The document summarizes the new product development process for the OPT 2027 outdoor payment terminal. It involves preliminary market research, engineering pre-studies, prototype testing and certification, and a product launch. Key steps include a management review of the feasibility study, signing off on the development order, designing and assembling prototypes, evaluating the prototypes, and completing safety and regulatory testing before marketing and launching the new product.
2. Intellect Business Partner ConferenceIntellect Business Partner Conference
The Birth Process of a new ProductThe Birth Process of a new Product
The OPT 2027The OPT 2027
Luc Ferange - Product Manager
6. Preliminary research by thePreliminary research by the
Product ManagerProduct Manager
INTERNET
VISIT FAIRS
7. Preliminary research by thePreliminary research by the
Product ManagerProduct Manager
INTERNET
VISIT FAIRS
CONSULTING
MAGAZINES
8. Preliminary research by thePreliminary research by the
Product ManagerProduct Manager
INTERNET
VISIT FAIRS
CONSULTING
MAGAZINES
VISIT
POTENTIONAL
CUSTOMERS
OR INTELLECT
DISTRIBUTORS
9. Preliminary research by thePreliminary research by the
Product ManagerProduct Manager
PRODUCING
A REPORT
10. Preliminary research by thePreliminary research by the
Product ManagerProduct Manager
PRODUCING
A REPORT
17. Company Product Strategy MeetingCompany Product Strategy Meeting
Management evaluates
the feasibility of the
project, based on the
preliminary information
go ahead for a pre-study
to be carried out by
engineering
18. Company Product Strategy MeetingCompany Product Strategy Meeting
Management evaluates
the feasibility of the
project, based on the
preliminary information
go ahead for a pre-study
to be carried out by
engineering
27. Pre-study by EngineeringPre-study by Engineering
PLANNING DISCUSSION
HAPPY END
Output of pre-study
• unit cost
• development cost
• preliminary planning
• risk assessment
• possible alternatives
28. Pre-study by EngineeringPre-study by Engineering
PLANNING DISCUSSION
HAPPY END
Output of pre-study
• unit cost
• development cost
• preliminary planning
• risk assessment
• possible alternatives
31. Company Product Strategy MeetingCompany Product Strategy Meeting
step 2: evaluation - project approvalstep 2: evaluation - project approval
Go or No Go based on:
• market input
• engineering results (cost-planning)
• sales prognoses
If OK the D.O. (Development Order)
can be made by the product manager
and signed by the management.
32. Company Product Strategy MeetingCompany Product Strategy Meeting
step 2: evaluation - project approvalstep 2: evaluation - project approval
Go or No Go based on:
• market input
• engineering results (cost-planning)
• sales prognoses
If OK the D.O. (Development Order)
can be made by the product manager
and signed by the management.
33.
34. Sign-off of the Development OrderSign-off of the Development Order
105. Testing and certification processTesting and certification process
CE CERTIFICATION
ELECTROSTATIC DISCHARGE TESTING
106. Testing and certification processTesting and certification process
CE CERTIFICATION
ELECTROSTATIC DISCHARGE TESTING
CE CERTIFICATION
MEASUREMENT OF THE RF RADIATION
107. Testing and certification processTesting and certification process
CE CERTIFICATION
ELECTROSTATIC DISCHARGE TESTING
CE CERTIFICATION
MEASUREMENT OF THE RF RADIATION
108. Testing and certification processTesting and certification process
CE CERTIFICATION
ELECTROSTATIC DISCHARGE TESTING
CE CERTIFICATION
MEASUREMENT OF THE RF RADIATION
109. Testing and certification examplesTesting and certification examples
CE CERTIFICATION
SECURITY DEBIS
SECURITY TNO
FCC CERTIFICATION
AND MANY OTHERS:
UL,C-TICK, CTR21,
ISDN, ETC
HEALTH & SAFETY
110. Testing and certification examplesTesting and certification examples
CE CERTIFICATION
SECURITY DEBIS
SECURITY TNO
FCC CERTIFICATION
AND MANY OTHERS:
UL,C-TICK, CTR21,
ISDN, ETC
HEALTH & SAFETY
111. Specific safety rules for the OPT used on aSpecific safety rules for the OPT used on a
petrol station forecourtpetrol station forecourt
DEFINITION OF THE EXPLOSION ZONES
112. Specific safety rules for the OPT used on aSpecific safety rules for the OPT used on a
petrol station forecourtpetrol station forecourt
DEFINITION OF THE EXPLOSION ZONES
113.
114. A specific test exampleA specific test example
Testing the OPT on strengthTesting the OPT on strength
and vibrationsand vibrations
115. Tested at the university of BrusselsTested at the university of Brussels
133. Con
A
Can you imagine that instead of sitting
here in this stupid machine, I could have
been in Lisbon having a nice meal at the
sea side. I hope I won’t regret this.