6. • Install a 12” strip of 5/8” OSB
tight to the outside wall
framing
• This will be part of the Air
Barrier and Vapour retarder
for the roof assembly
7. • Tape the OSB joints, and lap
the tape onto the
Blueskinned top plates
• Use vapour barrier tapes
(Siga Rissan or similar)