SlideShare a Scribd company logo
1 of 4
Download to read offline
A special technology insert to DatacenterDynamicsFOCUS
Sponsored by
6 www.datacenterdynamics.com
FOCUS on POWER cummins
What you should know
before designing an
electrical system
Cummins suggests three key factors
to consider
Three factors have to be considered when
determining what the power-distribution
infrastructure will look like, writes Cummins’
senior manager of strategic accounts
Richard Hallahan. They are the size of this
infrastructure, the reliability architecture and
operational complexity.
Hallahan takes a deep dive on each of these
factors in his whitepaper titled Data center
design decisions and their impact on power
system infrastructure.
Size matters
Hallahan’s first crucial factor is the size of
the infrastructure. Definition of the power
infrastructure for the entire facility is
closely related to heat generated by the IT
equipment. This is because IT and cooling
infrastructure are the biggest energy
consumers in the data center and their peak
consumption defines the facility’s power
needs.
Hallahan recommends two methods for
calculating electrical consumption of the IT
equipment. The first method is multiplying
the data center floor’s heat load by its area.
Heat load in this equation is expressed in
watts per square foot. Thus, a 48,000 sq ft data
center floor with heat density of 150 watts per
sq ft will consume 7,200,000 watts, or 7.2MW.
The second method is multiplying heat load
of an IT rack by the total number of racks on
the floor at full capacity. Using this equation,
IT equipment in a 600-rack data center with
capacity at 12kW per rack will also consume
7.2MW total.
Hallahan suggests a simple rule of thumb for
using the IT power number to calculate an
approximate power the entire data center is
going to consume. Since mechanical systems
of a facility often consume about the same
amount of power as the IT gear on the raised
floor, total data center power can be arrived
at by simply multiplying IT power by two.
How reliable do you want
to go?
The second key factor, reliability architecture,
considers which Tier of the Uptime Institute’s
Tier Classification system for infrastructure
reliability the facility is going to be designed
to. The decision to build to one of the four
tiers will to a large extent dictate the power
infrastructure’s design. At Tier II, for example,
some (but not all) components of the power
system will be redundant.
The reliability architecture further defines
power system infrastructure. The same Tier II
data center will most likely have paralleling
switchgear to integrate both generators into
the infrastructure instead of using a transfer
switch.
The higher the chosen reliability tier, the more
expensive the system will be.
Another aspect that influences power system
architecture and the facility’s initial cost is the
choice of operating voltage. Since there is
no rule of thumb for determining what cost
a certain operating voltage will translate to,
Hallahan recommends comparing the cost of
a number of designs with different operating
need caption
7www.datacenterdynamics.com
cummins FOCUS on CONTAINERS
voltages to determine the optimal one.
The complexity factor
Hallahan’s third key factor that determines
design of the power infrastructure is the
system’s operational complexity. This factor is
closely tied to the second factor of reliability
level, he writes. A higher Tier for example,
will create the necessity to install paralleling
switchgear and other automatically
controlled devices. More equipment means
a more complex operational sequence for
reacting to changes in normal operating
conditions like loss of utility power.
When utility power is lost, the sequence is
designed to transfer the data center load to
redundant power-path interconnections,
which keep the facility running during
an outage. The amount of power paths
in different systems can be two or more,
depending on design complexity.
The level of operational complexity a power
distribution system is going to have will be
determined to a large extent by the two
choices described above: size and reliability.
Examples of common power configurations
are isolated bus, multiple transfer pairs, main-
tie-main split generator bus and more.
More complexity is added by integration
of paralleling, power-transfer and system
controls into the larger power distribution
system for the facility. This can include more
supervisory control via a SCADA (supervisory
control and data acquisition) system.
Hallahan says standard architectures are
usually more reliable than custom-designed
Staying power
Q&A with Richard Hallahan, senior
manager of strategic accounts,
Cummins. Author of Data center design
decisions and their impact on power
system infrastructure
DatacenterDynamics FOCUS: How
universal is the rule of thumb that a
facility’s total power consumption is its
IT load times two?
Richard Hallahan: It is just a“rule of
thumb” I was given years ago by a
senior engineer. It gives you an order
of magnitude from which to start when
you are at the conceptual design stage
of a project. It always seems that owners
know what power density (w/ft² or kw/
rack) they want to achieve when the
facility is completely built out very early
on in the project. As design evolves, the
owner and consultant should continue
to enter known power consumption
values of all the equipment into their
calculation to further refine sizing needs
of the backup power system.
DCDF: What do new-generation
intelligent infrastructure management
tools do to the way electrical
infrastructure is designed?
RH: The new tools have not had a
significant impact on infrastructure
design, but I expect they will in the
near future. Right now, these tools
can compile a considerable amount of
data about power consumption trends
within the facility. As facilities strive
to become more and more energy
efficient, trend analysis will become key
to understanding where opportunities
exist to improve energy efficiency.
Electrical infrastructure design will
evolve to take advantage of these
opportunities.
DCDF: What key factors are considered
in the decision about the redundancy
level of a data center infrastructure?
RH: Start by understanding the business
impact associated with a loss of power to
facility. Once the impact is understood
it will be up to the owner to decide
how robust they want the facility. This
will drive the quantity of components
needed to support the load.
DCDF: Where is energy efficiency on the
list of top-ten factors to consider when
designing an electrical infrastructure?
RH: In the last five years, energy
efficiency has moved into the top five
factors because the cost of electricity is
the single largest expense over the life
of a data center. At start of the design of
a facility, energy efficiency is probably
#5, but as the design evolves and the
higher factors, like meeting reliability
goals, maintainability of the system,
cost targets etc. are solved by the design
concepts, energy efficiency moves up
the list. Alternatives to improve energy
efficient will be proposed and evaluated
and most likely accepted since they
will positively affect the total cost of
ownership of the facility.
Cummins provided the power
system at the data center of
Phoenix NAP, a provider of
colocation and other data center
services, which include Cloud
offerings, in its namesake city.
8 www.datacenterdynamics.com
FOCUS on POWER cummins
ones because they had been in operation
for many hours – enough to reveal flaws in
programming of sequences of operations.
Programming in standard architectures has
been used in multiple applications of the one
standard architecture, which makes it more
reliable than a custom design.
Another benefit of standard power system
architectures is easy replaceability of their
components. If any component of a standard
architecture needs to be replaced, the end
user usually has no trouble finding it on the
market. It should be readily available and
easily integrated into the infrastructure. This
reduces the potential for downtime.
Being able to easily replace failed parts is key
to equipment’s serviceability. More complex
custom-designed systems are also simply
more expensive. The more complex a system
is, the higher the cost of the hardware itself,
but there is also the added cost of testing
whether the system works as intended and
additional maintenance costs.
To summarize, a user has to know their future
data center’s floor area (or the number of racks)
and power density. They need to decide how
reliable of a facility they need and determine
the optimal level of complexity required.
Phoenix NAP’s focus on
reliability
Here’s an example of Cummins’power
architecture decision-making tenets applied
to a real-life project. Cummins provided the
power system at the data center of Phoenix
NAP, a provider of colocation and other
data center services, which include Cloud
offerings, in its namesake city. Cummins
delivered the data center’s entire standby
power system.
The top consideration for Phoenix NAP was
reliability, since its business success hinges on
its ability to ensure uptime for clients, which
include financial institutions, web properties
and web commerce companies.
At Phase I, the data center’s load would be 4MW,
expandable to 8MW in the second phase.The
power system had to be designed, however, to
eventually scale up to 40MW. Size of the data
center floor in Phase I was 45,000 sq ft.
The initial system was a digital paralleling
system that included DMC 200 controls, 10
section switchgear line-up and two 2MW
DQKAB generator sets in sound-attenuated
housing. More gen-sets would be added as
the business grows.
The system can be monitored and controlled
from three different locations in the data
center: control room, mechanical and
enclosure room.
Space at the site was limited, so finding
space to install UPS and generator systems
was a challenge. Cummins decided to put
the generator sets outdoors – hence the
acoustical enclosures. These enclosures (two
generators per enclosure) were custom-
designed. Paralleling gear was placed in an
outdoor enclosure as well.
Cox Communications’
complex needs
Another example of a real-life application of
Cummins’approach to power infrastructure
design was the work it did for Cox Enterprises.
Also in Phoenix, the service provider’s new
110,000 sq ft data center needed a standby
power system that would ensure the six
million residences and businesses in the
US that used Cox’s digital video, internet,
telephone and wireless services continued
receiving them uninterrupted.
Cummins installed a paralleling system with
two PowerCommand DCM 300 controllers
and three DQKAB diesel generator sets rated
at 2MW each. Cummins manufactured,
designed and integrated the system. It also
services it.
Cox needed 4.8MW of critical power, with
2.4MW of critical no-break power and 1.6MW
of short-break power for chillers, pumps,
air conditioners and lights. The initial phase
included three 2MW generators, but would
eventually have to accommodate three more.
Another requirement was for the system
to be able to shift load between A and B
switchgear, so total building load could be
supported by either of the two switchgear
sets for uninterrupted maintenance. n
need caption

More Related Content

What's hot

[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...Schneider Electric
 
Implementing energy efficient data centers
Implementing energy efficient  data centersImplementing energy efficient  data centers
Implementing energy efficient data centersSchneider Electric India
 
Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...PromiseBeshel
 
Integrated Control and Safety - Assessing the Benefits; Weighing the Risks
Integrated Control and Safety - Assessing the Benefits; Weighing the RisksIntegrated Control and Safety - Assessing the Benefits; Weighing the Risks
Integrated Control and Safety - Assessing the Benefits; Weighing the RisksSchneider Electric
 
Energy efficiency data center overview
Energy efficiency data center overviewEnergy efficiency data center overview
Energy efficiency data center overviewSchneider Electric
 
6dec2011 - Power Back-up_1
6dec2011 - Power Back-up_16dec2011 - Power Back-up_1
6dec2011 - Power Back-up_1Agora Group
 
[Webinar Presentation] Best Practices for IT/OT Convergence
[Webinar Presentation] Best Practices for IT/OT Convergence[Webinar Presentation] Best Practices for IT/OT Convergence
[Webinar Presentation] Best Practices for IT/OT ConvergenceSchneider Electric
 
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOMModeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOMijsrd.com
 
What is a data center
What is a data centerWhat is a data center
What is a data centerLivin Jose
 
Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...
Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...
Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...Steve Houck
 
Smart Energy in the Data Center
Smart Energy in the Data CenterSmart Energy in the Data Center
Smart Energy in the Data CenterSteve Houck
 
Maximize Your Data Center for Virtualization Initiatives
Maximize Your Data Center for Virtualization InitiativesMaximize Your Data Center for Virtualization Initiatives
Maximize Your Data Center for Virtualization InitiativesSchneider Electric
 
Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...
Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...
Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...Steve Houck
 
Denison university success story schneider electric
Denison university success story schneider electricDenison university success story schneider electric
Denison university success story schneider electricSchneider Electric
 
International Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart GridInternational Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart GridSchneider Electric
 
Underground Self-Healing Solution
Underground Self-Healing Solution Underground Self-Healing Solution
Underground Self-Healing Solution Schneider Electric
 
Information SCADA Subsystem
Information SCADA SubsystemInformation SCADA Subsystem
Information SCADA SubsystemMomir Boskovic
 
Making the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secureMaking the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secureSchneider Electric
 

What's hot (20)

[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
[Case study] Dakota Electric Association: Solutions to streamline GIS, design...
 
Implementing energy efficient data centers
Implementing energy efficient  data centersImplementing energy efficient  data centers
Implementing energy efficient data centers
 
Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...Investigation of the challenges in establishing plug and play low voltage dc ...
Investigation of the challenges in establishing plug and play low voltage dc ...
 
Integrated Control and Safety - Assessing the Benefits; Weighing the Risks
Integrated Control and Safety - Assessing the Benefits; Weighing the RisksIntegrated Control and Safety - Assessing the Benefits; Weighing the Risks
Integrated Control and Safety - Assessing the Benefits; Weighing the Risks
 
Energy efficiency data center overview
Energy efficiency data center overviewEnergy efficiency data center overview
Energy efficiency data center overview
 
6dec2011 - Power Back-up_1
6dec2011 - Power Back-up_16dec2011 - Power Back-up_1
6dec2011 - Power Back-up_1
 
[Webinar Presentation] Best Practices for IT/OT Convergence
[Webinar Presentation] Best Practices for IT/OT Convergence[Webinar Presentation] Best Practices for IT/OT Convergence
[Webinar Presentation] Best Practices for IT/OT Convergence
 
AccuSine pfv+
AccuSine pfv+ AccuSine pfv+
AccuSine pfv+
 
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOMModeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
Modeling Analysis& Solution of Power Quality Problems Using DVR & DSTATCOM
 
What is a data center
What is a data centerWhat is a data center
What is a data center
 
Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...
Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...
Overcoming Rack Power Limits with Virtual Power Systems Dynamic Redundancy an...
 
Smart Energy in the Data Center
Smart Energy in the Data CenterSmart Energy in the Data Center
Smart Energy in the Data Center
 
Maximize Your Data Center for Virtualization Initiatives
Maximize Your Data Center for Virtualization InitiativesMaximize Your Data Center for Virtualization Initiatives
Maximize Your Data Center for Virtualization Initiatives
 
Embedded systems Implementation in Cloud Challenges
Embedded systems Implementation in Cloud ChallengesEmbedded systems Implementation in Cloud Challenges
Embedded systems Implementation in Cloud Challenges
 
Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...
Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...
Virtual Power Systems - Intelligent Control of Energy (ICE) and Software Defi...
 
Denison university success story schneider electric
Denison university success story schneider electricDenison university success story schneider electric
Denison university success story schneider electric
 
International Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart GridInternational Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart Grid
 
Underground Self-Healing Solution
Underground Self-Healing Solution Underground Self-Healing Solution
Underground Self-Healing Solution
 
Information SCADA Subsystem
Information SCADA SubsystemInformation SCADA Subsystem
Information SCADA Subsystem
 
Making the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secureMaking the grid more efficient, flexible and secure
Making the grid more efficient, flexible and secure
 

Viewers also liked (16)

Buku pedoman
Buku pedomanBuku pedoman
Buku pedoman
 
Metas para el año 2016
Metas para el año  2016Metas para el año  2016
Metas para el año 2016
 
Df Iglesiarusas
Df IglesiarusasDf Iglesiarusas
Df Iglesiarusas
 
六閤彩开奖港彩结果
六閤彩开奖港彩结果六閤彩开奖港彩结果
六閤彩开奖港彩结果
 
David
DavidDavid
David
 
Resume
ResumeResume
Resume
 
Anne-Marie van Dijk Avantgarde
Anne-Marie van Dijk AvantgardeAnne-Marie van Dijk Avantgarde
Anne-Marie van Dijk Avantgarde
 
Photography
PhotographyPhotography
Photography
 
Kozma Botond Szilárd: Gerle Éva perverzióra való hajlamai a sorsképlete tükrében
Kozma Botond Szilárd: Gerle Éva perverzióra való hajlamai a sorsképlete tükrébenKozma Botond Szilárd: Gerle Éva perverzióra való hajlamai a sorsképlete tükrében
Kozma Botond Szilárd: Gerle Éva perverzióra való hajlamai a sorsképlete tükrében
 
tommy hilfiger tas
tommy hilfiger tastommy hilfiger tas
tommy hilfiger tas
 
Cre ar toledo juegos_038
Cre ar toledo juegos_038Cre ar toledo juegos_038
Cre ar toledo juegos_038
 
Ante A LiçãO
Ante A LiçãOAnte A LiçãO
Ante A LiçãO
 
2010.12.14 tns sofres les francais et leurs ecrans
2010.12.14 tns sofres les francais et leurs ecrans2010.12.14 tns sofres les francais et leurs ecrans
2010.12.14 tns sofres les francais et leurs ecrans
 
Jock Tamson's bairns - rejuvenating public libraries through family history
Jock Tamson's bairns - rejuvenating public libraries through family historyJock Tamson's bairns - rejuvenating public libraries through family history
Jock Tamson's bairns - rejuvenating public libraries through family history
 
Test bank And Solutions Manual
Test bank And Solutions ManualTest bank And Solutions Manual
Test bank And Solutions Manual
 
Grizzly -URSO CRIADO COMO UM CÃOZINHO DE ESTIMAÇÃO
Grizzly -URSO CRIADO COMO UM CÃOZINHO DE ESTIMAÇÃOGrizzly -URSO CRIADO COMO UM CÃOZINHO DE ESTIMAÇÃO
Grizzly -URSO CRIADO COMO UM CÃOZINHO DE ESTIMAÇÃO
 

Similar to DCD_FOCUS on POWER Article

White Paper-Data Centers Design Decisions
White Paper-Data Centers Design DecisionsWhite Paper-Data Centers Design Decisions
White Paper-Data Centers Design DecisionsRichard Hallahan, PE
 
Calculating total power
Calculating total powerCalculating total power
Calculating total powerjeet69
 
Schneider - ASK THE EXPERT - ITNEXT
Schneider - ASK THE EXPERT - ITNEXTSchneider - ASK THE EXPERT - ITNEXT
Schneider - ASK THE EXPERT - ITNEXTAniket Patange
 
Facility Optimization
Facility OptimizationFacility Optimization
Facility Optimizationcwoodson
 
PlanningDataCenterFacilities
PlanningDataCenterFacilitiesPlanningDataCenterFacilities
PlanningDataCenterFacilitiesJoseph Kassl
 
Energy performance in mission critical facilities
Energy performance in mission critical facilitiesEnergy performance in mission critical facilities
Energy performance in mission critical facilitiesAlcides Villarreal Polo
 
Wp 75-comparing-ups-system-design-configurations
Wp 75-comparing-ups-system-design-configurationsWp 75-comparing-ups-system-design-configurations
Wp 75-comparing-ups-system-design-configurationsLuisMaio8
 
BLOG-POST_DATA CENTER INCENTIVE PROGRAMS
BLOG-POST_DATA CENTER INCENTIVE PROGRAMSBLOG-POST_DATA CENTER INCENTIVE PROGRAMS
BLOG-POST_DATA CENTER INCENTIVE PROGRAMSDaniel Bodenski
 
Data Centre Overview
Data Centre OverviewData Centre Overview
Data Centre OverviewLogicalis
 
Logicalis - Data Centre Overview
Logicalis - Data Centre OverviewLogicalis - Data Centre Overview
Logicalis - Data Centre OverviewLogicalis
 
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRESCOMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRESKamran Hassan
 
Advanced Metering Infrastructure Standards and protocol
Advanced Metering Infrastructure Standards and protocolAdvanced Metering Infrastructure Standards and protocol
Advanced Metering Infrastructure Standards and protocolEklavya Sharma
 
Compu Dynamics White Paper - Essential Elements for Data Center Optimization
Compu Dynamics White Paper - Essential Elements for Data Center OptimizationCompu Dynamics White Paper - Essential Elements for Data Center Optimization
Compu Dynamics White Paper - Essential Elements for Data Center OptimizationDan Ephraim
 
sumerian_datacenter-consolidation-white_paper
sumerian_datacenter-consolidation-white_papersumerian_datacenter-consolidation-white_paper
sumerian_datacenter-consolidation-white_paperKelly Moscrop
 
Robust Free Power management: Dell OpenManage Power Center
Robust Free Power management: Dell OpenManage Power CenterRobust Free Power management: Dell OpenManage Power Center
Robust Free Power management: Dell OpenManage Power CenterPrincipled Technologies
 

Similar to DCD_FOCUS on POWER Article (20)

White Paper-Data Centers Design Decisions
White Paper-Data Centers Design DecisionsWhite Paper-Data Centers Design Decisions
White Paper-Data Centers Design Decisions
 
Calculating total power
Calculating total powerCalculating total power
Calculating total power
 
Schneider - ASK THE EXPERT - ITNEXT
Schneider - ASK THE EXPERT - ITNEXTSchneider - ASK THE EXPERT - ITNEXT
Schneider - ASK THE EXPERT - ITNEXT
 
Facility Optimization
Facility OptimizationFacility Optimization
Facility Optimization
 
PlanningDataCenterFacilities
PlanningDataCenterFacilitiesPlanningDataCenterFacilities
PlanningDataCenterFacilities
 
Computer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introductionComputer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introduction
 
Energy performance in mission critical facilities
Energy performance in mission critical facilitiesEnergy performance in mission critical facilities
Energy performance in mission critical facilities
 
Wp 75-comparing-ups-system-design-configurations
Wp 75-comparing-ups-system-design-configurationsWp 75-comparing-ups-system-design-configurations
Wp 75-comparing-ups-system-design-configurations
 
122 whitepaper
122 whitepaper122 whitepaper
122 whitepaper
 
BLOG-POST_DATA CENTER INCENTIVE PROGRAMS
BLOG-POST_DATA CENTER INCENTIVE PROGRAMSBLOG-POST_DATA CENTER INCENTIVE PROGRAMS
BLOG-POST_DATA CENTER INCENTIVE PROGRAMS
 
Data Centre Overview
Data Centre OverviewData Centre Overview
Data Centre Overview
 
Logicalis - Data Centre Overview
Logicalis - Data Centre OverviewLogicalis - Data Centre Overview
Logicalis - Data Centre Overview
 
Data Centers
Data CentersData Centers
Data Centers
 
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRESCOMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
 
Advanced Metering Infrastructure Standards and protocol
Advanced Metering Infrastructure Standards and protocolAdvanced Metering Infrastructure Standards and protocol
Advanced Metering Infrastructure Standards and protocol
 
Compu Dynamics White Paper - Essential Elements for Data Center Optimization
Compu Dynamics White Paper - Essential Elements for Data Center OptimizationCompu Dynamics White Paper - Essential Elements for Data Center Optimization
Compu Dynamics White Paper - Essential Elements for Data Center Optimization
 
sumerian_datacenter-consolidation-white_paper
sumerian_datacenter-consolidation-white_papersumerian_datacenter-consolidation-white_paper
sumerian_datacenter-consolidation-white_paper
 
Robust Free Power management: Dell OpenManage Power Center
Robust Free Power management: Dell OpenManage Power CenterRobust Free Power management: Dell OpenManage Power Center
Robust Free Power management: Dell OpenManage Power Center
 
StruxureWare DCIM Q&A
StruxureWare DCIM Q&AStruxureWare DCIM Q&A
StruxureWare DCIM Q&A
 
Data center m&e
Data center  m&eData center  m&e
Data center m&e
 

DCD_FOCUS on POWER Article

  • 1. A special technology insert to DatacenterDynamicsFOCUS Sponsored by
  • 2. 6 www.datacenterdynamics.com FOCUS on POWER cummins What you should know before designing an electrical system Cummins suggests three key factors to consider Three factors have to be considered when determining what the power-distribution infrastructure will look like, writes Cummins’ senior manager of strategic accounts Richard Hallahan. They are the size of this infrastructure, the reliability architecture and operational complexity. Hallahan takes a deep dive on each of these factors in his whitepaper titled Data center design decisions and their impact on power system infrastructure. Size matters Hallahan’s first crucial factor is the size of the infrastructure. Definition of the power infrastructure for the entire facility is closely related to heat generated by the IT equipment. This is because IT and cooling infrastructure are the biggest energy consumers in the data center and their peak consumption defines the facility’s power needs. Hallahan recommends two methods for calculating electrical consumption of the IT equipment. The first method is multiplying the data center floor’s heat load by its area. Heat load in this equation is expressed in watts per square foot. Thus, a 48,000 sq ft data center floor with heat density of 150 watts per sq ft will consume 7,200,000 watts, or 7.2MW. The second method is multiplying heat load of an IT rack by the total number of racks on the floor at full capacity. Using this equation, IT equipment in a 600-rack data center with capacity at 12kW per rack will also consume 7.2MW total. Hallahan suggests a simple rule of thumb for using the IT power number to calculate an approximate power the entire data center is going to consume. Since mechanical systems of a facility often consume about the same amount of power as the IT gear on the raised floor, total data center power can be arrived at by simply multiplying IT power by two. How reliable do you want to go? The second key factor, reliability architecture, considers which Tier of the Uptime Institute’s Tier Classification system for infrastructure reliability the facility is going to be designed to. The decision to build to one of the four tiers will to a large extent dictate the power infrastructure’s design. At Tier II, for example, some (but not all) components of the power system will be redundant. The reliability architecture further defines power system infrastructure. The same Tier II data center will most likely have paralleling switchgear to integrate both generators into the infrastructure instead of using a transfer switch. The higher the chosen reliability tier, the more expensive the system will be. Another aspect that influences power system architecture and the facility’s initial cost is the choice of operating voltage. Since there is no rule of thumb for determining what cost a certain operating voltage will translate to, Hallahan recommends comparing the cost of a number of designs with different operating need caption
  • 3. 7www.datacenterdynamics.com cummins FOCUS on CONTAINERS voltages to determine the optimal one. The complexity factor Hallahan’s third key factor that determines design of the power infrastructure is the system’s operational complexity. This factor is closely tied to the second factor of reliability level, he writes. A higher Tier for example, will create the necessity to install paralleling switchgear and other automatically controlled devices. More equipment means a more complex operational sequence for reacting to changes in normal operating conditions like loss of utility power. When utility power is lost, the sequence is designed to transfer the data center load to redundant power-path interconnections, which keep the facility running during an outage. The amount of power paths in different systems can be two or more, depending on design complexity. The level of operational complexity a power distribution system is going to have will be determined to a large extent by the two choices described above: size and reliability. Examples of common power configurations are isolated bus, multiple transfer pairs, main- tie-main split generator bus and more. More complexity is added by integration of paralleling, power-transfer and system controls into the larger power distribution system for the facility. This can include more supervisory control via a SCADA (supervisory control and data acquisition) system. Hallahan says standard architectures are usually more reliable than custom-designed Staying power Q&A with Richard Hallahan, senior manager of strategic accounts, Cummins. Author of Data center design decisions and their impact on power system infrastructure DatacenterDynamics FOCUS: How universal is the rule of thumb that a facility’s total power consumption is its IT load times two? Richard Hallahan: It is just a“rule of thumb” I was given years ago by a senior engineer. It gives you an order of magnitude from which to start when you are at the conceptual design stage of a project. It always seems that owners know what power density (w/ft² or kw/ rack) they want to achieve when the facility is completely built out very early on in the project. As design evolves, the owner and consultant should continue to enter known power consumption values of all the equipment into their calculation to further refine sizing needs of the backup power system. DCDF: What do new-generation intelligent infrastructure management tools do to the way electrical infrastructure is designed? RH: The new tools have not had a significant impact on infrastructure design, but I expect they will in the near future. Right now, these tools can compile a considerable amount of data about power consumption trends within the facility. As facilities strive to become more and more energy efficient, trend analysis will become key to understanding where opportunities exist to improve energy efficiency. Electrical infrastructure design will evolve to take advantage of these opportunities. DCDF: What key factors are considered in the decision about the redundancy level of a data center infrastructure? RH: Start by understanding the business impact associated with a loss of power to facility. Once the impact is understood it will be up to the owner to decide how robust they want the facility. This will drive the quantity of components needed to support the load. DCDF: Where is energy efficiency on the list of top-ten factors to consider when designing an electrical infrastructure? RH: In the last five years, energy efficiency has moved into the top five factors because the cost of electricity is the single largest expense over the life of a data center. At start of the design of a facility, energy efficiency is probably #5, but as the design evolves and the higher factors, like meeting reliability goals, maintainability of the system, cost targets etc. are solved by the design concepts, energy efficiency moves up the list. Alternatives to improve energy efficient will be proposed and evaluated and most likely accepted since they will positively affect the total cost of ownership of the facility. Cummins provided the power system at the data center of Phoenix NAP, a provider of colocation and other data center services, which include Cloud offerings, in its namesake city.
  • 4. 8 www.datacenterdynamics.com FOCUS on POWER cummins ones because they had been in operation for many hours – enough to reveal flaws in programming of sequences of operations. Programming in standard architectures has been used in multiple applications of the one standard architecture, which makes it more reliable than a custom design. Another benefit of standard power system architectures is easy replaceability of their components. If any component of a standard architecture needs to be replaced, the end user usually has no trouble finding it on the market. It should be readily available and easily integrated into the infrastructure. This reduces the potential for downtime. Being able to easily replace failed parts is key to equipment’s serviceability. More complex custom-designed systems are also simply more expensive. The more complex a system is, the higher the cost of the hardware itself, but there is also the added cost of testing whether the system works as intended and additional maintenance costs. To summarize, a user has to know their future data center’s floor area (or the number of racks) and power density. They need to decide how reliable of a facility they need and determine the optimal level of complexity required. Phoenix NAP’s focus on reliability Here’s an example of Cummins’power architecture decision-making tenets applied to a real-life project. Cummins provided the power system at the data center of Phoenix NAP, a provider of colocation and other data center services, which include Cloud offerings, in its namesake city. Cummins delivered the data center’s entire standby power system. The top consideration for Phoenix NAP was reliability, since its business success hinges on its ability to ensure uptime for clients, which include financial institutions, web properties and web commerce companies. At Phase I, the data center’s load would be 4MW, expandable to 8MW in the second phase.The power system had to be designed, however, to eventually scale up to 40MW. Size of the data center floor in Phase I was 45,000 sq ft. The initial system was a digital paralleling system that included DMC 200 controls, 10 section switchgear line-up and two 2MW DQKAB generator sets in sound-attenuated housing. More gen-sets would be added as the business grows. The system can be monitored and controlled from three different locations in the data center: control room, mechanical and enclosure room. Space at the site was limited, so finding space to install UPS and generator systems was a challenge. Cummins decided to put the generator sets outdoors – hence the acoustical enclosures. These enclosures (two generators per enclosure) were custom- designed. Paralleling gear was placed in an outdoor enclosure as well. Cox Communications’ complex needs Another example of a real-life application of Cummins’approach to power infrastructure design was the work it did for Cox Enterprises. Also in Phoenix, the service provider’s new 110,000 sq ft data center needed a standby power system that would ensure the six million residences and businesses in the US that used Cox’s digital video, internet, telephone and wireless services continued receiving them uninterrupted. Cummins installed a paralleling system with two PowerCommand DCM 300 controllers and three DQKAB diesel generator sets rated at 2MW each. Cummins manufactured, designed and integrated the system. It also services it. Cox needed 4.8MW of critical power, with 2.4MW of critical no-break power and 1.6MW of short-break power for chillers, pumps, air conditioners and lights. The initial phase included three 2MW generators, but would eventually have to accommodate three more. Another requirement was for the system to be able to shift load between A and B switchgear, so total building load could be supported by either of the two switchgear sets for uninterrupted maintenance. n need caption