SlideShare a Scribd company logo
1 of 76
Download to read offline
March, 2015
SPS Building Products; Floors and Shear Cores
March, 2015
The Sandwich Plate System - SPS
Exhibit 2
Structural Composite
• construction alternative to reinforced concrete and
stiffened steel in construction, civil engineering and
maritime structures
Key Benefits for Construction
• lightweight
• shorter erection schedule
• maximizes offsite construction
• minimizes logistics and risks
• easy to demount and reuse
History
• developed in 1993
• over 387 projects and 300,000m2 (3,230,000ft2) in service
in 30 countries
• used in ships, bridges, stadium and buildings
• approved by major global regulators
SPS
structure
Conventional stiffened
steel structure
Conventional concrete-
steel composite structure
March, 2015 Exhibit 3
Construction and Civil Engineering
SPS Applications
SPS FloorsSPS Terraces SPS Bridges SPS Protection
 75% lighter than
concrete changes
structural options
 prefabricated and very
fast to erect
 extended service life
 re-usable
SPS Overlay
Maritime
SPS Overlay
Bridge Deck
• existing steel decks stiffened in-situ
• fast process with no structural removal
• strengthening of existing deck/shell
• minimizes downtime
Steel Deck Repair Maritime New Build
SPS Hatch
Covers
 elements of a ship/maritime structure
 faster to build and easier to maintain
 built-in additional performance
 more benefits for military structures
SPS Citadel
Protection
March, 2015 Exhibit 4
Partners, Key Relationships and Customers
Joint Venture Partners
Key Relationships
Key Customers
HOFFMAN
March, 2015 Exhibit 5
What are SPS Floors?
SPS Floors
 a composite floor panel made of two steel
plates, a polyurethane core and a steel
perimeter bar or profile
 bolted together to the top flange of the structural
steel beams; generally made composite with
secondary beams
 prefabricated factory quality construction with
close dimensional tolerances
 proven and approved global technology
column
beam
Rigid, semi-rigid or
Simple connections
SPS
Floor
Panel
Bolted connection
to supporting
beams/girders
SPS
Floor
Panel
SPS
Floor
Panel
solid core
bubble core
Core Configuration
 Solid Core: thin floor plates with a compact solid
polyurethane core between faceplates
 Bubble Core: hexagonally closely packed air-filled
polypropylene spheres with diameter equal to core
thickness (deeper and stiffer core allowing longer
spans while remaining lightweight)
March, 2015
clean surfacessuper flat
Exhibit 6
Benefits of SPS Floors
all floor finishes possible
standard fasteners / hangers chilled beam and ducting better fit up
March, 2015 Exhibit 7
Benefits of SPS Floors
immediate structural capacity lightweight lifting equipment thinner floor
shorter erection schedule all bolted construction prefabricated
March, 2015 Exhibit 8
Benefits of SPS Floors
factory quality control close tolerances weather independent
diaphragm capacity lateral stability no construction waste
March, 2015 Exhibit 9
Engineering Design
Statics
 SPS Floors designed to satisfy serviceability and ultimate
limit states for the governing building codes and standards
Dynamics
 dynamic response assessed using;
- preliminary evaluation using HiVoSS method (Route 1)
- guidelines from Steel Construction Institute (Route 2)
- probability-based method (Route 3)
 meets industry-accepted criteria
Acoustics
 designed for minimum airborne sound insulation and
maximum impact sound insulation specified by local
building authority
 SPS Floors in combination with the specified floor and
ceiling meet the specified criteria
Fire
 industry-standard fire protection for steel structures can be
applied to the underside of SPS Floors to provide the
specified fire rating
March, 2015 Exhibit 10
Dynamic Design
Design Methods
 Route 1: preliminary evaluation using HiVoSS method
- applied to a typical bay
- read OS-RMS90 values according to the calculated
frequency, modal mass and damping
 Route 2: guidelines from Steel Construction Institute
- modal analysis for finite element model is conducted to
determine frequency, modal mass and mode shape.
- response factor, which is related to the peak
acceleration, is calculated
 Route 3: probability-based method
- walking paths are defined
- Monte Carlo Method is used to randomly generate
walking frequencies
Design Tools
 SAP2000, ANSYS
 MATLAB based program
 Microsoft Excel based program response factor of the floor (limit is 8)
finite element model in ANSYS
March, 2015 Exhibit 11
Passive Fire Protection
General
 fire insulation is applied to the underside of SPS
plates in accordance with the standards for the
desired fire rating
 details for fire insulation application available from IE
Tests/Certificates
Types of PFP systems
 cementitious spray
 intumescent coatings
 sprinklers
 fibreboard
Certificate
Date of
Issue
Authority
Fire
rating
(minutes)
Type of fire
insulation
Thickness
of SPS
(mm)
ABP 008 2009.11.18 BRE
60 Mineral wool 20
120 Mineral wool 50
BXUV.D305 2009.10.02 UL 120 Mineral wool 50
March, 2015 Exhibit 12
Acoustic Design
“…The SPS floor system is deemed to be acoustically acceptable as both a loading bearing separating floor construction and an internal
load bearing floor construction… also deemed to be acoustically acceptable for non-residential schemes including schools, office spaces,
industrial spaces, bars, clubs and other healthcare spaces…” - Sol Acoustics Ltd.
 SPS floors with fire protection combined with a wide range
of typical ceiling and floor finishes provide a sufficient
acoustic insulation for commercial and residential
buildings.
 Sample calculation using the acoustic design tool for a
typical floor buildup for residential floor, given below,
demonstrates that it meets UK building regulations; STC
ratings given in North American regulations are also met.
Floor Construction
Airborne sound
insulation (dB)
Impact sound
insulation (dB)
Rw Rw + Ctr Lnw
Base SPS-B 4-50-4 33 31 94
Residential
Fire
Insulation
50 mm Paroc FireSlab 150 fire on floor
and 25 mm on beams (2 hour fire rating)
11 8 -20
Flooring Carpet tile 0 0 -8
Raised
Floor
Kingspan RMG600 4 1 -6
Ceiling Armstrong bioguard acoustic board 7 6 -9
Overall Acoustic Performance 55 46 51
Design Limits na ≥ 45 ≤ 62
Acoustic Design Tool for SPS Floor
March, 2015 Exhibit 13
Bolts, Fasteners and Attachments
Bolts (typical spacing 500mm)
Approved Hilti Fasteners and Hangers
Double-sided Single-sided
tension control bolt hexagonal hollo-bolt
hex head bolt countersunk hollo-bolt
socket countersunk screw flush fit hollo-bolt
socket button head screw hexagonal box bolt
Fastener Recommended Pull-out Load
Description Type
SPS 3-20-3 SPS 4-20-4
SPS 4-50-4BC
kN lbs kN lbs
Stud X-EM8H, X-EM10H 2.9 657 3.4 772
Nail X-EGN 14MX 0.7 149 0.9 194
Threaded rod hanger X-HS U19 P8S15 1.6 358 3.0 672
Loop hanger X-CC U16 P8 1.4 314 1.5 336
Threaded rod hanger X-HS MX with X-EGN 14 MX - - 0.4 82
Loop hanger X-CC MX with X-EGN 14 MX 0.4 82 0.5 105
Threaded rod hanger X-HS MX with X-U 16 MX 0.8 179 1.0 225
Loop hanger X-CC MX with X-U 16 MX 0.6 142 0.9 202
Note: Tek screws with various diameters and thread types can also be used to their full capacity.
Please refer to http://www.evolutionfasteners.co.uk/Products/
March, 2015 Exhibit 14
Technical Notes
General
 have more than 70 technical notes
covering different aspects of SPS
plates
Technical Notes
 SPS Polyurethane Disposal
 SPS Structural Damping Characteristics
 SPS Panel Fabrication
 Repairing SPS Panels
 SPS Bond Strength for Steel Plates with
Surface Rust
 Fatigue Resistance at Steel-Elastomer
Interface
 Fire Resistance of SPS
 Surface Preparation for SPS Plates
 Protective Coatings for SPS Plates
 Recommended Fasteners for SPS Plates
 Thermal Transmittance of SPS Plates
…
March, 2015 Exhibit 15
Technical Summary
Typical Service Loads SDL 1.5kPa (0.22psi); LL 4.5kPa (0.65psi) (other loads and combinations readily accommodated)
Deflection Typically less than L/600 (for widths and live load listed above)
Dynamic Response
The stiffness of SPS panels and supporting beams are adjusted to meet needs of a particular
building or room (e.g. R-factor 6 is readily achieved for office floors)
Point Loads
Once bolted in place, SPS Floors are readily able to carry most typical wheel loads from
equipment such as Cherry Pickers, Scissor Lifts, Fork Lifts etc.
Ultimate Capacity
Ultimate capacity of SPS Floor panels is equal to plastic capacity of steel faceplates in bending
and exceeds the effects of standard imposed building loads (greater than 7.5kPa/1.09psi).
(Note: Ultimate capacity of beams is not covered by this data sheet)
Composite Action
Achieved through bolts connecting edges of SPS Floor panels to top flanges of supporting
beams. Welded connections also possible.
Stability
SPS Floors panels transfer diaphragm forces to the lateral load resisting system via bolts
connecting edges of panels to top flanges of supporting beams. Welded connections also
possible.
Fire Resistance
Up to 120:120:120 minutes using conventional fire protection which is either factory or field
applied. When shorter periods are required the thickness of the protection is reduced
accordingly. (Note: an untreated SPS panel achieves an inherent 30 minute resistance with a
20mm (0.8’’) core thickness, and 60 minutes for 25mm (1’’) cores)
Acoustics
Finished floors incorporating SPS Floor panels meet standard acoustic insulation requirements
for airborne, impact and flanking noise for all conventional building types. For instance: SPS Floor
design for hotels and offices provides: 49dB of airborne sound insulation; and 46dB of impact
sound absorption provided standard hotel finishes are applied.
Flatness Tolerance ±3 mm (0.1’’) over 3m (10’)
March, 2015 Exhibit 16
SPS Floors - Approvals / Certification
BRE Global Certification 
 Fabrication & Erection
 Static Performance
 Dynamic Performance
 Lateral Load Resistance
 Fire Resistance
 Acoustic Performance
 M&E Installation
 Fit-out
New York & UL Approvals 
March, 2015 Exhibit 17
Fabrication
 parametric CAD modules
 dedicated production line
 automated production
 CNC driven manufacturing
 fast efficient fabrication
 excellent dimensional tolerances
 adaptable geometry
 climatic control conditions
 maximum integration of details
March, 2015 Exhibit 18
Fabrication Tolerances
Description Range Tolerance
L SPS plate length (max) 5000mm to 9000mm (16.4’ to 30’) ±3mm (±0.1’’)
W SPS plate width (max) 1000mm to 3000mm (3.3’ to 10’) ±3mm (±0.1’’)
-
interior flatness (measured
in a 3m straight edge)
Plate width < 1000mm (3.3’)
Plate width > 1000mm (3.3’)
±2mm (±0.08’’)
±3mm (±0.1’’)
-
edge flatness (measured in
a 3m straight edge)
- ±3mm (±0.1’’)
Δ unrestrained twist -
±5mm (±0.2’’)
Fabrication and Assembly Tolerances
Bolting Tolerances
 Bolt hole size
-bolt hole size shall be 2 mm larger than the bolt hole diameter
 Bolt hole position
-the deviation from the intended position shall not exceed ±1mm
March, 2015 Exhibit 19
Quality Assurance Processes
General
 to ensure that the quality of all material or products and
associated production is verified and comply with the
contractual requirements, codes and standards.
 Quality Assurance Program compatible with ISO 9001
 certified by BRE to international and national standards
 health and safety
- safe working procedures are prescribed
- SPS panel production process is a non-hazardous
activity
- environmental documentation and procedures
relating to the injection process available from IE
March, 2015 Exhibit 20
Quality Assurance Processes
PU Elastomer Quality
 elastomer supplied as two separate components
(polyol, isocyanate)
 characteristics guaranteed by BASF Elastogran
Bond Quality
 steel plate surfaces must be free of rust, dust, grease,
oils and other soluble materials
 PosiTest used to measure bond strengths; compared
with specified values
Steel Quality
 the fabricator is responsible for purchasing the steel
according to the specifications as indicated on the
fabrication drawings or material lists
 no steel material to be used until the certificates of
compliance have been received and reviewed.
Injection Quality
 injection must be overseen by a qualified injection
engineer, who has received adequate training and has
been accredited by IE
 the calibration of the injection machine is checked at
the start of each project
March, 2015 Exhibit 21
SPS Floors - Shipping and Site Storage
Summary
 delivered on a flat-bed transport vehicle or
12.19m (40’) open top containers
 delivery vehicle shall be placed close to the
bay in which the SPS panels will be installed
to minimize the movement of the load
 shipping load sequence and container
contents are specified in method statements
 special care shall be taken to ensure that the
units are handled in accordance with the
method statement on lifting
 for storage of the SPS units, select a flat
unobstructed area in a location that is not
susceptible to damage from other
construction activities
 the storage area must be kept secure to
prevent vandalism or contamination of the
coated surfaces (by dirt, grease, or other
chemicals)
March, 2015 Exhibit 22
SPS Floors - Erection Sequence
1. Erect initial frame 2. Install pre-assembled floor units 3. Install infill floor panels
4. Erect next floor 5. Complete and hand-over floor 6. Clad and fit-out
March, 2015 Exhibit 23
SPS Floors - Erection Sequence
Benefits
 floor units combine plates with secondary beams
 no lifts required for metal decking, rebar or
concrete
 erected by primary steelwork contractor
 no specialist training or equipment required
 typically bolted to beams
 no on-site welding required - however is possible
 safer process with more consistent quality than
cast-in-place concrete floors
March, 2015 Exhibit 24
Method Statements
Objectives
 to ensure that SPS panels and their
associate components are handled
and installed appropriately such that:
- a safe construction site is
maintained
- damage to panels and coatings is
avoided
- the risk of errors is reduced
Method Statements
 Shipping and Site Storage
 Lifting Procedure
 Installation Procedure
 Installation of Mastic Compound
 On-Site Welding
 Cold Cutting Penetrations
March, 2015 Exhibit 25
SPS Floor Details - Plate to Beam Connections
tolerance gap 10-20mm
bolted connections from underside
bolted connections from topside
500mm (19.7’’)
March, 2015 Exhibit 26
SPS Floor Details - Plate Edge
channel section
SPS platesSPS plates
edge beam
March, 2015 Exhibit 27
SPS Floor Details - Plate Edge
SPS plates
edge beam
SPS plates
edge beam
SPS plates
edge beam
SPS plates
edge beam
March, 2015 Exhibit 28
SPS Floor Details - Column Penetrations
March, 2015 Exhibit 29
SPS Floor Details - Roof Connections
March, 2015 Exhibit 30
SPS Floor Details - Penetrations
pipe penetration
pipe penetrationpenetration with collar
March, 2015 Exhibit 31
SPS Floor Details - Penetrations
max opening size without reinforcement
PVC Pipe Penetrations drain penetration
800mm (31.5’’)
opening for sink
400mm (15.7’’)
400mm
(15.7’’)
March, 2015 Exhibit 32
SPS Floor Details - Commercially Available Hangers
hangers for HVAC ducts
hangers for cable traysself tapping threaded rod hangers
March, 2015 Exhibit 33
SPS Floor Details - Commercially Available Hangers
hangers for suspended ceilings
hangers for HVAC ductshangers for cable trays
Hangers for HVAC ducts
March, 2015 Exhibit 34
SPS Floor Details - Passive Fire Protection
fibreboard intumescent fire stop sleeve
March, 2015 Exhibit 35
SPS Floor Details - Passive Fire Protection
cementitious spray
fibreboard intumescent fire stop sleeve
fibreboard
March, 2015 Exhibit 36
SPS Floor Details – Façade Connections
SPS floorcurtain wall
SPS floor
curtain wall cementitious fire stop
March, 2015 Exhibit 37
SPS Shear Cores and Stairwells
 integrated openings, frame and floor connection
details
 thin walled system creates more rentable floor space
 delivered to site in single storey lifts
 all bolted construction
 integrated stairs and landings which allow immediate
man access
 simple design procedures (tools available)
SPS Floor
SPS Shear Core
SPS Shear Core/Wall Design Tool
SPS Floor Design Tool
March, 2015 Exhibit 38
SPS Floor Details - SPS Shear Core Connections
stairwell ceiling connectionshear plate connection
beam connection to core column connection to core
March, 2015 Exhibit 39
In-Plane Shear Tests
 tests conducted at the ATLSS Engineering
Research Centre (Lehigh University,
Bethlehem, PA)
 test characterizes behaviour of SPS plates
acting as floor or roof diaphragms and shear
cores in building structures
 strength test to determine the shear
stiffness and ultimate limit state
 cyclic load test to determine the energy
dissipation capacity of SPS plates
subjected to earthquake loads
Hydraulic Actuator
Loading Beam
Out of Plane Bracing
SPS 4-25-4 (4 m x 2 m)
Test Frame
Distributing Beam
Outrigger
Frame
March, 2015 Exhibit 40
In-Plane Shear Tests
frame installationframe fit-up
SPS installation installed test specimen
March, 2015 Exhibit 41
Project Portfolio
Project IE Client Eng. Area, m2 (ft2) Description Complete
Daytona Hospitality Suite Walkway
Florida, USA
Daytona International
Speedway, LLC
Walter P
Moore
1,608 (17,308) structural floor
October
2014
SPS Popout Panels
Oregon, USA
Hoffman Construction
via Hoffman
Construction
9,146 (98,447) panels for factory floor
September
2013
Birmingham New Street Car Park
Birmingham, UK
Watson Steel Atkins 362 (3,897) refurbishment; structural floor
March
2013
Custody Cells
London, UK
Wates
Anderson
Green
6,148 (66,177) walls and floors
November
2012
ICE Building
Alberta, CA
Supreme Group Dialog 782 (8,417) structural floor
August
2012
Retail Store (Mock Up)
California, USA
Foster & Partners Schuff Steel 298 (3,208) structural floor
June
2012
Academic Campus (Mock Up)
California, USA
Foster & Partners Schuff Steel 170 (1,830) structural floor
June
2012
Bankside Gym
London, UK
Watson Steel Atkins 138 (1,485) structural roof
April
2012
Storium Floating Museum
Okpo, Korea
DSME DSME 3,347 (36,027) structural floor
October
2011
Metropolitan Police Custody Centre
Croydon, UK
Wates via Wates 5,285 (56,887) walls and floor
May
2011
Gatwick Airport
London, UK
Fisher WSP Group 277 (2,982) refurbishment; structural floor
April
2011
Carnegie Hall
New York, USA
Metropolitan Walters
Robert Silman
Associates
1,586 (17,072)
refurbishment; addition of
mezzanine floor
March
2011
Weston-Super-Mare Pier
Bristol, UK
John Sisk &Sons
via John Sisk
&Sons
4,000 (43,056)
refurbishment; external structural
floor (pier)
November
2009
Manchester Airport T2
Manchester, UK
British Airport
Authority
WSP Group 349 (3,757) mezzanine floor and walkway
May
2008
March, 2015 Exhibit 42
ICE Building at University of Alberta
Innovation Centre for Engineering
 new building for University of Alberta
 infill SPS Floor plates installed above
mechanical room provided usable office
space
Technical Details (SPS 4-30-4)
Area 782m² (8417ft2)
Date August 2012
Location Edmonton, Canada
Owner University of Alberta
Architect Dialog
Engineer Dialog
Contractor EllisDon
Steel Erector Supreme Steel
Benefits
 prefabricated plates included penetrations
for services
 simple and efficient installation in space
with limited access
 thinner panels gave more headroom
March, 2015 Exhibit 43
ICE Building at University of Alberta
March, 2015 Exhibit 44
ICE Building at University of Alberta
March, 2015 Exhibit 45
Apple Store (Mock-Up)
Retail Store Mock-Up
 temporary structure constructed for
testing
 tested for floor vibrations and interaction
of structure with architectural finishes
 good correlation between measured and
predicted dynamic behaviour
Technical Details (SPS 6-50B-6, SPS 4-30-4)
Area 298m² (3208ft2)
Date June 2012
Location California, USA
Architect Foster + Partners
Engineer Foster + Partners
Contractor DPR Construction
Steel Erector Schuff Steel Co.
Benefits
 reduced depth and weight compared to
profiled metal decking and 110mm
(4.33’’) in-situ concrete slab alternative
(50mm/2’’ thicker and 40% heavier)
 erection speed - placed and bolted SPS
Floor plates in only 3.5 hours
 super flat floor
 subsequent trades complete fit-out
immediately after floor installation
March, 2015 Exhibit 46
Apple Store (Mock-Up)
March, 2015 Exhibit 47
Apple Store (Mock-Up)
March, 2015 Exhibit 48
Carnegie Hall
One of the World’s Greatest Concert Halls
 119 year old heritage; New York landmark
 underwent major refurbishment in very
constrained location
 SPS Floors were used as new floors within
existing structure frame
Benefits
 shallow depth maximised interior space
 light weight minimised load on existing structure
 ease of erection
 no wet concrete work above auditorium
 avoided need for crane as panels light enough
to use site access lift
 provided early protection deck for ongoing
refurbishment work
Technical Details (SPS 3-20-3)
Area 1,586m² (17,072ft2)
Date March 2011
Location New York, USA
Architect Iu + Bibliowicz
Engineer Robert Silman Assoc
Contractor Tishman Construction
Steel Erector Metropolitan Walters
March, 2015 Exhibit 49
Carnegie Hall
March, 2015 Exhibit 50
Carnegie Hall
March, 2015 Exhibit 51
Daytona Hospitality Suite Walkway
Daytona International Speedway
 the home of the Daytona 500, the most important
and prestigious race on the NASCAR calendar
 SPS floors were used for the renovation and
reconstruction of the Daytona speedway stadium
Benefits
 installed while the facility was still in use
 minimised load on the existing support structure
 enhanced spectator experience by providing
improved access to the Grand Stand and
Hospitality Suites
 25% shorter programme
 no wet work
Technical Details (SPS 4-20-4)
Area 1,608m² (17,308ft2)
Date October 2014
Location Florida, USA
Architect Rossetti
Engineer Walter P Moore
Contractor Barton Malow
Steel Erector Steel Fab
March, 2015 Exhibit 52
Daytona International Speedway
March, 2015 Exhibit 53
Daytona International Speedway
March, 2015 Exhibit 54
The Grand Pier (Weston-Super-Mare)
The Grand Pier
 main building gutted by fire in 2008
 rebuilt on the existing 105 year old structure
 located 400m (1,312’) out in the Bristol Channel
with demanding environmental conditions
 SPS Floors being used as main structural floor
Benefits
 light weight floor plates
 erection deck with immediate load capacity
 risk of weather delays being eliminated
 60 year design-life
Technical Details (SPS 5-50B-5)
Area 4,000m² (43,056ft2)
Date November 2009
Location Weston-super-Mare, UK
Owner Grand Pier Company
Architect Angus Meek
Engineer Fairhurst
Contractor John Sisk & Son
March, 2015 Exhibit 55
The Grand Pier (Weston-Super-Mare)
March, 2015 Exhibit 56
The Grand Pier (Weston-Super-Mare)
March, 2015 Exhibit 57
Metropolitan Police Custody Centres
SPS Modular Construction
 new-build programme of custody centres in
boroughs across London (Croydon, Brixton,
Kingston, Walworth and Woodgreen)
 rapid completion of overall structures
 holding cell unit consisted of SPS plates bolted
together to form walls and ceiling
Benefits
 lightweight and modular construction
 for ongoing custody cells, assembly of cells
completed at manufacturing plant
 connections, penetrations and coatings
incorporated during fabrication
 dramatic reduction in on-site construction time
 clean construction site with improved safety for
the workers
 no columns or beams
Technical Details (SPS 3-20-3, SPS 4-20-4)
Area 11,433m² (123,064ft2)
Date August, 2012
Location London, UK
Owner London Met Police
Architect Raymond Smith Partnership
Engineer Anderson Green
Contractor Wates
March, 2015 Exhibit 58
SPS Cells - Metropolitan Police Custody Centres
March, 2015 Exhibit 59
SPS Cells - Metropolitan Police Custody Centres
March, 2015 Exhibit 60
SPS Cells - Metropolitan Police Custody Centres
March, 2015 Exhibit 61
Bankside Health Club – SPS Roof
Gym Refurbishment
 located in one of London’s most vibrant cultural
destinations
 renovated to expand its studio offering
 SPS Panels were used for the roof deck
Benefits
 full structural capacity working platform once
installed
 installed by steel contractor using standard
techniques and cranes
 25% reduction in the supporting structure
 super thin and flat roof
 lightweight lifting equipment (spider crane)
 no formwork, shoring or cambering of beams
Technical Details (SPS 5-25-5)
Area 138m² (1,485ft2)
Date April, 2012
Location London, UK
Owner Native Land
Architect Rogers Strik Harbour + Partners
Engineer Waterman Group
Contractor Carillon
March, 2015 Exhibit 62
Bankside Health Club – SPS Roof
SPS
Concrete
March, 2015
SPS Roofs – Bankside Health Club
Exhibit 63
March, 2015 Exhibit 64
DSME Storium
Floating Museum
 converted from MV “Bow Hunter”, one of the first
vessels built by DSME in Korea
 exhibit spaces being created throughout the
vessel’s cargo storage tank via insertion of two
floors constructed of SPS panels
 a total of 480 panels, typically 5m (16’) in length
and ranging from 1.5m (5’) to 1.8m (6’) in width
being used
Benefits
 high performance control of noise and vibration
 fast installation in confined working area
 25% overall structure weight savings
 erection platform for upper level
 lightweight lifting equipment
Technical Details (SPS 4.5-20-4.5, SPS 5-20-5)
Area 3,347m² (36,027ft2)
Date October, 2011
Location Okpo, Korea
Owner DSME
Architect DSME
Engineer DSME
Contractor DSME
March, 2015 Exhibit 65
DSME Storium
March, 2015 Exhibit 66
DSME Storium
March, 2015 Exhibit 67
Intel Manufacturing Plant
Popout Panels for Chip Manufacturer
 designed and installed as cover plates for
access ports located on an extremely low
vibration waffle floor system
 pre-production testing of fabrication and injection
process for SPS panels completed prior to full
production
 produced target SPS panel quantities on a full-
scale production/assembly line
Benefits
 a lightweight alternative to concrete slab (the
largest panel weighing approximately
12.8kg/28.2lbs)
 simple to install or remove as required using
commercially available suction cups with
handles.
 high performance floor system (noise and
vibration resistant)
Technical Details (SPS 2-28-3)
Area 9,146m² (98,447ft2)
Date September 2013
Location Oregon, USA
Owner Intel
Architect via Hoffmann Construction
Engineer via Hoffmann Construction
Contractor Hoffmann Construction
March, 2015 Exhibit 68
Intel Manufacturing Plant
Mobilize Frames for Installation
March, 2015 Exhibit 69
Gatwick Airport
Second Busiest Airport in the UK
 extending retail space over baggage hall
 pedestrian link bridge required to span across
baggage hall with no columns
- suspended from above
- weight critical
- but must feel like concrete
Benefits
 allow supporting columns to be eliminated to
reduce obstructions in the baggage handling
area below
 installed by the same crew that installs the
supporting steel framing
 floors installed with forklift
 fast installation (“Could have placed over 75 of
these panels a day”)
Technical Details (SPS 4-20-4)
Area 277m² (2,982ft2)
Date April 2011
Location London, UK
Owner Gatwick Airport Limited
Architect Capita Symonds
Engineer WSP Group
Contractor Costain
March, 2015 Exhibit 70
Gatwick Airport
March, 2015 Exhibit 71
Manchester Airport T2
Third Busiest Airport in the UK
 SPS panels used for the mezzanine floor and
walkway to improve security facilities
 construction was carried out above the check-in
area while the terminal was fully operational
Benefits
 minimal disruption to the airport’s business
 simplified lifting operations in restricted and
public space
 fast installation of prefabricated panels
 clean, safe working practices
 full structural capacity once installed
Technical Details (SPS 3-20-3)
Area 349m² (3,757ft2)
Date May 2008
Location Manchester, UK
Owner Manchester Airports Group
Architect Pascall + Watson Architects
Engineer WSP Group
March, 2015 Exhibit 72
Manchester Airport T2
March, 2015
Category SPS Floors Concrete Floors
Price-performance  reduced weight for the floor and supporting frame
 reduced schedule
 thinner flooring system provides possibility of extra
floors within same building height
 Increased rentable area (smaller columns, thinner
core walls)
 crane capacity requirements reduced
 heavier floors heavier supporting structure
 extra costs associated with wet work (levelling with screed,
more trades, construction waste, curing time, props)
Schedule  25% reduction in superstructure programme
 earlier rental
 prefabricated; onsite assembly
 fewer construction operations
 no-curing and immediate structural capacity
 built-in lifting, leading edge and facade connections
 extended schedule associated with wet work (levelling with
screed, more trades, construction waste, curing time, props,
onsite construction)
Thickness  25-60mm (1’’-2.4’’)
 creates more rentable floor space
 150-250mm (6’’-10’’)
Weight  90-120kg/m2 (18-25 psf)  360-600kg/m2 (74-123 psf)
Diaphragm Capacity  transfer diaphragm forces to the lateral load resisting
system via bolt connecting the edges of panels to
top flanges of supporting beams
 continuity reinforcement is required to ensure the continuity
of the shear transfer across joints
Exhibit 73
Comparison between SPS and Concrete Floors
Concrete FloorSPS Floor
March, 2015
Category SPS Floors Concrete Floors
Acoustics  satisfies all standard acoustic insulation
requirements for airborne, impact and flanking noise
with conventional floor and ceiling finishes
 at least 150mm thickness to provide sufficient airborne
sound insulation
Dynamic Performance  the strength and stiffness of SPS panels and
supporting beams are tailored to meet the dynamic
criteria
 60%-75% lighter than concrete for the same
dynamic performance
 relies on large mass to satisfy dynamic criteria
Tolerances  ±3mm (±0.1’’) for length and width
 ±1mm (±0.04’’) for panel fastener position
 ±10mm (±0.4’’) for rebar location
 -6mm (-0.24’’) to +12mm (0.5’’) for thickness
Flatness  ±3mm (0.1’’) over 3m (10’)  generally ±5mm (0.2’’) over 3m (10’)
 usually requires leveling screed
Surface Protection  typically only a zinc-rich primer is required  water sealing and anti-stain coating required for exposed
concrete (extra cost)
Penetrations and Openings  included factory made laser cut holes reduces onsite
installation costs
 holes generally drilled on site by subcontractor
 opening locations are limited and generally require
reinforcement
Exhibit 74
Comparison between SPS and Concrete Floors
Concrete FloorSPS Floor
March, 2015
Category SPS Floors Concrete Floors
MEP Attachments  standard industry hangers and fasteners
 service location can be premarked in factory
 reinforcement may dictate location; dust
PFP  up to 120/120/120 minutes using conventional fire
protection (fibreboard, cementitious spray,
intumescent coatings, sprinklers)
 untreated SPS achieves 30 minutes resistance with
a 20mm (0.8’’) core and 60 minutes for 25mm (1’’)
 at least 120mm (4.7’’) thickness to achieve 120 minutes fire
resistance
Floor Finishes  all conventional floor finishes have been tested on
SPS floors and are easily installed
 high panel stiffness limits risk of cracking of finishes
in service
 extra cost for surface preparation, i.e. filling the cracks
 extra weight, construction time for levelling surface with
screed
Shipping  less weight
 less space
 stackable
-
Construction Operations  Immediate working platform for subsequent
construction activities once installed
 Weather independent
 single trade; no construction waste; no dust
 safer; less construction clutter
 no wet work
 concrete must cure prior to use as working platform
 special care shall be taken in cold weather
 construction and demolition waste need to be disposed
Exhibit 75
Comparison between SPS and Concrete Floors
Concrete FloorSPS Floor
March, 2015

More Related Content

What's hot

structural system.pdf
structural system.pdfstructural system.pdf
structural system.pdfJaySu14
 
Note on tunnel form construction
Note on tunnel form constructionNote on tunnel form construction
Note on tunnel form constructionRohanBuildersIndia
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesHussein Zidan
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architectsDeepak KUMAR
 
Advance structure system Notes 2
Advance structure system Notes 2Advance structure system Notes 2
Advance structure system Notes 2Aaqib Iqbal
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge pptSAI KIRAN
 
Multi storey frames
Multi storey framesMulti storey frames
Multi storey framesLALITH KUMAR
 
Portal frames final
Portal frames finalPortal frames final
Portal frames finalWen Crystal
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)mbrsalman
 

What's hot (20)

structural system.pdf
structural system.pdfstructural system.pdf
structural system.pdf
 
Tensile structures
Tensile structures Tensile structures
Tensile structures
 
Note on tunnel form construction
Note on tunnel form constructionNote on tunnel form construction
Note on tunnel form construction
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed Bridges
 
Form Active system
Form Active systemForm Active system
Form Active system
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Tensile structures
Tensile structuresTensile structures
Tensile structures
 
Design of steel structural elements
Design of steel structural elementsDesign of steel structural elements
Design of steel structural elements
 
Roof truss
Roof trussRoof truss
Roof truss
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architects
 
Advance structure system Notes 2
Advance structure system Notes 2Advance structure system Notes 2
Advance structure system Notes 2
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge ppt
 
Steel roof trusses
Steel roof trussesSteel roof trusses
Steel roof trusses
 
Design of arch bridges
Design of arch bridgesDesign of arch bridges
Design of arch bridges
 
Multi storey frames
Multi storey framesMulti storey frames
Multi storey frames
 
Portal frames final
Portal frames finalPortal frames final
Portal frames final
 
The shell structure system
The shell structure systemThe shell structure system
The shell structure system
 
flat Slab
flat Slabflat Slab
flat Slab
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
 
shear wall
shear wallshear wall
shear wall
 

Viewers also liked

INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTIONINNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTIONСергей Власкин
 
Verbus System Design Manual
Verbus System Design ManualVerbus System Design Manual
Verbus System Design ManualHugh Miller
 
STRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEETSTRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEETIjripublishers Ijri
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Darshiini Vig
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Chow Hong Da
 
Interior Design Btech Year Portfolio
Interior Design Btech Year PortfolioInterior Design Btech Year Portfolio
Interior Design Btech Year PortfolioTenikao
 
Materials used in ship building
Materials used in ship building  Materials used in ship building
Materials used in ship building Ayuob Yahay
 

Viewers also liked (7)

INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTIONINNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
 
Verbus System Design Manual
Verbus System Design ManualVerbus System Design Manual
Verbus System Design Manual
 
STRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEETSTRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEET
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
Interior Design Btech Year Portfolio
Interior Design Btech Year PortfolioInterior Design Btech Year Portfolio
Interior Design Btech Year Portfolio
 
Materials used in ship building
Materials used in ship building  Materials used in ship building
Materials used in ship building
 

Similar to 2015 03 23 SPS Floors - Generic Presentation

IRJET- Sandwich Plate System in Bridge Deck – A Review
IRJET-  	  Sandwich Plate System in Bridge Deck – A ReviewIRJET-  	  Sandwich Plate System in Bridge Deck – A Review
IRJET- Sandwich Plate System in Bridge Deck – A ReviewIRJET Journal
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfad_gordon
 
Greenflex presentation 0117
Greenflex presentation 0117Greenflex presentation 0117
Greenflex presentation 0117Giulio Zanelli
 
Longitudinally profiled plates
Longitudinally profiled platesLongitudinally profiled plates
Longitudinally profiled platesRandhir venugopal
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
A comprehensive approach to tank design and tank equipment selection
A comprehensive approach to tank design and tank equipment selectionA comprehensive approach to tank design and tank equipment selection
A comprehensive approach to tank design and tank equipment selectionMohieddin Hadidi
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsAMSYSCO Inc.
 
Steel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementSteel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementBekaert
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabsFOYSOLMAHMUD1
 
Imetco Overview For Linked In
Imetco Overview For Linked InImetco Overview For Linked In
Imetco Overview For Linked InAmy Stokes
 
Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...
Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...
Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...Airex Manufacturing Inc
 
Jungčių sitemos CLT konstrukcijoms
Jungčių sitemos CLT konstrukcijomsJungčių sitemos CLT konstrukcijoms
Jungčių sitemos CLT konstrukcijomsPaulius Milcius
 
ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...
ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...
ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...jbors
 

Similar to 2015 03 23 SPS Floors - Generic Presentation (20)

Car park 01
Car park 01Car park 01
Car park 01
 
IRJET- Sandwich Plate System in Bridge Deck – A Review
IRJET-  	  Sandwich Plate System in Bridge Deck – A ReviewIRJET-  	  Sandwich Plate System in Bridge Deck – A Review
IRJET- Sandwich Plate System in Bridge Deck – A Review
 
Product Catalogue
Product CatalogueProduct Catalogue
Product Catalogue
 
EC3 design
EC3 designEC3 design
EC3 design
 
Groundworks and Civil Engineering Products
Groundworks and Civil Engineering ProductsGroundworks and Civil Engineering Products
Groundworks and Civil Engineering Products
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdf
 
Greenflex presentation 0117
Greenflex presentation 0117Greenflex presentation 0117
Greenflex presentation 0117
 
Longitudinally profiled plates
Longitudinally profiled platesLongitudinally profiled plates
Longitudinally profiled plates
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
A comprehensive approach to tank design and tank equipment selection
A comprehensive approach to tank design and tank equipment selectionA comprehensive approach to tank design and tank equipment selection
A comprehensive approach to tank design and tank equipment selection
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
Steel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementSteel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcement
 
K2 flat roof mounting systems
K2 flat roof mounting systems K2 flat roof mounting systems
K2 flat roof mounting systems
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabs
 
Imetco Overview For Linked In
Imetco Overview For Linked InImetco Overview For Linked In
Imetco Overview For Linked In
 
Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...
Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...
Titan Out Engineering Solution of Wall Sealing Refrigerant Line Penetrations ...
 
Titan Outlet Airex Manufacturing Inc
Titan Outlet  Airex Manufacturing IncTitan Outlet  Airex Manufacturing Inc
Titan Outlet Airex Manufacturing Inc
 
Jungčių sitemos CLT konstrukcijoms
Jungčių sitemos CLT konstrukcijomsJungčių sitemos CLT konstrukcijoms
Jungčių sitemos CLT konstrukcijoms
 
ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...
ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...
ChemCo Systems InsulPOX™ Cryogenic Insulating Polymer Concrete (IPC) Overlay ...
 
Catlogue
CatlogueCatlogue
Catlogue
 

2015 03 23 SPS Floors - Generic Presentation

  • 1. March, 2015 SPS Building Products; Floors and Shear Cores
  • 2. March, 2015 The Sandwich Plate System - SPS Exhibit 2 Structural Composite • construction alternative to reinforced concrete and stiffened steel in construction, civil engineering and maritime structures Key Benefits for Construction • lightweight • shorter erection schedule • maximizes offsite construction • minimizes logistics and risks • easy to demount and reuse History • developed in 1993 • over 387 projects and 300,000m2 (3,230,000ft2) in service in 30 countries • used in ships, bridges, stadium and buildings • approved by major global regulators SPS structure Conventional stiffened steel structure Conventional concrete- steel composite structure
  • 3. March, 2015 Exhibit 3 Construction and Civil Engineering SPS Applications SPS FloorsSPS Terraces SPS Bridges SPS Protection  75% lighter than concrete changes structural options  prefabricated and very fast to erect  extended service life  re-usable SPS Overlay Maritime SPS Overlay Bridge Deck • existing steel decks stiffened in-situ • fast process with no structural removal • strengthening of existing deck/shell • minimizes downtime Steel Deck Repair Maritime New Build SPS Hatch Covers  elements of a ship/maritime structure  faster to build and easier to maintain  built-in additional performance  more benefits for military structures SPS Citadel Protection
  • 4. March, 2015 Exhibit 4 Partners, Key Relationships and Customers Joint Venture Partners Key Relationships Key Customers HOFFMAN
  • 5. March, 2015 Exhibit 5 What are SPS Floors? SPS Floors  a composite floor panel made of two steel plates, a polyurethane core and a steel perimeter bar or profile  bolted together to the top flange of the structural steel beams; generally made composite with secondary beams  prefabricated factory quality construction with close dimensional tolerances  proven and approved global technology column beam Rigid, semi-rigid or Simple connections SPS Floor Panel Bolted connection to supporting beams/girders SPS Floor Panel SPS Floor Panel solid core bubble core Core Configuration  Solid Core: thin floor plates with a compact solid polyurethane core between faceplates  Bubble Core: hexagonally closely packed air-filled polypropylene spheres with diameter equal to core thickness (deeper and stiffer core allowing longer spans while remaining lightweight)
  • 6. March, 2015 clean surfacessuper flat Exhibit 6 Benefits of SPS Floors all floor finishes possible standard fasteners / hangers chilled beam and ducting better fit up
  • 7. March, 2015 Exhibit 7 Benefits of SPS Floors immediate structural capacity lightweight lifting equipment thinner floor shorter erection schedule all bolted construction prefabricated
  • 8. March, 2015 Exhibit 8 Benefits of SPS Floors factory quality control close tolerances weather independent diaphragm capacity lateral stability no construction waste
  • 9. March, 2015 Exhibit 9 Engineering Design Statics  SPS Floors designed to satisfy serviceability and ultimate limit states for the governing building codes and standards Dynamics  dynamic response assessed using; - preliminary evaluation using HiVoSS method (Route 1) - guidelines from Steel Construction Institute (Route 2) - probability-based method (Route 3)  meets industry-accepted criteria Acoustics  designed for minimum airborne sound insulation and maximum impact sound insulation specified by local building authority  SPS Floors in combination with the specified floor and ceiling meet the specified criteria Fire  industry-standard fire protection for steel structures can be applied to the underside of SPS Floors to provide the specified fire rating
  • 10. March, 2015 Exhibit 10 Dynamic Design Design Methods  Route 1: preliminary evaluation using HiVoSS method - applied to a typical bay - read OS-RMS90 values according to the calculated frequency, modal mass and damping  Route 2: guidelines from Steel Construction Institute - modal analysis for finite element model is conducted to determine frequency, modal mass and mode shape. - response factor, which is related to the peak acceleration, is calculated  Route 3: probability-based method - walking paths are defined - Monte Carlo Method is used to randomly generate walking frequencies Design Tools  SAP2000, ANSYS  MATLAB based program  Microsoft Excel based program response factor of the floor (limit is 8) finite element model in ANSYS
  • 11. March, 2015 Exhibit 11 Passive Fire Protection General  fire insulation is applied to the underside of SPS plates in accordance with the standards for the desired fire rating  details for fire insulation application available from IE Tests/Certificates Types of PFP systems  cementitious spray  intumescent coatings  sprinklers  fibreboard Certificate Date of Issue Authority Fire rating (minutes) Type of fire insulation Thickness of SPS (mm) ABP 008 2009.11.18 BRE 60 Mineral wool 20 120 Mineral wool 50 BXUV.D305 2009.10.02 UL 120 Mineral wool 50
  • 12. March, 2015 Exhibit 12 Acoustic Design “…The SPS floor system is deemed to be acoustically acceptable as both a loading bearing separating floor construction and an internal load bearing floor construction… also deemed to be acoustically acceptable for non-residential schemes including schools, office spaces, industrial spaces, bars, clubs and other healthcare spaces…” - Sol Acoustics Ltd.  SPS floors with fire protection combined with a wide range of typical ceiling and floor finishes provide a sufficient acoustic insulation for commercial and residential buildings.  Sample calculation using the acoustic design tool for a typical floor buildup for residential floor, given below, demonstrates that it meets UK building regulations; STC ratings given in North American regulations are also met. Floor Construction Airborne sound insulation (dB) Impact sound insulation (dB) Rw Rw + Ctr Lnw Base SPS-B 4-50-4 33 31 94 Residential Fire Insulation 50 mm Paroc FireSlab 150 fire on floor and 25 mm on beams (2 hour fire rating) 11 8 -20 Flooring Carpet tile 0 0 -8 Raised Floor Kingspan RMG600 4 1 -6 Ceiling Armstrong bioguard acoustic board 7 6 -9 Overall Acoustic Performance 55 46 51 Design Limits na ≥ 45 ≤ 62 Acoustic Design Tool for SPS Floor
  • 13. March, 2015 Exhibit 13 Bolts, Fasteners and Attachments Bolts (typical spacing 500mm) Approved Hilti Fasteners and Hangers Double-sided Single-sided tension control bolt hexagonal hollo-bolt hex head bolt countersunk hollo-bolt socket countersunk screw flush fit hollo-bolt socket button head screw hexagonal box bolt Fastener Recommended Pull-out Load Description Type SPS 3-20-3 SPS 4-20-4 SPS 4-50-4BC kN lbs kN lbs Stud X-EM8H, X-EM10H 2.9 657 3.4 772 Nail X-EGN 14MX 0.7 149 0.9 194 Threaded rod hanger X-HS U19 P8S15 1.6 358 3.0 672 Loop hanger X-CC U16 P8 1.4 314 1.5 336 Threaded rod hanger X-HS MX with X-EGN 14 MX - - 0.4 82 Loop hanger X-CC MX with X-EGN 14 MX 0.4 82 0.5 105 Threaded rod hanger X-HS MX with X-U 16 MX 0.8 179 1.0 225 Loop hanger X-CC MX with X-U 16 MX 0.6 142 0.9 202 Note: Tek screws with various diameters and thread types can also be used to their full capacity. Please refer to http://www.evolutionfasteners.co.uk/Products/
  • 14. March, 2015 Exhibit 14 Technical Notes General  have more than 70 technical notes covering different aspects of SPS plates Technical Notes  SPS Polyurethane Disposal  SPS Structural Damping Characteristics  SPS Panel Fabrication  Repairing SPS Panels  SPS Bond Strength for Steel Plates with Surface Rust  Fatigue Resistance at Steel-Elastomer Interface  Fire Resistance of SPS  Surface Preparation for SPS Plates  Protective Coatings for SPS Plates  Recommended Fasteners for SPS Plates  Thermal Transmittance of SPS Plates …
  • 15. March, 2015 Exhibit 15 Technical Summary Typical Service Loads SDL 1.5kPa (0.22psi); LL 4.5kPa (0.65psi) (other loads and combinations readily accommodated) Deflection Typically less than L/600 (for widths and live load listed above) Dynamic Response The stiffness of SPS panels and supporting beams are adjusted to meet needs of a particular building or room (e.g. R-factor 6 is readily achieved for office floors) Point Loads Once bolted in place, SPS Floors are readily able to carry most typical wheel loads from equipment such as Cherry Pickers, Scissor Lifts, Fork Lifts etc. Ultimate Capacity Ultimate capacity of SPS Floor panels is equal to plastic capacity of steel faceplates in bending and exceeds the effects of standard imposed building loads (greater than 7.5kPa/1.09psi). (Note: Ultimate capacity of beams is not covered by this data sheet) Composite Action Achieved through bolts connecting edges of SPS Floor panels to top flanges of supporting beams. Welded connections also possible. Stability SPS Floors panels transfer diaphragm forces to the lateral load resisting system via bolts connecting edges of panels to top flanges of supporting beams. Welded connections also possible. Fire Resistance Up to 120:120:120 minutes using conventional fire protection which is either factory or field applied. When shorter periods are required the thickness of the protection is reduced accordingly. (Note: an untreated SPS panel achieves an inherent 30 minute resistance with a 20mm (0.8’’) core thickness, and 60 minutes for 25mm (1’’) cores) Acoustics Finished floors incorporating SPS Floor panels meet standard acoustic insulation requirements for airborne, impact and flanking noise for all conventional building types. For instance: SPS Floor design for hotels and offices provides: 49dB of airborne sound insulation; and 46dB of impact sound absorption provided standard hotel finishes are applied. Flatness Tolerance ±3 mm (0.1’’) over 3m (10’)
  • 16. March, 2015 Exhibit 16 SPS Floors - Approvals / Certification BRE Global Certification   Fabrication & Erection  Static Performance  Dynamic Performance  Lateral Load Resistance  Fire Resistance  Acoustic Performance  M&E Installation  Fit-out New York & UL Approvals 
  • 17. March, 2015 Exhibit 17 Fabrication  parametric CAD modules  dedicated production line  automated production  CNC driven manufacturing  fast efficient fabrication  excellent dimensional tolerances  adaptable geometry  climatic control conditions  maximum integration of details
  • 18. March, 2015 Exhibit 18 Fabrication Tolerances Description Range Tolerance L SPS plate length (max) 5000mm to 9000mm (16.4’ to 30’) ±3mm (±0.1’’) W SPS plate width (max) 1000mm to 3000mm (3.3’ to 10’) ±3mm (±0.1’’) - interior flatness (measured in a 3m straight edge) Plate width < 1000mm (3.3’) Plate width > 1000mm (3.3’) ±2mm (±0.08’’) ±3mm (±0.1’’) - edge flatness (measured in a 3m straight edge) - ±3mm (±0.1’’) Δ unrestrained twist - ±5mm (±0.2’’) Fabrication and Assembly Tolerances Bolting Tolerances  Bolt hole size -bolt hole size shall be 2 mm larger than the bolt hole diameter  Bolt hole position -the deviation from the intended position shall not exceed ±1mm
  • 19. March, 2015 Exhibit 19 Quality Assurance Processes General  to ensure that the quality of all material or products and associated production is verified and comply with the contractual requirements, codes and standards.  Quality Assurance Program compatible with ISO 9001  certified by BRE to international and national standards  health and safety - safe working procedures are prescribed - SPS panel production process is a non-hazardous activity - environmental documentation and procedures relating to the injection process available from IE
  • 20. March, 2015 Exhibit 20 Quality Assurance Processes PU Elastomer Quality  elastomer supplied as two separate components (polyol, isocyanate)  characteristics guaranteed by BASF Elastogran Bond Quality  steel plate surfaces must be free of rust, dust, grease, oils and other soluble materials  PosiTest used to measure bond strengths; compared with specified values Steel Quality  the fabricator is responsible for purchasing the steel according to the specifications as indicated on the fabrication drawings or material lists  no steel material to be used until the certificates of compliance have been received and reviewed. Injection Quality  injection must be overseen by a qualified injection engineer, who has received adequate training and has been accredited by IE  the calibration of the injection machine is checked at the start of each project
  • 21. March, 2015 Exhibit 21 SPS Floors - Shipping and Site Storage Summary  delivered on a flat-bed transport vehicle or 12.19m (40’) open top containers  delivery vehicle shall be placed close to the bay in which the SPS panels will be installed to minimize the movement of the load  shipping load sequence and container contents are specified in method statements  special care shall be taken to ensure that the units are handled in accordance with the method statement on lifting  for storage of the SPS units, select a flat unobstructed area in a location that is not susceptible to damage from other construction activities  the storage area must be kept secure to prevent vandalism or contamination of the coated surfaces (by dirt, grease, or other chemicals)
  • 22. March, 2015 Exhibit 22 SPS Floors - Erection Sequence 1. Erect initial frame 2. Install pre-assembled floor units 3. Install infill floor panels 4. Erect next floor 5. Complete and hand-over floor 6. Clad and fit-out
  • 23. March, 2015 Exhibit 23 SPS Floors - Erection Sequence Benefits  floor units combine plates with secondary beams  no lifts required for metal decking, rebar or concrete  erected by primary steelwork contractor  no specialist training or equipment required  typically bolted to beams  no on-site welding required - however is possible  safer process with more consistent quality than cast-in-place concrete floors
  • 24. March, 2015 Exhibit 24 Method Statements Objectives  to ensure that SPS panels and their associate components are handled and installed appropriately such that: - a safe construction site is maintained - damage to panels and coatings is avoided - the risk of errors is reduced Method Statements  Shipping and Site Storage  Lifting Procedure  Installation Procedure  Installation of Mastic Compound  On-Site Welding  Cold Cutting Penetrations
  • 25. March, 2015 Exhibit 25 SPS Floor Details - Plate to Beam Connections tolerance gap 10-20mm bolted connections from underside bolted connections from topside 500mm (19.7’’)
  • 26. March, 2015 Exhibit 26 SPS Floor Details - Plate Edge channel section SPS platesSPS plates edge beam
  • 27. March, 2015 Exhibit 27 SPS Floor Details - Plate Edge SPS plates edge beam SPS plates edge beam SPS plates edge beam SPS plates edge beam
  • 28. March, 2015 Exhibit 28 SPS Floor Details - Column Penetrations
  • 29. March, 2015 Exhibit 29 SPS Floor Details - Roof Connections
  • 30. March, 2015 Exhibit 30 SPS Floor Details - Penetrations pipe penetration pipe penetrationpenetration with collar
  • 31. March, 2015 Exhibit 31 SPS Floor Details - Penetrations max opening size without reinforcement PVC Pipe Penetrations drain penetration 800mm (31.5’’) opening for sink 400mm (15.7’’) 400mm (15.7’’)
  • 32. March, 2015 Exhibit 32 SPS Floor Details - Commercially Available Hangers hangers for HVAC ducts hangers for cable traysself tapping threaded rod hangers
  • 33. March, 2015 Exhibit 33 SPS Floor Details - Commercially Available Hangers hangers for suspended ceilings hangers for HVAC ductshangers for cable trays Hangers for HVAC ducts
  • 34. March, 2015 Exhibit 34 SPS Floor Details - Passive Fire Protection fibreboard intumescent fire stop sleeve
  • 35. March, 2015 Exhibit 35 SPS Floor Details - Passive Fire Protection cementitious spray fibreboard intumescent fire stop sleeve fibreboard
  • 36. March, 2015 Exhibit 36 SPS Floor Details – Façade Connections SPS floorcurtain wall SPS floor curtain wall cementitious fire stop
  • 37. March, 2015 Exhibit 37 SPS Shear Cores and Stairwells  integrated openings, frame and floor connection details  thin walled system creates more rentable floor space  delivered to site in single storey lifts  all bolted construction  integrated stairs and landings which allow immediate man access  simple design procedures (tools available) SPS Floor SPS Shear Core SPS Shear Core/Wall Design Tool SPS Floor Design Tool
  • 38. March, 2015 Exhibit 38 SPS Floor Details - SPS Shear Core Connections stairwell ceiling connectionshear plate connection beam connection to core column connection to core
  • 39. March, 2015 Exhibit 39 In-Plane Shear Tests  tests conducted at the ATLSS Engineering Research Centre (Lehigh University, Bethlehem, PA)  test characterizes behaviour of SPS plates acting as floor or roof diaphragms and shear cores in building structures  strength test to determine the shear stiffness and ultimate limit state  cyclic load test to determine the energy dissipation capacity of SPS plates subjected to earthquake loads Hydraulic Actuator Loading Beam Out of Plane Bracing SPS 4-25-4 (4 m x 2 m) Test Frame Distributing Beam Outrigger Frame
  • 40. March, 2015 Exhibit 40 In-Plane Shear Tests frame installationframe fit-up SPS installation installed test specimen
  • 41. March, 2015 Exhibit 41 Project Portfolio Project IE Client Eng. Area, m2 (ft2) Description Complete Daytona Hospitality Suite Walkway Florida, USA Daytona International Speedway, LLC Walter P Moore 1,608 (17,308) structural floor October 2014 SPS Popout Panels Oregon, USA Hoffman Construction via Hoffman Construction 9,146 (98,447) panels for factory floor September 2013 Birmingham New Street Car Park Birmingham, UK Watson Steel Atkins 362 (3,897) refurbishment; structural floor March 2013 Custody Cells London, UK Wates Anderson Green 6,148 (66,177) walls and floors November 2012 ICE Building Alberta, CA Supreme Group Dialog 782 (8,417) structural floor August 2012 Retail Store (Mock Up) California, USA Foster & Partners Schuff Steel 298 (3,208) structural floor June 2012 Academic Campus (Mock Up) California, USA Foster & Partners Schuff Steel 170 (1,830) structural floor June 2012 Bankside Gym London, UK Watson Steel Atkins 138 (1,485) structural roof April 2012 Storium Floating Museum Okpo, Korea DSME DSME 3,347 (36,027) structural floor October 2011 Metropolitan Police Custody Centre Croydon, UK Wates via Wates 5,285 (56,887) walls and floor May 2011 Gatwick Airport London, UK Fisher WSP Group 277 (2,982) refurbishment; structural floor April 2011 Carnegie Hall New York, USA Metropolitan Walters Robert Silman Associates 1,586 (17,072) refurbishment; addition of mezzanine floor March 2011 Weston-Super-Mare Pier Bristol, UK John Sisk &Sons via John Sisk &Sons 4,000 (43,056) refurbishment; external structural floor (pier) November 2009 Manchester Airport T2 Manchester, UK British Airport Authority WSP Group 349 (3,757) mezzanine floor and walkway May 2008
  • 42. March, 2015 Exhibit 42 ICE Building at University of Alberta Innovation Centre for Engineering  new building for University of Alberta  infill SPS Floor plates installed above mechanical room provided usable office space Technical Details (SPS 4-30-4) Area 782m² (8417ft2) Date August 2012 Location Edmonton, Canada Owner University of Alberta Architect Dialog Engineer Dialog Contractor EllisDon Steel Erector Supreme Steel Benefits  prefabricated plates included penetrations for services  simple and efficient installation in space with limited access  thinner panels gave more headroom
  • 43. March, 2015 Exhibit 43 ICE Building at University of Alberta
  • 44. March, 2015 Exhibit 44 ICE Building at University of Alberta
  • 45. March, 2015 Exhibit 45 Apple Store (Mock-Up) Retail Store Mock-Up  temporary structure constructed for testing  tested for floor vibrations and interaction of structure with architectural finishes  good correlation between measured and predicted dynamic behaviour Technical Details (SPS 6-50B-6, SPS 4-30-4) Area 298m² (3208ft2) Date June 2012 Location California, USA Architect Foster + Partners Engineer Foster + Partners Contractor DPR Construction Steel Erector Schuff Steel Co. Benefits  reduced depth and weight compared to profiled metal decking and 110mm (4.33’’) in-situ concrete slab alternative (50mm/2’’ thicker and 40% heavier)  erection speed - placed and bolted SPS Floor plates in only 3.5 hours  super flat floor  subsequent trades complete fit-out immediately after floor installation
  • 46. March, 2015 Exhibit 46 Apple Store (Mock-Up)
  • 47. March, 2015 Exhibit 47 Apple Store (Mock-Up)
  • 48. March, 2015 Exhibit 48 Carnegie Hall One of the World’s Greatest Concert Halls  119 year old heritage; New York landmark  underwent major refurbishment in very constrained location  SPS Floors were used as new floors within existing structure frame Benefits  shallow depth maximised interior space  light weight minimised load on existing structure  ease of erection  no wet concrete work above auditorium  avoided need for crane as panels light enough to use site access lift  provided early protection deck for ongoing refurbishment work Technical Details (SPS 3-20-3) Area 1,586m² (17,072ft2) Date March 2011 Location New York, USA Architect Iu + Bibliowicz Engineer Robert Silman Assoc Contractor Tishman Construction Steel Erector Metropolitan Walters
  • 49. March, 2015 Exhibit 49 Carnegie Hall
  • 50. March, 2015 Exhibit 50 Carnegie Hall
  • 51. March, 2015 Exhibit 51 Daytona Hospitality Suite Walkway Daytona International Speedway  the home of the Daytona 500, the most important and prestigious race on the NASCAR calendar  SPS floors were used for the renovation and reconstruction of the Daytona speedway stadium Benefits  installed while the facility was still in use  minimised load on the existing support structure  enhanced spectator experience by providing improved access to the Grand Stand and Hospitality Suites  25% shorter programme  no wet work Technical Details (SPS 4-20-4) Area 1,608m² (17,308ft2) Date October 2014 Location Florida, USA Architect Rossetti Engineer Walter P Moore Contractor Barton Malow Steel Erector Steel Fab
  • 52. March, 2015 Exhibit 52 Daytona International Speedway
  • 53. March, 2015 Exhibit 53 Daytona International Speedway
  • 54. March, 2015 Exhibit 54 The Grand Pier (Weston-Super-Mare) The Grand Pier  main building gutted by fire in 2008  rebuilt on the existing 105 year old structure  located 400m (1,312’) out in the Bristol Channel with demanding environmental conditions  SPS Floors being used as main structural floor Benefits  light weight floor plates  erection deck with immediate load capacity  risk of weather delays being eliminated  60 year design-life Technical Details (SPS 5-50B-5) Area 4,000m² (43,056ft2) Date November 2009 Location Weston-super-Mare, UK Owner Grand Pier Company Architect Angus Meek Engineer Fairhurst Contractor John Sisk & Son
  • 55. March, 2015 Exhibit 55 The Grand Pier (Weston-Super-Mare)
  • 56. March, 2015 Exhibit 56 The Grand Pier (Weston-Super-Mare)
  • 57. March, 2015 Exhibit 57 Metropolitan Police Custody Centres SPS Modular Construction  new-build programme of custody centres in boroughs across London (Croydon, Brixton, Kingston, Walworth and Woodgreen)  rapid completion of overall structures  holding cell unit consisted of SPS plates bolted together to form walls and ceiling Benefits  lightweight and modular construction  for ongoing custody cells, assembly of cells completed at manufacturing plant  connections, penetrations and coatings incorporated during fabrication  dramatic reduction in on-site construction time  clean construction site with improved safety for the workers  no columns or beams Technical Details (SPS 3-20-3, SPS 4-20-4) Area 11,433m² (123,064ft2) Date August, 2012 Location London, UK Owner London Met Police Architect Raymond Smith Partnership Engineer Anderson Green Contractor Wates
  • 58. March, 2015 Exhibit 58 SPS Cells - Metropolitan Police Custody Centres
  • 59. March, 2015 Exhibit 59 SPS Cells - Metropolitan Police Custody Centres
  • 60. March, 2015 Exhibit 60 SPS Cells - Metropolitan Police Custody Centres
  • 61. March, 2015 Exhibit 61 Bankside Health Club – SPS Roof Gym Refurbishment  located in one of London’s most vibrant cultural destinations  renovated to expand its studio offering  SPS Panels were used for the roof deck Benefits  full structural capacity working platform once installed  installed by steel contractor using standard techniques and cranes  25% reduction in the supporting structure  super thin and flat roof  lightweight lifting equipment (spider crane)  no formwork, shoring or cambering of beams Technical Details (SPS 5-25-5) Area 138m² (1,485ft2) Date April, 2012 Location London, UK Owner Native Land Architect Rogers Strik Harbour + Partners Engineer Waterman Group Contractor Carillon
  • 62. March, 2015 Exhibit 62 Bankside Health Club – SPS Roof SPS Concrete
  • 63. March, 2015 SPS Roofs – Bankside Health Club Exhibit 63
  • 64. March, 2015 Exhibit 64 DSME Storium Floating Museum  converted from MV “Bow Hunter”, one of the first vessels built by DSME in Korea  exhibit spaces being created throughout the vessel’s cargo storage tank via insertion of two floors constructed of SPS panels  a total of 480 panels, typically 5m (16’) in length and ranging from 1.5m (5’) to 1.8m (6’) in width being used Benefits  high performance control of noise and vibration  fast installation in confined working area  25% overall structure weight savings  erection platform for upper level  lightweight lifting equipment Technical Details (SPS 4.5-20-4.5, SPS 5-20-5) Area 3,347m² (36,027ft2) Date October, 2011 Location Okpo, Korea Owner DSME Architect DSME Engineer DSME Contractor DSME
  • 65. March, 2015 Exhibit 65 DSME Storium
  • 66. March, 2015 Exhibit 66 DSME Storium
  • 67. March, 2015 Exhibit 67 Intel Manufacturing Plant Popout Panels for Chip Manufacturer  designed and installed as cover plates for access ports located on an extremely low vibration waffle floor system  pre-production testing of fabrication and injection process for SPS panels completed prior to full production  produced target SPS panel quantities on a full- scale production/assembly line Benefits  a lightweight alternative to concrete slab (the largest panel weighing approximately 12.8kg/28.2lbs)  simple to install or remove as required using commercially available suction cups with handles.  high performance floor system (noise and vibration resistant) Technical Details (SPS 2-28-3) Area 9,146m² (98,447ft2) Date September 2013 Location Oregon, USA Owner Intel Architect via Hoffmann Construction Engineer via Hoffmann Construction Contractor Hoffmann Construction
  • 68. March, 2015 Exhibit 68 Intel Manufacturing Plant Mobilize Frames for Installation
  • 69. March, 2015 Exhibit 69 Gatwick Airport Second Busiest Airport in the UK  extending retail space over baggage hall  pedestrian link bridge required to span across baggage hall with no columns - suspended from above - weight critical - but must feel like concrete Benefits  allow supporting columns to be eliminated to reduce obstructions in the baggage handling area below  installed by the same crew that installs the supporting steel framing  floors installed with forklift  fast installation (“Could have placed over 75 of these panels a day”) Technical Details (SPS 4-20-4) Area 277m² (2,982ft2) Date April 2011 Location London, UK Owner Gatwick Airport Limited Architect Capita Symonds Engineer WSP Group Contractor Costain
  • 70. March, 2015 Exhibit 70 Gatwick Airport
  • 71. March, 2015 Exhibit 71 Manchester Airport T2 Third Busiest Airport in the UK  SPS panels used for the mezzanine floor and walkway to improve security facilities  construction was carried out above the check-in area while the terminal was fully operational Benefits  minimal disruption to the airport’s business  simplified lifting operations in restricted and public space  fast installation of prefabricated panels  clean, safe working practices  full structural capacity once installed Technical Details (SPS 3-20-3) Area 349m² (3,757ft2) Date May 2008 Location Manchester, UK Owner Manchester Airports Group Architect Pascall + Watson Architects Engineer WSP Group
  • 72. March, 2015 Exhibit 72 Manchester Airport T2
  • 73. March, 2015 Category SPS Floors Concrete Floors Price-performance  reduced weight for the floor and supporting frame  reduced schedule  thinner flooring system provides possibility of extra floors within same building height  Increased rentable area (smaller columns, thinner core walls)  crane capacity requirements reduced  heavier floors heavier supporting structure  extra costs associated with wet work (levelling with screed, more trades, construction waste, curing time, props) Schedule  25% reduction in superstructure programme  earlier rental  prefabricated; onsite assembly  fewer construction operations  no-curing and immediate structural capacity  built-in lifting, leading edge and facade connections  extended schedule associated with wet work (levelling with screed, more trades, construction waste, curing time, props, onsite construction) Thickness  25-60mm (1’’-2.4’’)  creates more rentable floor space  150-250mm (6’’-10’’) Weight  90-120kg/m2 (18-25 psf)  360-600kg/m2 (74-123 psf) Diaphragm Capacity  transfer diaphragm forces to the lateral load resisting system via bolt connecting the edges of panels to top flanges of supporting beams  continuity reinforcement is required to ensure the continuity of the shear transfer across joints Exhibit 73 Comparison between SPS and Concrete Floors Concrete FloorSPS Floor
  • 74. March, 2015 Category SPS Floors Concrete Floors Acoustics  satisfies all standard acoustic insulation requirements for airborne, impact and flanking noise with conventional floor and ceiling finishes  at least 150mm thickness to provide sufficient airborne sound insulation Dynamic Performance  the strength and stiffness of SPS panels and supporting beams are tailored to meet the dynamic criteria  60%-75% lighter than concrete for the same dynamic performance  relies on large mass to satisfy dynamic criteria Tolerances  ±3mm (±0.1’’) for length and width  ±1mm (±0.04’’) for panel fastener position  ±10mm (±0.4’’) for rebar location  -6mm (-0.24’’) to +12mm (0.5’’) for thickness Flatness  ±3mm (0.1’’) over 3m (10’)  generally ±5mm (0.2’’) over 3m (10’)  usually requires leveling screed Surface Protection  typically only a zinc-rich primer is required  water sealing and anti-stain coating required for exposed concrete (extra cost) Penetrations and Openings  included factory made laser cut holes reduces onsite installation costs  holes generally drilled on site by subcontractor  opening locations are limited and generally require reinforcement Exhibit 74 Comparison between SPS and Concrete Floors Concrete FloorSPS Floor
  • 75. March, 2015 Category SPS Floors Concrete Floors MEP Attachments  standard industry hangers and fasteners  service location can be premarked in factory  reinforcement may dictate location; dust PFP  up to 120/120/120 minutes using conventional fire protection (fibreboard, cementitious spray, intumescent coatings, sprinklers)  untreated SPS achieves 30 minutes resistance with a 20mm (0.8’’) core and 60 minutes for 25mm (1’’)  at least 120mm (4.7’’) thickness to achieve 120 minutes fire resistance Floor Finishes  all conventional floor finishes have been tested on SPS floors and are easily installed  high panel stiffness limits risk of cracking of finishes in service  extra cost for surface preparation, i.e. filling the cracks  extra weight, construction time for levelling surface with screed Shipping  less weight  less space  stackable - Construction Operations  Immediate working platform for subsequent construction activities once installed  Weather independent  single trade; no construction waste; no dust  safer; less construction clutter  no wet work  concrete must cure prior to use as working platform  special care shall be taken in cold weather  construction and demolition waste need to be disposed Exhibit 75 Comparison between SPS and Concrete Floors Concrete FloorSPS Floor