SlideShare a Scribd company logo
1 of 8
Download to read offline
PROJECTS
Meet the Adjudicator: LK Shields
interviews Construction
Adjudicator Niall Lawless
by Jamie Ritchie
Meet the Adjudicator: LK Shields
interviews Construction Adjudicator
Niall Lawless
29th September 2017 | by Jamie Ritchie
“Adjudication can quickly and irrevocably upend the ADR landscape and status
quo, and unfortunately this has contributed to many ‘thought leaders’
rejecting or being unwilling to promote adjudication as an effective dispute
resolution mechanism. This is doing a great disservice to clients, contractors
and sub-contractors.” Niall Lawless
Jamie Ritchie, Associate Solicitor (Projects, Construction and Energy) at LK Shields is a practitioner with experience of
acting on behalf of claimants (referring parties) and defendants (responding parties) in construction adjudication. In
order to help promote  awareness of this form of dispute resolution within the Irish construction industry, Jamie
recently interviewed Niall Lawless (Irish Construction Adjudicator and co-author of the CIC Users’ Guide to
Adjudication) in order to get his take on the future of this currently underutilised process. Below is a transcript of that
interview.
Jamie: Niall, thank you for taking the time to talk to us.  In your own words, how would you define
adjudication?
Niall: In Ireland adjudication provides the parties to a construction contract with a process whereby an independent
third party makes a quick decision when the parties are in disagreement over payment.  The adjudicator’s decision is
binding until determined by arbitration or litigation and the parties may agree that the adjudicator’s decision is final
and binding.
Jamie: You have many years’ experience of adjudication across multiple jurisdictions. Tell us a bit about
your experience and your background? 
Niall: My early ADR experience was as a Chartered Building Services Engineer and Mechanical Engineer acting as
expert witness at all pleading stages and giving evidence under examination in arbitration and the Technology and
Construction Court in London numerous times. That led me to Fellowship of the Chartered Institute of Arbitrators in
2001, and becoming a Chartered Arbitrator in 2004. With the rapid and widespread adoption of adjudication in the UK
effectively displacing construction industry arbitration and litigation, it was natural to want to apply the practice and
procedure, knowledge, process and skills learned through arbitration to make adjudication decisions.
I have just started a second three year term as Chair of the Construction Industry Council (UK) Adjudicator Nominating
Body Management Board. I am a Centre for Effective Dispute Resolution (CEDR) and a Chartered Institute of
Arbitrator’s (CIArb) accredited mediator, experienced acting as mediator in multi-million Euro construction and
engineering disputes.
Jamie: What would you say are the main differences between adjudication in the UK and Ireland?
Niall: In arbitration it is widely recognised that allowing the parties to bifurcate their dispute into liability and quantum
can be the most cost effective and efficient way to proceed.  Over the last year I have been involved with two
substantial disputes referred to adjudication where the parties did not want a decision on an amount of money, rather
just a decision on principle.  In one dispute the parties asked the adjudicator to decide what the conditions of contract
were, and in another dispute the parties asked the adjudicator to decide the method of measurement which ought
properly to be applied to thermal insulation work undertaken.  The adjudicator’s decision on these matters would
allow the parties to move forward together.
For me the dominant and regrettable difference is that in the UK parties can refer any dispute, whereas in Ireland the
referral is limited to a payment dispute.  This limits party autonomy, it constrains adjudication and reduces its efficacy,
and can undermine the objective of the dispute being processed in the shortest time and at the lowest cost.
Jamie: Given that the Construction Contracts Act (2013) provides that a party to a construction contract
can only refer a payment dispute to adjudication.  In your own words, how would you define a payment
dispute?
Niall: In adjudication, the words ‘payment dispute’ do not have a specialised meaning.  In the ordinary use of the
English language, there is a dispute over payment if a party has refused to pay a sum claimed, or has denied that the
sum claimed is owed.
Adjudicators regularly face a jurisdictional challenge on the grounds 'No dispute has crystallised'. To avoid incurring
cost and time, referring parties should make sure that a dispute has crystallised and is suitable for adjudication.  For a
dispute to crystallise there must have been an opportunity for each of the parties to consider the position adopted by
the other and to formulate reasoned arguments.  If a claim is ignored a dispute can also crystallise.  There does not
have to be an express rejection of a claim, a dispute can arise through a period of silence.  The period of silence before
inferring there is a dispute depends heavily upon the specific circumstances.  Adjudicators should not adopt an overly
legalistic analysis of what the dispute between the parties is.
Jamie: The Act has facilitated the establishment of a panel of adjudicators.  What is the typical professional
background of an adjudicator and what do they typically charge?
Niall: Following a rigorous assessment process the Public Appointments Service recommended suitably qualified
persons for selection to the Department of Jobs, Enterprise and Innovation’s Panel of Adjudicators.  The Panel
comprises construction and legal professionals meeting the requirements set out in section 8 of the Construction
Contracts Act.
Becoming a construction adjudicator requires a significant investment in education and training, which is expensive
and time consuming.  Skilled adjudicators continue such investments so that they are always kept abreast with
developments and updates in the industry.  The parties in adjudication should expect to pay an hourly rate
commensurate with employing someone qualified to a senior level in their primary profession, and who has additional
expertise and skills.  Whereas there is some consistency as to the hourly charge of lawyer adjudicators, there is a wide
diversity in the hourly charge rate of construction profession adjudicators.  Some of whom take the view that as they
operate at the same level and perform the same work as lawyer adjudicators, plus they utilise their sector-specific
knowledge and expertise, the hourly charges should be similar or higher. Other construction profession adjudicators
charge an hourly rate consistent with the lower rates for providing architectural, engineering or quantity surveying
services.
Jamie: What are the most common grounds which you have come across for challenging an adjudicator’s
decision?
Niall: Jurisdiction is an adjudicator’s authority to make a decision.  The Notice of Intention confines the limits of the
adjudicator's jurisdiction.  If the adjudicator does not have jurisdiction, or acts in a way to lose jurisdiction, then a
competent court will not enforce any purported adjudicator’s decision.
In adjudication, it is common for the responding party to raise jurisdictional challenges, these will fall into two
categories.  The first are threshold jurisdictional challenges: for example a dispute has not crystallised, the adjudicator
has not been properly appointed, or there has been a document or procedural misstep.  The second are breach of
natural justice jurisdictional challenges: for example the adjudicator has given one party unfair advantage, was biased,
or used their own expert knowledge without allowing the parties to make submissions.
To help maintain confidence and good order in the adjudication system, the adjudicator should investigate any
challenge to their jurisdiction and arrive at a non-binding conclusion.  To avoid incurring unnecessary expense, the
best time to do that is as soon as possible.  It is a regrettable feature of adjudication that the adjudicator and the
parties spend a great deal of time and money dealing with jurisdiction.
Jamie: Under what circumstances would you hold an oral hearing in adjudication?
Niall: The adjudicator is empowered to decide the adjudication procedure.  For example, the adjudicator can take the
initiative in ascertaining the facts and the law necessary to reach a decision, make use of their own specialist
knowledge, and decide whether it is necessary or helpful in their decision-making to meet jointly with the parties and
their representatives.
Although most adjudication is on a documents only basis, there are times when the adjudicator or the parties want to
have a meeting.  Whereas the Construction Contracts Act uses the term ‘oral hearing’, in adjudication, I normally use
the term ‘meeting’ rather than ‘hearing’. In legal terminology, a ‘hearing’ is a legal proceeding where a disputed fact or
issue of law is tried and evidence is presented to help determine an issue.  The term ‘meeting’ connotes a less formal,
less adversarial proceeding, with more relaxed standards of evidence and process.
Any meeting should have a specific purpose.  A meeting can be helpful where the quality of submissions is
inadequate; there is conflicting evidence from experts or witnesses of fact, to inspect site based physical evidence, or
for other reasons.  If both parties want to have a meeting, I will accommodate their request, even if the meeting costs
will be large compared to the amount in dispute.  If only one party wants to have a meeting, I will accommodate its
request, only if the meeting will assist me in making my decision.
Jamie: In your experience, what is the single biggest mistake a referring party and a responding party can
make in adjudication?
Niall: Before referring your dispute to adjudication, you must decide that it is the best course of action for you.  Have
you really reached the ‘end of the road’ with negotiation, early neutral evaluation and mediation?  Have you learned
anything during those alternative dispute resolution procedures that helps inform your decision whether to use
adjudication, or what is the best time to do that?  For example, when you commence adjudication, will the other party
have a valid response that you owe them money, or will your referral to adjudication trigger the other party to
commence adjudication against you?  In addition, it makes little sense to invest energy and resources to prevail in
adjudication, and then a court judgment to enforce the adjudicator’s decision, if the other party will not have the
money to pay you.
Before commencing adjudication, you should audit your adjudication risk.  Risk audit is a process, which helps you
make sensible commercial decisions.  It highlights risks, their nature and scope, and allows you to determine how to
prevent or reduce the risks.  The biggest mistake that a referring party can make is not to undertake a formal audit of
risk.
The response is the responding party’s opportunity to refute all of the allegations that the referring party has made. It
should rebut the factual and legal claims advanced; it should explain the basis for the rebuttal by clarifying what the
facts are, and referring their effect to the contract and the law; it should set out full details of any cross-claims.
However, in adjudication the responding party will usually only have seven to fourteen days to prepare its response to
convince the adjudicator that there is a more plausible alternative story.
With good practice of construction management, much of the information required to prepare a response should be
readily available. The information required will be the same information that you have relied upon to reject the
referring party’s claims, and therefore should be on file. The biggest mistake a responding party can make is not to
contemporaneously document in detail with supporting evidence why it has not paid money claimed.
Jamie: In your experience, what are the biggest challenges that adjudicators face?
Niall: Acting as adjudicator is not for the faint hearted.  It can be a brutal process with many snares and traps set along
the way.  It is in the nature of some claims consultants, lawyers and parties to bully and routinely use intimidatory
tactics in adjudication. Parties will use tactics such as making spurious challenges as to jurisdiction, deliberately
seeking to confuse the adjudicator by the use of technical or esoteric legal arguments; threatening to take legal
action against the adjudicator or to report him to his professional institution. They seek extensions of time alleging
that the timetable is unfair and a breach of natural justice.  They use bellicose language.  They unreasonably refuse to
pay the adjudicator’s fees and expenses.
Jamie: How do you think contractual adjudication in Ireland will interact with statutory adjudication over
time?  Do you think that statutory adjudication will make the use of contractual adjudication (and
independent nominating bodies) more common?
Niall: Adjudication provisions are becoming widespread in contracts and situations where there is no statutory
entitlement.  As an engineer I have acted as adjudicator in several non-statutory adjudications, for example, in a multi-
million pound engineering and technology transfer dispute, and also in process engineering disputes.
For a more detailed discussion on the appointment of adjudicators by independent nominating bodies I would refer
the reader to the CIC Users' Guide to Adjudication: Ireland published on 26 July 2017.  The Users’ Guide to
Adjudication: Ireland is available for free download from CIC’s website here.  
Jamie: What are the main advantages and disadvantages of adjudication?
Niall: Arbitration and litigation are more expensive and time consuming than adjudication.  Where adjudication enjoys
the full backing of the courts, it expedites and facilitates the flow of money through the contractual chain.  
Adjudication is short lived and contemporary; if it takes place during the construction contract, it allows the parties to
modify their conduct or performance early.  Adjudication prevents small disputes becoming big disputes.  
Adjudication can be informal, and allows for self-representation.  Experience shows that an adjudicator’s decision is
often the final solution, or that it provides the parties with the basis to negotiate an alternative final solution
acceptable to them.
Jamie: There appears to be a reluctance amongst the construction industry in Ireland to embrace
adjudication in the same way it has done in the UK.  Why do you think that is?
Niall: In Ireland under the Construction Contracts Act, absent agreement between the parties, the adjudicator
appointment will be made by the Chairperson of the Panel appointed by the Minister responsible.  Based on
anticipated adjudication referrals during the first five years the Minister’s Panel was initially limited in size to some
thirty members.
In Malaysia the Kuala Lumpur Regional Centre for Arbitration (KLRCA) is the default adjudicator appointment body.  By
way of contrast, the total number of adjudicators empanelled by the KLRCA has increased from 363 as at 15 April
2016 to 446 as at 15 of April 2017.
Ireland has a wealth of construction and engineering ADR talent, and I believe that there is a sense of
disenfranchisement and exclusion from the opportunity to act as adjudicator.  Adjudication can quickly and
irrevocably upend the ADR landscape and status quo, and unfortunately this has contributed to many ‘thought
leaders’ rejecting or being unwilling to promote adjudication as an effective dispute resolution mechanism.  This is
doing a great disservice to clients, contractors and sub-contractors.  The irony of this rejection of promoting
adjudication is that with few adjudication referrals in Ireland, there is little incentive for the size of the Minister’s Panel
of Adjudicators to increase.
Jamie: Do you think that adjudication has the potential to become the main method of resolving
construction payment disputes in Ireland?
Niall: In 2012, when I went to Malaysia to undertake the training to be considered for the KLRCA panel of adjudicators
provided for under the Construction Industry Payment and Adjudication Act (CIPAA), there was cynicism as to whether
adjudication would be successful.  Malaysian people said that culturally, adjudication was not acceptable, we prefer to
mediate; adjudication will cause a loss of face, which is offensive and not tolerable; employers are vexatious, if I
adjudicate it will be the last time I work for that organisation; adjudication is not suitable for complex disputes,
because of tight timescale; adjudication is unsuitable for final account disputes; adjudication is uncertain and does not
give a final resolution of the dispute; there will be problems with enforcement, even if I win, the other party will not pay.
Notwithstanding the above concerns (and although Malaysia is considerably bigger than Ireland) it is worthwhile
noting that the CIPAA became law on 18 June 2012, and came into force on 15 April 2014.  To 31 December 2014 –
there were 29 adjudicator appointments; to 31 December 2015 – there were 199 adjudicator appointments; to 31
December 2016 – there were 461 adjudicator appointments; to 31 December 2017 – the KLRCA is forecasting 700
adjudicator appointments.
There is no cultural or structural impediment to the adoption of adjudication in the Republic of Ireland. Adjudication is
widely used in Northern Ireland, albeit more aggressively than in Great Britain.
If you are interested in learning more about adjudication please do not hesitate to contact Jamie Ritchie at
jritchie@lkshields.ie in the Projects and Construction team at LK Shields.
About the Author
Jamie Ritchie
Associate Solicitor
Jamie Ritchie is a commercially minded solicitor with extensive former industry experience
as a consultant in construction and procurement. He is also an Associate Member of the
Chartered Institute of Arbitrators.
T: +353 1 6385896 E: jritchie@lkshields.ie

More Related Content

What's hot

What’s new in Fla. Bar 02.24.17
What’s new in Fla. Bar 02.24.17What’s new in Fla. Bar 02.24.17
What’s new in Fla. Bar 02.24.17Arthur Garcia
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketFrancis Ho
 
Piddington CPD - Mediation - 9 November 2016 Final
Piddington CPD - Mediation - 9 November 2016 FinalPiddington CPD - Mediation - 9 November 2016 Final
Piddington CPD - Mediation - 9 November 2016 FinalAaron McDonald
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionJustin DeMerchant
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONOluwaseyi Bamigboye
 
Delivering unbundled legal services 2012
Delivering unbundled legal services  2012Delivering unbundled legal services  2012
Delivering unbundled legal services 2012Richard S. Granat
 
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...Association for Conflict Resolution (ACR)
 
Dispute resolution in construction
Dispute resolution in construction Dispute resolution in construction
Dispute resolution in construction MARTIN BURNS
 
Proportionality in Ediscovery
Proportionality in EdiscoveryProportionality in Ediscovery
Proportionality in EdiscoveryJosh Kubicki
 
In Dire Need of Resolution
In Dire Need of ResolutionIn Dire Need of Resolution
In Dire Need of ResolutionRoland Schroeder
 
Whitepaper: Legal Holds & Data Preservation 2014
Whitepaper: Legal Holds & Data Preservation 2014Whitepaper: Legal Holds & Data Preservation 2014
Whitepaper: Legal Holds & Data Preservation 2014Zapproved
 
Advantages and Disadvantages of Arbitration and Mediation
Advantages and Disadvantages of Arbitration and MediationAdvantages and Disadvantages of Arbitration and Mediation
Advantages and Disadvantages of Arbitration and MediationDementian Guschov
 

What's hot (17)

What’s new in Fla. Bar 02.24.17
What’s new in Fla. Bar 02.24.17What’s new in Fla. Bar 02.24.17
What’s new in Fla. Bar 02.24.17
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom Market
 
Piddington CPD - Mediation - 9 November 2016 Final
Piddington CPD - Mediation - 9 November 2016 FinalPiddington CPD - Mediation - 9 November 2016 Final
Piddington CPD - Mediation - 9 November 2016 Final
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
 
Delivering unbundled legal services 2012
Delivering unbundled legal services  2012Delivering unbundled legal services  2012
Delivering unbundled legal services 2012
 
Global Mediation Guide
Global Mediation Guide Global Mediation Guide
Global Mediation Guide
 
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
 
Priavte court
Priavte courtPriavte court
Priavte court
 
Dispute resolution in construction
Dispute resolution in construction Dispute resolution in construction
Dispute resolution in construction
 
A PROPOSED ROADMAP TO OPTIMISE THE
A PROPOSED ROADMAP TO OPTIMISE THEA PROPOSED ROADMAP TO OPTIMISE THE
A PROPOSED ROADMAP TO OPTIMISE THE
 
Proportionality in Ediscovery
Proportionality in EdiscoveryProportionality in Ediscovery
Proportionality in Ediscovery
 
ADR
ADRADR
ADR
 
In Dire Need of Resolution
In Dire Need of ResolutionIn Dire Need of Resolution
In Dire Need of Resolution
 
Whitepaper: Legal Holds & Data Preservation 2014
Whitepaper: Legal Holds & Data Preservation 2014Whitepaper: Legal Holds & Data Preservation 2014
Whitepaper: Legal Holds & Data Preservation 2014
 
Advantages and Disadvantages of Arbitration and Mediation
Advantages and Disadvantages of Arbitration and MediationAdvantages and Disadvantages of Arbitration and Mediation
Advantages and Disadvantages of Arbitration and Mediation
 
A d r
A d rA d r
A d r
 

Similar to Meet the Adjudicator

CONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'Brien
CONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'BrienCONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'Brien
CONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'BrienJohn FFF O'Brien
 
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...TheGimhan123
 
The REALTOR Code of Ethics New Member Orientation Program
The REALTOR Code of EthicsNew Member Orientation ProgramThe REALTOR Code of EthicsNew Member Orientation Program
The REALTOR Code of Ethics New Member Orientation Program Evangeline Yia
 
Writing Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu NwaigboWriting Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu NwaigboOnyeka Nwaigbo
 
North london lsca_tax_mediation_seminar
North london lsca_tax_mediation_seminarNorth london lsca_tax_mediation_seminar
North london lsca_tax_mediation_seminarchome4
 
ADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxzulkiflimohdzain1
 
ADR-converted.pdf
ADR-converted.pdfADR-converted.pdf
ADR-converted.pdfmallikmaro
 
Lecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdfLecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdfjonathan539518
 
Saving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationSaving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationOluwaseyi Bamigboye
 
What is Advisory ADR?
What is Advisory ADR? What is Advisory ADR?
What is Advisory ADR? adrchambers
 
Civil And Commercial Mediation
Civil And Commercial MediationCivil And Commercial Mediation
Civil And Commercial MediationIn Place Of Strife
 
Mitigating Litigation Risk at the Deal Table M&A Part II
Mitigating Litigation Risk at the Deal Table M&A Part II Mitigating Litigation Risk at the Deal Table M&A Part II
Mitigating Litigation Risk at the Deal Table M&A Part II Polsinelli PC
 
Resolving Investment Fraud Disputes
Resolving Investment Fraud DisputesResolving Investment Fraud Disputes
Resolving Investment Fraud Disputesblocklandsman
 
405693104-workload-of-a-lawyer-pptx.pptx
405693104-workload-of-a-lawyer-pptx.pptx405693104-workload-of-a-lawyer-pptx.pptx
405693104-workload-of-a-lawyer-pptx.pptxDarwin11
 
Advocates Edinburgh 081107
Advocates Edinburgh 081107Advocates Edinburgh 081107
Advocates Edinburgh 081107Chris_Makin
 

Similar to Meet the Adjudicator (18)

CONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'Brien
CONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'BrienCONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'Brien
CONSTRUCTION Oct16 Wars Behind Closed Doors John Farage O'Brien
 
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...Alternative  Dispute Resolution methods  Level III - B.Sc QS (Salford) March ...
Alternative Dispute Resolution methods Level III - B.Sc QS (Salford) March ...
 
The REALTOR Code of Ethics New Member Orientation Program
The REALTOR Code of EthicsNew Member Orientation ProgramThe REALTOR Code of EthicsNew Member Orientation Program
The REALTOR Code of Ethics New Member Orientation Program
 
Arbitration notes
Arbitration notesArbitration notes
Arbitration notes
 
Writing Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu NwaigboWriting Sample 3 - Onyekachukwu Nwaigbo
Writing Sample 3 - Onyekachukwu Nwaigbo
 
Arbitration Act in Bangladesh
Arbitration Act in BangladeshArbitration Act in Bangladesh
Arbitration Act in Bangladesh
 
North london lsca_tax_mediation_seminar
North london lsca_tax_mediation_seminarNorth london lsca_tax_mediation_seminar
North london lsca_tax_mediation_seminar
 
ADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptxADR Final - short version - 16-10-2023.pptx
ADR Final - short version - 16-10-2023.pptx
 
ADR-converted.pdf
ADR-converted.pdfADR-converted.pdf
ADR-converted.pdf
 
Lecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdfLecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdf
 
January 2018 newsletter
January 2018 newsletterJanuary 2018 newsletter
January 2018 newsletter
 
Saving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial ArbitrationSaving Time and Costs in Commercial Arbitration
Saving Time and Costs in Commercial Arbitration
 
What is Advisory ADR?
What is Advisory ADR? What is Advisory ADR?
What is Advisory ADR?
 
Civil And Commercial Mediation
Civil And Commercial MediationCivil And Commercial Mediation
Civil And Commercial Mediation
 
Mitigating Litigation Risk at the Deal Table M&A Part II
Mitigating Litigation Risk at the Deal Table M&A Part II Mitigating Litigation Risk at the Deal Table M&A Part II
Mitigating Litigation Risk at the Deal Table M&A Part II
 
Resolving Investment Fraud Disputes
Resolving Investment Fraud DisputesResolving Investment Fraud Disputes
Resolving Investment Fraud Disputes
 
405693104-workload-of-a-lawyer-pptx.pptx
405693104-workload-of-a-lawyer-pptx.pptx405693104-workload-of-a-lawyer-pptx.pptx
405693104-workload-of-a-lawyer-pptx.pptx
 
Advocates Edinburgh 081107
Advocates Edinburgh 081107Advocates Edinburgh 081107
Advocates Edinburgh 081107
 

Recently uploaded

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 

Recently uploaded (20)

🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 

Meet the Adjudicator

  • 1. PROJECTS Meet the Adjudicator: LK Shields interviews Construction Adjudicator Niall Lawless by Jamie Ritchie
  • 2. Meet the Adjudicator: LK Shields interviews Construction Adjudicator Niall Lawless 29th September 2017 | by Jamie Ritchie “Adjudication can quickly and irrevocably upend the ADR landscape and status quo, and unfortunately this has contributed to many ‘thought leaders’ rejecting or being unwilling to promote adjudication as an effective dispute resolution mechanism. This is doing a great disservice to clients, contractors and sub-contractors.” Niall Lawless Jamie Ritchie, Associate Solicitor (Projects, Construction and Energy) at LK Shields is a practitioner with experience of acting on behalf of claimants (referring parties) and defendants (responding parties) in construction adjudication. In order to help promote  awareness of this form of dispute resolution within the Irish construction industry, Jamie recently interviewed Niall Lawless (Irish Construction Adjudicator and co-author of the CIC Users’ Guide to Adjudication) in order to get his take on the future of this currently underutilised process. Below is a transcript of that interview. Jamie: Niall, thank you for taking the time to talk to us.  In your own words, how would you define adjudication? Niall: In Ireland adjudication provides the parties to a construction contract with a process whereby an independent third party makes a quick decision when the parties are in disagreement over payment.  The adjudicator’s decision is binding until determined by arbitration or litigation and the parties may agree that the adjudicator’s decision is final and binding. Jamie: You have many years’ experience of adjudication across multiple jurisdictions. Tell us a bit about your experience and your background?  Niall: My early ADR experience was as a Chartered Building Services Engineer and Mechanical Engineer acting as expert witness at all pleading stages and giving evidence under examination in arbitration and the Technology and Construction Court in London numerous times. That led me to Fellowship of the Chartered Institute of Arbitrators in 2001, and becoming a Chartered Arbitrator in 2004. With the rapid and widespread adoption of adjudication in the UK effectively displacing construction industry arbitration and litigation, it was natural to want to apply the practice and procedure, knowledge, process and skills learned through arbitration to make adjudication decisions. I have just started a second three year term as Chair of the Construction Industry Council (UK) Adjudicator Nominating Body Management Board. I am a Centre for Effective Dispute Resolution (CEDR) and a Chartered Institute of Arbitrator’s (CIArb) accredited mediator, experienced acting as mediator in multi-million Euro construction and
  • 3. engineering disputes. Jamie: What would you say are the main differences between adjudication in the UK and Ireland? Niall: In arbitration it is widely recognised that allowing the parties to bifurcate their dispute into liability and quantum can be the most cost effective and efficient way to proceed.  Over the last year I have been involved with two substantial disputes referred to adjudication where the parties did not want a decision on an amount of money, rather just a decision on principle.  In one dispute the parties asked the adjudicator to decide what the conditions of contract were, and in another dispute the parties asked the adjudicator to decide the method of measurement which ought properly to be applied to thermal insulation work undertaken.  The adjudicator’s decision on these matters would allow the parties to move forward together. For me the dominant and regrettable difference is that in the UK parties can refer any dispute, whereas in Ireland the referral is limited to a payment dispute.  This limits party autonomy, it constrains adjudication and reduces its efficacy, and can undermine the objective of the dispute being processed in the shortest time and at the lowest cost. Jamie: Given that the Construction Contracts Act (2013) provides that a party to a construction contract can only refer a payment dispute to adjudication.  In your own words, how would you define a payment dispute? Niall: In adjudication, the words ‘payment dispute’ do not have a specialised meaning.  In the ordinary use of the English language, there is a dispute over payment if a party has refused to pay a sum claimed, or has denied that the sum claimed is owed. Adjudicators regularly face a jurisdictional challenge on the grounds 'No dispute has crystallised'. To avoid incurring cost and time, referring parties should make sure that a dispute has crystallised and is suitable for adjudication.  For a dispute to crystallise there must have been an opportunity for each of the parties to consider the position adopted by the other and to formulate reasoned arguments.  If a claim is ignored a dispute can also crystallise.  There does not have to be an express rejection of a claim, a dispute can arise through a period of silence.  The period of silence before inferring there is a dispute depends heavily upon the specific circumstances.  Adjudicators should not adopt an overly legalistic analysis of what the dispute between the parties is. Jamie: The Act has facilitated the establishment of a panel of adjudicators.  What is the typical professional background of an adjudicator and what do they typically charge? Niall: Following a rigorous assessment process the Public Appointments Service recommended suitably qualified persons for selection to the Department of Jobs, Enterprise and Innovation’s Panel of Adjudicators.  The Panel comprises construction and legal professionals meeting the requirements set out in section 8 of the Construction Contracts Act. Becoming a construction adjudicator requires a significant investment in education and training, which is expensive and time consuming.  Skilled adjudicators continue such investments so that they are always kept abreast with developments and updates in the industry.  The parties in adjudication should expect to pay an hourly rate commensurate with employing someone qualified to a senior level in their primary profession, and who has additional expertise and skills.  Whereas there is some consistency as to the hourly charge of lawyer adjudicators, there is a wide diversity in the hourly charge rate of construction profession adjudicators.  Some of whom take the view that as they
  • 4. operate at the same level and perform the same work as lawyer adjudicators, plus they utilise their sector-specific knowledge and expertise, the hourly charges should be similar or higher. Other construction profession adjudicators charge an hourly rate consistent with the lower rates for providing architectural, engineering or quantity surveying services. Jamie: What are the most common grounds which you have come across for challenging an adjudicator’s decision? Niall: Jurisdiction is an adjudicator’s authority to make a decision.  The Notice of Intention confines the limits of the adjudicator's jurisdiction.  If the adjudicator does not have jurisdiction, or acts in a way to lose jurisdiction, then a competent court will not enforce any purported adjudicator’s decision. In adjudication, it is common for the responding party to raise jurisdictional challenges, these will fall into two categories.  The first are threshold jurisdictional challenges: for example a dispute has not crystallised, the adjudicator has not been properly appointed, or there has been a document or procedural misstep.  The second are breach of natural justice jurisdictional challenges: for example the adjudicator has given one party unfair advantage, was biased, or used their own expert knowledge without allowing the parties to make submissions. To help maintain confidence and good order in the adjudication system, the adjudicator should investigate any challenge to their jurisdiction and arrive at a non-binding conclusion.  To avoid incurring unnecessary expense, the best time to do that is as soon as possible.  It is a regrettable feature of adjudication that the adjudicator and the parties spend a great deal of time and money dealing with jurisdiction. Jamie: Under what circumstances would you hold an oral hearing in adjudication? Niall: The adjudicator is empowered to decide the adjudication procedure.  For example, the adjudicator can take the initiative in ascertaining the facts and the law necessary to reach a decision, make use of their own specialist knowledge, and decide whether it is necessary or helpful in their decision-making to meet jointly with the parties and their representatives. Although most adjudication is on a documents only basis, there are times when the adjudicator or the parties want to have a meeting.  Whereas the Construction Contracts Act uses the term ‘oral hearing’, in adjudication, I normally use the term ‘meeting’ rather than ‘hearing’. In legal terminology, a ‘hearing’ is a legal proceeding where a disputed fact or issue of law is tried and evidence is presented to help determine an issue.  The term ‘meeting’ connotes a less formal, less adversarial proceeding, with more relaxed standards of evidence and process. Any meeting should have a specific purpose.  A meeting can be helpful where the quality of submissions is inadequate; there is conflicting evidence from experts or witnesses of fact, to inspect site based physical evidence, or for other reasons.  If both parties want to have a meeting, I will accommodate their request, even if the meeting costs will be large compared to the amount in dispute.  If only one party wants to have a meeting, I will accommodate its request, only if the meeting will assist me in making my decision. Jamie: In your experience, what is the single biggest mistake a referring party and a responding party can make in adjudication? Niall: Before referring your dispute to adjudication, you must decide that it is the best course of action for you.  Have
  • 5. you really reached the ‘end of the road’ with negotiation, early neutral evaluation and mediation?  Have you learned anything during those alternative dispute resolution procedures that helps inform your decision whether to use adjudication, or what is the best time to do that?  For example, when you commence adjudication, will the other party have a valid response that you owe them money, or will your referral to adjudication trigger the other party to commence adjudication against you?  In addition, it makes little sense to invest energy and resources to prevail in adjudication, and then a court judgment to enforce the adjudicator’s decision, if the other party will not have the money to pay you. Before commencing adjudication, you should audit your adjudication risk.  Risk audit is a process, which helps you make sensible commercial decisions.  It highlights risks, their nature and scope, and allows you to determine how to prevent or reduce the risks.  The biggest mistake that a referring party can make is not to undertake a formal audit of risk. The response is the responding party’s opportunity to refute all of the allegations that the referring party has made. It should rebut the factual and legal claims advanced; it should explain the basis for the rebuttal by clarifying what the facts are, and referring their effect to the contract and the law; it should set out full details of any cross-claims. However, in adjudication the responding party will usually only have seven to fourteen days to prepare its response to convince the adjudicator that there is a more plausible alternative story. With good practice of construction management, much of the information required to prepare a response should be readily available. The information required will be the same information that you have relied upon to reject the referring party’s claims, and therefore should be on file. The biggest mistake a responding party can make is not to contemporaneously document in detail with supporting evidence why it has not paid money claimed. Jamie: In your experience, what are the biggest challenges that adjudicators face? Niall: Acting as adjudicator is not for the faint hearted.  It can be a brutal process with many snares and traps set along the way.  It is in the nature of some claims consultants, lawyers and parties to bully and routinely use intimidatory tactics in adjudication. Parties will use tactics such as making spurious challenges as to jurisdiction, deliberately seeking to confuse the adjudicator by the use of technical or esoteric legal arguments; threatening to take legal action against the adjudicator or to report him to his professional institution. They seek extensions of time alleging that the timetable is unfair and a breach of natural justice.  They use bellicose language.  They unreasonably refuse to pay the adjudicator’s fees and expenses. Jamie: How do you think contractual adjudication in Ireland will interact with statutory adjudication over time?  Do you think that statutory adjudication will make the use of contractual adjudication (and independent nominating bodies) more common? Niall: Adjudication provisions are becoming widespread in contracts and situations where there is no statutory entitlement.  As an engineer I have acted as adjudicator in several non-statutory adjudications, for example, in a multi- million pound engineering and technology transfer dispute, and also in process engineering disputes. For a more detailed discussion on the appointment of adjudicators by independent nominating bodies I would refer the reader to the CIC Users' Guide to Adjudication: Ireland published on 26 July 2017.  The Users’ Guide to Adjudication: Ireland is available for free download from CIC’s website here.  
  • 6. Jamie: What are the main advantages and disadvantages of adjudication? Niall: Arbitration and litigation are more expensive and time consuming than adjudication.  Where adjudication enjoys the full backing of the courts, it expedites and facilitates the flow of money through the contractual chain.   Adjudication is short lived and contemporary; if it takes place during the construction contract, it allows the parties to modify their conduct or performance early.  Adjudication prevents small disputes becoming big disputes.   Adjudication can be informal, and allows for self-representation.  Experience shows that an adjudicator’s decision is often the final solution, or that it provides the parties with the basis to negotiate an alternative final solution acceptable to them. Jamie: There appears to be a reluctance amongst the construction industry in Ireland to embrace adjudication in the same way it has done in the UK.  Why do you think that is? Niall: In Ireland under the Construction Contracts Act, absent agreement between the parties, the adjudicator appointment will be made by the Chairperson of the Panel appointed by the Minister responsible.  Based on anticipated adjudication referrals during the first five years the Minister’s Panel was initially limited in size to some thirty members. In Malaysia the Kuala Lumpur Regional Centre for Arbitration (KLRCA) is the default adjudicator appointment body.  By way of contrast, the total number of adjudicators empanelled by the KLRCA has increased from 363 as at 15 April 2016 to 446 as at 15 of April 2017. Ireland has a wealth of construction and engineering ADR talent, and I believe that there is a sense of disenfranchisement and exclusion from the opportunity to act as adjudicator.  Adjudication can quickly and irrevocably upend the ADR landscape and status quo, and unfortunately this has contributed to many ‘thought leaders’ rejecting or being unwilling to promote adjudication as an effective dispute resolution mechanism.  This is doing a great disservice to clients, contractors and sub-contractors.  The irony of this rejection of promoting adjudication is that with few adjudication referrals in Ireland, there is little incentive for the size of the Minister’s Panel of Adjudicators to increase. Jamie: Do you think that adjudication has the potential to become the main method of resolving construction payment disputes in Ireland? Niall: In 2012, when I went to Malaysia to undertake the training to be considered for the KLRCA panel of adjudicators provided for under the Construction Industry Payment and Adjudication Act (CIPAA), there was cynicism as to whether adjudication would be successful.  Malaysian people said that culturally, adjudication was not acceptable, we prefer to mediate; adjudication will cause a loss of face, which is offensive and not tolerable; employers are vexatious, if I adjudicate it will be the last time I work for that organisation; adjudication is not suitable for complex disputes, because of tight timescale; adjudication is unsuitable for final account disputes; adjudication is uncertain and does not give a final resolution of the dispute; there will be problems with enforcement, even if I win, the other party will not pay. Notwithstanding the above concerns (and although Malaysia is considerably bigger than Ireland) it is worthwhile noting that the CIPAA became law on 18 June 2012, and came into force on 15 April 2014.  To 31 December 2014 – there were 29 adjudicator appointments; to 31 December 2015 – there were 199 adjudicator appointments; to 31 December 2016 – there were 461 adjudicator appointments; to 31 December 2017 – the KLRCA is forecasting 700
  • 7. adjudicator appointments. There is no cultural or structural impediment to the adoption of adjudication in the Republic of Ireland. Adjudication is widely used in Northern Ireland, albeit more aggressively than in Great Britain. If you are interested in learning more about adjudication please do not hesitate to contact Jamie Ritchie at jritchie@lkshields.ie in the Projects and Construction team at LK Shields.
  • 8. About the Author Jamie Ritchie Associate Solicitor Jamie Ritchie is a commercially minded solicitor with extensive former industry experience as a consultant in construction and procurement. He is also an Associate Member of the Chartered Institute of Arbitrators. T: +353 1 6385896 E: jritchie@lkshields.ie