BLUEPRINT PELAKSANAAN
PROJEK / PROGRAM PEMBANGUNAN RISDA
ROLLING PLAN 4 TAHUN 2024, RMKe-12
NEGERI PAHANG
Perkara (%) JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
KPI UMUM PENCAPAIAN 2024
RUMUSAN
AGIHAN SILING VS POTENSI NEGERI
PROJEK / PROGRAM / SUB-PROGRAM PM
AGIHAN SILING POTENSI NEGERI
RM FIZ RM FIZ
1 PEMB. KAW. BERTANAM GETAH PK 45,000,000
1.1 TAN. SEM. GETAH RMKe-12 1.1.1 BAN. SEMASA BTSP 20,508,600 2,660 13,045,320.00 1,692.00
1.1.2 BAN. BERTURUT BTSP 5,156,780 2,775 3,990,288.95 2,774.88
JUMLAH KECIL BTSP 25,665,380 5,435 17,035,608.95 4,466.88
1.2 TAN. SEM. GETAH SAMB. BTSP 2,023,500 1,721 2,019,711.12 1,726.39
1.3 BAN. ANG. PEDLM BBIP 50,120 160 35,041.50 114.00
1.4 BAN. TBG. PELANCARAN (BTP) BTSP 10,000 5 8,000.00 81.77
1.5 PENGEMBANGAN 1.5.1 KHID. PGM BPPT 1,492,390 21,800 1,767,670.00 27,850.00
1.5.2 GAP BPPT 406,460 10,307 331,180.00 12,812.00
1.5.3 PIPK BPPT 1,101,150 14,721 901,150.00 1,200.00
JUMLAH KECIL BPPT 3,000,000 46,828 2,437,250.00 48,946.00
1.5.4 IIP BTSP 814,000 1,414 1,255,752.75 1,791.64
1.6 PRASARANA ASAS PERTANIAN (PAP) BTSP 4,798,000 2,180 4,551,250.00 441.66
1.7 AKT. EKO. TAMB. & PEMB. USA. 1.7.1 AET BPU 4,575,700 360 3,778,000.00 290.00
(AET & PU) 1.7.2 PEMB. USA. BPU 1,888,300 660 1,978,000.00 490.00
1.7.3 JELITA@RISDA BPU 2,175,000 145 2,175,000.00 145.00
JUMLAH KECIL BPU 8,639,000 1,165 7,931,000.00 925.00
2 PEMB. SEMULA HASIL BAHARU 4,020,000
2.1 AGROMAKANAN BPK 4,020,000 201 4,020,000.00 232.00
2.2 KHID. LAT. PK 2.2.1 KHID. LAT. PK BL 0 0
2.2.2 KAJ. IMP. BDPS 0 0
2.3 ICT PK RISDA BTM 0 0
3 RAWAT & CEGAH PENYAKIT LDP BPPT 2,050,000 2,411 2,121,984.00 3,316.00
4 PEN. PROD. GETAH (PROGET) PEKEBUN KECIL 5,000,000
4.1 PENG. HASIL GETAH MTG (PHGM) 4.1.1 BAN. SEMASA BPP 4,207,500 1,650 4,302,535.53 1,687.27
4.2 GETAH MATANG-TANAM SEMULA (GMTS) BPP 58,740 147 60,000.00 150.00
4.3 INSENTIF PEDALAMAN MATANG (IPM) BPP 18,000 90 2,000.00 10.00
4.4 FAS. PEMASARAN GETAH (FASGET) 4.4.1 FASGET BPP 65,000 2 196,000.00 6.00
4.4.2 PL BPP 0 0 999,800.00
4.4.3 RKPK BTSP 598,560 296 546,671.78 202.00
4.4.4 IPS BPP 52,200 29 95,400.00 3.00
JUMLAH KECIL BPP 715,760 1,837,871.78 211.00
5 PEN. PROD. LATEKS (PROTEKS) PEKEBUN KECIL 160,000
5.1 INS. PROD. LATEKS (INTEKS) BPP 71,600 36 33,181.90 66.36
5.2 GERAN PEMASARAN LATEKS (GPL) BPP 20,000 2 15,000.00 2.00
5.3 INS. GALAKAN TENAGA KERJA LATEKS (GTEKS) BPP 68,400 19 90,000.00 21.00
6 BANTUAN MUSIM TENGKUJUH 19,389,600 24,237 14,538,400.00 18,173.00
JUMLAH KESELURUHAN 75,619,600 62,857,337.55 67,385.97
OVERALL
PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12
SUB-PROGRAM 1.1.1 : SEMASA
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
Peruntukkan Peruntukkan diterima ikut sukuan
Minta peruntukkan diberi pada
sukuan pertama dan kedua atau
diberi sekali gus tanpa sukuan
Bekalan Benih - saiz benih tidak sama seperti LO yang dikeluarkan
Minta dikembalikan perbezaa nilai
ke akaun pemilik dalam ipower bagi
ansuran seterusnya
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12
SUB-PROGRAM 1.1.1 : SEMASA
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 1,387,800.00 180
3 PRD - TEMERLOH 1,734,750.00 225.00
4 PRD - PAHANG TIMUR 1,804,140.00 234.00
5 PRD -BERA 20,508,600 2,660.00 1,526,580.00 198.0
6 PRD - MARAN 1,387,800.00 180
7 PRD - RAUB 1,734,750.00 225
8 PRD - BENTONG 1,387,800.00 180
9 PRD - LIPIS 2,081,700.00 270
10 IKPK KG. AWAH, PAHANG
JUMLAH 13,045,320.00 1692.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12
SUB-PROGRAM 1.1.2 : BERTURUT
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
Peruntukkan Peruntukkan diterima ikut sukuan
Minta peruntukkan diberi pada
sukuan pertama dan kedua atau
diberi sekali gus tanpa sukuan
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12
SUB-PROGRAM 1.1.2 : BERTURUT
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 306,981.84 219.3887
3 PRD - TEMERLOH 464,986.66 316.8372
4 PRD - PAHANG TIMUR 511,854.75 357.1777
5 PRD -BERA 5,156,780 2,775 559,171.39 393.80
6 PRD - MARAN 606,544.15 414.9692
7 PRD - RAUB 517,243.50 360.5866
8 PRD - BENTONG 369,419.80 246.8861
9 PRD - LIPIS 654,086.86 465.23788
10 IKPK KG. AWAH, PAHANG
JUMLAH 3,990,288.95 2,774.88
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.2 : TANAM SEMULA GETAH SAMBUNGAN (TSGS)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
Peruntukkan Peruntukkan diterima ikut sukuan
Minta peruntukkan diberi pada
sukuan pertama dan kedua atau
diberi sekali gus tanpa sukuan
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.2 : TANAM SEMULA GETAH SAMBUNGAN (TSGS)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 172,845.37 149.46
3 PRD - TEMERLOH 357,917.58 306.48
4 PRD - PAHANG TIMUR 316,156.52 265.46
5 PRD -BERA 2,023,500 1,721 318,524.99 271.67
6 PRD - MARAN 218,343.79 189.66
7 PRD - RAUB 137,244.58 117.74
8 PRD - BENTONG 97,883.56 83.44
9 PRD - LIPIS 400,794.73 342.47
10 IKPK KG. AWAH, PAHANG
JUMLAH 2,019,711.12 1726.3895
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.3 : BANTUAN ANGKUTAN KAWASAN PEDALAMAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal
Perbelanjaan
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.3 : BANTUAN ANGKUTAN KAWASAN PEDALAMAN
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 35,041.50 114
3 PRD - TEMERLOH
4 PRD - PAHANG TIMUR
5 PRD -BERA 50,120 160
6 PRD - MARAN
7 PRD - RAUB
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 35,041.50 114
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.4 : BANTUAN TABUNG PELANCARAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.4 : BANTUAN TABUNG PELANCARAN
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(J/K TSB)
KEWANGAN
(RM)
FIZIKAL
(J/K TSB)
KEWANGAN
(RM)
FIZIKAL
(J/K TSB)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT
3 PRD - TEMERLOH 4,000.00 44.56
4 PRD - PAHANG TIMUR
5 PRD -BERA 10,000 5
6 PRD - MARAN 4,000.00 37.21
7 PRD - RAUB
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 8,000.00 81.77
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.1 : KHIDMAT PENGEMBANGAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.1 : KHIDMAT PENGEMBANGAN
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
1 PRN - NEGERI PAHANG 747,670.00 2,200.00
2 PRD - JERANTUT 107,000.00 2,325.00
3 PRD - TEMERLOH 148,000.00 4,320.00
4 PRD - PAHANG TIMUR 148,000.00 3,780.00
5 PRD -BERA 1,492,390 21,800 107,000.00 2,325.00
6 PRD - MARAN 107,000.00 2,325.00
7 PRD - RAUB 148,000.00 4,320.00
8 PRD - BENTONG 107,000.00 2,325.00
9 PRD - LIPIS 148,000.00 3,930.00
10 IKPK KG. AWAH, PAHANG
JUMLAH 1,767,670.00 27,850.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.2 : GAP
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
PPP kurang ilmu mengenai GAP PPP baru dan kurang mahir dalam perlaksanaan GAP Kursus GAP secara kerap.
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.2 : GAP
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
1 PRN - NEGERI PAHANG 20,000.00 200
2 PRD - JERANTUT 30,640.00 1,227.00
3 PRD - TEMERLOH 60,360.00 2,118.00
4 PRD - PAHANG TIMUR 37,620.00 1,589.00
5 PRD -BERA 406,460 10,307 32,500.00 1,405.00
6 PRD - MARAN 33,420.00 1,379.00
7 PRD - RAUB 32,200.00 1,306.00
8 PRD - BENTONG 40,580.00 1,725.00
9 PRD - LIPIS 43,860.00 1,863.00
10 IKPK KG. AWAH, PAHANG
JUMLAH 331,180.00 12,812.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.3 : PEMBANGUNAN INSTITUSI PEKEBUN KECIL (PIPK)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
Tuisyen Rakyat Selaraskan peruntukkan dengan tuntutan di Unit Kewangan
Agihan peruntukkan perlu selaras
dengan takwim kalendar
persekolahan
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.3 : PEMBANGUNAN INSTITUSI PEKEBUN KECIL (PIPK)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
1 PRN - NEGERI PAHANG 194,000.00 43
2 PRD - JERANTUT 54,700.00 86.00
3 PRD - TEMERLOH 127,400.00 232.00
4 PRD - PAHANG TIMUR 87,450.00 147.00
5 PRD -BERA 1,101,150 14,721 91,400.00 112.00
6 PRD - MARAN 72,700.00 146.00
7 PRD - RAUB 116,600.00 200.00
8 PRD - BENTONG 54,700.00 86.00
9 PRD - LIPIS 102,200.00 148.00
10 IKPK KG. AWAH, PAHANG
JUMLAH 901,150.00 1,200.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.4 : INSENTIF INPUT PERTANIAN (IIP)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.5 : PENGEMBANGAN
SUB-PROGRAM 1.5.4 : INSENTIF INPUT PERTANIAN (IIP)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 197,908.37 149.46
3 PRD - TEMERLOH 357,917.58 306.48
4 PRD - PAHANG TIMUR 99,171.60 265.46
5 PRD -BERA 814,000 1,414 211,185.00 356.90
6 PRD - MARAN 116,909.80 211.77
7 PRD - RAUB 55,987.50 117.74
8 PRD - BENTONG 48,324.60 83.44
9 PRD - LIPIS 168,348.30 300.38
10 IKPK KG. AWAH, PAHANG
JUMLAH 1,255,752.75 1,791.64
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.6 : PRASARANA ASAS PERTANIAN (PAP)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
Peruntukkan Nilai yang diterima tidak sama dengan keluasan saiz projek
Mohon peruntukkan diberi pada
sukuan pertama bagi mengelakkan
kerja-kerja prasarana pada hujung
tahun
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.6 : PRASARANA ASAS PERTANIAN (PAP)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 599,750.00 24.61
3 PRD - TEMERLOH 599,750.00 14.94
4 PRD - PAHANG TIMUR 605,750.00 318.00
5 PRD -BERA 4,798,000 2,180 600,000.00 17.50
6 PRD - MARAN 400,000.00 10.00
7 PRD - RAUB 850,000.00 23.60
8 PRD - BENTONG 400,000.00 10.55
9 PRD - LIPIS 496,000.00 22.46
10 IKPK KG. AWAH, PAHANG
JUMLAH 4,551,250.00 441.66
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN
SUB-PROGRAM 1.7.1 : AKTIVITI EKONOMI TAMBAHAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN
SUB-PROGRAM 1.7.1 : AKTIVITI EKONOMI TAMBAHAN
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 486,000.00 37
3 PRD - TEMERLOH 486,000.00 37
4 PRD - PAHANG TIMUR 446,000.00 34
5 PRD -BERA 4,575,700 360 466,000.00 36
6 PRD - MARAN 446,000.00 34
7 PRD - RAUB 486,000.00 37
8 PRD - BENTONG 476,000.00 38
9 PRD - LIPIS 486,000.00 37
10 IKPK KG. AWAH, PAHANG
JUMLAH 3,778,000.00 290.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN
SUB-PROGRAM 1.7.2 : PEMBANGUNAN USAHAWAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN
SUB-PROGRAM 1.7.2 : PEMBANGUNAN USAHAWAN
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
1 PRN - NEGERI PAHANG 653,000.00 381
2 PRD - JERANTUT 205,000.00 15
3 PRD - TEMERLOH 160,000.00 14
4 PRD - PAHANG TIMUR 160,000.00 14
5 PRD -BERA 1,888,300 660 150,000.00 13
6 PRD - MARAN 200,000.00 14
7 PRD - RAUB 150,000.00 13
8 PRD - BENTONG 150,000.00 13
9 PRD - LIPIS 150,000.00 13
10 IKPK KG. AWAH, PAHANG
JUMLAH 1,978,000.00 490.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN
SUB-PROGRAM 1.7. : JELITA@RISDA
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN
SUB-PROGRAM 1.7.3 : JELITA
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
KEWANGAN
(RM)
FIZIKAL
(USA. PK)
1 PRN - NEGERI PAHANG 2,175,000.00 145.00
2 PRD - JERANTUT
3 PRD - TEMERLOH
4 PRD - PAHANG TIMUR
5 PRD -BERA 1,888,300 660
6 PRD - MARAN
7 PRD - RAUB
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 2,175,000.00 145.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 2.1 : AGROMAKANAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 2.1 : AGROMAKANAN
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
KEWANGAN
(RM)
FIZIKAL
(ORG PK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 460,000.00 10.00
3 PRD - TEMERLOH 500,000.00 26.00
4 PRD - PAHANG TIMUR 520,000.00 48.00
5 PRD -BERA 4,020,000 201 500,000.00 37.00
6 PRD - MARAN 460,000.00 26.00
7 PRD - RAUB 660,000.00 33.00
8 PRD - BENTONG 460,000.00 26.00
9 PRD - LIPIS 460,000.00 21.00
10 IKPK KG. AWAH, PAHANG
JUMLAH 4,020,000.00 232.00
MENGIKUT PT NEGERI PAHANG
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal
Perbelanjaan
CADANGAN UNJURAN PENCAPAIAN (%)
PROGRAM 2.2 : KHIDMAT LATIHAN PEKEBUN KECIL
SUB-PROGRAM 2.2.1 : KHIDMAT LATIHAN PEKEBUN KECIL
MAIN
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal
Perbelanjaan
CADANGAN UNJURAN PENCAPAIAN (%)
PROGRAM 2.2 : KHIDMAT LATIHAN PEKEBUN KECIL
SUB-PROGRAM 2.2.2 : KAJIAN IMPAK
MAIN
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal
Perbelanjaan
CADANGAN UNJURAN PENCAPAIAN (%)
PROGRAM 2.3 : ICT PEKEBUN KECIL RISDA
MAIN
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 3.1 : RAWAT & CEGAH PENYAKIT LURUHAN DAUN PESTALOTIOPSIS
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
Cuaca Sukar melakukan semburan ketika musim hujan (musim tengkujuh) Elakkan peruntukkan hujung tahun
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 3.1 : RAWAT & CEGAH PENYAKIT LURUHAN DAUN PESTALOTIOPSIS
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 144,000.00 225.00
3 PRD - TEMERLOH 273,600.00 428.00
4 PRD - PAHANG TIMUR 281,664.00 440.00
5 PRD -BERA 2,050,000 2,411 292,608.00 457.00
6 PRD - MARAN 259,200.00 405.00
7 PRD - RAUB 282,240.00 441.00
8 PRD - BENTONG 253,440.00 396.00
9 PRD - LIPIS 335,232.00 524.00
10 IKPK KG. AWAH, PAHANG
JUMLAH 2,121,984.00 3,316.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 4.1 : PENGELUARAN HASIL GETAH MATANG (PHGM)
SUB-PROGRAM 4.1.1 : ANSURAN 1
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 4.1 : PENGELUARAN HASIL GETAH MATANG (PHGM)
SUB-PROGRAM 4.1.1 : ANSURAN 1
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 280,588.49 110.03
3 PRD - TEMERLOH 1,493,147.15 585.55
4 PRD - PAHANG TIMUR 638,552.90 250.41
5 PRD -BERA 4,207,500 1,650 510,000.00 200.00
6 PRD - MARAN 382,500.00 150.00
7 PRD - RAUB 306,000.00 120.00
8 PRD - BENTONG 329,638.50 129.27
9 PRD - LIPIS 362,108.50 142
10 IKPK KG. AWAH, PAHANG
JUMLAH 4,302,535.53 1,687.27
MENGIKUT PT NEGERI PAHANG
PROGRAM 4.2 : GETAH MATANG-TANAM SEMULA (GMTS)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 4.2 : GETAH MATANG-TANAM SEMULA (GMTS)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 6,000.00 15.00
3 PRD - TEMERLOH 9,000.00 22.50
4 PRD - PAHANG TIMUR 7,800.00 19.50
5 PRD -BERA 58,740 147 6,600.00 16.50
6 PRD - MARAN 6,600.00 16.50
7 PRD - RAUB 9,000.00 22.50
8 PRD - BENTONG 6,000.00 15.00
9 PRD - LIPIS 9,000.00 22.50
10 IKPK KG. AWAH, PAHANG
JUMLAH 60,000.00 150.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 4.3 : INSENTIF PEDALAMAN MATANG (IPM)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 4.3 : INSENTIF PEDALAMAN MATANG (IPM)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 2,000.00 10
3 PRD - TEMERLOH
4 PRD - PAHANG TIMUR
5 PRD -BERA 18,000 90
6 PRD - MARAN
7 PRD - RAUB
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 2,000.00 10
MENGIKUT PT NEGERI PAHANG
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.1 : FASILITI PEMASARAN GETAH (FASGET)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.1 : FASILITI PEMASARAN GETAH (FASGET)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(UNIT)
KEWANGAN
(RM)
FIZIKAL
(UNIT)
KEWANGAN
(RM)
FIZIKAL
(UNIT)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 43,000.00 1
3 PRD - TEMERLOH 43,000.00 1
4 PRD - PAHANG TIMUR 15,000.00 1
5 PRD -BERA 65,000 2
6 PRD - MARAN 50,000.00 1
7 PRD - RAUB 30,000.00 2
8 PRD - BENTONG 15,000.00 1
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 196,000.00 7
MENGIKUT PT NEGERI PAHANG
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.2 : PRASARANA LADANG (PL)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.2 : PRASARANA LADANG (PL)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT
3 PRD - TEMERLOH 285,000.00
4 PRD - PAHANG TIMUR 242,300.00
5 PRD -BERA 0 0
6 PRD - MARAN
7 PRD - RAUB 472,500.00
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 999,800.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.3 : RANCANGAN KHAS PEMULIHAN KEBUN (RKPK)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.3 : RANCANGAN KHAS PEMULIHAN KEBUN (RKPK)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT
3 PRD - TEMERLOH
4 PRD - PAHANG TIMUR
5 PRD -BERA 598,560 296
6 PRD - MARAN
7 PRD - RAUB
8 PRD - BENTONG
9 PRD - LIPIS 546,671.78 202.00
10 IKPK KG. AWAH, PAHANG
JUMLAH 546,671.78 202.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.4 : INSENTIF PENGELUARAN SKRAP (IPS)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET)
SUB-PROGRAM 4.4.4 : INSENTIF PENGELUARAN SKRAP (IPS)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(ORG. PK)
KEWANGAN
(RM)
FIZIKAL
(ORG. PK)
KEWANGAN
(RM)
FIZIKAL
(ORG. PK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT 54,000.00 1.00
3 PRD - TEMERLOH 36,000.00 1.00
4 PRD - PAHANG TIMUR
5 PRD -BERA 52,200 29
6 PRD - MARAN 5,400.00 1.00
7 PRD - RAUB
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 95,400.00 3.00
MENGIKUT PT NEGERI PAHANG
PROGRAM 5.1 : INSENTIF PENGELUARAN LATEKS (INTEKS)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 5.1 : INSENTIF PENGELUARAN LATEKS (INTEKS)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
KEWANGAN
(RM)
FIZIKAL
(HEK)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT
3 PRD - TEMERLOH
4 PRD - PAHANG TIMUR 13,181.90 26.36
5 PRD -BERA 52,200 29
6 PRD - MARAN
7 PRD - RAUB 20,000.00 40.00
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 33,181.90 66.36
MENGIKUT PT NEGERI PAHANG
PROGRAM 5.2 : GERAN PENGELUARAN LATEKS (GPL)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 5.2 : GERAN PENGELUARAN LATEKS (GPL)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(J/K)
KEWANGAN
(RM)
FIZIKAL
(J/K)
KEWANGAN
(RM)
FIZIKAL
(J/K)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT
3 PRD - TEMERLOH
4 PRD - PAHANG TIMUR 5,000.00 1
5 PRD -BERA 20,000 2
6 PRD - MARAN
7 PRD - RAUB 10,000.00 1
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 15,000.00 2
MENGIKUT PT NEGERI PAHANG
PROGRAM 5.3 : INSENTIF GALAKAN TENAGA UPAH LATEKS (GTEKS)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 5.3 : INSENTIF GALAKAN TENAGA UPAH LATEKS (GTEKS)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(J/K)
KEWANGAN
(RM)
FIZIKAL
(J/K)
KEWANGAN
(RM)
FIZIKAL
(J/K)
1 PRN - NEGERI PAHANG
2 PRD - JERANTUT
3 PRD - TEMERLOH
4 PRD - PAHANG TIMUR 54,000.00 9
5 PRD -BERA 68,400 19
6 PRD - MARAN
7 PRD - RAUB 36,000.00 12
8 PRD - BENTONG
9 PRD - LIPIS
10 IKPK KG. AWAH, PAHANG
JUMLAH 90,000.00 21
MENGIKUT PT NEGERI PAHANG
PROGRAM 6.1 : BANTUAN MUSIM TENGKUJUH (BMT OE 2024)
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 10 20 30 40 50 60 70 80 90 100
Perbelanjaan 5 15 30 35 45 60 65 75 90 100
CADANGAN UNJURAN PENCAPAIAN (%)
KETETAPAN KPI UMUM PENCAPAIAN 2024
Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fizikal 5 15 25 35 45 50 65 80 95 100 100 100
Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100
MAIN
ISU KETERANGAN ISU CADANGAN PENYELESAIAN
penggunaan apps kesukaran pekebun kecil untuk updated permohonan PK kurang berkemahiran dalam ICT
kelulusan bmt kelulusan lot jadi berganda upgrade sistem kelulusan ebmt
ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
PROGRAM 6.1 : BANTUAN MUSIM TENGKUJUH (BMT OE 2024)
MAIN
PT
AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI
KEWANGAN
(RM)
FIZIKAL
(J/K)
KEWANGAN
(RM)
FIZIKAL
(J/K)
KEWANGAN
(RM)
FIZIKAL
(J/K)
1 PRN - NEGERI PAHANG 186,400.00 233.00
2 PRD - JERANTUT 1,731,200.00 2,164.00
3 PRD - TEMERLOH 3,019,200.00 3,774.00
4 PRD - PAHANG TIMUR 1,308,000.00 1,635.00
5 PRD -BERA 19,389,600 24,237 1,375,200.00 1,719.00
6 PRD - MARAN 1,556,000.00 1,945.00
7 PRD - RAUB 1,679,200.00 2,099.00
8 PRD - BENTONG 1,252,800.00 1,566.00
9 PRD - LIPIS 2,430,400.00 3,038.00
10 IKPK KG. AWAH, PAHANG
JUMLAH 14,538,400.00 18,173.00
MENGIKUT PT NEGERI PAHANG
SEKIAN, TERIMA KASIH

More Related Content

Similar to blueprint RP4 Tahun 2024 NEGERI PAHANG (1).pptx

Combined Pat Presentation Oct - Copy
Combined Pat Presentation  Oct  - CopyCombined Pat Presentation  Oct  - Copy
Combined Pat Presentation Oct - CopyJohn Osborne
ย 
Business Plan - Term Project
Business Plan - Term ProjectBusiness Plan - Term Project
Business Plan - Term ProjectKevin Swenson
ย 
Reducing_Learning_Curve_in_LB_GB_Sujith
Reducing_Learning_Curve_in_LB_GB_SujithReducing_Learning_Curve_in_LB_GB_Sujith
Reducing_Learning_Curve_in_LB_GB_SujithSujith Kolath
ย 
Fiscal deficit in india
Fiscal deficit in india Fiscal deficit in india
Fiscal deficit in india akhilareddy176
ย 
Presentation Data Depts
Presentation Data DeptsPresentation Data Depts
Presentation Data Deptsglnarasi
ย 
Project Example 4
Project Example 4Project Example 4
Project Example 4Yiyi Wang (Vivi)
ย 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7Michael Cary
ย 
3Q10 Earnings Results
3Q10 Earnings Results3Q10 Earnings Results
3Q10 Earnings ResultsGafisa RI !
ย 
Mid cap & small cap performance
Mid cap & small cap performanceMid cap & small cap performance
Mid cap & small cap performanceBFSICM
ย 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - TrainingMohammed Feroze
ย 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxKhaled Jomaa
ย 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxSIBANJAN MISHRA
ย 
9. Source Cost Methodology
9. Source Cost Methodology9. Source Cost Methodology
9. Source Cost MethodologyLeonardo Figueroa
ย 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingLean6Sigma4all
ย 
Marketing plan
Marketing planMarketing plan
Marketing planIgreenet Team
ย 
Marketing
MarketingMarketing
MarketingIgreenet Biz
ย 
Formempad04isi
Formempad04isiFormempad04isi
Formempad04isiChella Chibi
ย 
Formempad04isi
Formempad04isiFormempad04isi
Formempad04isiChella Chibi
ย 

Similar to blueprint RP4 Tahun 2024 NEGERI PAHANG (1).pptx (20)

Combined Pat Presentation Oct - Copy
Combined Pat Presentation  Oct  - CopyCombined Pat Presentation  Oct  - Copy
Combined Pat Presentation Oct - Copy
ย 
TeamSixBP
TeamSixBPTeamSixBP
TeamSixBP
ย 
Business Plan - Term Project
Business Plan - Term ProjectBusiness Plan - Term Project
Business Plan - Term Project
ย 
Reducing_Learning_Curve_in_LB_GB_Sujith
Reducing_Learning_Curve_in_LB_GB_SujithReducing_Learning_Curve_in_LB_GB_Sujith
Reducing_Learning_Curve_in_LB_GB_Sujith
ย 
Fiscal deficit in india
Fiscal deficit in india Fiscal deficit in india
Fiscal deficit in india
ย 
Presentation Data Depts
Presentation Data DeptsPresentation Data Depts
Presentation Data Depts
ย 
Project Example 4
Project Example 4Project Example 4
Project Example 4
ย 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7
ย 
sk chemicals 285130 Algorithm Investment Report
sk chemicals 285130 Algorithm Investment Reportsk chemicals 285130 Algorithm Investment Report
sk chemicals 285130 Algorithm Investment Report
ย 
3Q10 Earnings Results
3Q10 Earnings Results3Q10 Earnings Results
3Q10 Earnings Results
ย 
Mid cap & small cap performance
Mid cap & small cap performanceMid cap & small cap performance
Mid cap & small cap performance
ย 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
ย 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
ย 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
ย 
9. Source Cost Methodology
9. Source Cost Methodology9. Source Cost Methodology
9. Source Cost Methodology
ย 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream Mapping
ย 
Marketing plan
Marketing planMarketing plan
Marketing plan
ย 
Marketing
MarketingMarketing
Marketing
ย 
Formempad04isi
Formempad04isiFormempad04isi
Formempad04isi
ย 
Formempad04isi
Formempad04isiFormempad04isi
Formempad04isi
ย 

Recently uploaded

An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCNAP Global Network
ย 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processNAP Global Network
ย 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
ย 
Top Rated Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
ย 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterChristina Parmionova
ย 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...SUHANI PANDEY
ย 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learningNAP Global Network
ย 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...tanu pandey
ย 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
ย 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
ย 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
ย 
โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...ranjana rawat
ย 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
ย 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
ย 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...tanu pandey
ย 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisChristina Parmionova
ย 
Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...Dipal Arora
ย 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.Christina Parmionova
ย 

Recently uploaded (20)

An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
ย 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
ย 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
ย 
Top Rated Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
ย 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
ย 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
ย 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
ย 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
ย 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
ย 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
ย 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
ย 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
ย 
โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
โ†‘VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
ย 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
ย 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
ย 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
ย 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
ย 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
ย 
Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts โ˜Ž๏ธ8617370543 Starting From 5K to 25K ...
ย 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
ย 

blueprint RP4 Tahun 2024 NEGERI PAHANG (1).pptx

  • 1. BLUEPRINT PELAKSANAAN PROJEK / PROGRAM PEMBANGUNAN RISDA ROLLING PLAN 4 TAHUN 2024, RMKe-12 NEGERI PAHANG
  • 2. Perkara (%) JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 KPI UMUM PENCAPAIAN 2024
  • 3. RUMUSAN AGIHAN SILING VS POTENSI NEGERI PROJEK / PROGRAM / SUB-PROGRAM PM AGIHAN SILING POTENSI NEGERI RM FIZ RM FIZ 1 PEMB. KAW. BERTANAM GETAH PK 45,000,000 1.1 TAN. SEM. GETAH RMKe-12 1.1.1 BAN. SEMASA BTSP 20,508,600 2,660 13,045,320.00 1,692.00 1.1.2 BAN. BERTURUT BTSP 5,156,780 2,775 3,990,288.95 2,774.88 JUMLAH KECIL BTSP 25,665,380 5,435 17,035,608.95 4,466.88 1.2 TAN. SEM. GETAH SAMB. BTSP 2,023,500 1,721 2,019,711.12 1,726.39 1.3 BAN. ANG. PEDLM BBIP 50,120 160 35,041.50 114.00 1.4 BAN. TBG. PELANCARAN (BTP) BTSP 10,000 5 8,000.00 81.77 1.5 PENGEMBANGAN 1.5.1 KHID. PGM BPPT 1,492,390 21,800 1,767,670.00 27,850.00 1.5.2 GAP BPPT 406,460 10,307 331,180.00 12,812.00 1.5.3 PIPK BPPT 1,101,150 14,721 901,150.00 1,200.00 JUMLAH KECIL BPPT 3,000,000 46,828 2,437,250.00 48,946.00 1.5.4 IIP BTSP 814,000 1,414 1,255,752.75 1,791.64 1.6 PRASARANA ASAS PERTANIAN (PAP) BTSP 4,798,000 2,180 4,551,250.00 441.66 1.7 AKT. EKO. TAMB. & PEMB. USA. 1.7.1 AET BPU 4,575,700 360 3,778,000.00 290.00 (AET & PU) 1.7.2 PEMB. USA. BPU 1,888,300 660 1,978,000.00 490.00 1.7.3 JELITA@RISDA BPU 2,175,000 145 2,175,000.00 145.00 JUMLAH KECIL BPU 8,639,000 1,165 7,931,000.00 925.00 2 PEMB. SEMULA HASIL BAHARU 4,020,000 2.1 AGROMAKANAN BPK 4,020,000 201 4,020,000.00 232.00 2.2 KHID. LAT. PK 2.2.1 KHID. LAT. PK BL 0 0 2.2.2 KAJ. IMP. BDPS 0 0 2.3 ICT PK RISDA BTM 0 0 3 RAWAT & CEGAH PENYAKIT LDP BPPT 2,050,000 2,411 2,121,984.00 3,316.00 4 PEN. PROD. GETAH (PROGET) PEKEBUN KECIL 5,000,000 4.1 PENG. HASIL GETAH MTG (PHGM) 4.1.1 BAN. SEMASA BPP 4,207,500 1,650 4,302,535.53 1,687.27 4.2 GETAH MATANG-TANAM SEMULA (GMTS) BPP 58,740 147 60,000.00 150.00 4.3 INSENTIF PEDALAMAN MATANG (IPM) BPP 18,000 90 2,000.00 10.00 4.4 FAS. PEMASARAN GETAH (FASGET) 4.4.1 FASGET BPP 65,000 2 196,000.00 6.00 4.4.2 PL BPP 0 0 999,800.00 4.4.3 RKPK BTSP 598,560 296 546,671.78 202.00 4.4.4 IPS BPP 52,200 29 95,400.00 3.00 JUMLAH KECIL BPP 715,760 1,837,871.78 211.00 5 PEN. PROD. LATEKS (PROTEKS) PEKEBUN KECIL 160,000 5.1 INS. PROD. LATEKS (INTEKS) BPP 71,600 36 33,181.90 66.36 5.2 GERAN PEMASARAN LATEKS (GPL) BPP 20,000 2 15,000.00 2.00 5.3 INS. GALAKAN TENAGA KERJA LATEKS (GTEKS) BPP 68,400 19 90,000.00 21.00 6 BANTUAN MUSIM TENGKUJUH 19,389,600 24,237 14,538,400.00 18,173.00 JUMLAH KESELURUHAN 75,619,600 62,857,337.55 67,385.97 OVERALL
  • 4. PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12 SUB-PROGRAM 1.1.1 : SEMASA Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN Peruntukkan Peruntukkan diterima ikut sukuan Minta peruntukkan diberi pada sukuan pertama dan kedua atau diberi sekali gus tanpa sukuan Bekalan Benih - saiz benih tidak sama seperti LO yang dikeluarkan Minta dikembalikan perbezaa nilai ke akaun pemilik dalam ipower bagi ansuran seterusnya ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 5. PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12 SUB-PROGRAM 1.1.1 : SEMASA MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 1,387,800.00 180 3 PRD - TEMERLOH 1,734,750.00 225.00 4 PRD - PAHANG TIMUR 1,804,140.00 234.00 5 PRD -BERA 20,508,600 2,660.00 1,526,580.00 198.0 6 PRD - MARAN 1,387,800.00 180 7 PRD - RAUB 1,734,750.00 225 8 PRD - BENTONG 1,387,800.00 180 9 PRD - LIPIS 2,081,700.00 270 10 IKPK KG. AWAH, PAHANG JUMLAH 13,045,320.00 1692.00 MENGIKUT PT NEGERI PAHANG
  • 6. PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12 SUB-PROGRAM 1.1.2 : BERTURUT Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN Peruntukkan Peruntukkan diterima ikut sukuan Minta peruntukkan diberi pada sukuan pertama dan kedua atau diberi sekali gus tanpa sukuan ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 7. PROGRAM 1.1 : TANAM SEMULA GETAH RMKe-12 SUB-PROGRAM 1.1.2 : BERTURUT MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 306,981.84 219.3887 3 PRD - TEMERLOH 464,986.66 316.8372 4 PRD - PAHANG TIMUR 511,854.75 357.1777 5 PRD -BERA 5,156,780 2,775 559,171.39 393.80 6 PRD - MARAN 606,544.15 414.9692 7 PRD - RAUB 517,243.50 360.5866 8 PRD - BENTONG 369,419.80 246.8861 9 PRD - LIPIS 654,086.86 465.23788 10 IKPK KG. AWAH, PAHANG JUMLAH 3,990,288.95 2,774.88 MENGIKUT PT NEGERI PAHANG
  • 8. PROGRAM 1.2 : TANAM SEMULA GETAH SAMBUNGAN (TSGS) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN Peruntukkan Peruntukkan diterima ikut sukuan Minta peruntukkan diberi pada sukuan pertama dan kedua atau diberi sekali gus tanpa sukuan ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 9. PROGRAM 1.2 : TANAM SEMULA GETAH SAMBUNGAN (TSGS) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 172,845.37 149.46 3 PRD - TEMERLOH 357,917.58 306.48 4 PRD - PAHANG TIMUR 316,156.52 265.46 5 PRD -BERA 2,023,500 1,721 318,524.99 271.67 6 PRD - MARAN 218,343.79 189.66 7 PRD - RAUB 137,244.58 117.74 8 PRD - BENTONG 97,883.56 83.44 9 PRD - LIPIS 400,794.73 342.47 10 IKPK KG. AWAH, PAHANG JUMLAH 2,019,711.12 1726.3895 MENGIKUT PT NEGERI PAHANG
  • 10. PROGRAM 1.3 : BANTUAN ANGKUTAN KAWASAN PEDALAMAN Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal Perbelanjaan CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 11. PROGRAM 1.3 : BANTUAN ANGKUTAN KAWASAN PEDALAMAN MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 35,041.50 114 3 PRD - TEMERLOH 4 PRD - PAHANG TIMUR 5 PRD -BERA 50,120 160 6 PRD - MARAN 7 PRD - RAUB 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 35,041.50 114 MENGIKUT PT NEGERI PAHANG
  • 12. PROGRAM 1.4 : BANTUAN TABUNG PELANCARAN Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 13. PROGRAM 1.4 : BANTUAN TABUNG PELANCARAN MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (J/K TSB) KEWANGAN (RM) FIZIKAL (J/K TSB) KEWANGAN (RM) FIZIKAL (J/K TSB) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 3 PRD - TEMERLOH 4,000.00 44.56 4 PRD - PAHANG TIMUR 5 PRD -BERA 10,000 5 6 PRD - MARAN 4,000.00 37.21 7 PRD - RAUB 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 8,000.00 81.77 MENGIKUT PT NEGERI PAHANG
  • 14. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.1 : KHIDMAT PENGEMBANGAN Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 15. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.1 : KHIDMAT PENGEMBANGAN MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) 1 PRN - NEGERI PAHANG 747,670.00 2,200.00 2 PRD - JERANTUT 107,000.00 2,325.00 3 PRD - TEMERLOH 148,000.00 4,320.00 4 PRD - PAHANG TIMUR 148,000.00 3,780.00 5 PRD -BERA 1,492,390 21,800 107,000.00 2,325.00 6 PRD - MARAN 107,000.00 2,325.00 7 PRD - RAUB 148,000.00 4,320.00 8 PRD - BENTONG 107,000.00 2,325.00 9 PRD - LIPIS 148,000.00 3,930.00 10 IKPK KG. AWAH, PAHANG JUMLAH 1,767,670.00 27,850.00 MENGIKUT PT NEGERI PAHANG
  • 16. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.2 : GAP Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN PPP kurang ilmu mengenai GAP PPP baru dan kurang mahir dalam perlaksanaan GAP Kursus GAP secara kerap. ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 17. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.2 : GAP MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) 1 PRN - NEGERI PAHANG 20,000.00 200 2 PRD - JERANTUT 30,640.00 1,227.00 3 PRD - TEMERLOH 60,360.00 2,118.00 4 PRD - PAHANG TIMUR 37,620.00 1,589.00 5 PRD -BERA 406,460 10,307 32,500.00 1,405.00 6 PRD - MARAN 33,420.00 1,379.00 7 PRD - RAUB 32,200.00 1,306.00 8 PRD - BENTONG 40,580.00 1,725.00 9 PRD - LIPIS 43,860.00 1,863.00 10 IKPK KG. AWAH, PAHANG JUMLAH 331,180.00 12,812.00 MENGIKUT PT NEGERI PAHANG
  • 18. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.3 : PEMBANGUNAN INSTITUSI PEKEBUN KECIL (PIPK) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN Tuisyen Rakyat Selaraskan peruntukkan dengan tuntutan di Unit Kewangan Agihan peruntukkan perlu selaras dengan takwim kalendar persekolahan ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 19. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.3 : PEMBANGUNAN INSTITUSI PEKEBUN KECIL (PIPK) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) 1 PRN - NEGERI PAHANG 194,000.00 43 2 PRD - JERANTUT 54,700.00 86.00 3 PRD - TEMERLOH 127,400.00 232.00 4 PRD - PAHANG TIMUR 87,450.00 147.00 5 PRD -BERA 1,101,150 14,721 91,400.00 112.00 6 PRD - MARAN 72,700.00 146.00 7 PRD - RAUB 116,600.00 200.00 8 PRD - BENTONG 54,700.00 86.00 9 PRD - LIPIS 102,200.00 148.00 10 IKPK KG. AWAH, PAHANG JUMLAH 901,150.00 1,200.00 MENGIKUT PT NEGERI PAHANG
  • 20. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.4 : INSENTIF INPUT PERTANIAN (IIP) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 21. PROGRAM 1.5 : PENGEMBANGAN SUB-PROGRAM 1.5.4 : INSENTIF INPUT PERTANIAN (IIP) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 197,908.37 149.46 3 PRD - TEMERLOH 357,917.58 306.48 4 PRD - PAHANG TIMUR 99,171.60 265.46 5 PRD -BERA 814,000 1,414 211,185.00 356.90 6 PRD - MARAN 116,909.80 211.77 7 PRD - RAUB 55,987.50 117.74 8 PRD - BENTONG 48,324.60 83.44 9 PRD - LIPIS 168,348.30 300.38 10 IKPK KG. AWAH, PAHANG JUMLAH 1,255,752.75 1,791.64 MENGIKUT PT NEGERI PAHANG
  • 22. PROGRAM 1.6 : PRASARANA ASAS PERTANIAN (PAP) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN Peruntukkan Nilai yang diterima tidak sama dengan keluasan saiz projek Mohon peruntukkan diberi pada sukuan pertama bagi mengelakkan kerja-kerja prasarana pada hujung tahun ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 23. PROGRAM 1.6 : PRASARANA ASAS PERTANIAN (PAP) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 599,750.00 24.61 3 PRD - TEMERLOH 599,750.00 14.94 4 PRD - PAHANG TIMUR 605,750.00 318.00 5 PRD -BERA 4,798,000 2,180 600,000.00 17.50 6 PRD - MARAN 400,000.00 10.00 7 PRD - RAUB 850,000.00 23.60 8 PRD - BENTONG 400,000.00 10.55 9 PRD - LIPIS 496,000.00 22.46 10 IKPK KG. AWAH, PAHANG JUMLAH 4,551,250.00 441.66 MENGIKUT PT NEGERI PAHANG
  • 24. PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN SUB-PROGRAM 1.7.1 : AKTIVITI EKONOMI TAMBAHAN Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 25. PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN SUB-PROGRAM 1.7.1 : AKTIVITI EKONOMI TAMBAHAN MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (USA. PK) KEWANGAN (RM) FIZIKAL (USA. PK) KEWANGAN (RM) FIZIKAL (USA. PK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 486,000.00 37 3 PRD - TEMERLOH 486,000.00 37 4 PRD - PAHANG TIMUR 446,000.00 34 5 PRD -BERA 4,575,700 360 466,000.00 36 6 PRD - MARAN 446,000.00 34 7 PRD - RAUB 486,000.00 37 8 PRD - BENTONG 476,000.00 38 9 PRD - LIPIS 486,000.00 37 10 IKPK KG. AWAH, PAHANG JUMLAH 3,778,000.00 290.00 MENGIKUT PT NEGERI PAHANG
  • 26. PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN SUB-PROGRAM 1.7.2 : PEMBANGUNAN USAHAWAN Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 27. PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN SUB-PROGRAM 1.7.2 : PEMBANGUNAN USAHAWAN MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (USA. PK) KEWANGAN (RM) FIZIKAL (USA. PK) KEWANGAN (RM) FIZIKAL (USA. PK) 1 PRN - NEGERI PAHANG 653,000.00 381 2 PRD - JERANTUT 205,000.00 15 3 PRD - TEMERLOH 160,000.00 14 4 PRD - PAHANG TIMUR 160,000.00 14 5 PRD -BERA 1,888,300 660 150,000.00 13 6 PRD - MARAN 200,000.00 14 7 PRD - RAUB 150,000.00 13 8 PRD - BENTONG 150,000.00 13 9 PRD - LIPIS 150,000.00 13 10 IKPK KG. AWAH, PAHANG JUMLAH 1,978,000.00 490.00 MENGIKUT PT NEGERI PAHANG
  • 28. PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN SUB-PROGRAM 1.7. : JELITA@RISDA Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 29. PROGRAM 1.7 : AKTIVITI EKONOMI TAMBAHAN & PEMBANGUNAN USAHAWAN SUB-PROGRAM 1.7.3 : JELITA MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (USA. PK) KEWANGAN (RM) FIZIKAL (USA. PK) KEWANGAN (RM) FIZIKAL (USA. PK) 1 PRN - NEGERI PAHANG 2,175,000.00 145.00 2 PRD - JERANTUT 3 PRD - TEMERLOH 4 PRD - PAHANG TIMUR 5 PRD -BERA 1,888,300 660 6 PRD - MARAN 7 PRD - RAUB 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 2,175,000.00 145.00 MENGIKUT PT NEGERI PAHANG
  • 30. PROGRAM 2.1 : AGROMAKANAN Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 31. PROGRAM 2.1 : AGROMAKANAN MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) KEWANGAN (RM) FIZIKAL (ORG PK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 460,000.00 10.00 3 PRD - TEMERLOH 500,000.00 26.00 4 PRD - PAHANG TIMUR 520,000.00 48.00 5 PRD -BERA 4,020,000 201 500,000.00 37.00 6 PRD - MARAN 460,000.00 26.00 7 PRD - RAUB 660,000.00 33.00 8 PRD - BENTONG 460,000.00 26.00 9 PRD - LIPIS 460,000.00 21.00 10 IKPK KG. AWAH, PAHANG JUMLAH 4,020,000.00 232.00 MENGIKUT PT NEGERI PAHANG
  • 32. Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal Perbelanjaan CADANGAN UNJURAN PENCAPAIAN (%) PROGRAM 2.2 : KHIDMAT LATIHAN PEKEBUN KECIL SUB-PROGRAM 2.2.1 : KHIDMAT LATIHAN PEKEBUN KECIL MAIN KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 33. Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal Perbelanjaan CADANGAN UNJURAN PENCAPAIAN (%) PROGRAM 2.2 : KHIDMAT LATIHAN PEKEBUN KECIL SUB-PROGRAM 2.2.2 : KAJIAN IMPAK MAIN KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 34. Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal Perbelanjaan CADANGAN UNJURAN PENCAPAIAN (%) PROGRAM 2.3 : ICT PEKEBUN KECIL RISDA MAIN KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 35. PROGRAM 3.1 : RAWAT & CEGAH PENYAKIT LURUHAN DAUN PESTALOTIOPSIS Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN Cuaca Sukar melakukan semburan ketika musim hujan (musim tengkujuh) Elakkan peruntukkan hujung tahun ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 36. PROGRAM 3.1 : RAWAT & CEGAH PENYAKIT LURUHAN DAUN PESTALOTIOPSIS MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 144,000.00 225.00 3 PRD - TEMERLOH 273,600.00 428.00 4 PRD - PAHANG TIMUR 281,664.00 440.00 5 PRD -BERA 2,050,000 2,411 292,608.00 457.00 6 PRD - MARAN 259,200.00 405.00 7 PRD - RAUB 282,240.00 441.00 8 PRD - BENTONG 253,440.00 396.00 9 PRD - LIPIS 335,232.00 524.00 10 IKPK KG. AWAH, PAHANG JUMLAH 2,121,984.00 3,316.00 MENGIKUT PT NEGERI PAHANG
  • 37. PROGRAM 4.1 : PENGELUARAN HASIL GETAH MATANG (PHGM) SUB-PROGRAM 4.1.1 : ANSURAN 1 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 38. PROGRAM 4.1 : PENGELUARAN HASIL GETAH MATANG (PHGM) SUB-PROGRAM 4.1.1 : ANSURAN 1 MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 280,588.49 110.03 3 PRD - TEMERLOH 1,493,147.15 585.55 4 PRD - PAHANG TIMUR 638,552.90 250.41 5 PRD -BERA 4,207,500 1,650 510,000.00 200.00 6 PRD - MARAN 382,500.00 150.00 7 PRD - RAUB 306,000.00 120.00 8 PRD - BENTONG 329,638.50 129.27 9 PRD - LIPIS 362,108.50 142 10 IKPK KG. AWAH, PAHANG JUMLAH 4,302,535.53 1,687.27 MENGIKUT PT NEGERI PAHANG
  • 39. PROGRAM 4.2 : GETAH MATANG-TANAM SEMULA (GMTS) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 40. PROGRAM 4.2 : GETAH MATANG-TANAM SEMULA (GMTS) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 6,000.00 15.00 3 PRD - TEMERLOH 9,000.00 22.50 4 PRD - PAHANG TIMUR 7,800.00 19.50 5 PRD -BERA 58,740 147 6,600.00 16.50 6 PRD - MARAN 6,600.00 16.50 7 PRD - RAUB 9,000.00 22.50 8 PRD - BENTONG 6,000.00 15.00 9 PRD - LIPIS 9,000.00 22.50 10 IKPK KG. AWAH, PAHANG JUMLAH 60,000.00 150.00 MENGIKUT PT NEGERI PAHANG
  • 41. PROGRAM 4.3 : INSENTIF PEDALAMAN MATANG (IPM) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 42. PROGRAM 4.3 : INSENTIF PEDALAMAN MATANG (IPM) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 2,000.00 10 3 PRD - TEMERLOH 4 PRD - PAHANG TIMUR 5 PRD -BERA 18,000 90 6 PRD - MARAN 7 PRD - RAUB 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 2,000.00 10 MENGIKUT PT NEGERI PAHANG
  • 43. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.1 : FASILITI PEMASARAN GETAH (FASGET) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 44. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.1 : FASILITI PEMASARAN GETAH (FASGET) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (UNIT) KEWANGAN (RM) FIZIKAL (UNIT) KEWANGAN (RM) FIZIKAL (UNIT) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 43,000.00 1 3 PRD - TEMERLOH 43,000.00 1 4 PRD - PAHANG TIMUR 15,000.00 1 5 PRD -BERA 65,000 2 6 PRD - MARAN 50,000.00 1 7 PRD - RAUB 30,000.00 2 8 PRD - BENTONG 15,000.00 1 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 196,000.00 7 MENGIKUT PT NEGERI PAHANG
  • 45. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.2 : PRASARANA LADANG (PL) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 46. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.2 : PRASARANA LADANG (PL) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 3 PRD - TEMERLOH 285,000.00 4 PRD - PAHANG TIMUR 242,300.00 5 PRD -BERA 0 0 6 PRD - MARAN 7 PRD - RAUB 472,500.00 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 999,800.00 MENGIKUT PT NEGERI PAHANG
  • 47. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.3 : RANCANGAN KHAS PEMULIHAN KEBUN (RKPK) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 48. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.3 : RANCANGAN KHAS PEMULIHAN KEBUN (RKPK) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 3 PRD - TEMERLOH 4 PRD - PAHANG TIMUR 5 PRD -BERA 598,560 296 6 PRD - MARAN 7 PRD - RAUB 8 PRD - BENTONG 9 PRD - LIPIS 546,671.78 202.00 10 IKPK KG. AWAH, PAHANG JUMLAH 546,671.78 202.00 MENGIKUT PT NEGERI PAHANG
  • 49. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.4 : INSENTIF PENGELUARAN SKRAP (IPS) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 50. PROGRAM 4.4 : FASILITI PEMASARAN GETAH (FASGET) SUB-PROGRAM 4.4.4 : INSENTIF PENGELUARAN SKRAP (IPS) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (ORG. PK) KEWANGAN (RM) FIZIKAL (ORG. PK) KEWANGAN (RM) FIZIKAL (ORG. PK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 54,000.00 1.00 3 PRD - TEMERLOH 36,000.00 1.00 4 PRD - PAHANG TIMUR 5 PRD -BERA 52,200 29 6 PRD - MARAN 5,400.00 1.00 7 PRD - RAUB 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 95,400.00 3.00 MENGIKUT PT NEGERI PAHANG
  • 51. PROGRAM 5.1 : INSENTIF PENGELUARAN LATEKS (INTEKS) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 52. PROGRAM 5.1 : INSENTIF PENGELUARAN LATEKS (INTEKS) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) KEWANGAN (RM) FIZIKAL (HEK) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 3 PRD - TEMERLOH 4 PRD - PAHANG TIMUR 13,181.90 26.36 5 PRD -BERA 52,200 29 6 PRD - MARAN 7 PRD - RAUB 20,000.00 40.00 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 33,181.90 66.36 MENGIKUT PT NEGERI PAHANG
  • 53. PROGRAM 5.2 : GERAN PENGELUARAN LATEKS (GPL) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 54. PROGRAM 5.2 : GERAN PENGELUARAN LATEKS (GPL) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (J/K) KEWANGAN (RM) FIZIKAL (J/K) KEWANGAN (RM) FIZIKAL (J/K) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 3 PRD - TEMERLOH 4 PRD - PAHANG TIMUR 5,000.00 1 5 PRD -BERA 20,000 2 6 PRD - MARAN 7 PRD - RAUB 10,000.00 1 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 15,000.00 2 MENGIKUT PT NEGERI PAHANG
  • 55. PROGRAM 5.3 : INSENTIF GALAKAN TENAGA UPAH LATEKS (GTEKS) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 56. PROGRAM 5.3 : INSENTIF GALAKAN TENAGA UPAH LATEKS (GTEKS) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (J/K) KEWANGAN (RM) FIZIKAL (J/K) KEWANGAN (RM) FIZIKAL (J/K) 1 PRN - NEGERI PAHANG 2 PRD - JERANTUT 3 PRD - TEMERLOH 4 PRD - PAHANG TIMUR 54,000.00 9 5 PRD -BERA 68,400 19 6 PRD - MARAN 7 PRD - RAUB 36,000.00 12 8 PRD - BENTONG 9 PRD - LIPIS 10 IKPK KG. AWAH, PAHANG JUMLAH 90,000.00 21 MENGIKUT PT NEGERI PAHANG
  • 57. PROGRAM 6.1 : BANTUAN MUSIM TENGKUJUH (BMT OE 2024) Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 10 20 30 40 50 60 70 80 90 100 Perbelanjaan 5 15 30 35 45 60 65 75 90 100 CADANGAN UNJURAN PENCAPAIAN (%) KETETAPAN KPI UMUM PENCAPAIAN 2024 Perkara (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Fizikal 5 15 25 35 45 50 65 80 95 100 100 100 Perbelanjaan 5 15 25 35 45 50 65 80 95 100 100 100 MAIN ISU KETERANGAN ISU CADANGAN PENYELESAIAN penggunaan apps kesukaran pekebun kecil untuk updated permohonan PK kurang berkemahiran dalam ICT kelulusan bmt kelulusan lot jadi berganda upgrade sistem kelulusan ebmt ISU PELAKSANAAN DAN CADANGAN PENYELESAIAN
  • 58. PROGRAM 6.1 : BANTUAN MUSIM TENGKUJUH (BMT OE 2024) MAIN PT AGIHAN SILING KEPERLUAN BAHAGIAN POTENSI NEGERI KEWANGAN (RM) FIZIKAL (J/K) KEWANGAN (RM) FIZIKAL (J/K) KEWANGAN (RM) FIZIKAL (J/K) 1 PRN - NEGERI PAHANG 186,400.00 233.00 2 PRD - JERANTUT 1,731,200.00 2,164.00 3 PRD - TEMERLOH 3,019,200.00 3,774.00 4 PRD - PAHANG TIMUR 1,308,000.00 1,635.00 5 PRD -BERA 19,389,600 24,237 1,375,200.00 1,719.00 6 PRD - MARAN 1,556,000.00 1,945.00 7 PRD - RAUB 1,679,200.00 2,099.00 8 PRD - BENTONG 1,252,800.00 1,566.00 9 PRD - LIPIS 2,430,400.00 3,038.00 10 IKPK KG. AWAH, PAHANG JUMLAH 14,538,400.00 18,173.00 MENGIKUT PT NEGERI PAHANG