SlideShare a Scribd company logo
1 of 31
Location
 Powerhouse and headworks is located at Suindibar (14
  km before Besisahar).
 Dam Site: Besisahar (4 km before Besisahar).
 Elevation: 760m (2,490 ft)
 40 km upstream of the existing Lower Marsyangdi
  Hydropower Plant.
Construction
 Project Initiation: 2001
 Project Completed: 2007
 Project was financially and technically supported by
  Germany.
General Info
 Run-of-river type with daily pondage of 5 hours
    peaking.
   Second largest hydro-electric project.
   Max. gross head: 110m
   Net head: 98m
   Installed Capacity: 70MW(two 35MW turbines)
   Annual average energy: 398 GWh
Dam, Spillway and Intake
             Structures
 Type of dam: combined concrete gravity and rockfill
  dam.
 34.5m height above foundation.
 Power tunnel length
   Low pressure: 5,230m(between desander outlet and
    surge tank)
   High pressure: 225m (between surge tank and discharge
    measurement chamber)
 Spillway: 3 radial gates
   W x H = 12 x 19.54 m
 Spillway capacity: 4,270 m3/s
at headwater level of 626 masl
 Leakage of certain amount of
  water due to rocks or
  minerals settling.
Turbine being shut
Surge Tank & Penstock
 Vertical, circular surge tank with net diameter 20m.
 Height 45 m


 1 concrete cased steel pipe Penstock.
 Length: 212-218m (between discharge
  measurement chamber
  and turbine inlet valve)
 Guide vanes are designed
 to:
   Allow the water to enter
    the    runner    without
    shock. Entire vane is not
    open initially and only
    certain water is flowed
    and when the turbine is
    run for sometime, entire
    vane is open.
   Allow the water to flow
    over     them    without
    forming eddies.
   Allow required quantity
    of water to enter the
    turbine.
Turbine Details
 2 Francis, vertical shaft
 40 m3/s rated discharge
 Gross head: 110m
 Rated Output: 35.9 MW
 Rated Speed: 333.33 rpm
 Erosion in turbines are many due to cavitation.
 Cavitation is the formation of bubbles filled with
 vapours within the body of moving liquid. It causes:
   Noise and vibration of various parts.
   Causes pitting (erosion of material) making the surface
    rough.
   Reduction in discharge which causes suddent drop in
    power output and efficiency.
Generators
 Two 3-phase synchoronous
    generators.
   Rated output: 39 MVA
   Rated voltage: 11 KV ± 7.5%
   Rated frequency: 50 Hz
   Power factor: 0.85-0.9
   Rated speed: 333.33 rpm (18 poles)
Excitation System
 Consists of autonomic voltage regulator (AVR), exciter,
    measuring elements, power system stabilizer (PSS) and
    limitation and protection unit.
   Exciter is required to provide necessary field current to the
    rotor winding of a sync. machine.
   Exciter has its field winding in the stator, and armature
    winding in the rotor.
   Exciter is controlled by the AVR, which is very effective
    during steady-state operation, but, in case of sudden
    disturbances it may have negative influence on the damping
    of power swings, because then it forces field current changes
    in the generator.
   This may be eliminated by introducing the power system
    stabilizer (PSS).
 Here, STATIC excitation (self-excited) DC system is
    used.
   It consists of thyristor or transistor bridge and
    transformer.
   Energy needed for excitation is brought to generator
    field winding via slip-rings with carbon brushes.
   The main disadvantage is that excitation supply
    voltage, and thereby excitation current, depends
    directly on generator output voltage.
   Another problem: large time constant (about 3 sec)
    and commutation difficulties.
Transformers
 Ratio : 132 ∕ √3 : 11 KV
 Total of 5 tr. used: four 3-phase and one 1-phase.
 Rated Power: 14.5 MVA
 Forced oil type transformers. Oil is circulated by pump
  from the top of the transformer tank to a cooling plant.
 For regulating the voltage, load tap changers are
  provided.
 Oil/air heat exchanger used.
 Buchholz        Relay      protects
  transformers from all kinds of
  faults.
 It is equipped with an external
  overhead oil reservoir called
  a conservator.
 Function of Conservator: To allow
  room for oil expansion and
  contraction.
 The conservator acts as a
  reservoir of oil that can then flow
  back into the tank so that no air
  enters it.
 Breather are used to absorb
  the moisture content from
  the sucked air, while the
  transformer     oil    gets
  expanded due to heating.
 Breathers make use of
  silica gel coloured with
  brown used extensively in
  power transformers.
Circuit Breaker
 SF-6 CB used.
 Rated voltage: 145 KV
 Rated lightning withstand
  voltage: 650 KV
 Rated normal current:
  3150 A
 Rated out-of-phase
  breaking current: 10 KA
 From right to left:
    Switches, SF6 Circuit Breaker, Current Transformer,
     Switches, Potential Transformer, 132 KV NEA TL
Potential Transformer
 Primary Voltage: 132000/ √3
 Secondary Voltage: 110/ √3
 50 VA
Monthly Generation Report from
                   Commissioning till date
                                                     Generation (MWh)
                                                                      2068/69
S.N   Month
                   Designed     67/68                                        % inc/dec with respect to
                                            Target       Generation
                                                                      Design     66/67     67/68     Target
 1    Shrawan      47,840.00   38,821.40   38,683.14     44,085.60    -9.9%      13.4%     11.0%     11.4%
 2    Bhadra       47,110.00   34,967.10   37,766.30     46,977.90    -1.6%      14.3%     32.6%     22.8%
 3    Ashwin       46,980.00   38,460.50   37,763.22     42,807.70    -8.9%      24.9%     11.3%     13.4%
 4    Kartik       42,225.00   37,942.20   37,906.55     43,003.00    1.8%       14.0%     13.3%     13.4%
 5    Mangsir      30,805.00   20,057.90   36,810.44     36,903.30    19.8%      0.3%      84.0%         0.3%
 6    Poush        21,410.00   27,531.70   27,459.97     27,596.25    28.9%      1.8%      0.2%          0.5%
 7    Magh         15,990.00   21,542.80   21,509.72     12,596.75    -21.2%    -41.0%    -41.5%     -41.4%
 8    Falgun       14,610.00   19,874.80   22,509.63
 9    Chaitra      17,565.00   20,831.30   22,371.43
 10   Baisakh      26,305.00   28,733.20   30,483.50
 11   Jestha       39,615.00   44,877.40   43,439.36
 12   Asadh        47,135.00   43,511.40   42,603.22
Annual Gen.(GWh)    397.59      377.14      399.31
Fault Sheet and Log
Presented by:
       Bhavin Pradhan
       Bishnu Dawadi
       Kalyan Shrestha
        Kishwor Karki
       Umesh Gurung
       Roshan Gurung

DEPARTMENT OF ELECTRICAL
       ENGINEERING
Kathmandu Engineering College

More Related Content

What's hot

400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
220 kv training by saurabh chauhan
 220 kv training by saurabh chauhan 220 kv training by saurabh chauhan
220 kv training by saurabh chauhansaurabh chauhan
 
Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plantSwapnil Gadgune
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -HydraulicsCivil Zone
 
Lec7. Design Of Forebay-1.pdf
Lec7. Design Of Forebay-1.pdfLec7. Design Of Forebay-1.pdf
Lec7. Design Of Forebay-1.pdfHadiqa Qadir
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptxWajidMalik27
 
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualGaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualFatin62c
 
Desin of penstock pipe ppt
Desin of penstock pipe pptDesin of penstock pipe ppt
Desin of penstock pipe pptzafaralam7868
 
grid sub-station training Report
grid sub-station training Report grid sub-station training Report
grid sub-station training Report ravi kant
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Nikhil Jaipurkar
 
pelamis wave energy convertor ppt
pelamis wave energy convertor pptpelamis wave energy convertor ppt
pelamis wave energy convertor pptchakri218
 
Future of Hydro Power Development in India
Future of Hydro Power Development in IndiaFuture of Hydro Power Development in India
Future of Hydro Power Development in IndiaIPPAI
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepalBishal Rimal
 
practical training report on turbogenerator
practical training report on turbogeneratorpractical training report on turbogenerator
practical training report on turbogeneratorPriyank Bisht
 
Power plant training in Delhi NCR
Power plant training in Delhi NCRPower plant training in Delhi NCR
Power plant training in Delhi NCRRaj Nayak
 
Various types of gates, their important components
Various types of gates, their important componentsVarious types of gates, their important components
Various types of gates, their important componentsIEI GSC
 
Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardI.E.T. lucknow
 

What's hot (20)

400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
220 kv training by saurabh chauhan
 220 kv training by saurabh chauhan 220 kv training by saurabh chauhan
220 kv training by saurabh chauhan
 
Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plant
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -Hydraulics
 
NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
 
Lec7. Design Of Forebay-1.pdf
Lec7. Design Of Forebay-1.pdfLec7. Design Of Forebay-1.pdf
Lec7. Design Of Forebay-1.pdf
 
SLUICE GATE
SLUICE GATESLUICE GATE
SLUICE GATE
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
 
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualGaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
 
Desin of penstock pipe ppt
Desin of penstock pipe pptDesin of penstock pipe ppt
Desin of penstock pipe ppt
 
grid sub-station training Report
grid sub-station training Report grid sub-station training Report
grid sub-station training Report
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
 
pelamis wave energy convertor ppt
pelamis wave energy convertor pptpelamis wave energy convertor ppt
pelamis wave energy convertor ppt
 
Future of Hydro Power Development in India
Future of Hydro Power Development in IndiaFuture of Hydro Power Development in India
Future of Hydro Power Development in India
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepal
 
practical training report on turbogenerator
practical training report on turbogeneratorpractical training report on turbogenerator
practical training report on turbogenerator
 
Power plant training in Delhi NCR
Power plant training in Delhi NCRPower plant training in Delhi NCR
Power plant training in Delhi NCR
 
Various types of gates, their important components
Various types of gates, their important componentsVarious types of gates, their important components
Various types of gates, their important components
 
Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyard
 

Similar to Marsyangdi Hydropower Plant Location and Key Details

Similar to Marsyangdi Hydropower Plant Location and Key Details (20)

Modi Khola Hydropower Field Report
Modi Khola Hydropower Field ReportModi Khola Hydropower Field Report
Modi Khola Hydropower Field Report
 
ELEKTRA_new
ELEKTRA_newELEKTRA_new
ELEKTRA_new
 
Turbo generator
Turbo generator Turbo generator
Turbo generator
 
TC-MODULE – 2.pdf
TC-MODULE – 2.pdfTC-MODULE – 2.pdf
TC-MODULE – 2.pdf
 
Experiment 2 AC Machines
Experiment 2 AC MachinesExperiment 2 AC Machines
Experiment 2 AC Machines
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
Design turbo generator
Design turbo generatorDesign turbo generator
Design turbo generator
 
Naps
Naps Naps
Naps
 
5.2.c gen basics
5.2.c gen basics5.2.c gen basics
5.2.c gen basics
 
Vocational training
Vocational trainingVocational training
Vocational training
 
TOP412GN.pdf
TOP412GN.pdfTOP412GN.pdf
TOP412GN.pdf
 
Vocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR UttarakhandVocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR Uttarakhand
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving station
 
lift ppt
lift pptlift ppt
lift ppt
 
Report hydroelectric power plant
Report hydroelectric power plantReport hydroelectric power plant
Report hydroelectric power plant
 
Kulekhani I hydropower ,Nepal
Kulekhani I hydropower ,NepalKulekhani I hydropower ,Nepal
Kulekhani I hydropower ,Nepal
 
engineering and utilities report
engineering and utilities reportengineering and utilities report
engineering and utilities report
 
Parel carshed training
Parel carshed trainingParel carshed training
Parel carshed training
 
Sunshine welding generator 50 hz
Sunshine welding generator 50 hzSunshine welding generator 50 hz
Sunshine welding generator 50 hz
 
Catalog biến tần trung thế Fuji Electric
Catalog biến tần trung thế Fuji ElectricCatalog biến tần trung thế Fuji Electric
Catalog biến tần trung thế Fuji Electric
 

Marsyangdi Hydropower Plant Location and Key Details

  • 1.
  • 2.
  • 3. Location  Powerhouse and headworks is located at Suindibar (14 km before Besisahar).  Dam Site: Besisahar (4 km before Besisahar).  Elevation: 760m (2,490 ft)  40 km upstream of the existing Lower Marsyangdi Hydropower Plant.
  • 4. Construction  Project Initiation: 2001  Project Completed: 2007  Project was financially and technically supported by Germany.
  • 5. General Info  Run-of-river type with daily pondage of 5 hours peaking.  Second largest hydro-electric project.  Max. gross head: 110m  Net head: 98m  Installed Capacity: 70MW(two 35MW turbines)  Annual average energy: 398 GWh
  • 6.
  • 7. Dam, Spillway and Intake Structures  Type of dam: combined concrete gravity and rockfill dam.  34.5m height above foundation.  Power tunnel length  Low pressure: 5,230m(between desander outlet and surge tank)  High pressure: 225m (between surge tank and discharge measurement chamber)
  • 8.
  • 9.  Spillway: 3 radial gates W x H = 12 x 19.54 m  Spillway capacity: 4,270 m3/s at headwater level of 626 masl  Leakage of certain amount of water due to rocks or minerals settling.
  • 10.
  • 11.
  • 12.
  • 14. Surge Tank & Penstock  Vertical, circular surge tank with net diameter 20m.  Height 45 m  1 concrete cased steel pipe Penstock.  Length: 212-218m (between discharge measurement chamber and turbine inlet valve)
  • 15.  Guide vanes are designed to:  Allow the water to enter the runner without shock. Entire vane is not open initially and only certain water is flowed and when the turbine is run for sometime, entire vane is open.  Allow the water to flow over them without forming eddies.  Allow required quantity of water to enter the turbine.
  • 16. Turbine Details  2 Francis, vertical shaft  40 m3/s rated discharge  Gross head: 110m  Rated Output: 35.9 MW  Rated Speed: 333.33 rpm
  • 17.  Erosion in turbines are many due to cavitation.  Cavitation is the formation of bubbles filled with vapours within the body of moving liquid. It causes:  Noise and vibration of various parts.  Causes pitting (erosion of material) making the surface rough.  Reduction in discharge which causes suddent drop in power output and efficiency.
  • 18. Generators  Two 3-phase synchoronous generators.  Rated output: 39 MVA  Rated voltage: 11 KV ± 7.5%  Rated frequency: 50 Hz  Power factor: 0.85-0.9  Rated speed: 333.33 rpm (18 poles)
  • 19. Excitation System  Consists of autonomic voltage regulator (AVR), exciter, measuring elements, power system stabilizer (PSS) and limitation and protection unit.  Exciter is required to provide necessary field current to the rotor winding of a sync. machine.  Exciter has its field winding in the stator, and armature winding in the rotor.  Exciter is controlled by the AVR, which is very effective during steady-state operation, but, in case of sudden disturbances it may have negative influence on the damping of power swings, because then it forces field current changes in the generator.  This may be eliminated by introducing the power system stabilizer (PSS).
  • 20.  Here, STATIC excitation (self-excited) DC system is used.  It consists of thyristor or transistor bridge and transformer.  Energy needed for excitation is brought to generator field winding via slip-rings with carbon brushes.  The main disadvantage is that excitation supply voltage, and thereby excitation current, depends directly on generator output voltage.  Another problem: large time constant (about 3 sec) and commutation difficulties.
  • 21.
  • 22. Transformers  Ratio : 132 ∕ √3 : 11 KV  Total of 5 tr. used: four 3-phase and one 1-phase.  Rated Power: 14.5 MVA  Forced oil type transformers. Oil is circulated by pump from the top of the transformer tank to a cooling plant.  For regulating the voltage, load tap changers are provided.  Oil/air heat exchanger used.
  • 23.  Buchholz Relay protects transformers from all kinds of faults.  It is equipped with an external overhead oil reservoir called a conservator.  Function of Conservator: To allow room for oil expansion and contraction.  The conservator acts as a reservoir of oil that can then flow back into the tank so that no air enters it.
  • 24.  Breather are used to absorb the moisture content from the sucked air, while the transformer oil gets expanded due to heating.  Breathers make use of silica gel coloured with brown used extensively in power transformers.
  • 25. Circuit Breaker  SF-6 CB used.  Rated voltage: 145 KV  Rated lightning withstand voltage: 650 KV  Rated normal current: 3150 A  Rated out-of-phase breaking current: 10 KA
  • 26.  From right to left:  Switches, SF6 Circuit Breaker, Current Transformer, Switches, Potential Transformer, 132 KV NEA TL
  • 27.
  • 28. Potential Transformer  Primary Voltage: 132000/ √3  Secondary Voltage: 110/ √3  50 VA
  • 29. Monthly Generation Report from Commissioning till date Generation (MWh) 2068/69 S.N Month Designed 67/68 % inc/dec with respect to Target Generation Design 66/67 67/68 Target 1 Shrawan 47,840.00 38,821.40 38,683.14 44,085.60 -9.9% 13.4% 11.0% 11.4% 2 Bhadra 47,110.00 34,967.10 37,766.30 46,977.90 -1.6% 14.3% 32.6% 22.8% 3 Ashwin 46,980.00 38,460.50 37,763.22 42,807.70 -8.9% 24.9% 11.3% 13.4% 4 Kartik 42,225.00 37,942.20 37,906.55 43,003.00 1.8% 14.0% 13.3% 13.4% 5 Mangsir 30,805.00 20,057.90 36,810.44 36,903.30 19.8% 0.3% 84.0% 0.3% 6 Poush 21,410.00 27,531.70 27,459.97 27,596.25 28.9% 1.8% 0.2% 0.5% 7 Magh 15,990.00 21,542.80 21,509.72 12,596.75 -21.2% -41.0% -41.5% -41.4% 8 Falgun 14,610.00 19,874.80 22,509.63 9 Chaitra 17,565.00 20,831.30 22,371.43 10 Baisakh 26,305.00 28,733.20 30,483.50 11 Jestha 39,615.00 44,877.40 43,439.36 12 Asadh 47,135.00 43,511.40 42,603.22 Annual Gen.(GWh) 397.59 377.14 399.31
  • 31. Presented by: Bhavin Pradhan Bishnu Dawadi Kalyan Shrestha Kishwor Karki Umesh Gurung Roshan Gurung DEPARTMENT OF ELECTRICAL ENGINEERING Kathmandu Engineering College