PT PERTAMINA (PERSERO)
DIREKTORAT PENGOLAHAN

Heater 211 H-1 RU II Dumai

CONFIDENTIAL AND PROPRIETARY
Any use of this material without specific permission of Pertamina is strictly
prohibited
KONDISI AWAL

STATUS per 24 FEB

Tindal Lanjut
Beberapa Assesment :
• Seluruh tube radiant sisi Recycle dilakukan insitu metalografi
dan metal assesment lainnya.
• Seluruh structure Heater dilakukan assesment oleh LUK & JGC
menggunakan finite element (strutural model).
• Seluruh sambungan las tube heater recycle section heater
dilakukan phased array test dan NDT test.
• Convection Section dilakukan assesment & hydrostatic test.
• Stack dan structure Heater diakukan pengukuran theodolete
untuk mendapatkan verticality yang terjadi.
KONDISI AWAL

STATUS per 24 FEB

Tindal Lanjut
Beberapa pekerjaan demolish :
•
•
•
•
•
•
•

Penyingkiran refractories eks center wall.
Penyingkiran refractories eks floor section.
Penyingkiran potongan eks tube-2 recycle section
Penyingkiran seluruh eks ceramic fibre dalam heater
Penyingkiran seluruh burner system
Penyingkiran seluruh sootblower
Penyingkiran pipa, structure, bordes yang lepas/putus.
KONDISI AWAL

STATUS per 24 FEB

Tindal Lanjut
Pekerjaan Mechanical saat ini :
• Pemasangan reinforcement, penguatan-2 dan
skur dilakukan dalam perbaikan structure..
• Penggantian sejumlah 11 batang tube SS
347 di Recycle Section
• Penggantian/perbaikan seluruh tube hanger
• Pekerjaan Perbaikan seluruh ceramic fiber
bagian dalam heater.
• Pekerjaan perbaikan/reposisi dinding selatan &
utara.
• Pekerjaan perbaikan seluruh refractories floor
section.
• Pekerjaan perbaikan seluruh (24 set) burner
system.
• Pekerjaan penggantian baru selururh
sootblower (12 unit).
• Pekerjaan perbaikan/pemasangan center wall.
• Pekerjaan perbaikan/penggantian
support, spring dan piping system.
• Pekerjaan Perbaikan 2 set damper system dan
stack.
• Perbaikan/penggantian seluruh thermowell dan
seluruh instrumentation
• Penggantian seluruh cableling instrumentation
dan electrical.
• Pekerjaan perbaikan O2 Analizer
• Penggantian seluruh gasket system
• Penggantian seluruh pipe insulation yang
terbakar
• Pekerjaan fabrikasi piping untuk
penggantian, terus berlangsung.

4
CATATAN :
•
•
•
•

Seluruh soot blower diperbaiki vendor LTSA
Dinding sisi selatan dilaksanakan oleh PT SISTEC
Dinding sisi utara dilaksanakan oleh PT KOIN
Untuk Ceramic Blanket sisi selatan & utara dilaksanakan oleh
PT GAM dengan material dikirim by air freight dari surabaya
setiap 2 hari mulai tgl. 24 Feb .
• Sedangkan untuk Ceramic Blanket sisi barat & timur dilaksanakan oleh PT SSS dengan material di kirim by air freight dari
Jakarta setiap 2 hari mulai tgl. 26 Feb.
• Structure model assesment dilakukan oleh LUK dan JGC yang
untuk melakukan perkuatan dan reinforcement pada strukture
yang rusak.
• Tube 6 batang @ 9 m & 9 batang @ 3 m dari RU V menggunakan hercules
AU tiba tgl. 28 Feb di Dumai RU II
TERIMA KASIH

6

More Related Content

Featured

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Featured (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Kerusakan 211 h 1

  • 1. PT PERTAMINA (PERSERO) DIREKTORAT PENGOLAHAN Heater 211 H-1 RU II Dumai CONFIDENTIAL AND PROPRIETARY Any use of this material without specific permission of Pertamina is strictly prohibited
  • 2. KONDISI AWAL STATUS per 24 FEB Tindal Lanjut Beberapa Assesment : • Seluruh tube radiant sisi Recycle dilakukan insitu metalografi dan metal assesment lainnya. • Seluruh structure Heater dilakukan assesment oleh LUK & JGC menggunakan finite element (strutural model). • Seluruh sambungan las tube heater recycle section heater dilakukan phased array test dan NDT test. • Convection Section dilakukan assesment & hydrostatic test. • Stack dan structure Heater diakukan pengukuran theodolete untuk mendapatkan verticality yang terjadi.
  • 3. KONDISI AWAL STATUS per 24 FEB Tindal Lanjut Beberapa pekerjaan demolish : • • • • • • • Penyingkiran refractories eks center wall. Penyingkiran refractories eks floor section. Penyingkiran potongan eks tube-2 recycle section Penyingkiran seluruh eks ceramic fibre dalam heater Penyingkiran seluruh burner system Penyingkiran seluruh sootblower Penyingkiran pipa, structure, bordes yang lepas/putus.
  • 4. KONDISI AWAL STATUS per 24 FEB Tindal Lanjut Pekerjaan Mechanical saat ini : • Pemasangan reinforcement, penguatan-2 dan skur dilakukan dalam perbaikan structure.. • Penggantian sejumlah 11 batang tube SS 347 di Recycle Section • Penggantian/perbaikan seluruh tube hanger • Pekerjaan Perbaikan seluruh ceramic fiber bagian dalam heater. • Pekerjaan perbaikan/reposisi dinding selatan & utara. • Pekerjaan perbaikan seluruh refractories floor section. • Pekerjaan perbaikan seluruh (24 set) burner system. • Pekerjaan penggantian baru selururh sootblower (12 unit). • Pekerjaan perbaikan/pemasangan center wall. • Pekerjaan perbaikan/penggantian support, spring dan piping system. • Pekerjaan Perbaikan 2 set damper system dan stack. • Perbaikan/penggantian seluruh thermowell dan seluruh instrumentation • Penggantian seluruh cableling instrumentation dan electrical. • Pekerjaan perbaikan O2 Analizer • Penggantian seluruh gasket system • Penggantian seluruh pipe insulation yang terbakar • Pekerjaan fabrikasi piping untuk penggantian, terus berlangsung. 4
  • 5. CATATAN : • • • • Seluruh soot blower diperbaiki vendor LTSA Dinding sisi selatan dilaksanakan oleh PT SISTEC Dinding sisi utara dilaksanakan oleh PT KOIN Untuk Ceramic Blanket sisi selatan & utara dilaksanakan oleh PT GAM dengan material dikirim by air freight dari surabaya setiap 2 hari mulai tgl. 24 Feb . • Sedangkan untuk Ceramic Blanket sisi barat & timur dilaksanakan oleh PT SSS dengan material di kirim by air freight dari Jakarta setiap 2 hari mulai tgl. 26 Feb. • Structure model assesment dilakukan oleh LUK dan JGC yang untuk melakukan perkuatan dan reinforcement pada strukture yang rusak. • Tube 6 batang @ 9 m & 9 batang @ 3 m dari RU V menggunakan hercules AU tiba tgl. 28 Feb di Dumai RU II