Danish District Heating Sector Visit to Brzece – 28.05.2015
Andrei Ovidiu Bita – Balkan Area Sales Manager
•2
Energy Challenges looking to District Heating
• Increased energy consumption by growing demographics & wealth
• Energy consumption will grow by over a third up to 2035
• 70% of the world‘s estimated 10 billion inhabitants will be part of massive
urban networks by 2050
• Cities are home to 80% of EUs population and to more than half the
people on the planet
• Up to 70% of carbon emissions come from cities and cities have an extra
responsibility to combat climate change
• Long overdue need for action
Accelerating the uptake
of energy efficiency and
renewable energy in the
global energy mix
is the single biggest
contribution to keep
global temperature rise
under 2C
•3
Who We Are & Our Vision
To make the World's energy supply more efficient
and reduce the global energy loss with leading
insulation products, improving the environment for
the populations in all continents.
The world’s leading
manufacturer of pre-
insulated pipes for
energy efficient
transportation of
gases and liquids for
district energy.
•4
Our Focus
Oil & Gas
Industry
District energy – heating & cooling
Sales
Production
Mobile Plant
Joint venture
 8 plants in Europe, 1 in Asia, 2 mobile production units
 14 Sales units
 Joint ventures in China and Dubai
 Distributors in more than 30 countries
 More than 5,000 km pre-insulated pipes every year
 More than LOGSTOR pipe supplied to date
Headquarters in Denmark 1,500 employees Annual turnover > 250 MEUR Owner: Triton Fund III
The LOGSTOR Group & our global presence
The LOGSTOR Group & our Balkan presence
•Flexibility and
speedy deliveries &
service
•LOGSTOR continues
its international
growth strategy and
takes over production
and sales from the
competitor Stizo Termo
SA in Romania as of 1
March 2009.
•Better presence
on Balkan Markets
•Competitive
prices - same
LOGSTOR
QUALITY
•7
Our Value Proposition
Lowest total cost of operation
• Insulation Technologies
• Lifetime Insulation protection
• Integrated Solutions
Effective installation
• LOGSTOR Joints
• LOGSTOR Design Services
• Documentation & Certification
Longest life time
• Surveillance
• LOGSTOR Calculator
• LOGSTOR Services
Customer Excellence
• Responsiveness
• Transport & Delivery Accuracy
• Accountability
•8
Integrated Solutions
• One integrated solution for the whole pipe system
• Designed to minimize installation & operating costs
• Optimum insulation ensures low operating costs
– Reduces heat loss
– Improve energy efficiency
– Reduces CO2 emissions
• Service before, during and after installation
• Quality, durability and lifetime beyond 30 years
• 50 years of experience inventing pre-insulated pipe technology
•9
The largest producer of high quality pre-insulated solutions
• Pre-insulated pipes for temperatures from: -200 to +250°C
Straight pipes, from DN 20 to DN1200
– More than 10,000 km
• Flexible pipes, from DN15 to DN110
– More than 3,000 km
• Joints (mechanical, shrinkable & weldable)
– More than 1,000,000 units
• Pre-insulated fittings
– More than 250,000 units
•10
Total Cost of Ownership / Lifetime costs
1. Investment costs (Non-recurrent costs)
– Purchase costs, components
– Installation costs
– Costs of planning and commissioning
2. Operating costs (annual costs)
– Costs of energy & heat loss
– Costs of maintenance
– Costs of repairs
– Costs of poor quality
3. Total costs of the solution
Investment Cost
Operating Costs
30 years
•11
Our Services
• Before installation
– Design Manual - optimal design of the pipe system
– Calculator – calculate how to minimize operation costs, heat loss and CO2 emissions
• During installation
– Weldmaster - greater security, better quality control and easy traceability of joints
– Complete Manual for Handling and Installation
– Training courses & certification - fitters and supervisors
• After installation
– LOGSTOR Detect - monitors and reports on failures or potential failures
•12
Our Experience & Know-How
• Suitable for big, medium and small scale district energy
– New installations & Maintenance
– Retrofit applications
– Compatible with existing pipe systems
• Quick adaptation to new markets
– Mobile production plants
– Global network of alliances and partners
• 50 years of experience with pre-insulated solutions
•13
Documentation, Quality & Safety
• The European standards = 30 years service life
– Comply or do better!
– External tests of properties
– Constantly internal test
• Focus on quality
– ISO 9001 certification
– EUROHEAT & POWER certified
• Focus on environmental aspects
– ISO 14001 certification
• Focus on Health & Safety for our people
– Leading & lagging indicators at all sites
– OHSAS 18001 certification on selected sites
•14
Energy Efficiency / Heat Loss
• Lower operating costs
• Less environmental impact
Our diffusion barrier
– Prevents ageing of insulation
– Reduces energy losses
– Implemented in pipes & joints
Cyclopentane, λ = 0.012
W/mK
CO2, λ = 0.017 W/mK
λair= 0.0<27 W/mK
Oxygen
NitrogenLambda (λ)
expresses the
insulation property of
a material. The lower
the lambda value, the
better the insulation.
The heat loss from LOGSTOR pre-insulated pipes fitted with a diffusion barrier is as
much as 15-30% less than if the diffusion barrier is omitted from the specifications.
•15
Internal Testing
• We measures the lambda value continuously
• Test equipment delivered by the Danish Technological Institute
• We participate in Round Robin tests with external institutes
• Results available on: www.logstor.com
•04/06/2015
•16
Costs Of Maintenance & Repair
Durable jointing systems
• Joint systems constructed to 30+ years of operation
• Fusion welded joints
• Shrinkable systems including joints, bends and branches
•04/06/2015
•17
System monitoring / surveillance
• Our LOGSTOR Detect system monitors the functionality of a pipe system
• Offered as a cloud based solution (Software as a Service)
• Impedance and resistance measurement identify any faults in the pipe system
• Monitoring of wells & control of temperature and pressure
• Our solution analyse all data from the system. x
• Communication via GPRS
•04/06/2015
•18
Our Innovative design – Reduce Costs
Designed to reduce the meter of pipes and components required
• Reduced purchase costs & installation costs
• Reduced time of installation & civil works
E-Comp TwinPipes Curved pipes
•04/06/2015
•19
Our Innovative design – Twin Pipe
•04/06/2015
You avoid 9 joints and 8 welds
Possible up to DN 200
You avoid 3 joints
Possible up to DN 100
Reduces excavation by 20%
•20
Our Innovative software
•04/06/2015
• LOGSTOR Calculator
– Web based tool to calculate
• Heat loss
• Costs for heat loss
• CO2 emissions
– Calculations as support for decisions on insulation series and design
•21
Serbia – KfW IV overview
•04/06/2015
• Reconstruction of DH networks in 17 cities at the same time;
• Contract signed end of May 2013;
• Entire design checked and modified by internal LOGSTOR design
department together with end beneficiaries;
• More than
- 89 km of preinsulated pipes;
- 6000 pcs of preinsulated fittings;
- 20.000 pcs of joints
, delivered in less than 12 months despite of hundreds of unforeseen
changes of design according real on-site situation.
•22
Serbia – KfW IV overview
•04/06/2015
• Due to the complexity of the project and short implementation period, inevitably problems
occurred, such as:
- Differences between designed situation vs. on-site reality;
- Damaged products due improper transportation or unloading;
- Wrong delivered products;
- Various installing issues;
All of them were immediately solved by mean of LOGSTOR permanent support !
•23
Serbia – KfW IV overview
•04/06/2015
• LOGSTOR quality was implemented:
- Diffusion barrier / NO ageing, high insulation capacity;
- ONE-TIME compensators – NO U-loops, less works and
pressure losses;
- Local insulation foam packs technology – quick installation,
reliable joints;
- Surveillance system plus training in groups of cities;
By means LOGSTOR factories positioning – flexible deliveries and
fast reaction were possible – against complicated export procedures.
Following the proper conduct of the contract, additional orders and
even a new city is being delivered as we speak.
•24
Nobody is perfect....
But we are close to ...
and still improving.
Documentation @
www.logstor.com/documentation
•25
Or want to know some more details….

More Related Content

What's hot

[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...
[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...
[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...GBC Finland
 
Water and Wastewater Flow Solutions by Badger Meter
Water and Wastewater Flow Solutions by Badger MeterWater and Wastewater Flow Solutions by Badger Meter
Water and Wastewater Flow Solutions by Badger MeterThompson Equipment Company
 
Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...
Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...
Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...Blue I Water Technologies
 
CPM Perfect Manhole CPD
CPM Perfect Manhole CPDCPM Perfect Manhole CPD
CPM Perfect Manhole CPDDan Mulkern
 
Commercial presentation jan 2013
Commercial presentation   jan 2013Commercial presentation   jan 2013
Commercial presentation jan 2013Solmatix Renewables
 

What's hot (8)

Rīgas māju atjaunošanas pieredze. Igaunijas pieredze
Rīgas māju atjaunošanas pieredze. Igaunijas pieredzeRīgas māju atjaunošanas pieredze. Igaunijas pieredze
Rīgas māju atjaunošanas pieredze. Igaunijas pieredze
 
[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...
[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...
[Nordic GBC Conference 2013] Helga Jóhanna Bjarnadóttir: Höfðabakki 9 - Susta...
 
Water and Wastewater Flow Solutions by Badger Meter
Water and Wastewater Flow Solutions by Badger MeterWater and Wastewater Flow Solutions by Badger Meter
Water and Wastewater Flow Solutions by Badger Meter
 
E2S Company overview
E2S Company overviewE2S Company overview
E2S Company overview
 
Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...
Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...
Introducing: Advanced Water Monitoring & Control Innovation for Industrial, M...
 
CPM Perfect Manhole CPD
CPM Perfect Manhole CPDCPM Perfect Manhole CPD
CPM Perfect Manhole CPD
 
Envelope Design Training
Envelope Design TrainingEnvelope Design Training
Envelope Design Training
 
Commercial presentation jan 2013
Commercial presentation   jan 2013Commercial presentation   jan 2013
Commercial presentation jan 2013
 

Similar to Andrej prezentacija Logstor DBDH Kopaonik

Title Product brochure and services_LAPSOLITE.pdf
Title Product brochure and services_LAPSOLITE.pdfTitle Product brochure and services_LAPSOLITE.pdf
Title Product brochure and services_LAPSOLITE.pdfAdrianaHernandez788600
 
Heat Networks Code of Practice
Heat Networks Code of PracticeHeat Networks Code of Practice
Heat Networks Code of PracticeSimon Owen FIRP
 
Circular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptxCircular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptxMircea Gingu
 
Introduction to djuvik
Introduction to djuvikIntroduction to djuvik
Introduction to djuvikCem Sayar
 
COMOSS, the solution partner
COMOSS, the solution partnerCOMOSS, the solution partner
COMOSS, the solution partnermakattocomoss
 
Engineering systems : sustainability rules.
Engineering systems : sustainability rules.Engineering systems : sustainability rules.
Engineering systems : sustainability rules.BRONSWERK
 
2015 Turn Cycle Solutions Millyard Resentation
2015 Turn Cycle Solutions Millyard Resentation2015 Turn Cycle Solutions Millyard Resentation
2015 Turn Cycle Solutions Millyard Resentationmsnelling
 
Pas2030 presentation april 2013 3
Pas2030 presentation april 2013 3Pas2030 presentation april 2013 3
Pas2030 presentation april 2013 3Scott Buckler
 
Refrigeration Brochure
Refrigeration BrochureRefrigeration Brochure
Refrigeration Brochurea1-cbiss
 
REMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREAS
REMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREASREMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREAS
REMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREASiQHub
 
Energizing a sustainable rail industry
Energizing a sustainable rail industryEnergizing a sustainable rail industry
Energizing a sustainable rail industryEaton Electrical
 
Erkasis company presentation
Erkasis company presentationErkasis company presentation
Erkasis company presentationTomasz Szewczyk
 
Energy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of CambridgeEnergy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of CambridgeJISC's Green ICT Programme
 
Case study abb mission and vision
Case study abb mission and visionCase study abb mission and vision
Case study abb mission and visionVictoria University
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Morgan
 

Similar to Andrej prezentacija Logstor DBDH Kopaonik (20)

Title Product brochure and services_LAPSOLITE.pdf
Title Product brochure and services_LAPSOLITE.pdfTitle Product brochure and services_LAPSOLITE.pdf
Title Product brochure and services_LAPSOLITE.pdf
 
iCool CO2 transcritical condensing units
iCool CO2 transcritical condensing unitsiCool CO2 transcritical condensing units
iCool CO2 transcritical condensing units
 
Heat Networks Code of Practice
Heat Networks Code of PracticeHeat Networks Code of Practice
Heat Networks Code of Practice
 
Circular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptxCircular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptx
 
Introduction to djuvik
Introduction to djuvikIntroduction to djuvik
Introduction to djuvik
 
COMOSS, the solution partner
COMOSS, the solution partnerCOMOSS, the solution partner
COMOSS, the solution partner
 
COMOSS, the solution partner
COMOSS, the solution partnerCOMOSS, the solution partner
COMOSS, the solution partner
 
ISS Company Profile 2015 most updated
ISS Company Profile 2015 most updatedISS Company Profile 2015 most updated
ISS Company Profile 2015 most updated
 
Engineering systems : sustainability rules.
Engineering systems : sustainability rules.Engineering systems : sustainability rules.
Engineering systems : sustainability rules.
 
2015 Turn Cycle Solutions Millyard Resentation
2015 Turn Cycle Solutions Millyard Resentation2015 Turn Cycle Solutions Millyard Resentation
2015 Turn Cycle Solutions Millyard Resentation
 
Pas2030 presentation april 2013 3
Pas2030 presentation april 2013 3Pas2030 presentation april 2013 3
Pas2030 presentation april 2013 3
 
Refrigeration Brochure
Refrigeration BrochureRefrigeration Brochure
Refrigeration Brochure
 
REMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREAS
REMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREASREMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREAS
REMOTE NETWORK CONDUCTIVITY MONITORING IN DUAL SUPPLY AREAS
 
Kevin Fitzgibbon
Kevin FitzgibbonKevin Fitzgibbon
Kevin Fitzgibbon
 
Energizing a sustainable rail industry
Energizing a sustainable rail industryEnergizing a sustainable rail industry
Energizing a sustainable rail industry
 
AMFA Company profile . !BS shw
AMFA Company profile . !BS shwAMFA Company profile . !BS shw
AMFA Company profile . !BS shw
 
Erkasis company presentation
Erkasis company presentationErkasis company presentation
Erkasis company presentation
 
Energy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of CambridgeEnergy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of Cambridge
 
Case study abb mission and vision
Case study abb mission and visionCase study abb mission and vision
Case study abb mission and vision
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
 

Andrej prezentacija Logstor DBDH Kopaonik

  • 1. LOGSTOR Defining Network Efficiency •1 Danish District Heating Sector Visit to Brzece – 28.05.2015 Andrei Ovidiu Bita – Balkan Area Sales Manager
  • 2. •2 Energy Challenges looking to District Heating • Increased energy consumption by growing demographics & wealth • Energy consumption will grow by over a third up to 2035 • 70% of the world‘s estimated 10 billion inhabitants will be part of massive urban networks by 2050 • Cities are home to 80% of EUs population and to more than half the people on the planet • Up to 70% of carbon emissions come from cities and cities have an extra responsibility to combat climate change • Long overdue need for action Accelerating the uptake of energy efficiency and renewable energy in the global energy mix is the single biggest contribution to keep global temperature rise under 2C
  • 3. •3 Who We Are & Our Vision To make the World's energy supply more efficient and reduce the global energy loss with leading insulation products, improving the environment for the populations in all continents. The world’s leading manufacturer of pre- insulated pipes for energy efficient transportation of gases and liquids for district energy.
  • 4. •4 Our Focus Oil & Gas Industry District energy – heating & cooling
  • 5. Sales Production Mobile Plant Joint venture  8 plants in Europe, 1 in Asia, 2 mobile production units  14 Sales units  Joint ventures in China and Dubai  Distributors in more than 30 countries  More than 5,000 km pre-insulated pipes every year  More than LOGSTOR pipe supplied to date Headquarters in Denmark 1,500 employees Annual turnover > 250 MEUR Owner: Triton Fund III The LOGSTOR Group & our global presence
  • 6. The LOGSTOR Group & our Balkan presence •Flexibility and speedy deliveries & service •LOGSTOR continues its international growth strategy and takes over production and sales from the competitor Stizo Termo SA in Romania as of 1 March 2009. •Better presence on Balkan Markets •Competitive prices - same LOGSTOR QUALITY
  • 7. •7 Our Value Proposition Lowest total cost of operation • Insulation Technologies • Lifetime Insulation protection • Integrated Solutions Effective installation • LOGSTOR Joints • LOGSTOR Design Services • Documentation & Certification Longest life time • Surveillance • LOGSTOR Calculator • LOGSTOR Services Customer Excellence • Responsiveness • Transport & Delivery Accuracy • Accountability
  • 8. •8 Integrated Solutions • One integrated solution for the whole pipe system • Designed to minimize installation & operating costs • Optimum insulation ensures low operating costs – Reduces heat loss – Improve energy efficiency – Reduces CO2 emissions • Service before, during and after installation • Quality, durability and lifetime beyond 30 years • 50 years of experience inventing pre-insulated pipe technology
  • 9. •9 The largest producer of high quality pre-insulated solutions • Pre-insulated pipes for temperatures from: -200 to +250°C Straight pipes, from DN 20 to DN1200 – More than 10,000 km • Flexible pipes, from DN15 to DN110 – More than 3,000 km • Joints (mechanical, shrinkable & weldable) – More than 1,000,000 units • Pre-insulated fittings – More than 250,000 units
  • 10. •10 Total Cost of Ownership / Lifetime costs 1. Investment costs (Non-recurrent costs) – Purchase costs, components – Installation costs – Costs of planning and commissioning 2. Operating costs (annual costs) – Costs of energy & heat loss – Costs of maintenance – Costs of repairs – Costs of poor quality 3. Total costs of the solution Investment Cost Operating Costs 30 years
  • 11. •11 Our Services • Before installation – Design Manual - optimal design of the pipe system – Calculator – calculate how to minimize operation costs, heat loss and CO2 emissions • During installation – Weldmaster - greater security, better quality control and easy traceability of joints – Complete Manual for Handling and Installation – Training courses & certification - fitters and supervisors • After installation – LOGSTOR Detect - monitors and reports on failures or potential failures
  • 12. •12 Our Experience & Know-How • Suitable for big, medium and small scale district energy – New installations & Maintenance – Retrofit applications – Compatible with existing pipe systems • Quick adaptation to new markets – Mobile production plants – Global network of alliances and partners • 50 years of experience with pre-insulated solutions
  • 13. •13 Documentation, Quality & Safety • The European standards = 30 years service life – Comply or do better! – External tests of properties – Constantly internal test • Focus on quality – ISO 9001 certification – EUROHEAT & POWER certified • Focus on environmental aspects – ISO 14001 certification • Focus on Health & Safety for our people – Leading & lagging indicators at all sites – OHSAS 18001 certification on selected sites
  • 14. •14 Energy Efficiency / Heat Loss • Lower operating costs • Less environmental impact Our diffusion barrier – Prevents ageing of insulation – Reduces energy losses – Implemented in pipes & joints Cyclopentane, λ = 0.012 W/mK CO2, λ = 0.017 W/mK λair= 0.0<27 W/mK Oxygen NitrogenLambda (λ) expresses the insulation property of a material. The lower the lambda value, the better the insulation. The heat loss from LOGSTOR pre-insulated pipes fitted with a diffusion barrier is as much as 15-30% less than if the diffusion barrier is omitted from the specifications.
  • 15. •15 Internal Testing • We measures the lambda value continuously • Test equipment delivered by the Danish Technological Institute • We participate in Round Robin tests with external institutes • Results available on: www.logstor.com •04/06/2015
  • 16. •16 Costs Of Maintenance & Repair Durable jointing systems • Joint systems constructed to 30+ years of operation • Fusion welded joints • Shrinkable systems including joints, bends and branches •04/06/2015
  • 17. •17 System monitoring / surveillance • Our LOGSTOR Detect system monitors the functionality of a pipe system • Offered as a cloud based solution (Software as a Service) • Impedance and resistance measurement identify any faults in the pipe system • Monitoring of wells & control of temperature and pressure • Our solution analyse all data from the system. x • Communication via GPRS •04/06/2015
  • 18. •18 Our Innovative design – Reduce Costs Designed to reduce the meter of pipes and components required • Reduced purchase costs & installation costs • Reduced time of installation & civil works E-Comp TwinPipes Curved pipes •04/06/2015
  • 19. •19 Our Innovative design – Twin Pipe •04/06/2015 You avoid 9 joints and 8 welds Possible up to DN 200 You avoid 3 joints Possible up to DN 100 Reduces excavation by 20%
  • 20. •20 Our Innovative software •04/06/2015 • LOGSTOR Calculator – Web based tool to calculate • Heat loss • Costs for heat loss • CO2 emissions – Calculations as support for decisions on insulation series and design
  • 21. •21 Serbia – KfW IV overview •04/06/2015 • Reconstruction of DH networks in 17 cities at the same time; • Contract signed end of May 2013; • Entire design checked and modified by internal LOGSTOR design department together with end beneficiaries; • More than - 89 km of preinsulated pipes; - 6000 pcs of preinsulated fittings; - 20.000 pcs of joints , delivered in less than 12 months despite of hundreds of unforeseen changes of design according real on-site situation.
  • 22. •22 Serbia – KfW IV overview •04/06/2015 • Due to the complexity of the project and short implementation period, inevitably problems occurred, such as: - Differences between designed situation vs. on-site reality; - Damaged products due improper transportation or unloading; - Wrong delivered products; - Various installing issues; All of them were immediately solved by mean of LOGSTOR permanent support !
  • 23. •23 Serbia – KfW IV overview •04/06/2015 • LOGSTOR quality was implemented: - Diffusion barrier / NO ageing, high insulation capacity; - ONE-TIME compensators – NO U-loops, less works and pressure losses; - Local insulation foam packs technology – quick installation, reliable joints; - Surveillance system plus training in groups of cities; By means LOGSTOR factories positioning – flexible deliveries and fast reaction were possible – against complicated export procedures. Following the proper conduct of the contract, additional orders and even a new city is being delivered as we speak.
  • 24. •24 Nobody is perfect.... But we are close to ... and still improving. Documentation @ www.logstor.com/documentation
  • 25. •25 Or want to know some more details….