2. Project Timeline
October 2013 - Did research on local companies
November 2013 - Bids submitted by 3 companies
December 2013 - Applied for Alliant Energy Rebate
Feb. 2014 - Accepted Proposal from Eagle Point Solar
March 2014 - Applied for ECIA ERLF Loan
April 2014 - Alliant Energy Assessment
May 2014 - Installed Occupancy Light Sensors
May 2014 - Projected Started
June 2014 - Estimated Completion Date
Aug. 2014 - Panels and Inverter Install Complete
Sept. 2014 - Passed Alliant Inspection
Sept. 2014 - Received Permission to Operate
Sept. 2014 - Loan Closed with ECIA
October 2014 - Rebate submitted with Alliant
December 2014 - Rebate check received from Alliant