Question 3- Xebec Technologies Corporation submitted their proposal to the United States Air Force. The air force requires that all proposals be submitted in a PERT format. Xebec went back and reworked the numbers. The revised PERT data are listed below. Draw the network diagram for this project. 1- What is the project expected time of completion? 2- What is the standard deviation of the critical path?.