SlideShare a Scribd company logo
1 of 24
Download to read offline
Using AI-led assurance
to deliver projects on
time and on budget
Dev Amratia - CEO
OECD, 17 May 2023
2
More than 75% of projects are late with 50% late by at least 5 months
3
Why do so many projects fail to finish on time? Put simply, complexity and bias.
Incredibly
complex
project
schedules
Overheads and time-
bound costs spiral
Contractor’s profit
margin squeezed and
quality affected
Trust between
contractor and owner-
operator breaks down
Business case for project
is weakened or collapses
Owner-operator’s
business is devalued
Legal issues ensue with
liquidated damages
awarded
Reputational damage
hurts everyone involved
Contracting and
baselining
exercises
undermined
Unexpected
delays
materialise
without warning
Key milestones
missed again
and again
Failure to
mitigate risky
activities
Inaccurate
forecasting
Salience
bias
Availability
bias
Optimism
bias
Failure to
mitigate risks
the project
team hasn’t
factored
Failure to
mitigate
boring risks
4
nPlan’s Unified AI Platform is a data-derived schedule and risk forecasting solution
delivered
via
Machine learning
Past project
schedules
How long might my
project take?
What might go
wrong with my
project?
What can I do to reduce
risk or capture
opportunity?
nPlan
Platform
nPlan
Portfolio
nPlan
Insights
The platform uses past project data and machine learning to generate unbiased forecasts of project outcomes;
results are shared via our Portfolio, Insights, and Bid products.
nPlan
Bid
5
Two key areas of focus are identifying unknown unknowns and providing independent assurance
nPlan seeks to answer the question “when will my project most probably finish?”
● The things that keep you up at night –
what might the team not be thinking of
that you should be? What might derail
all your planning?
Identifying Unknown Unknowns
● Making sure the team is focused on
the most valuable risk areas with a
comprehensive, 3rd party analysis
Providing Independent Assurance
6
pre-sanction execution
Individual
projects
Portfolio of
projects
Tender
Evaluation
Business
Case
Assurance
Portfolio
Monitoring
Project
Delivery
nPlan enables customers to drive value across the project lifecycle and across the wider portfolio
7
Gather
information
about the
project,
context,
objectives
Run the
simulation
Reach
consensus on
probability of
risks occurring
Identify
activities in
schedule to
which to apply
discrete risks
Define, apply
uncertainties to
activities
Run the
simulation
QSRA
nPlan
Obtain schedule
file
Time and effort
Human processing
(Compounding) error
Computer processing
nPlan’s approach solves for QSRA in a nimble, data-driven way that allows for rapid iteration and
scenario comparison
8
9
Win more work with credible, realistic plans that give clients total peace of mind
Quantify key risks that could consume contingency and profit to protect margins
Establish the optimum contracting model for achieving project objectives, every time
Assurance of sub-contractor & master schedules to correctly set expectations and deliver
Implement mitigation strategies for different risks to control schedule and increase margins
Deliver more active risk management without straining finite resources
Benefits depending on the project dynamic
Has amassed over
75 Construction schedules
creating the biggest
dataset of its kind in
the world
600,000
$22M
In funding from backers
including Google Ventures, the
founder of Deepmind, and the
former CEO of McKinsey
Secured Customers include:
Founded in the
UK
in 2017
Team of
- and growing
Hypothesis: we can use AI to identify
risks and forecast projects
Taking optimism bias (and a bunch of other biases)
quite literally out of the equation and going a long way
towards solving the problem of delayed projects
C A S E S T U D Y
How Rail Projects Victoria used AI-powered
forecasting and risk management to choose
the best tender for its South Geelong to
Waurn Ponds Duplication Project
About the Project
Project Name:
Project Type:
Project Value:
Works to start:
South Geelong to Waurn Ponds Duplication
Railway construction
~$900M AUD
Late 2022
13
nPlan’s AI learnt
how rail projects
are delivered
RPV shared bid
schedules with
nPlan
The bid schedules
were processed in
nPlan Project
RPV used nPlan’s
findings to evolve
the bid schedules
nPlan processed
the iterated bid
schedules
1 2 3 4 5
How nPlan worked with RPV
RPV selected
a tender
6
14
Data in the side-by-
side analysis
provided by nPlan
15
Cost Avoidance
Time →
Target date p-value
Early finish @ P50
Late finish @ P50
Target finish date
16
Cost Avoidance
17
100x
ROI of client
investment in nPlan so
far:
Value of unmitigated
total risks identified by
nPlan @ P80
Value of risks identified
and actioned so far:
$19.4M
RESULTS AT TENDER AWARD
$8.25M
18
Benefits for Rail Projects Victoria
Easily assess
whether schedules
are realistic
Benefits for chosen contractor
Quantify project
risk contingency
Compare bid
schedules with
quantitative data
Develop risk mindset
from the tender phase
Formalise key
milestones which work
for both contract
parties
Rewarded for
developing a
rigorous, realistic
schedule
Start project from
position of trust
with owner-
operator
Start negotiation
phase with a de-
risked schedule
Receive ongoing
insights from nPlan to
help with identification
of risks
Build trust with
contractor partner
before a contract is
awarded
19
4. Project Overrun Insurance
We have defined a new category;
Algorithm-led Assurance
Our Algorithm-led Assurance product is being used by
contractors, owner-operators, and government agencies.
We’ve proven we can acquire data at an incredible scale,
and provide valuable services today.
This has created a big and new
opportunity for us in insurance
Through the largest capacity providers in the world, we can
underwrite the outcomes of construction projects. We will
do this through a world-first product; project over-run
insurance, starting with a $500m capacity.
Our first product is scaling up
20
0
2
4
6
8
10
12
14
16
18
20
22
We are developing the world’s only
project over-run insurance
21
● The Owner or Contractor enters an agreement
with us (the Insurer), against the impact of
severe delays.
● nPlan’s assurance product is mandated as a risk
control measure, and provides the risk
parameters for the insurance to be priced.
● The product payout is based on a time trigger,
contingent on sufficient conditions remaining
true throughout the project.
Jul
2023
Oct
2023
Jan
2024
Mar
2024
Jun
2024
Sep
2024
Dec
2024
Feb
2025
May
2025
Aug
2025
Nov
2025
Jan
2026
Apr
2026
Jul
2026
Oct
2026
Dec
2026
Mar
2027
Jun
2027
Sep
2027
Dec
2027
Feb
2028
May
2028
Likelihood
(%)
Most likely Insured Range
End date
This is a big opportunity, and we ran a backtest with our reinsurance
partners on our data to quantify it
22
Project Size
Between $30m and $1b
Dataset
10 Years of data, 16985 projects
(~1% of the world’s total projects
in that period)
Underwriting
15% of project cost
0.8% premium
Capacity
$815b of total underwriting
$10b capacity requirement
$6.5b of premiums
$1.6b total payouts
PnL
$2b management fees for the
MGA
$3b syndicate profit
30% return for syndicate
The next steps for Insurance is to build the initial basket of projects that require
underwriting
- The basket must be sufficiently diverse, demonstrating sufficient non-correlated
risks
- The exact policy terms and conditions to be agreed and finalised
- Fill the capacity requirements based on the basket of projects and quantum of risk
to be traded.
If you would like to discuss partnering on a
project or portfolio of projects - please let
me know
www.nplan.io
www.nplan.io

More Related Content

Similar to Using AI led assurance to deliver projects on time and on budget - D. Amratia, CEO, nPlan

Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...Association for Project Management
 
project managment.ppt
project managment.pptproject managment.ppt
project managment.pptHinaAsghar16
 
Predicting surety claims
Predicting surety claimsPredicting surety claims
Predicting surety claimsLee Scoggins
 
Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...Association for Project Management
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.commkhilauria
 
Pragmatic Approaches to Project Costs Estimation
Pragmatic Approaches to Project Costs EstimationPragmatic Approaches to Project Costs Estimation
Pragmatic Approaches to Project Costs EstimationChristopher Akinlade
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy systempriyang2004
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...mtingle
 
Avoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAvoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAconex
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacPMA Consultants
 

Similar to Using AI led assurance to deliver projects on time and on budget - D. Amratia, CEO, nPlan (20)

Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
project managment.ppt
project managment.pptproject managment.ppt
project managment.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
Unit 2.pptx
Unit 2.pptxUnit 2.pptx
Unit 2.pptx
 
04 project cost managment
04 project cost managment04 project cost managment
04 project cost managment
 
Predicting surety claims
Predicting surety claimsPredicting surety claims
Predicting surety claims
 
Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...Applying risk factors in the strategic selection of portfolio projects, prese...
Applying risk factors in the strategic selection of portfolio projects, prese...
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.com
 
Pragmatic Approaches to Project Costs Estimation
Pragmatic Approaches to Project Costs EstimationPragmatic Approaches to Project Costs Estimation
Pragmatic Approaches to Project Costs Estimation
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Project planning: A career path
Project planning: A career pathProject planning: A career path
Project planning: A career path
 
Avoid the risk and streamline your project controls
Avoid the risk and streamline your project controlsAvoid the risk and streamline your project controls
Avoid the risk and streamline your project controls
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 

More from OECD Governance

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators SlidesOECD Governance
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...OECD Governance
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...OECD Governance
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...OECD Governance
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...OECD Governance
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmOECD Governance
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...OECD Governance
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...OECD Governance
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...OECD Governance
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023OECD Governance
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...OECD Governance
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsOECD Governance
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfOECD Governance
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxOECD Governance
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxOECD Governance
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxOECD Governance
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxOECD Governance
 
Session-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptx
Session-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptxSession-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptx
Session-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptxOECD Governance
 

More from OECD Governance (20)

Public Integrity Indicators Slides
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators Slides
 
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
 
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovš...
 
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
 
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
 
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
 
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
 
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
 
Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023
 
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
 
Digital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and Recommendations
 
Buliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdf
 
Session-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptx
 
Session-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptx
 
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
 
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
 
Session-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptx
Session-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptxSession-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptx
Session-3-GOV-Green-Budgeting-in-the-Budget-Cycle.pptx
 

Recently uploaded

Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...narwatsonia7
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Christina Parmionova
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxHenryBriggs2
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26JSchaus & Associates
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbaisonalikaur4
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.Christina Parmionova
 
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...saminamagar
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...ankitnayak356677
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Christina Parmionova
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhellokittymaearciaga
 
Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170avaniranaescorts
 

Recently uploaded (20)

Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
 
productionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptxproductionpost-productiondiary-240320114322-5004daf6.pptx
productionpost-productiondiary-240320114322-5004daf6.pptx
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 
2024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 262024: The FAR, Federal Acquisition Regulations - Part 26
2024: The FAR, Federal Acquisition Regulations - Part 26
 
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.
 
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...call girls in DLF Phase 1  gurgaon  🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
call girls in DLF Phase 1 gurgaon 🔝 >༒9540349809 🔝 genuine Escort Service 🔝...
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vasant Kunj DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptx
 
Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170Call Girls In Le Meridien hotel New Delhi 9873777170
Call Girls In Le Meridien hotel New Delhi 9873777170
 

Using AI led assurance to deliver projects on time and on budget - D. Amratia, CEO, nPlan

  • 1. Using AI-led assurance to deliver projects on time and on budget Dev Amratia - CEO OECD, 17 May 2023
  • 2. 2 More than 75% of projects are late with 50% late by at least 5 months
  • 3. 3 Why do so many projects fail to finish on time? Put simply, complexity and bias. Incredibly complex project schedules Overheads and time- bound costs spiral Contractor’s profit margin squeezed and quality affected Trust between contractor and owner- operator breaks down Business case for project is weakened or collapses Owner-operator’s business is devalued Legal issues ensue with liquidated damages awarded Reputational damage hurts everyone involved Contracting and baselining exercises undermined Unexpected delays materialise without warning Key milestones missed again and again Failure to mitigate risky activities Inaccurate forecasting Salience bias Availability bias Optimism bias Failure to mitigate risks the project team hasn’t factored Failure to mitigate boring risks
  • 4. 4 nPlan’s Unified AI Platform is a data-derived schedule and risk forecasting solution delivered via Machine learning Past project schedules How long might my project take? What might go wrong with my project? What can I do to reduce risk or capture opportunity? nPlan Platform nPlan Portfolio nPlan Insights The platform uses past project data and machine learning to generate unbiased forecasts of project outcomes; results are shared via our Portfolio, Insights, and Bid products. nPlan Bid
  • 5. 5 Two key areas of focus are identifying unknown unknowns and providing independent assurance nPlan seeks to answer the question “when will my project most probably finish?” ● The things that keep you up at night – what might the team not be thinking of that you should be? What might derail all your planning? Identifying Unknown Unknowns ● Making sure the team is focused on the most valuable risk areas with a comprehensive, 3rd party analysis Providing Independent Assurance
  • 7. 7 Gather information about the project, context, objectives Run the simulation Reach consensus on probability of risks occurring Identify activities in schedule to which to apply discrete risks Define, apply uncertainties to activities Run the simulation QSRA nPlan Obtain schedule file Time and effort Human processing (Compounding) error Computer processing nPlan’s approach solves for QSRA in a nimble, data-driven way that allows for rapid iteration and scenario comparison
  • 8. 8
  • 9. 9 Win more work with credible, realistic plans that give clients total peace of mind Quantify key risks that could consume contingency and profit to protect margins Establish the optimum contracting model for achieving project objectives, every time Assurance of sub-contractor & master schedules to correctly set expectations and deliver Implement mitigation strategies for different risks to control schedule and increase margins Deliver more active risk management without straining finite resources Benefits depending on the project dynamic
  • 10. Has amassed over 75 Construction schedules creating the biggest dataset of its kind in the world 600,000 $22M In funding from backers including Google Ventures, the founder of Deepmind, and the former CEO of McKinsey Secured Customers include: Founded in the UK in 2017 Team of - and growing Hypothesis: we can use AI to identify risks and forecast projects Taking optimism bias (and a bunch of other biases) quite literally out of the equation and going a long way towards solving the problem of delayed projects
  • 11. C A S E S T U D Y How Rail Projects Victoria used AI-powered forecasting and risk management to choose the best tender for its South Geelong to Waurn Ponds Duplication Project
  • 12. About the Project Project Name: Project Type: Project Value: Works to start: South Geelong to Waurn Ponds Duplication Railway construction ~$900M AUD Late 2022
  • 13. 13 nPlan’s AI learnt how rail projects are delivered RPV shared bid schedules with nPlan The bid schedules were processed in nPlan Project RPV used nPlan’s findings to evolve the bid schedules nPlan processed the iterated bid schedules 1 2 3 4 5 How nPlan worked with RPV RPV selected a tender 6
  • 14. 14 Data in the side-by- side analysis provided by nPlan
  • 15. 15 Cost Avoidance Time → Target date p-value Early finish @ P50 Late finish @ P50 Target finish date
  • 17. 17 100x ROI of client investment in nPlan so far: Value of unmitigated total risks identified by nPlan @ P80 Value of risks identified and actioned so far: $19.4M RESULTS AT TENDER AWARD $8.25M
  • 18. 18 Benefits for Rail Projects Victoria Easily assess whether schedules are realistic Benefits for chosen contractor Quantify project risk contingency Compare bid schedules with quantitative data Develop risk mindset from the tender phase Formalise key milestones which work for both contract parties Rewarded for developing a rigorous, realistic schedule Start project from position of trust with owner- operator Start negotiation phase with a de- risked schedule Receive ongoing insights from nPlan to help with identification of risks Build trust with contractor partner before a contract is awarded
  • 20. We have defined a new category; Algorithm-led Assurance Our Algorithm-led Assurance product is being used by contractors, owner-operators, and government agencies. We’ve proven we can acquire data at an incredible scale, and provide valuable services today. This has created a big and new opportunity for us in insurance Through the largest capacity providers in the world, we can underwrite the outcomes of construction projects. We will do this through a world-first product; project over-run insurance, starting with a $500m capacity. Our first product is scaling up 20
  • 21. 0 2 4 6 8 10 12 14 16 18 20 22 We are developing the world’s only project over-run insurance 21 ● The Owner or Contractor enters an agreement with us (the Insurer), against the impact of severe delays. ● nPlan’s assurance product is mandated as a risk control measure, and provides the risk parameters for the insurance to be priced. ● The product payout is based on a time trigger, contingent on sufficient conditions remaining true throughout the project. Jul 2023 Oct 2023 Jan 2024 Mar 2024 Jun 2024 Sep 2024 Dec 2024 Feb 2025 May 2025 Aug 2025 Nov 2025 Jan 2026 Apr 2026 Jul 2026 Oct 2026 Dec 2026 Mar 2027 Jun 2027 Sep 2027 Dec 2027 Feb 2028 May 2028 Likelihood (%) Most likely Insured Range End date
  • 22. This is a big opportunity, and we ran a backtest with our reinsurance partners on our data to quantify it 22 Project Size Between $30m and $1b Dataset 10 Years of data, 16985 projects (~1% of the world’s total projects in that period) Underwriting 15% of project cost 0.8% premium Capacity $815b of total underwriting $10b capacity requirement $6.5b of premiums $1.6b total payouts PnL $2b management fees for the MGA $3b syndicate profit 30% return for syndicate
  • 23. The next steps for Insurance is to build the initial basket of projects that require underwriting - The basket must be sufficiently diverse, demonstrating sufficient non-correlated risks - The exact policy terms and conditions to be agreed and finalised - Fill the capacity requirements based on the basket of projects and quantum of risk to be traded. If you would like to discuss partnering on a project or portfolio of projects - please let me know