throw payload. • 2nd, tether is in a higher elliptic orbit and rotating slowly. It rendezvous with payload (moderate relative speed), rotates, and tosses. • 3rd, demo at maximum rotation. • Limited operation system for paying customers.
  • 27. Aggressive Development Plan Leads to a 2015 IOC
  • 28. Remaining Phase II Tasks • Complete Boost Facility Concept Definition • Complete Operational System Deployment Concept • Define Grapple Requirements Using Rendezvous and Capture Simulation • Define Grapple Concept • Complete Survivability and Collision Avoidance Analyses • Complete Follow-on Program Plans • Estimate System Cost
  • 29. Tether Systems Have the Potential to Enable Low Cost Access to Space • Concept feasibility study already completed. • Key targets for technical risk reduction have been identified. • Tether experiments have already flown in space. • Near term experiments further reduce potential system risks. • Phase II analyses reveal near term demonstrations and flight experiments required for full scale system development. • Commercial development path will probably be required. Modest near term government investment is encouraged to fund demos and experiments.