SlideShare a Scribd company logo
1 of 13
Download to read offline
Solutions Development Team
Service Level Agreements with Business Partners
SLA
Database Support and Maintenance
Database Issue 1 day TAT
Additional database functionality Project Dependent
Temporary Solution Needed 1 day TAT
Vbscript Requests
New 8 days to complete coding
Revision 8 days to complete coding
Database Projects
Claims Management Manage 5 projects in parallel
Emrollment Operations Manage 5 projects in parallel
Other Manage 2 projects in parallel
Dataset Intake and Management/ Script Monitoring
No System Issues all production tools available by 9:30AM
System Issues No commitment
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
DRIVERS
Database Support and Maintenance Requests 232 250 242 191 186 155 126 179 165 195 136 116
Database Issue 1,585 168 200 185 122 126 98 93 117 138 137 109 92
Additional database functionality 445 54 39 42 50 42 47 22 50 21 42 22 14
Temporary Solution Needed 143 10 11 15 19 18 10 11 12 6 16 5 10
Vbscript Requests Requests 4 4 7 4 6 3 5 14 2 5 12 8
New 43 2 2 3 2 3 2 3 10 1 3 8 4
Revision 31 2 2 4 2 3 1 2 4 1 2 4 4
Database Projects Projects 2 2 1 2 2 1 2 2 1 2 2 1
Claims Management 2 2 2 2
Emrollment Operations 2 2 2 2
Other 1 1 1 1
Dataset Intake and Management/ Script Monitoring Work Days 21 21 22 21 22 21 21 23 19 22 21 20
No System Issues 154 11 13 14 12 14 13 12 15 11 13 14 12
System Issues 100 10 8 8 9 8 8 9 8 8 9 7 8
Business Support - Knowledge Base ONLY Requests
Corporate Project Support 6 1 0 1 0 1 0 1 0 1 0 1 0
Organization Support 6 0 1 0 1 0 1 0 1 0 1 0 1
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
REASONABLE EXPECTATION TO PERFORM (item/hour)
Database Support and Maintenance TAT
Database Issue 2 hrs 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Additional database functionality NA 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
Temporary Solution Needed 4 hrs 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
VBScripts
New TAT
Workflow development and review 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Spec Development and Review 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
Code Development 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Revision TAT
Workflow development and review 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
Spec Development and Review 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
Code Development 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Database Projects
Initial Fact finding 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Project Charter, Supporting Documentation, Research 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Database Development 20 days 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Documentation (Test Plans, Procedures, Job Aids) 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
User Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
User Training 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
Dataset Intake and Management/Script Monitoring
No System Issues 14 hrs 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
System Issues 21 hrs 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
Business Support - Knowledge Base ONLY
Corporate Project Support 1 day 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
Organization Support 1 day 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
AVAILABLE PRODUCTIVE TIME
% Time Related to Meeting, Vacation, etc. 23% 23% 23% 23% 23% 23% 23% 23% 23% 23% 23% 23%
% Time on Production 77% 77% 77% 77% 77% 77% 77% 77% 77% 77% 77% 77%
Adjusted REs
Database Support and Maintenance
Database Issue 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39
Additional database functionality 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
Temporary Solution Needed 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19
VBScripts
New
Workflow development and review 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Spec Development and Review 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Code Development 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Revision
Workflow development and review 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Spec Development and Review 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Code Development 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Database Projects
Initial Fact finding 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Project Charter, Supporting Documentation, Research 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Database Development 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Documentation (Test Plans, Procedures, Job Aids) 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
User Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
User Training 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Dataset Intake and Management/Script Monitoring
No System Issues 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
System Issues 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Business Support - Knowledge Base ONLY
Corporate Project Support 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
Organization Support 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
Days in the Month 261 22 21 22 21 23 21 22 23 20 23 22 21
Hours Available per FTE 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.4 164.91 157.74 150.57
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Database Support and Maintenance
Database Issue
Volumes 1585.00 168.00 200.00 185.00 122.00 126.00 98.00 93.00 117.00 138.00 137.00 109.00 92.00
Units Per Hour 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39
Total Hours Needed 4116.88 436.36 519.48 480.52 316.88 327.27 254.55 241.56 303.90 358.44 355.84 283.12 238.96
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Database Issues 2.20 2.77 3.45 3.05 2.10 1.98 1.69 1.53 1.84 2.50 2.16 1.79 1.59
Additional database functionality
Volumes 445.00 54.00 39.00 42.00 50.00 42.00 47.00 22.00 50.00 21.00 42.00 22.00 14.00
Units Per Hour 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
Total Hours Needed 4143.70 502.83 363.16 391.09 465.58 391.09 437.65 204.86 465.58 195.55 391.09 204.86 130.36
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Additional Database Functionality 2.21 3.19 2.41 2.48 3.09 2.37 2.91 1.30 2.82 1.36 2.37 1.30 0.87
Temporary Solution Needed
Volumes 143.00 10.00 11.00 15.00 19.00 18.00 10.00 11.00 12.00 6.00 16.00 5.00 10.00
Units Per Hour 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19
Total Hours Needed 742.86 51.95 57.14 77.92 98.70 93.51 51.95 57.14 62.34 31.17 83.12 25.97 51.95
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Temporary Solution Needed 0.40 0.33 0.38 0.49 0.66 0.57 0.35 0.36 0.38 0.22 0.50 0.16 0.35
Total FTEs Required - Database Support and Maintenance 4.81 6.28 6.24 6.02 5.85 4.92 4.94 3.19 5.04 4.08 5.03 3.26 2.80
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
VBScripts
New
Workflow development and review
Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00
Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 2002.01 93.12 93.12 139.68 93.12 139.68 93.12 139.68 465.58 46.56 139.68 372.47 186.23
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Workflow Development and Review 1.05 0.59 0.62 0.89 0.62 0.85 0.62 0.89 2.82 0.32 0.85 2.36 1.24
Spec Development and Review
Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00
Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Total Hours Needed 1201.21 55.87 55.87 83.81 55.87 83.81 55.87 83.81 279.35 27.94 83.81 223.48 111.74
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Spec Development and Review 0.63 0.35 0.37 0.53 0.37 0.51 0.37 0.53 1.69 0.19 0.51 1.42 0.74
Code Development
Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00
Units Per Hour 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Total Hours Needed 1541.55 71.70 71.70 107.55 71.70 107.55 71.70 107.55 358.50 35.85 107.55 286.80 143.40
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Code Development 0.81 0.45 0.48 0.68 0.48 0.65 0.48 0.68 2.17 0.25 0.65 1.82 0.95
Testing
Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00
Units Per Hour 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
Total Hours Needed 1541.55 71.70 71.70 107.55 71.70 107.55 71.70 107.55 358.50 35.85 107.55 286.80 143.40
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Testing 0.81 0.45 0.48 0.68 0.48 0.65 0.48 0.68 2.17 0.25 0.65 1.82 0.95
Total FTEs Required - New 3.31 1.85 1.94 2.78 1.94 2.66 1.94 2.78 8.87 1.02 2.66 7.41 3.88
Revision
Workflow development and review
Volumes 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00
Units Per Hour 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
Total Hours Needed 666.81 43.02 43.02 86.04 43.02 64.53 21.51 43.02 86.04 21.51 43.02 86.04 86.04
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Workflow Development and Review 0.35 0.27 0.29 0.55 0.29 0.39 0.14 0.27 0.52 0.15 0.26 0.55 0.57
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Spec Development and Review
Volumes 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00
Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Total Hours Needed 865.99 55.87 55.87 111.74 55.87 83.81 27.94 55.87 111.74 27.94 55.87 111.74 111.74
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Spec Development and Review 0.46 0.35 0.37 0.71 0.37 0.51 0.19 0.35 0.68 0.19 0.34 0.71 0.74
Code Development
Volumes 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00
Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 1443.31 93.12 93.12 186.23 93.12 139.68 46.56 93.12 186.23 46.56 93.12 186.23 186.23
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Code Development 0.77 0.59 0.62 1.18 0.62 0.85 0.31 0.59 1.13 0.32 0.56 1.18 1.24
Testing
Suspended Claim Receipts 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00
Volumes 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 1443.31 93.12 93.12 186.23 93.12 139.68 46.56 93.12 186.23 46.56 93.12 186.23 186.23
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Testing 0.77 0.59 0.62 1.18 0.62 0.85 0.31 0.59 1.13 0.32 0.56 1.18 1.24
Total FTEs Required - Revision 2.35 1.81 1.89 3.62 1.89 2.59 0.95 1.81 3.46 0.99 1.73 3.62 3.79
TOTAL FTEs REQUIRED - VBSCRIPT 5.66 3.66 3.84 6.40 3.84 5.25 2.89 4.59 12.32 2.01 4.39 11.03 7.67
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Database Projects
Initial Fact finding
Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00
Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Initial Fact Finding 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31
Project Charter, Supporting Documentation, Research
Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00
Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Project Charter, etc 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31
Database Development
Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00
Units Per Hour 0.01 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
Total Hours Needed 3724.68 372.47 372.47 186.23 372.47 372.47 186.23 372.47 372.47 186.23 372.47 372.47 186.23
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Database Development 1.98 2.36 2.47 1.18 2.47 2.26 1.24 2.36 2.26 1.30 2.26 2.36 1.24
Testing
Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00
Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Testing 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31
Documentation (Test Plans, Procedures, Job Aids)
Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00
Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Documentation 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
User Testing
Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00
Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - User Testing 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31
User Training
Suspended Claim Receipts 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00
Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Total Hours Needed 558.70 55.87 55.87 27.94 55.87 55.87 27.94 55.87 55.87 27.94 55.87 55.87 27.94
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - User Training 0.30 0.35 0.37 0.18 0.37 0.34 0.19 0.35 0.34 0.19 0.34 0.35 0.19
TOTAL FTEs REQUIRED - Database Projects 4.75 5.67 5.94 2.83 5.94 5.42 2.97 5.67 5.42 3.12 5.42 5.67 2.97
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Dataset Intake and Management/ Script Monitoring
No System Issues
Volumes 154.00 11.00 13.00 14.00 12.00 14.00 13.00 12.00 15.00 11.00 13.00 14.00 12.00
Units Per Hour 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
Total Hours Needed 2800.00 200.00 236.36 254.55 218.18 254.55 236.36 218.18 272.73 200.00 236.36 254.55 218.18
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - No System Issues 1.50 1.27 1.57 1.61 1.45 1.54 1.57 1.38 1.65 1.39 1.43 1.61 1.45
System Issues
Volumes 100.00 10.00 8.00 8.00 9.00 8.00 8.00 9.00 8.00 8.00 9.00 7.00 8.00
Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Total Hours Needed 2727.27 272.73 218.18 218.18 245.45 218.18 218.18 245.45 218.18 218.18 245.45 190.91 218.18
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - System Issues 1.46 1.73 1.45 1.38 1.63 1.32 1.45 1.56 1.32 1.52 1.49 1.21 1.45
Total FTEs Required - Dataset Intake and Management/Script Monitoring 2.95 3.00 3.02 3.00 3.08 2.87 3.02 2.94 2.98 2.92 2.92 2.82 2.90
Business Support - Knowledge Base ONLY
Corporate Project Support
Volumes 6.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00
Units Per Hour 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
Total Hours Needed 55.87 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Corporate Project Support 0.03 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00
Organization Support
Volumes 6.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00
Units Per Hour 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
Total Hours Needed 55.87 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31
FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57
Total FTEs Required - Organizational Support 0.03 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06
Total FTEs Required - Business Support - Knowledge Base ONLY 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
NON-VARIABLE POSITIONS
Senior Manager 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Total Non-Variable FTEs Required 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
SUMMARY
Total FTEs Required - Database Support and Maintenance 4.81 6.28 6.24 6.02 5.85 4.92 4.94 3.19 5.04 4.08 5.03 3.26 2.80
TOTAL FTEs REQUIRED - VBSCRIPT 5.66 3.66 3.84 6.40 3.84 5.25 2.89 4.59 12.32 2.01 4.39 11.03 7.67
TOTAL FTEs REQUIRED - Database Projects 4.75 5.67 5.94 2.83 5.94 5.42 2.97 5.67 5.42 3.12 5.42 5.67 2.97
Solutions Development Team
Staffing Model
Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total FTEs Required - Dataset Intake and Management/Script Monitoring 2.95 3.00 3.02 3.00 3.08 2.87 3.02 2.94 2.98 2.92 2.92 2.82 2.90
Total FTEs Required - Business Support - Knowledge Base ONLY 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
Total Non-Variable FTEs Required 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Total FTEs Required 18.73 19.17 19.59 18.80 19.27 19.02 14.38 16.95 26.32 12.69 18.32 23.34 16.90
Solutions Development Team
Staffing Model
Total Staff FTE Requirements
ANNUAL Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
SUMMARY
Total FTEs Required - Database Support and Maintenance 4.81 6.28 6.24 6.02 5.85 4.92 4.94 3.19 5.04 4.08 5.03 3.26 2.80
TOTAL FTEs REQUIRED - VBSCRIPT 5.66 3.66 3.84 6.40 3.84 5.25 2.89 4.59 12.32 2.01 4.39 11.03 7.67
TOTAL FTEs REQUIRED - Database Projects 4.75 5.67 5.94 2.83 5.94 5.42 2.97 5.67 5.42 3.12 5.42 5.67 2.97
Total FTEs Required - Dataset Intake and Management/Script Monitoring 2.95 3.00 3.02 3.00 3.08 2.87 3.02 2.94 2.98 2.92 2.92 2.82 2.90
Total FTEs Required - Business Support - Knowledge Base ONLY 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
Total Non-Variable FTEs Required 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Total FTEs Required 18.73 19.17 19.59 18.80 19.27 19.02 14.38 16.95 26.32 12.69 18.32 23.34 16.90
Solutions Development Team
Staffing Plan
Grade Level FTE DBSM VBS DB DSIandSM Leadership Total
Team member 1 I 1 10% 40% 50% 100%
Team member 2 J 1 5% 40% 35% 20% 100%
Team member 3 K 1 20% 60% 15% 5% 100%
Team member 4 L 1 30% 70% 100%
Team member 5 L 1 40% 40% 20% 100%
Team member 6 L 1 5% 70% 20% 5% 100%
Team member 7 L 1 10% 90% 100%
Team member 8 L 1 30% 20% 50% 100%
Team member 9 M 1 5% 20% 10% 65% 100%
Team member 10 M 1 10% 20% 20% 50% 100%
Team member 11 M 1 20% 20% 10% 50% 100%
Count 11 1.85 2.5 4 2.15 0.5

More Related Content

Similar to StaffingModel_EXAMPLE

Performance tuning intro
Performance tuning introPerformance tuning intro
Performance tuning introaioughydchapter
 
Minimum viable product_to_deliver_business_value_v0.4
Minimum viable product_to_deliver_business_value_v0.4Minimum viable product_to_deliver_business_value_v0.4
Minimum viable product_to_deliver_business_value_v0.4Archana Joshi
 
香港六合彩
香港六合彩香港六合彩
香港六合彩taoyan
 
The 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck EzellThe 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck EzellDatavail
 
Best Practices SQL 2005 SSIS
Best Practices SQL 2005 SSISBest Practices SQL 2005 SSIS
Best Practices SQL 2005 SSISptolozah
 
[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & Processes
[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & Processes[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & Processes
[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & ProcessesRakuten Group, Inc.
 
Q T P Tutorial
Q T P  TutorialQ T P  Tutorial
Q T P Tutorialrosereddy
 
BI Project report
BI Project reportBI Project report
BI Project reporthlel
 
Bb world 2011 capacity planning
Bb world 2011 capacity planningBb world 2011 capacity planning
Bb world 2011 capacity planningSteve Feldman
 
Generic Framework for Knowledge Classification-1
Generic Framework  for Knowledge Classification-1Generic Framework  for Knowledge Classification-1
Generic Framework for Knowledge Classification-1Venkata Vineel
 
Performance Stability, Tips and Tricks and Underscores
Performance Stability, Tips and Tricks and UnderscoresPerformance Stability, Tips and Tricks and Underscores
Performance Stability, Tips and Tricks and UnderscoresJitendra Singh
 
5 practical operability techniques for teams - Matthew Skelton - ADDO 2018
5 practical operability techniques for teams - Matthew Skelton - ADDO 20185 practical operability techniques for teams - Matthew Skelton - ADDO 2018
5 practical operability techniques for teams - Matthew Skelton - ADDO 2018Conflux
 
LeSS Like Adoption @ SAP
LeSS Like Adoption @ SAPLeSS Like Adoption @ SAP
LeSS Like Adoption @ SAPRobert Briese
 
5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...
5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...
5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...Matthew Skelton
 
Redgate Community Circle: Tools For SQL Server Performance Tuning
Redgate Community Circle: Tools For SQL Server Performance TuningRedgate Community Circle: Tools For SQL Server Performance Tuning
Redgate Community Circle: Tools For SQL Server Performance TuningGrant Fritchey
 
Value add: Single User Performance Testing (http://managingperformancetesting...
Value add: Single User Performance Testing (http://managingperformancetesting...Value add: Single User Performance Testing (http://managingperformancetesting...
Value add: Single User Performance Testing (http://managingperformancetesting...akbollinger
 
5 practical operability techniques - Matthew Skelton - SkillsMatter 2018
5 practical operability techniques - Matthew Skelton - SkillsMatter 20185 practical operability techniques - Matthew Skelton - SkillsMatter 2018
5 practical operability techniques - Matthew Skelton - SkillsMatter 2018Matthew Skelton
 

Similar to StaffingModel_EXAMPLE (20)

Performance tuning intro
Performance tuning introPerformance tuning intro
Performance tuning intro
 
Minimum viable product_to_deliver_business_value_v0.4
Minimum viable product_to_deliver_business_value_v0.4Minimum viable product_to_deliver_business_value_v0.4
Minimum viable product_to_deliver_business_value_v0.4
 
香港六合彩
香港六合彩香港六合彩
香港六合彩
 
The 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck EzellThe 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck Ezell
 
Best Practices SQL 2005 SSIS
Best Practices SQL 2005 SSISBest Practices SQL 2005 SSIS
Best Practices SQL 2005 SSIS
 
Qtp tutorial
Qtp tutorialQtp tutorial
Qtp tutorial
 
[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & Processes
[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & Processes[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & Processes
[Rakuten TechConf2014] [C-6] Japan ICHIBA Daily Work - Tools & Processes
 
Q T P Tutorial
Q T P  TutorialQ T P  Tutorial
Q T P Tutorial
 
Performance Tuning intro
Performance Tuning introPerformance Tuning intro
Performance Tuning intro
 
BI Project report
BI Project reportBI Project report
BI Project report
 
Bb world 2011 capacity planning
Bb world 2011 capacity planningBb world 2011 capacity planning
Bb world 2011 capacity planning
 
Generic Framework for Knowledge Classification-1
Generic Framework  for Knowledge Classification-1Generic Framework  for Knowledge Classification-1
Generic Framework for Knowledge Classification-1
 
Performance Stability, Tips and Tricks and Underscores
Performance Stability, Tips and Tricks and UnderscoresPerformance Stability, Tips and Tricks and Underscores
Performance Stability, Tips and Tricks and Underscores
 
5 practical operability techniques for teams - Matthew Skelton - ADDO 2018
5 practical operability techniques for teams - Matthew Skelton - ADDO 20185 practical operability techniques for teams - Matthew Skelton - ADDO 2018
5 practical operability techniques for teams - Matthew Skelton - ADDO 2018
 
Introduction to DevOps
Introduction to DevOpsIntroduction to DevOps
Introduction to DevOps
 
LeSS Like Adoption @ SAP
LeSS Like Adoption @ SAPLeSS Like Adoption @ SAP
LeSS Like Adoption @ SAP
 
5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...
5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...
5 practical operability techniques for teams - Matthew Skelton - SQUID meetup...
 
Redgate Community Circle: Tools For SQL Server Performance Tuning
Redgate Community Circle: Tools For SQL Server Performance TuningRedgate Community Circle: Tools For SQL Server Performance Tuning
Redgate Community Circle: Tools For SQL Server Performance Tuning
 
Value add: Single User Performance Testing (http://managingperformancetesting...
Value add: Single User Performance Testing (http://managingperformancetesting...Value add: Single User Performance Testing (http://managingperformancetesting...
Value add: Single User Performance Testing (http://managingperformancetesting...
 
5 practical operability techniques - Matthew Skelton - SkillsMatter 2018
5 practical operability techniques - Matthew Skelton - SkillsMatter 20185 practical operability techniques - Matthew Skelton - SkillsMatter 2018
5 practical operability techniques - Matthew Skelton - SkillsMatter 2018
 

StaffingModel_EXAMPLE

  • 1. Solutions Development Team Service Level Agreements with Business Partners SLA Database Support and Maintenance Database Issue 1 day TAT Additional database functionality Project Dependent Temporary Solution Needed 1 day TAT Vbscript Requests New 8 days to complete coding Revision 8 days to complete coding Database Projects Claims Management Manage 5 projects in parallel Emrollment Operations Manage 5 projects in parallel Other Manage 2 projects in parallel Dataset Intake and Management/ Script Monitoring No System Issues all production tools available by 9:30AM System Issues No commitment
  • 2. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec DRIVERS Database Support and Maintenance Requests 232 250 242 191 186 155 126 179 165 195 136 116 Database Issue 1,585 168 200 185 122 126 98 93 117 138 137 109 92 Additional database functionality 445 54 39 42 50 42 47 22 50 21 42 22 14 Temporary Solution Needed 143 10 11 15 19 18 10 11 12 6 16 5 10 Vbscript Requests Requests 4 4 7 4 6 3 5 14 2 5 12 8 New 43 2 2 3 2 3 2 3 10 1 3 8 4 Revision 31 2 2 4 2 3 1 2 4 1 2 4 4 Database Projects Projects 2 2 1 2 2 1 2 2 1 2 2 1 Claims Management 2 2 2 2 Emrollment Operations 2 2 2 2 Other 1 1 1 1 Dataset Intake and Management/ Script Monitoring Work Days 21 21 22 21 22 21 21 23 19 22 21 20 No System Issues 154 11 13 14 12 14 13 12 15 11 13 14 12 System Issues 100 10 8 8 9 8 8 9 8 8 9 7 8 Business Support - Knowledge Base ONLY Requests Corporate Project Support 6 1 0 1 0 1 0 1 0 1 0 1 0 Organization Support 6 0 1 0 1 0 1 0 1 0 1 0 1
  • 3. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec REASONABLE EXPECTATION TO PERFORM (item/hour) Database Support and Maintenance TAT Database Issue 2 hrs 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 Additional database functionality NA 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 Temporary Solution Needed 4 hrs 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 VBScripts New TAT Workflow development and review 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Spec Development and Review 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 Code Development 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Revision TAT Workflow development and review 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 Spec Development and Review 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 Code Development 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Database Projects Initial Fact finding 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Project Charter, Supporting Documentation, Research 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Database Development 20 days 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Documentation (Test Plans, Procedures, Job Aids) 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 User Testing 5 days 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 User Training 3 days 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 Dataset Intake and Management/Script Monitoring No System Issues 14 hrs 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 System Issues 21 hrs 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 Business Support - Knowledge Base ONLY Corporate Project Support 1 day 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 Organization Support 1 day 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
  • 4. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec AVAILABLE PRODUCTIVE TIME % Time Related to Meeting, Vacation, etc. 23% 23% 23% 23% 23% 23% 23% 23% 23% 23% 23% 23% % Time on Production 77% 77% 77% 77% 77% 77% 77% 77% 77% 77% 77% 77% Adjusted REs Database Support and Maintenance Database Issue 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 Additional database functionality 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 Temporary Solution Needed 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 VBScripts New Workflow development and review 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Spec Development and Review 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Code Development 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Revision Workflow development and review 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Spec Development and Review 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Code Development 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Database Projects Initial Fact finding 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Project Charter, Supporting Documentation, Research 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Database Development 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Documentation (Test Plans, Procedures, Job Aids) 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 User Testing 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 User Training 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Dataset Intake and Management/Script Monitoring No System Issues 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 System Issues 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Business Support - Knowledge Base ONLY Corporate Project Support 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 Organization Support 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 Days in the Month 261 22 21 22 21 23 21 22 23 20 23 22 21 Hours Available per FTE 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.4 164.91 157.74 150.57
  • 5. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Database Support and Maintenance Database Issue Volumes 1585.00 168.00 200.00 185.00 122.00 126.00 98.00 93.00 117.00 138.00 137.00 109.00 92.00 Units Per Hour 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 Total Hours Needed 4116.88 436.36 519.48 480.52 316.88 327.27 254.55 241.56 303.90 358.44 355.84 283.12 238.96 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Database Issues 2.20 2.77 3.45 3.05 2.10 1.98 1.69 1.53 1.84 2.50 2.16 1.79 1.59 Additional database functionality Volumes 445.00 54.00 39.00 42.00 50.00 42.00 47.00 22.00 50.00 21.00 42.00 22.00 14.00 Units Per Hour 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 Total Hours Needed 4143.70 502.83 363.16 391.09 465.58 391.09 437.65 204.86 465.58 195.55 391.09 204.86 130.36 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Additional Database Functionality 2.21 3.19 2.41 2.48 3.09 2.37 2.91 1.30 2.82 1.36 2.37 1.30 0.87 Temporary Solution Needed Volumes 143.00 10.00 11.00 15.00 19.00 18.00 10.00 11.00 12.00 6.00 16.00 5.00 10.00 Units Per Hour 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 Total Hours Needed 742.86 51.95 57.14 77.92 98.70 93.51 51.95 57.14 62.34 31.17 83.12 25.97 51.95 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Temporary Solution Needed 0.40 0.33 0.38 0.49 0.66 0.57 0.35 0.36 0.38 0.22 0.50 0.16 0.35 Total FTEs Required - Database Support and Maintenance 4.81 6.28 6.24 6.02 5.85 4.92 4.94 3.19 5.04 4.08 5.03 3.26 2.80
  • 6. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec VBScripts New Workflow development and review Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00 Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 2002.01 93.12 93.12 139.68 93.12 139.68 93.12 139.68 465.58 46.56 139.68 372.47 186.23 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Workflow Development and Review 1.05 0.59 0.62 0.89 0.62 0.85 0.62 0.89 2.82 0.32 0.85 2.36 1.24 Spec Development and Review Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00 Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Total Hours Needed 1201.21 55.87 55.87 83.81 55.87 83.81 55.87 83.81 279.35 27.94 83.81 223.48 111.74 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Spec Development and Review 0.63 0.35 0.37 0.53 0.37 0.51 0.37 0.53 1.69 0.19 0.51 1.42 0.74 Code Development Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00 Units Per Hour 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Total Hours Needed 1541.55 71.70 71.70 107.55 71.70 107.55 71.70 107.55 358.50 35.85 107.55 286.80 143.40 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Code Development 0.81 0.45 0.48 0.68 0.48 0.65 0.48 0.68 2.17 0.25 0.65 1.82 0.95 Testing Volumes 43.00 2.00 2.00 3.00 2.00 3.00 2.00 3.00 10.00 1.00 3.00 8.00 4.00 Units Per Hour 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 Total Hours Needed 1541.55 71.70 71.70 107.55 71.70 107.55 71.70 107.55 358.50 35.85 107.55 286.80 143.40 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Testing 0.81 0.45 0.48 0.68 0.48 0.65 0.48 0.68 2.17 0.25 0.65 1.82 0.95 Total FTEs Required - New 3.31 1.85 1.94 2.78 1.94 2.66 1.94 2.78 8.87 1.02 2.66 7.41 3.88 Revision Workflow development and review Volumes 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00 Units Per Hour 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 Total Hours Needed 666.81 43.02 43.02 86.04 43.02 64.53 21.51 43.02 86.04 21.51 43.02 86.04 86.04 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Workflow Development and Review 0.35 0.27 0.29 0.55 0.29 0.39 0.14 0.27 0.52 0.15 0.26 0.55 0.57
  • 7. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Spec Development and Review Volumes 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00 Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Total Hours Needed 865.99 55.87 55.87 111.74 55.87 83.81 27.94 55.87 111.74 27.94 55.87 111.74 111.74 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Spec Development and Review 0.46 0.35 0.37 0.71 0.37 0.51 0.19 0.35 0.68 0.19 0.34 0.71 0.74 Code Development Volumes 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00 Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 1443.31 93.12 93.12 186.23 93.12 139.68 46.56 93.12 186.23 46.56 93.12 186.23 186.23 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Code Development 0.77 0.59 0.62 1.18 0.62 0.85 0.31 0.59 1.13 0.32 0.56 1.18 1.24 Testing Suspended Claim Receipts 31.00 2.00 2.00 4.00 2.00 3.00 1.00 2.00 4.00 1.00 2.00 4.00 4.00 Volumes 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 1443.31 93.12 93.12 186.23 93.12 139.68 46.56 93.12 186.23 46.56 93.12 186.23 186.23 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Testing 0.77 0.59 0.62 1.18 0.62 0.85 0.31 0.59 1.13 0.32 0.56 1.18 1.24 Total FTEs Required - Revision 2.35 1.81 1.89 3.62 1.89 2.59 0.95 1.81 3.46 0.99 1.73 3.62 3.79 TOTAL FTEs REQUIRED - VBSCRIPT 5.66 3.66 3.84 6.40 3.84 5.25 2.89 4.59 12.32 2.01 4.39 11.03 7.67
  • 8. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Database Projects Initial Fact finding Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Initial Fact Finding 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31 Project Charter, Supporting Documentation, Research Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Project Charter, etc 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31 Database Development Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 Units Per Hour 0.01 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 Total Hours Needed 3724.68 372.47 372.47 186.23 372.47 372.47 186.23 372.47 372.47 186.23 372.47 372.47 186.23 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Database Development 1.98 2.36 2.47 1.18 2.47 2.26 1.24 2.36 2.26 1.30 2.26 2.36 1.24 Testing Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Testing 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31 Documentation (Test Plans, Procedures, Job Aids) Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Documentation 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31
  • 9. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec User Testing Volumes 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 Units Per Hour 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 Total Hours Needed 931.17 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 93.12 93.12 46.56 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - User Testing 0.50 0.59 0.62 0.30 0.62 0.56 0.31 0.59 0.56 0.32 0.56 0.59 0.31 User Training Suspended Claim Receipts 20.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 2.00 2.00 1.00 Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Total Hours Needed 558.70 55.87 55.87 27.94 55.87 55.87 27.94 55.87 55.87 27.94 55.87 55.87 27.94 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - User Training 0.30 0.35 0.37 0.18 0.37 0.34 0.19 0.35 0.34 0.19 0.34 0.35 0.19 TOTAL FTEs REQUIRED - Database Projects 4.75 5.67 5.94 2.83 5.94 5.42 2.97 5.67 5.42 3.12 5.42 5.67 2.97
  • 10. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Dataset Intake and Management/ Script Monitoring No System Issues Volumes 154.00 11.00 13.00 14.00 12.00 14.00 13.00 12.00 15.00 11.00 13.00 14.00 12.00 Units Per Hour 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 Total Hours Needed 2800.00 200.00 236.36 254.55 218.18 254.55 236.36 218.18 272.73 200.00 236.36 254.55 218.18 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - No System Issues 1.50 1.27 1.57 1.61 1.45 1.54 1.57 1.38 1.65 1.39 1.43 1.61 1.45 System Issues Volumes 100.00 10.00 8.00 8.00 9.00 8.00 8.00 9.00 8.00 8.00 9.00 7.00 8.00 Units Per Hour 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Total Hours Needed 2727.27 272.73 218.18 218.18 245.45 218.18 218.18 245.45 218.18 218.18 245.45 190.91 218.18 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - System Issues 1.46 1.73 1.45 1.38 1.63 1.32 1.45 1.56 1.32 1.52 1.49 1.21 1.45 Total FTEs Required - Dataset Intake and Management/Script Monitoring 2.95 3.00 3.02 3.00 3.08 2.87 3.02 2.94 2.98 2.92 2.92 2.82 2.90 Business Support - Knowledge Base ONLY Corporate Project Support Volumes 6.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 Units Per Hour 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 Total Hours Needed 55.87 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Corporate Project Support 0.03 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 Organization Support Volumes 6.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 1.00 Units Per Hour 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 Total Hours Needed 55.87 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 0.00 9.31 FTE Hours Available 1871.37 157.74 150.57 157.74 150.57 164.91 150.57 157.74 164.91 143.40 164.91 157.74 150.57 Total FTEs Required - Organizational Support 0.03 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 0.00 0.06 Total FTEs Required - Business Support - Knowledge Base ONLY 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 NON-VARIABLE POSITIONS Senior Manager 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 Total Non-Variable FTEs Required 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 SUMMARY Total FTEs Required - Database Support and Maintenance 4.81 6.28 6.24 6.02 5.85 4.92 4.94 3.19 5.04 4.08 5.03 3.26 2.80 TOTAL FTEs REQUIRED - VBSCRIPT 5.66 3.66 3.84 6.40 3.84 5.25 2.89 4.59 12.32 2.01 4.39 11.03 7.67 TOTAL FTEs REQUIRED - Database Projects 4.75 5.67 5.94 2.83 5.94 5.42 2.97 5.67 5.42 3.12 5.42 5.67 2.97
  • 11. Solutions Development Team Staffing Model Annual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total FTEs Required - Dataset Intake and Management/Script Monitoring 2.95 3.00 3.02 3.00 3.08 2.87 3.02 2.94 2.98 2.92 2.92 2.82 2.90 Total FTEs Required - Business Support - Knowledge Base ONLY 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 Total Non-Variable FTEs Required 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 Total FTEs Required 18.73 19.17 19.59 18.80 19.27 19.02 14.38 16.95 26.32 12.69 18.32 23.34 16.90
  • 12. Solutions Development Team Staffing Model Total Staff FTE Requirements ANNUAL Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec SUMMARY Total FTEs Required - Database Support and Maintenance 4.81 6.28 6.24 6.02 5.85 4.92 4.94 3.19 5.04 4.08 5.03 3.26 2.80 TOTAL FTEs REQUIRED - VBSCRIPT 5.66 3.66 3.84 6.40 3.84 5.25 2.89 4.59 12.32 2.01 4.39 11.03 7.67 TOTAL FTEs REQUIRED - Database Projects 4.75 5.67 5.94 2.83 5.94 5.42 2.97 5.67 5.42 3.12 5.42 5.67 2.97 Total FTEs Required - Dataset Intake and Management/Script Monitoring 2.95 3.00 3.02 3.00 3.08 2.87 3.02 2.94 2.98 2.92 2.92 2.82 2.90 Total FTEs Required - Business Support - Knowledge Base ONLY 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 Total Non-Variable FTEs Required 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 Total FTEs Required 18.73 19.17 19.59 18.80 19.27 19.02 14.38 16.95 26.32 12.69 18.32 23.34 16.90
  • 13. Solutions Development Team Staffing Plan Grade Level FTE DBSM VBS DB DSIandSM Leadership Total Team member 1 I 1 10% 40% 50% 100% Team member 2 J 1 5% 40% 35% 20% 100% Team member 3 K 1 20% 60% 15% 5% 100% Team member 4 L 1 30% 70% 100% Team member 5 L 1 40% 40% 20% 100% Team member 6 L 1 5% 70% 20% 5% 100% Team member 7 L 1 10% 90% 100% Team member 8 L 1 30% 20% 50% 100% Team member 9 M 1 5% 20% 10% 65% 100% Team member 10 M 1 10% 20% 20% 50% 100% Team member 11 M 1 20% 20% 10% 50% 100% Count 11 1.85 2.5 4 2.15 0.5