Schedule Performance Index (SPI) in Project Management

1,230 views

Published on

How to calculate and interpret SPI as it is used in earned value analysis in project management. Download additional slides, videos, and resources at https://www.christiansonjs.com/

Signup for The Free-Range Technologist, a monthly newsletter filled with creative commons resources, useful apps, and lifehacks: https://mailchi.mp/f8f0219bc305/jscott

Published in: Engineering
  • Don't forget another good way of simplifying your writing is using external resources (such as ⇒ www.HelpWriting.net ⇐ ). This will definitely make your life more easier
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • Hi there! I just wanted to share a list of sites that helped me a lot during my studies: .................................................................................................................................... www.EssayWrite.best - Write an essay .................................................................................................................................... www.LitReview.xyz - Summary of books .................................................................................................................................... www.Coursework.best - Online coursework .................................................................................................................................... www.Dissertations.me - proquest dissertations .................................................................................................................................... www.ReMovie.club - Movies reviews .................................................................................................................................... www.WebSlides.vip - Best powerpoint presentations .................................................................................................................................... www.WritePaper.info - Write a research paper .................................................................................................................................... www.EddyHelp.com - Homework help online .................................................................................................................................... www.MyResumeHelp.net - Professional resume writing service .................................................................................................................................. www.HelpWriting.net - Help with writing any papers ......................................................................................................................................... Save so as not to lose
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • Be the first to like this

Schedule Performance Index (SPI) in Project Management

  1. 1. Scheduling Performance Index (SPI)
  2. 2. SPI = EV PV Scheduling Performance Index (SPI)
  3. 3. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule
  4. 4. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Today Activity A: PV BY TODAY= $16,000
  5. 5. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Activity A: PV BY TODAY= $16,000 Today
  6. 6. Scheduling Performance Index (CPI) 50% Activity A: Total PV = $24,000 (CPI)SPI Activity A: PV BY TODAY= $16,000 Today
  7. 7. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 50% EV= $24,000* 50% = $12,000 SPI EV $12,000 Activity A: PV BY TODAY= $16,000 Today $16,000
  8. 8. Scheduling Performance Index SPI $12,000 = = .75 0.75 $16,000 0 0.5 1 1.5 2 2.5
  9. 9. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 0.75
  10. 10. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Project 0.75
  11. 11. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Today Activity A: PV BY TODAY= $16,000
  12. 12. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Activity A: PV BY TODAY= $16,000 Today
  13. 13. Scheduling Performance Index (CPI) 83.33% Activity A: Total PV = $24,000 (CPI)SPI Activity A: PV BY TODAY= $16,000 Today
  14. 14. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 EV= $24,000* 83.33% = ~$20,000 SPI EV $20,000 Activity A: PV BY TODAY= $16,000 Today $16,000 83.33%
  15. 15. 0 0.5 1 1.5 2 2.5 1.25 Scheduling Performance Index SPI= = 1.25 $16,000 $20,000
  16. 16. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 1.25
  17. 17. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI 1.25 Project
  18. 18. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule
  19. 19. Be Careful When Using Money to Measure Time
  20. 20. Be Careful When Using Money to Measure Time Activity A: Total PV = $24,000 EV= $24,000* 75.00% = ~$18,000EV $18,000 Activity A: PV BY TODAY= $24,000 LF= Jan 4, 2020 Interpretation of SPI Today June 5, 2021 EV 75.00% SPI = $24,000 $18,000 = 0.75 <-18 Months Late->
  21. 21. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 0.75
  22. 22. Be Careful When Using Money to Measure Time Activity A: Total PV = $24,000 EV= $24,000* 100.00% = ~$24,000EV $24,000 Activity A: PV BY TODAY= $24,000 LF= Jan 4, 2020 Interpretation of SPI Today June 5, 2021 EV 100.00% SPI = $24,000 $24,000 = 1.0 <-18 Months Late->
  23. 23. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 1.00
  24. 24. Indexes to Monitor Progress

×