3. ANALISA HARGA SATUAN PEKERJAAN
KODE ANALISA
SATUAN
PEKERJAAN
INDEKS SATUAN
HARGA SATUAN
TOTAL HARGA SATUAN PEKERJAAN (HSP)
BAHAN UPAH
II. PEKERJAAN TANAH
6.1
1 m3 Galian Tanah
Biasa Sedalam 1 m
6.1.1 Tenaga
Pekerja
0.400 Oh Rp 42,000.00 Rp 16,800.00
mandor 0.04 Oh
Rp 80,000.00
Rp 3,200.00
total Rp 20,000.00
6.2 1 m3 Galian Tanah Biasa sedalam 2
6.2.1 Tenaga
Pekerja 0.526 Oh Rp 42,000.00 Rp 22,092.00
Mandor 0.052 Oh Rp 80,000.00 Rp 4,160.00
Total Rp 26,252.00
1 m3 Galian Tanah Biasa sedalam 1.5 m Rp 23,126.00
HARGASATUANPEKERJAAN
(HSP)
4. ANALISA HARGA SATUAN PEKERJAAN
KODE
ANALISA
SATUAN
PEKERJAAN
INDEKS SATUAN
HARGA SATUAN
TOTAL HARGA SATUAN PEKERJAAN (HSP)
BAHAN UPAH
II. PEKERJAAN TANAH
6.4 1 m3 Urugan Kembali
6.4.1 Tenaga
Pekerja 0.192 Oh Rp 42,000.00 Rp 8,064.00
mandor 0.019 Oh Rp 80,000.00 Rp 1,520.00
Total Rp 9,584.00
6.5 1 m3 Urugan Pasir
6.5.1 Bahan
Pasir Urug 1.2 m3 Rp 115,000.00 Rp 138,000.00
Sub Total Rp 138,000.00
6.5.2 Tenaga
Pekerja 0.3 Oh Rp 42,000.00 Rp 12,600.00
Mandor 0.01 Oh Rp 80,000.00 Rp 800.00
Sub Total Rp 13,400.00
total Rp 151,400.00
5. ANALISA HARGA SATUAN PEKERJAAN
KODE
ANALISA
SATUAN PEKERJAAN INDEKS SATUAN
HARGA SATUAN
TOTAL HARGA SATUAN PEKERJAAN (HSP)
BAHAN UPAH
III. PEKERJAAN PONDASI
6.6 1 M3 Pasang Pondasi Batu Kali 1 Pc : 5 ps
6.6.1 Bahan
Batu Belah 1.1 m3 Rp 205,500.00 Rp 226,050.00
Semen Portland 136 m3 Rp 1,406.00 Rp 191,216.00
Pasir Pasang 0.544 m3 Rp 233,400.00 Rp 126,969.60
Sub Total Rp 544,235.60
6.6.2 Tenaga
Pekerja 1.5 Oh Rp 42,000.00 Rp 63,000.00
Tukang Batu 0.6 Oh Rp 65,000.00 Rp 39,000.00
Kepala Tukang 0.06 Oh Rp 75,000.00 Rp 4,500.00
Mandor 0.075 Oh Rp 80,000.00 Rp 6,000.00
Sub Total Rp 112,500.00
total Rp 656,735.60
6. ANALISA HARGA SATUAN PEKERJAAN
KODE
ANALISA
SATUAN PEKERJAAN INDEKS SATUAN
HARGA SATUAN
TOTAL HARGA SATUAN PEKERJAAN (HSP)
BAHAN UPAH
6.14 1 m3 Pasang Pondasi Batu Kosong
6.14.1 Bahan
Batu Belah 1.1 m3 Rp 205,500.00 Rp 226,050.00
Pasir Urug 0.3 kg Rp 115,000.00 Rp 34,500.00
Sub Total Rp 260,550.00
6.14.2 Tenaga
Pekerja 0.78 Oh Rp 42,000.00 Rp 32,760.00
Tukang Batu 0.39 Oh Rp 65,000.00 Rp 25,350.00
Kepala Tukang 0.039 Oh Rp 75,000.00 Rp 2,925.00
Mandor 0.039 Oh Rp 80,000.00 Rp 3,120.00
Sub Total Rp 64,155.00
Total 324705
7. 6.39 1 m3 Membuat Sloof Bertulang (200 kg besi + beskisting
Bahan
Kayu Terentang
0.27 m3
Rp 2,127,500.00 -- Rp 574,425.00
Paku Biasa 2" - 5"
2 kg
Rp 13,800.00 -- Rp 27,600.00
Minyak Bekisting
0.6 lt
Rp 9,200.00 -- Rp 5,520.00
Besi Beton Polos
200 kg
Rp 10,925.00 -- Rp 2,185,000.00
Kawat Beton
3 kg
Rp 17,250.00 -- Rp 51,750.00
Semen Portland
323 kg
Rp 1,495.00 -- Rp 482,885.00
Pasir Beton
0.52 m3
Rp 133,750.00 -- Rp 69,550.00
Koral Beton
0.78 m3
Rp 162,500.00 -- Rp 126,750.00
Sub Total -- Rp 3,523,480.00
Tenaga
Pekerja 5.6 Oh -- Rp 42,000.00 Rp 235,200.00
Tukang Batu 0.35 Oh -- Rp 55,000.00 Rp 19,250.00
Tukang Kayu 1.56 Oh -- Rp 70,000.00 Rp 109,200.00
Tukang Besi 1.4 Oh -- Rp 55,000.00 Rp 77,000.00
Kepala Tukang 0.331 Oh -- Rp 60,000.00 Rp 19,860.00
Mandor 0.17 Oh -- Rp 80,000.00 Rp 13,600.00
Sub Total -- Rp 474,110.00
Total -- Rp 3,997,590.00
8. Uraian
no
URAIAN PEKERJAAN SATUAN
VOLUME KODE
ANALISA
HARGA SATUAN JUMLAH HARGA JUMLAH HARGA
BAHAN UPAH BAHAN UPAH
II PEKERJAAN TANAH
1 M3 Galian Tanah Biasa Sedalam 1 m
m3 --
Rp 20,000.00 Rp 20,000.00 Rp 20,000.00
1 m3 Galian Tanah Biasa Sedalam 2 m
m3 --
Rp 26,252.00 Rp 26,252.00 Rp 26,252.00
1 m3 Galian Tanah Biasa Sedalam 1.5 m
m3 17.25
Rp 23,126.00 Rp 398,923.50 Rp 398,923.50
1 m3 Urugan Kembali
m3 7.5
Rp 9,584.00 Rp 71,880.00 Rp 71,880.00
1 m3 Urugan Pasir
m3 --
Rp 13,800.00 Rp 13,400.00 Rp 13,800.00 Rp 13,400.00 Rp 27,200.00
Total Rp 544,255.50
III PEKERJAAN PONDASI
1 m3 Pasang Pondasi Batu Kzli 1 Pc : 5 Ps m3 9.75 Rp 112,500.00 Rp 544,235.60 Rp 1,096,875.00 Rp 5,306,297.10 Rp 6,403,172.10
total Rp 6,457,427.10
1 m3 Membuat Sloof Beton Bertulang (200 kg
besi + bekisting)
m3 0.15
Rp 3,523,480.00 Rp 474,110.00 Rp 528,522.00 Rp 71,116.50 Rp 599,638.50
TOTAL KESELURUSAH PEMBUATAN PONDASI Rp 7,547,065.5
9. TABEL KURVA S
Pekerjaan HSP VOLUME HARGA Prosentase (%)
Galian Tanah Rp 23,126.00 17.25 Rp 398,923.50 5
Pemasangan Pondasi Rp 656,735.00 9.75 Rp 6,403,166.25 86
Penimbunan Tanah Rp 9,584.00 7.5 Rp 71,880.00 1
Pemasangan Sloof Rp 3,997,590.00 0.15 Rp 599,638.50 8
Rp 7,547,065.5 100
12. 3.865988372
477.9767442
1.897848837
0
100
200
300
400
500
600
Batu Belah Semen Portland Pasir Pasang
JumlahMterial
Material (m3)
GRAFIK KEBUTUHAN MATERIAL
HARI KE-2
4.115406977
508.8139535
2.020290698
0
100
200
300
400
500
600
Batu Belah Semen Portland Pasir Pasang
JumlahMaterial
Material (m3)
GRAFIK KEBUTUHAN MATERIAL
HARI KE-3