1. The KAPSARC SAP PM IMPLEMENTATION PLAN is developed to track status and
milestones of the implementation. The plan has been divided into four phases;
Phase I: utility plants partial SAP PM Startup plans
Phase II: Completion of utility plant SAP PM Implementation
Phase III: Residential SAP implementation.
Phase IV: Iconic Building SAP implementation
Phase I: KAPSARC utility plants partial SAP PM Startup plans
ACTION STATUS Action ETC
by
Assignment of a new SAP Completed Part of the configuration
Plant and configuring it
as Planning Plant
Creation of Operation Completed Part of the configuration
and Maintenance Cost
Centers
Identifying Locations, Completed Part of the configuration
Planner Group and Work
Centers in the system
Building the Structure of 1: Functional Location first batch is already uploaded.
the Functional Location
2: FL hierarchy needs to be completed manually
Adding equipment Program is in place and first batch is already uploaded (300)
records equipment
Reflecting the different Roles has been already assigned
Authorization Roles
Adding Task List General task list to be ready by next week.
Adding Standard Text To be completed as part of the uploading program by IT with the
vendor. Once the program is available, OM to create it otherwise it
needs to be created manually
Maintenance items
Maintenance Plans