1. Cost and material Estimation Summary of
A Residential Building
Jarsing Pauwa
S. No. Description Amount
1 Sub structure 856,238.84
2 GROUND FLOOR
Superstructure works 865,019.42
Finishing works 1,021,230.35
3 FIRST FLOOR
Superstructure works 1,122,900.15
Finishing works 919,568.22
4 Sloping roof
Superstructure works 389,474.94
Finishing works 11,658.00
Total Cost 5,186,089.91
5 Electrical works 8% of total cost 414,887.19
6 Sanitation works 7.5% of total cost 388,956.74
7 Miscellaneous expenses 10% of total cost 518,608.99
Grand Total 6,508,542.84
Certification:
Here with this, we certify that the present construction cost as estimated of a residential
building owned by JARSING PAUWA is in Nepalese Rupees six million five hundred eight
thousand five hundred and forty three.
REVIEW
Sub-Structure Cost 856,238.84 13%
Super-structure Cost 2,377,394.51 37%
Finishing Cost 1,952,456.57 30%
Electrical+Sanitation Cost 803,843.94 12%
Miscellaneous expances 518,608.99 8%
Total 6,508,542.84 100%
Total Floor area (1125+1145) 2,270.00 Sqft
Unit Cost in Aggregate 2,867.20 Sqft
Thank You.
Prepared By:
Er.Sarita Ranabhat
20 Janaurary 13