Improving Contract (Management) Capabilities
to Reduce Project Risks
Matthew Rae
Manager Networks Procurement
Oil & Gas Procurement and Supply
26-27 November 2013
APA Group, November 2013 2
Project Risk - what can go wrong?
APA Group, November 2013 3
APA Group, November 2013 4
Mexican President Felipe Calderon ordered an
investigation into the blast, yet 14 months on
the cause has still not been confirmed.
Contractual issues that arise from such an incident:
Consequential Loss
direct and indirect
Public & Product Liability Insurance claims
Workers Compensation claims
Warranties
Liquidated Damages
Defects Liability
APA Group, November 2013 5
APA Group, November 2013 6
The cause of the incident, a Columbia Gas worker, who
responding to a gas leak, came to the building and began using
a metal probe to make holes, as he tried to measure gas levels.
In the process, the worker punctured a gas line that was
improperly marked. Once the worker realized this, people in
the area were evacuated immediately.
It took Columbia Gas up to thirty minutes to shut off the gas,
but in that time, enough gas had already seeped into the
building, which then led to the explosion.
APA Group, November 2013 7
Agenda
About APA
Overcoming limitations and the need for flexibility
Building risk and reward into contracts
Your legal department and you drafting governance and dispute resolution
Challenging the pricing and terms
Questions
APA Group, November 2013 8
APA asset and investment portfolio
APA Group, November 2013 9
June 2000 June 2013
Infrastructure owner and manager Integrated operating business
Market
capital
$0.49 billion $5.1 billion
S&P/ASX 50
MSCI and FTSE World Indices
Assets
owned /
operated
$1.3 billion $12 billion
7,000 km gas transmission 14,120 km gas transmission
25,000 km gas distribution
Underground and LNG gas storage facilities
430 MW power generation (1)
239 km HV electricity transmission
Transporting 25%
of domestic natural gas
Transporting 50% of domestic natural gas,
70% in east Australia
Employees 6 More than 1,500
Operator External (Agility) Internal
… to Australia’s largest gas infrastructure business
(1) Includes the Diamantina and Leichhardt power stations under development
From IPO in June 2000…
APA Group, November 2013 10
Overcoming limitations and the need for flexibility
APA Group, November 2013 11
Energy industry is among the most dispute-intensive industries in the world economy
Oil and gas contracts generate a high volume of disputes
Type of dispute and stakeholders involved vary
A contract is an agreement between two parties
The nature of oil and gas contractual disputes
Contract management is aimed
not at finding fault, but rather at
identifying problems and finding solutions together
with all contracting parties involved
Overcoming limitations and the need for flexibility
APA Group, November 2013 12
In todays market….majority of companies have
standard form contracts
Drafted by the party with superior bargaining
power
Basic PO’s through to complex agreements
Market power may dictate a ‘take them or leave
them approach’
Intention is to improve efficiency
Standard form contracts
Overcoming limitations and the need for flexibility
APA Group, November 2013 13
There is no one size fits all approach
Companies usually have a standard contractual position
End users should understand the acceptable changes
A starting point for contractual discussions as part of the sourcing process
Flexibility in terms and conditions
The focus when negotiating t’s and c’s should be on
reaching agreement with the other party,
this will require
Overcoming limitations and the need for flexibility
APA Group, November 2013 14
Building risk and reward into contracts
APA Group, November 2013 15
Under or over specifying requirements
Contractor hitting a third party asset
Late project delivery and impacts
Major gas leak and potential gas outage
Environmental incident
Explosion
Fatality or serious injury
What risk?
Every risk has a “likelihood” and a “consequence”.
The higher likelihood and the worse the consequence, the higher the
risk rating
What is the appropriate allocation of project risks for a contract?
Building risk and reward into contracts
APA Group, November 2013 16
“Carrot and Stick”
Risk and reward can mean different things
Rewarding the contractor for over performing
The reward or carrot
Needs to be commensurate with value and risk
Performance based contracting
Reward types
Building risk and reward into contracts
APA Group, November 2013 17
To incentivise parties to the contract
For the appropriate allocation of risk
Contractors perspective….. more interest in the rewards and less in accepting
risk
To provide a framework for both contracting parties
“Back to back” any risks associated with penalties in third party agreements
with the contractor delivering the works
Why build risk and reward clauses into contracts?
Many contracting parties…..“enter into discussions about risk-reward to
reduce the chances of something going wrong, but get scared off the idea by
a sudden realisation about what might happen if something goes right.”
Source: Edward Height, a director at Source Information Services
Building risk and reward into contracts
APA Group, November 2013 18
Uncommon for standard form contracts to have them
A successful risk-reward mechanism is often based on predefined KPI’s or SLA’s
It’s not all about the bonus for exceeding milestones
Linking risk and reward mechanisms
Liquidated Damages (LD’s)
Consequential Loss & Limited Liability
Transferring too much risk can mean high contingency costs
Representing risk and reward clauses in contracts
Building risk and reward into contracts
APA Group, November 2013 19
Your legal department and you – drafting,
governance and dispute resolution
APA Group, November 2013 20
Engaging with legal from the outset and throughout
Majority of companies have standard form contracts
Talk to your Legal Department re customised or “off the shelf
agreement
Identify clarifications and/or exceptions to T’s and C’s
Post implementation reviews - feedback
Contract selection and drafting
Drafting, governance and dispute resolution
APA Group, November 2013 21
Governance and Dispute Resolution
Most contracts do not deal with the situation in which a dispute arises
Building these clauses in contracts provides a means of resolving commercial
disputes
Care needs to be taken in completing schedules that comprise dispute resolution so
that the provision has the effect intended by the parties.
Dispute resolution clauses should be drafted with clarity, precision and to ensure
they meet the intended purpose.
If contractual disputes do arise, it is important that these are managed in close
liaison with legal counsel to avoid any unnecessary litigation
Poorly drafted dispute resolution clauses may result in delay, expense
and inconvenience
Drafting, governance and dispute resolution
………. the very opposite of the desired result !!
APA Group, November 2013 22
Challenging the pricing decisions and terms
APA Group, November 2013 23
What is the pricing methodology to be used?
– Fixed Lump Sum Price
– Schedule of Rates
– Cost plus
– Management Fee
What are the major price drivers?
– Cost of Labour
– Raw Materials Pricing
– Manufacturing and Tooling Costs
– Freight and Logistic Costs
What is the rise and fall mechanism?
– CPI movements
– FOREX Movements
– Commodity price movements
Types of pricing decisions?
How can we challenge the contractor’s
pricing decisions?………………..in a word:
“transparency”
Challenging the pricing decisions and terms
APA Group, November 2013 24
Understanding what makes up the cost of a finished product
Numerous sources of market indicators
Exploring rates for materials
Price of iron ore, directly
impacts the price of ERW
and Seamless Line Pipe
Oil is major component in
the production Pipe and
Fittings
The major raw material
input to meter set pipe
work, valves and fittings
Exchange rate also has an
impact on the imported
content component of
materials
Challenging the pricing decisions and terms
APA Group, November 2013 25
An example of a typical Schedule of Rates
Exploring rates for labour
Item Trade UOM Normal Time Penalty Rate
1 Trade Assistant $/Hour $53.40 $72.00
2 Crew Hourly Rate $/Hour $1,306.00 $1,633.00
3 Team Leader $/Hour $80.00 $100.00
4
Field Operative /
Labourer
$/Hour $60.00 $75.00
5 Plant Operator $/Hour $65.00 $82.00
6 Welder $/Hour $160.00 $200.00
7 Gasfitter $/Hour $120.00 $150.00
Challenging the pricing decisions and terms
APA Group, November 2013 26
Labour rates driven by Enterprise Bargaining Agreement (EBA’s)
EBA’s can be both union and non-unionised
Unionised EBA’s are available in the public domain, which allows us to see the
labour breakdown
Exploring rates for labour – rate buildups
Amount UOM Hrly Rate
Base Rate $30.00
Superannuation 9.50 % $0.38
Workers Compensation 4.00 % $0.16
Overtime Meal Allowance 20.00 $ $2.63
Travel Allowance $0.75 $/km $9.87
Leave Loading 17.50 % $0.69
Living Away from Home (Distant Work) $62.70 $/day $8.25
First Aid Allowance (min qualification) $2.61 $/day $0.34
Overhead 7.50 % $0.30
Profit 20.00 % $0.79
Income Tax 15.00 % $0.59
Actual Rate $53.40
Trade Assistant $53.40 per hour
Statutory
Requirements
Meal allowance
payable when required
to work Overtime, e.g.
by more than 1.5hrs
Annual leave payment
paid with Leave loading
of 17.5%
A payment made to a
worker where an
employment event
requires them to use
accommodation other
than their normal
place of residence
Statutory
Requirements
Understand labour cost……for cost avoidance and
to avoid double dipping !!Challenging the pricing decisions and terms
APA Group, November 2013 27
Total Cost of Ownership (TCO) of the life of an asset
Include: planning, design, construction and acquisition, maintenance, renewal,
depreciation and cost of finance
TCO expands the narrow confines of price to a vast field of opportunities
Price is not only different from cost, in fact it is merely one element of cost
Through life support/TCO
Anyone can get a lower price.
The object of good business is to
attain the lowest TCO.
Challenging the pricing decisions and terms
APA Group, November 2013 28
Procurement set the pricing structure
Dependent on the type of good or service
Rates x Hours = Happiness
Lump Sum Contracts = high mark-up/contingency for allocation of risk
Understanding the impact on cost a change in on one or more components has
on total cost
Using mutually agreed rise and fall mechanisms
Challenging the contractor’s pricing/costing decisions
Challenging the pricing decisions and terms
APA Group, November 2013 29
Be clear on the outcome you are driving to achieve
Focus should be on reaching agreement with the other party - stay
flexible
Own and understand your contract
Spend your companies money as if it were your own….seek
transparency, ask questions
Avoid Mexico….its far too dangerous there !!!
Some key takeaways…
APA Group, November 2013 30
Questions
APA Group, November 2013 31
For further information contact
Matthew Rae
Manager Networks Procurement, APA Group
Tel: +61 8 8113 9029
E-mail: matthew.rae@apa.com.au
or visit APA’s website
www.apa.com.au
Delivering Australia’s Energy

More Related Content

Similar to Improving Contractor (Management) Capabilities to Reduce Project Risks

Resolving Legal and Audit Issues in an Internal Compliance Investigation
Resolving Legal and Audit Issues in anInternal Compliance InvestigationResolving Legal and Audit Issues in anInternal Compliance Investigation
Resolving Legal and Audit Issues in an Internal Compliance InvestigationPYA, P.C.
 
The Contracting Conundrum (Apr 2009)
The Contracting Conundrum (Apr 2009)The Contracting Conundrum (Apr 2009)
The Contracting Conundrum (Apr 2009)David Noort
 
33.1.016 Construction Fuel Case Study
33.1.016 Construction Fuel Case Study33.1.016 Construction Fuel Case Study
33.1.016 Construction Fuel Case StudyClark Cledwyn Bagaipo
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projectsCraig Brown
 
Tmt conference 2013 presentation slide pack
Tmt conference 2013   presentation slide packTmt conference 2013   presentation slide pack
Tmt conference 2013 presentation slide packEversheds Sutherland
 
FASBIASB Field testing white paper 11 October 2013
FASBIASB Field testing white paper 11 October 2013FASBIASB Field testing white paper 11 October 2013
FASBIASB Field testing white paper 11 October 2013Eve Pastor, CPA, CGMA
 
Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...
Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...
Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...Energy Construction Forum
 
PM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement ManagementPM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement ManagementMohammad Elsheimy
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4Thanh Nguyen
 
12/05: ARTBA DBE “Listening Session” Statement
12/05: ARTBA DBE “Listening Session” Statement12/05: ARTBA DBE “Listening Session” Statement
12/05: ARTBA DBE “Listening Session” Statementartba
 
Procurement in the age of Agile: Enlightened Agile Teams and Heathen Vendors
Procurement in the age of Agile: Enlightened Agile Teams and Heathen VendorsProcurement in the age of Agile: Enlightened Agile Teams and Heathen Vendors
Procurement in the age of Agile: Enlightened Agile Teams and Heathen VendorsSteve Nunziata
 
Market intelligence March 2016
Market intelligence March 2016Market intelligence March 2016
Market intelligence March 2016Alan Birse
 
Supply chain risks mitigation 080515 ahmed aliyu_lawal
Supply chain risks mitigation 080515  ahmed aliyu_lawalSupply chain risks mitigation 080515  ahmed aliyu_lawal
Supply chain risks mitigation 080515 ahmed aliyu_lawalAliyu Ahmed
 
Conflict Mineral Compliance Toolkit For Executives
Conflict Mineral Compliance Toolkit For Executives Conflict Mineral Compliance Toolkit For Executives
Conflict Mineral Compliance Toolkit For Executives Matt Whitteker
 
Agile Contracts by Drew Jemilo (Agile2015)
Agile Contracts by Drew Jemilo (Agile2015)Agile Contracts by Drew Jemilo (Agile2015)
Agile Contracts by Drew Jemilo (Agile2015)Drew Jemilo
 

Similar to Improving Contractor (Management) Capabilities to Reduce Project Risks (20)

Practitioner class 3: Contract strategy
Practitioner class 3: Contract strategyPractitioner class 3: Contract strategy
Practitioner class 3: Contract strategy
 
Pacific case
Pacific casePacific case
Pacific case
 
Resolving Legal and Audit Issues in an Internal Compliance Investigation
Resolving Legal and Audit Issues in anInternal Compliance InvestigationResolving Legal and Audit Issues in anInternal Compliance Investigation
Resolving Legal and Audit Issues in an Internal Compliance Investigation
 
1504 CIPS Qatar IDH
1504 CIPS Qatar IDH1504 CIPS Qatar IDH
1504 CIPS Qatar IDH
 
The Contracting Conundrum (Apr 2009)
The Contracting Conundrum (Apr 2009)The Contracting Conundrum (Apr 2009)
The Contracting Conundrum (Apr 2009)
 
33.1.016 Construction Fuel Case Study
33.1.016 Construction Fuel Case Study33.1.016 Construction Fuel Case Study
33.1.016 Construction Fuel Case Study
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projects
 
Tmt conference 2013 presentation slide pack
Tmt conference 2013   presentation slide packTmt conference 2013   presentation slide pack
Tmt conference 2013 presentation slide pack
 
FASBIASB Field testing white paper 11 October 2013
FASBIASB Field testing white paper 11 October 2013FASBIASB Field testing white paper 11 October 2013
FASBIASB Field testing white paper 11 October 2013
 
Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...
Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...
Contractor Track: Need for Speed - Project Acceleration, Tech Trends, Logisti...
 
PM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement ManagementPM Notebook - Chapter 12 - Procurement Management
PM Notebook - Chapter 12 - Procurement Management
 
Creating the Innovation Platform
Creating the Innovation PlatformCreating the Innovation Platform
Creating the Innovation Platform
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
 
12/05: ARTBA DBE “Listening Session” Statement
12/05: ARTBA DBE “Listening Session” Statement12/05: ARTBA DBE “Listening Session” Statement
12/05: ARTBA DBE “Listening Session” Statement
 
Procurement in the age of Agile: Enlightened Agile Teams and Heathen Vendors
Procurement in the age of Agile: Enlightened Agile Teams and Heathen VendorsProcurement in the age of Agile: Enlightened Agile Teams and Heathen Vendors
Procurement in the age of Agile: Enlightened Agile Teams and Heathen Vendors
 
Market intelligence March 2016
Market intelligence March 2016Market intelligence March 2016
Market intelligence March 2016
 
ENGINEERING-ECONOMY.docx
ENGINEERING-ECONOMY.docxENGINEERING-ECONOMY.docx
ENGINEERING-ECONOMY.docx
 
Supply chain risks mitigation 080515 ahmed aliyu_lawal
Supply chain risks mitigation 080515  ahmed aliyu_lawalSupply chain risks mitigation 080515  ahmed aliyu_lawal
Supply chain risks mitigation 080515 ahmed aliyu_lawal
 
Conflict Mineral Compliance Toolkit For Executives
Conflict Mineral Compliance Toolkit For Executives Conflict Mineral Compliance Toolkit For Executives
Conflict Mineral Compliance Toolkit For Executives
 
Agile Contracts by Drew Jemilo (Agile2015)
Agile Contracts by Drew Jemilo (Agile2015)Agile Contracts by Drew Jemilo (Agile2015)
Agile Contracts by Drew Jemilo (Agile2015)
 

Improving Contractor (Management) Capabilities to Reduce Project Risks

  • 1. Improving Contract (Management) Capabilities to Reduce Project Risks Matthew Rae Manager Networks Procurement Oil & Gas Procurement and Supply 26-27 November 2013
  • 2. APA Group, November 2013 2 Project Risk - what can go wrong?
  • 4. APA Group, November 2013 4 Mexican President Felipe Calderon ordered an investigation into the blast, yet 14 months on the cause has still not been confirmed. Contractual issues that arise from such an incident: Consequential Loss direct and indirect Public & Product Liability Insurance claims Workers Compensation claims Warranties Liquidated Damages Defects Liability
  • 6. APA Group, November 2013 6 The cause of the incident, a Columbia Gas worker, who responding to a gas leak, came to the building and began using a metal probe to make holes, as he tried to measure gas levels. In the process, the worker punctured a gas line that was improperly marked. Once the worker realized this, people in the area were evacuated immediately. It took Columbia Gas up to thirty minutes to shut off the gas, but in that time, enough gas had already seeped into the building, which then led to the explosion.
  • 7. APA Group, November 2013 7 Agenda About APA Overcoming limitations and the need for flexibility Building risk and reward into contracts Your legal department and you drafting governance and dispute resolution Challenging the pricing and terms Questions
  • 8. APA Group, November 2013 8 APA asset and investment portfolio
  • 9. APA Group, November 2013 9 June 2000 June 2013 Infrastructure owner and manager Integrated operating business Market capital $0.49 billion $5.1 billion S&P/ASX 50 MSCI and FTSE World Indices Assets owned / operated $1.3 billion $12 billion 7,000 km gas transmission 14,120 km gas transmission 25,000 km gas distribution Underground and LNG gas storage facilities 430 MW power generation (1) 239 km HV electricity transmission Transporting 25% of domestic natural gas Transporting 50% of domestic natural gas, 70% in east Australia Employees 6 More than 1,500 Operator External (Agility) Internal … to Australia’s largest gas infrastructure business (1) Includes the Diamantina and Leichhardt power stations under development From IPO in June 2000…
  • 10. APA Group, November 2013 10 Overcoming limitations and the need for flexibility
  • 11. APA Group, November 2013 11 Energy industry is among the most dispute-intensive industries in the world economy Oil and gas contracts generate a high volume of disputes Type of dispute and stakeholders involved vary A contract is an agreement between two parties The nature of oil and gas contractual disputes Contract management is aimed not at finding fault, but rather at identifying problems and finding solutions together with all contracting parties involved Overcoming limitations and the need for flexibility
  • 12. APA Group, November 2013 12 In todays market….majority of companies have standard form contracts Drafted by the party with superior bargaining power Basic PO’s through to complex agreements Market power may dictate a ‘take them or leave them approach’ Intention is to improve efficiency Standard form contracts Overcoming limitations and the need for flexibility
  • 13. APA Group, November 2013 13 There is no one size fits all approach Companies usually have a standard contractual position End users should understand the acceptable changes A starting point for contractual discussions as part of the sourcing process Flexibility in terms and conditions The focus when negotiating t’s and c’s should be on reaching agreement with the other party, this will require Overcoming limitations and the need for flexibility
  • 14. APA Group, November 2013 14 Building risk and reward into contracts
  • 15. APA Group, November 2013 15 Under or over specifying requirements Contractor hitting a third party asset Late project delivery and impacts Major gas leak and potential gas outage Environmental incident Explosion Fatality or serious injury What risk? Every risk has a “likelihood” and a “consequence”. The higher likelihood and the worse the consequence, the higher the risk rating What is the appropriate allocation of project risks for a contract? Building risk and reward into contracts
  • 16. APA Group, November 2013 16 “Carrot and Stick” Risk and reward can mean different things Rewarding the contractor for over performing The reward or carrot Needs to be commensurate with value and risk Performance based contracting Reward types Building risk and reward into contracts
  • 17. APA Group, November 2013 17 To incentivise parties to the contract For the appropriate allocation of risk Contractors perspective….. more interest in the rewards and less in accepting risk To provide a framework for both contracting parties “Back to back” any risks associated with penalties in third party agreements with the contractor delivering the works Why build risk and reward clauses into contracts? Many contracting parties…..“enter into discussions about risk-reward to reduce the chances of something going wrong, but get scared off the idea by a sudden realisation about what might happen if something goes right.” Source: Edward Height, a director at Source Information Services Building risk and reward into contracts
  • 18. APA Group, November 2013 18 Uncommon for standard form contracts to have them A successful risk-reward mechanism is often based on predefined KPI’s or SLA’s It’s not all about the bonus for exceeding milestones Linking risk and reward mechanisms Liquidated Damages (LD’s) Consequential Loss & Limited Liability Transferring too much risk can mean high contingency costs Representing risk and reward clauses in contracts Building risk and reward into contracts
  • 19. APA Group, November 2013 19 Your legal department and you – drafting, governance and dispute resolution
  • 20. APA Group, November 2013 20 Engaging with legal from the outset and throughout Majority of companies have standard form contracts Talk to your Legal Department re customised or “off the shelf agreement Identify clarifications and/or exceptions to T’s and C’s Post implementation reviews - feedback Contract selection and drafting Drafting, governance and dispute resolution
  • 21. APA Group, November 2013 21 Governance and Dispute Resolution Most contracts do not deal with the situation in which a dispute arises Building these clauses in contracts provides a means of resolving commercial disputes Care needs to be taken in completing schedules that comprise dispute resolution so that the provision has the effect intended by the parties. Dispute resolution clauses should be drafted with clarity, precision and to ensure they meet the intended purpose. If contractual disputes do arise, it is important that these are managed in close liaison with legal counsel to avoid any unnecessary litigation Poorly drafted dispute resolution clauses may result in delay, expense and inconvenience Drafting, governance and dispute resolution ………. the very opposite of the desired result !!
  • 22. APA Group, November 2013 22 Challenging the pricing decisions and terms
  • 23. APA Group, November 2013 23 What is the pricing methodology to be used? – Fixed Lump Sum Price – Schedule of Rates – Cost plus – Management Fee What are the major price drivers? – Cost of Labour – Raw Materials Pricing – Manufacturing and Tooling Costs – Freight and Logistic Costs What is the rise and fall mechanism? – CPI movements – FOREX Movements – Commodity price movements Types of pricing decisions? How can we challenge the contractor’s pricing decisions?………………..in a word: “transparency” Challenging the pricing decisions and terms
  • 24. APA Group, November 2013 24 Understanding what makes up the cost of a finished product Numerous sources of market indicators Exploring rates for materials Price of iron ore, directly impacts the price of ERW and Seamless Line Pipe Oil is major component in the production Pipe and Fittings The major raw material input to meter set pipe work, valves and fittings Exchange rate also has an impact on the imported content component of materials Challenging the pricing decisions and terms
  • 25. APA Group, November 2013 25 An example of a typical Schedule of Rates Exploring rates for labour Item Trade UOM Normal Time Penalty Rate 1 Trade Assistant $/Hour $53.40 $72.00 2 Crew Hourly Rate $/Hour $1,306.00 $1,633.00 3 Team Leader $/Hour $80.00 $100.00 4 Field Operative / Labourer $/Hour $60.00 $75.00 5 Plant Operator $/Hour $65.00 $82.00 6 Welder $/Hour $160.00 $200.00 7 Gasfitter $/Hour $120.00 $150.00 Challenging the pricing decisions and terms
  • 26. APA Group, November 2013 26 Labour rates driven by Enterprise Bargaining Agreement (EBA’s) EBA’s can be both union and non-unionised Unionised EBA’s are available in the public domain, which allows us to see the labour breakdown Exploring rates for labour – rate buildups Amount UOM Hrly Rate Base Rate $30.00 Superannuation 9.50 % $0.38 Workers Compensation 4.00 % $0.16 Overtime Meal Allowance 20.00 $ $2.63 Travel Allowance $0.75 $/km $9.87 Leave Loading 17.50 % $0.69 Living Away from Home (Distant Work) $62.70 $/day $8.25 First Aid Allowance (min qualification) $2.61 $/day $0.34 Overhead 7.50 % $0.30 Profit 20.00 % $0.79 Income Tax 15.00 % $0.59 Actual Rate $53.40 Trade Assistant $53.40 per hour Statutory Requirements Meal allowance payable when required to work Overtime, e.g. by more than 1.5hrs Annual leave payment paid with Leave loading of 17.5% A payment made to a worker where an employment event requires them to use accommodation other than their normal place of residence Statutory Requirements Understand labour cost……for cost avoidance and to avoid double dipping !!Challenging the pricing decisions and terms
  • 27. APA Group, November 2013 27 Total Cost of Ownership (TCO) of the life of an asset Include: planning, design, construction and acquisition, maintenance, renewal, depreciation and cost of finance TCO expands the narrow confines of price to a vast field of opportunities Price is not only different from cost, in fact it is merely one element of cost Through life support/TCO Anyone can get a lower price. The object of good business is to attain the lowest TCO. Challenging the pricing decisions and terms
  • 28. APA Group, November 2013 28 Procurement set the pricing structure Dependent on the type of good or service Rates x Hours = Happiness Lump Sum Contracts = high mark-up/contingency for allocation of risk Understanding the impact on cost a change in on one or more components has on total cost Using mutually agreed rise and fall mechanisms Challenging the contractor’s pricing/costing decisions Challenging the pricing decisions and terms
  • 29. APA Group, November 2013 29 Be clear on the outcome you are driving to achieve Focus should be on reaching agreement with the other party - stay flexible Own and understand your contract Spend your companies money as if it were your own….seek transparency, ask questions Avoid Mexico….its far too dangerous there !!! Some key takeaways…
  • 30. APA Group, November 2013 30 Questions
  • 31. APA Group, November 2013 31 For further information contact Matthew Rae Manager Networks Procurement, APA Group Tel: +61 8 8113 9029 E-mail: matthew.rae@apa.com.au or visit APA’s website www.apa.com.au Delivering Australia’s Energy