SlideShare a Scribd company logo
1 of 15
Download to read offline
Enterprise Environmental Factors and
Organizational Process Assets
Produced by Dr. Linda P. Dowdell, MS, MBA, PMP, PMI-ACP
Project Management Solutions, LLC
PMI® New York City
 One of the dilemmas that concern project
managers is how to initiate a project
 The dilemma increases when project
managers are new to the organization –
especially when they work as consultants
 The dilemma increases even more when
project managers must take mandatory
training geared for new resources, and
postpone to learn about enterprise
environmental factors and organizational
process assets.
2
 The mentioned dilemmas are inevitable; however,
project managers should initiate a project in parallel
with two knowledge areas, Project Integration
Management and Project Stakeholder Management
(PMI® standards) because
 the first knowledge area starts with a Project Charter which
contains key information to justify a project, a list of key
stakeholders, etc.
 the second knowledge area identifies the stakeholders in more
detail, which will be part of a Stakeholder Registry
 At the same time, project managers need to
familiarize themselves with the enterprise
environmental factors, and the organizational process
assets – because these contain the factors about the
company and the assets which could be applied to
projects.
3
These process assets are outside of PMI standards
but form part of an organization (e.g., policies,
historical information, lessons learned, etc.)
These process assets are important because they
influence the recommended processes (PMBOK®,
for example) which are necessary to develop a
project.
Note: Generally, each PMI® process group
(initiating, planning, executing, monitoring,
controlling and closing) makes reference to
organizational process assets (whatever they
are).
4
PMI® makes references to 2 categories of
organizational process assets which are specific
to the performing organization
Processes and Procedures (for initiating, planning,
executing, and closing)
Plans
Processes
Politics
Procedures
Corporate Knowledge Base
Lessons learned
Historical information
5
PMBOK, Fifth Edition, p. 27-28
These are the categories which are specific to the
performing organization to conduct project work
(1) Processes and Procedures for Initiating and
Planning
 Guidelines and criteria to tailor processes and procedures that
are standard to the organization
 Organizational standards for policies such as human resources,
health and safety, ethics, project management, etc.
 Organizational standards for product and project life cycle
 Organizational standards for quality policies and procedures
such as process audits, improvement targets, checklists, process
definition, etc.
 Templates such as risk register, stakeholder register, contract
templates, etc.)
6
PMBOK, Fifth Edition, pp. 27-28
These are the categories which are specific to the
performing organization to conduct project work
(cont.)
(1) Processes and procedures for execution, monitoring
y controlling
◦ Procedures for change control (and the steps required),
which includes how approval and validation of changes will
be done
◦ Procedures for financial controls such as time reporting,
accounting codes (e.g., cost centers), how consultants will
report time, etc.
◦ Procedures for issue and defect management
◦ Communication requirements such as retention policies,etc.
◦ Procedures for approving project work
◦ Guides, work instructions, performance measurement
criteria
7
PMBOK, Fifth Edition, p. 27-28
These are the categories which are specific to
the performing organization to conduct
project work (cont.)
(1) Processes and procedures for closing
Guides or requirements to close projects
Lessons learned
Project audit requirements by required parties
Project evaluations by required parties
Product validations (by required parties) along with
corresponding acceptance criteria
8
PMBOK, Fifth Edition, p. 27-28
These are the categories which are specific to the
performing organization to conduct project work
(cont.)
(2) Corporate Knowledge Base
These are the knowledge bases that are necessary to
archive and retrieve information
Configuration management knowledge bases
Financial databases (which can be systems)
Historical information and lessons learned knowledge
bases (e.g., SharePoint)
Issue and defect management databases
Process measurement databases
Project files of previous projects
9
PMBOK, Fifth Edition, p. 27-28
Enterprise environmental factors are outside PMI®
standards but form part of and may be unique to
organizations (e.g., culture, infrastructure, etc.).
Enterprise environmental factors are important
because they influence the recommended and
necessary processes to develop a project.
Note: Generally, each PMI® process group
(initiating, planning, executing, monitoring,
controlling and closing) makes reference to
enterprise environmental factors (whatever they
are).
10
Enterprise environmental factors are NOT
under the control of the project management
team, but they do influence, constrain, or
help direct a project. In other words, these
environmental factors could improve or
constrain project management options that in
turn may influence the outcome of a project
in a positive or negative manner.
Enterprise environmental factors are necessary
inputs to most PMI® planning processes.
11
PMBOK, Fifth Edition, p. 29
Among others, the following enterprise environmental
factors include:
 Culture, infrastructure and governance of the organization
 Geographic distribution of facilities and resources
 Government or industry standards
◦ Regulatory agency regulations
◦ Codes of conduct
◦ Project standards
◦ Quality standards
◦ Workmanship standards
 Infrastructure
◦ Existing facilities
◦ Capital equipment
 Existing human resources
◦ Skills
◦ Disciplines and knowledge (design, dev, contracting, purchasing)
12
PMBOK, Fifth Edition, p. 29
Among others, the following enterprise
environmental factors include (cont.):
 Personnel administration
◦ Guidelines in selecting and retaining personnel
◦ Employee performance reviews and training records
◦ Reward and overtime policy
◦ Time tracking
 Work authorization systems
 Market conditions
 Stakeholder risk tolerances
 Political climate
13
PMBOK, Fifth Edition, p. 29
Among others, the following enterprise
environmental factors include (cont.):
 Established communication channels
 Commercial databases (standardized cost
estimating, industry risk study information,
risk databases)
 Project management information system
◦ Scheduling tool, configuration management system,
repositories, web sites, etc.
14
PMBOK, Fifth Edition, p. 29
Considerations to initiate a project3

More Related Content

What's hot

Basic Project documents
Basic Project documentsBasic Project documents
Basic Project documentsGhulam Jilani
 
Bringing it all Together: Exploring all the Components of a Quality Managemen...
Bringing it all Together: Exploring all the Components of a Quality Managemen...Bringing it all Together: Exploring all the Components of a Quality Managemen...
Bringing it all Together: Exploring all the Components of a Quality Managemen...International Federation of Accountants
 
RESULT BASED M&E in FFA-revised
RESULT BASED M&E in FFA-revisedRESULT BASED M&E in FFA-revised
RESULT BASED M&E in FFA-revisedStephen Musimba
 
Project Evaluation, Recycling and Closing
Project Evaluation, Recycling and ClosingProject Evaluation, Recycling and Closing
Project Evaluation, Recycling and ClosingJo Balucanag - Bitonio
 
13 project monitoring and evaluation
13 project monitoring and evaluation13 project monitoring and evaluation
13 project monitoring and evaluationrajkpandey2000
 
Eliminate Turbulence Between IT and the Business with Business Value Dashboards
Eliminate Turbulence Between IT and the Business with Business Value DashboardsEliminate Turbulence Between IT and the Business with Business Value Dashboards
Eliminate Turbulence Between IT and the Business with Business Value DashboardsTeamQuest Corporation
 
Business Impact Analysis - The Most Important Step during BCMS Implementation
Business Impact Analysis - The Most Important Step during BCMS ImplementationBusiness Impact Analysis - The Most Important Step during BCMS Implementation
Business Impact Analysis - The Most Important Step during BCMS ImplementationPECB
 
Critical Success Factors (CSFs) In International ERP Implementations with que...
Critical Success Factors (CSFs) In International ERP Implementations with que...Critical Success Factors (CSFs) In International ERP Implementations with que...
Critical Success Factors (CSFs) In International ERP Implementations with que...Moutasm Tamimi
 
Risk and Regulatory Change Management - 360factors EUEC 2015 Presentation
Risk and Regulatory Change Management - 360factors EUEC 2015 PresentationRisk and Regulatory Change Management - 360factors EUEC 2015 Presentation
Risk and Regulatory Change Management - 360factors EUEC 2015 Presentation360factors
 
Regulatory Change Management
Regulatory Change ManagementRegulatory Change Management
Regulatory Change Management360factors
 
REGULATORY CHANGE MANAGEMENT (RCM) In Environmental Health and Safety
REGULATORY CHANGE MANAGEMENT  (RCM)   In Environmental Health and SafetyREGULATORY CHANGE MANAGEMENT  (RCM)   In Environmental Health and Safety
REGULATORY CHANGE MANAGEMENT (RCM) In Environmental Health and Safety360factors
 
Leveraging Gap Assessments and Internal Audits in ISO 22301
Leveraging Gap Assessments and Internal Audits in ISO 22301Leveraging Gap Assessments and Internal Audits in ISO 22301
Leveraging Gap Assessments and Internal Audits in ISO 22301PECB
 

What's hot (20)

Basic Project documents
Basic Project documentsBasic Project documents
Basic Project documents
 
Bringing it all Together: Exploring all the Components of a Quality Managemen...
Bringing it all Together: Exploring all the Components of a Quality Managemen...Bringing it all Together: Exploring all the Components of a Quality Managemen...
Bringing it all Together: Exploring all the Components of a Quality Managemen...
 
ISA 315 (Revised) - Exposure Draft Webinar, October 3rd, 2018
ISA 315 (Revised) - Exposure Draft Webinar, October 3rd, 2018ISA 315 (Revised) - Exposure Draft Webinar, October 3rd, 2018
ISA 315 (Revised) - Exposure Draft Webinar, October 3rd, 2018
 
ISA 315 (Revised) - Exposure Draft Webinar
ISA 315 (Revised) - Exposure Draft WebinarISA 315 (Revised) - Exposure Draft Webinar
ISA 315 (Revised) - Exposure Draft Webinar
 
What’s New for Firms’ Monitoring and Remediation Processes
What’s New for Firms’ Monitoring and Remediation ProcessesWhat’s New for Firms’ Monitoring and Remediation Processes
What’s New for Firms’ Monitoring and Remediation Processes
 
RESULT BASED M&E in FFA-revised
RESULT BASED M&E in FFA-revisedRESULT BASED M&E in FFA-revised
RESULT BASED M&E in FFA-revised
 
Project monitoring
Project monitoringProject monitoring
Project monitoring
 
Project Evaluation, Recycling and Closing
Project Evaluation, Recycling and ClosingProject Evaluation, Recycling and Closing
Project Evaluation, Recycling and Closing
 
13 project monitoring and evaluation
13 project monitoring and evaluation13 project monitoring and evaluation
13 project monitoring and evaluation
 
Eliminate Turbulence Between IT and the Business with Business Value Dashboards
Eliminate Turbulence Between IT and the Business with Business Value DashboardsEliminate Turbulence Between IT and the Business with Business Value Dashboards
Eliminate Turbulence Between IT and the Business with Business Value Dashboards
 
Business Impact Analysis - The Most Important Step during BCMS Implementation
Business Impact Analysis - The Most Important Step during BCMS ImplementationBusiness Impact Analysis - The Most Important Step during BCMS Implementation
Business Impact Analysis - The Most Important Step during BCMS Implementation
 
Quality Control Guide Orientation Slides
Quality Control Guide Orientation SlidesQuality Control Guide Orientation Slides
Quality Control Guide Orientation Slides
 
Critical Success Factors (CSFs) In International ERP Implementations with que...
Critical Success Factors (CSFs) In International ERP Implementations with que...Critical Success Factors (CSFs) In International ERP Implementations with que...
Critical Success Factors (CSFs) In International ERP Implementations with que...
 
Overview of the New International Code of Ethics
Overview of the New International Code of EthicsOverview of the New International Code of Ethics
Overview of the New International Code of Ethics
 
Risk and Regulatory Change Management - 360factors EUEC 2015 Presentation
Risk and Regulatory Change Management - 360factors EUEC 2015 PresentationRisk and Regulatory Change Management - 360factors EUEC 2015 Presentation
Risk and Regulatory Change Management - 360factors EUEC 2015 Presentation
 
Regulatory Change Management
Regulatory Change ManagementRegulatory Change Management
Regulatory Change Management
 
Fm, corporate finance
Fm, corporate financeFm, corporate finance
Fm, corporate finance
 
Richard A Denman - Resume
Richard A Denman - ResumeRichard A Denman - Resume
Richard A Denman - Resume
 
REGULATORY CHANGE MANAGEMENT (RCM) In Environmental Health and Safety
REGULATORY CHANGE MANAGEMENT  (RCM)   In Environmental Health and SafetyREGULATORY CHANGE MANAGEMENT  (RCM)   In Environmental Health and Safety
REGULATORY CHANGE MANAGEMENT (RCM) In Environmental Health and Safety
 
Leveraging Gap Assessments and Internal Audits in ISO 22301
Leveraging Gap Assessments and Internal Audits in ISO 22301Leveraging Gap Assessments and Internal Audits in ISO 22301
Leveraging Gap Assessments and Internal Audits in ISO 22301
 

Similar to Considerations to initiate a project3

project risk management, Ppm 8212 lecture four,
 project risk management, Ppm  8212  lecture  four,  project risk management, Ppm  8212  lecture  four,
project risk management, Ppm 8212 lecture four, xariir rooble
 
PMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkPMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkAndrew Mikityuk
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementAndrew Mikityuk
 
In the Penal Colony” and The Lottery”Find a passage from eac
In the Penal Colony” and The Lottery”Find a passage from eacIn the Penal Colony” and The Lottery”Find a passage from eac
In the Penal Colony” and The Lottery”Find a passage from eacMalikPinckney86
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdfMUST
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration managementreddvise
 
04.integration management updated
04.integration management updated04.integration management updated
04.integration management updatedShraddha PMP
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify StakeholdersDavidMcLachlan1
 
Introduction of Project management ppt
Introduction of Project management pptIntroduction of Project management ppt
Introduction of Project management pptSourabh Kumar
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management areaZaur Ahmadov, PMP
 
PMP Training Course - Lecture 2
PMP Training Course - Lecture 2PMP Training Course - Lecture 2
PMP Training Course - Lecture 2The Daily PM
 
IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015
IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015
IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015Go Green
 

Similar to Considerations to initiate a project3 (20)

project risk management, Ppm 8212 lecture four,
 project risk management, Ppm  8212  lecture  four,  project risk management, Ppm  8212  lecture  four,
project risk management, Ppm 8212 lecture four,
 
PMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkPMP Preparation 1 - Framework
PMP Preparation 1 - Framework
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
In the Penal Colony” and The Lottery”Find a passage from eac
In the Penal Colony” and The Lottery”Find a passage from eacIn the Penal Colony” and The Lottery”Find a passage from eac
In the Penal Colony” and The Lottery”Find a passage from eac
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdf
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration management
 
Project management – standard for today´s modern company
Project management – standard for today´s modern companyProject management – standard for today´s modern company
Project management – standard for today´s modern company
 
04.integration management updated
04.integration management updated04.integration management updated
04.integration management updated
 
Mangemnt3207.pptx
Mangemnt3207.pptxMangemnt3207.pptx
Mangemnt3207.pptx
 
03ch
03ch03ch
03ch
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
Introduction of Project management ppt
Introduction of Project management pptIntroduction of Project management ppt
Introduction of Project management ppt
 
#Pmp in a3 edition_1
#Pmp in a3 edition_1#Pmp in a3 edition_1
#Pmp in a3 edition_1
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management area
 
PMP Training Course - Lecture 2
PMP Training Course - Lecture 2PMP Training Course - Lecture 2
PMP Training Course - Lecture 2
 
IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015
IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015
IEMA & Go Green South West Seminar: Martin Baxter Update to 14001:2015
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 

Considerations to initiate a project3

  • 1. Enterprise Environmental Factors and Organizational Process Assets Produced by Dr. Linda P. Dowdell, MS, MBA, PMP, PMI-ACP Project Management Solutions, LLC PMI® New York City
  • 2.  One of the dilemmas that concern project managers is how to initiate a project  The dilemma increases when project managers are new to the organization – especially when they work as consultants  The dilemma increases even more when project managers must take mandatory training geared for new resources, and postpone to learn about enterprise environmental factors and organizational process assets. 2
  • 3.  The mentioned dilemmas are inevitable; however, project managers should initiate a project in parallel with two knowledge areas, Project Integration Management and Project Stakeholder Management (PMI® standards) because  the first knowledge area starts with a Project Charter which contains key information to justify a project, a list of key stakeholders, etc.  the second knowledge area identifies the stakeholders in more detail, which will be part of a Stakeholder Registry  At the same time, project managers need to familiarize themselves with the enterprise environmental factors, and the organizational process assets – because these contain the factors about the company and the assets which could be applied to projects. 3
  • 4. These process assets are outside of PMI standards but form part of an organization (e.g., policies, historical information, lessons learned, etc.) These process assets are important because they influence the recommended processes (PMBOK®, for example) which are necessary to develop a project. Note: Generally, each PMI® process group (initiating, planning, executing, monitoring, controlling and closing) makes reference to organizational process assets (whatever they are). 4
  • 5. PMI® makes references to 2 categories of organizational process assets which are specific to the performing organization Processes and Procedures (for initiating, planning, executing, and closing) Plans Processes Politics Procedures Corporate Knowledge Base Lessons learned Historical information 5 PMBOK, Fifth Edition, p. 27-28
  • 6. These are the categories which are specific to the performing organization to conduct project work (1) Processes and Procedures for Initiating and Planning  Guidelines and criteria to tailor processes and procedures that are standard to the organization  Organizational standards for policies such as human resources, health and safety, ethics, project management, etc.  Organizational standards for product and project life cycle  Organizational standards for quality policies and procedures such as process audits, improvement targets, checklists, process definition, etc.  Templates such as risk register, stakeholder register, contract templates, etc.) 6 PMBOK, Fifth Edition, pp. 27-28
  • 7. These are the categories which are specific to the performing organization to conduct project work (cont.) (1) Processes and procedures for execution, monitoring y controlling ◦ Procedures for change control (and the steps required), which includes how approval and validation of changes will be done ◦ Procedures for financial controls such as time reporting, accounting codes (e.g., cost centers), how consultants will report time, etc. ◦ Procedures for issue and defect management ◦ Communication requirements such as retention policies,etc. ◦ Procedures for approving project work ◦ Guides, work instructions, performance measurement criteria 7 PMBOK, Fifth Edition, p. 27-28
  • 8. These are the categories which are specific to the performing organization to conduct project work (cont.) (1) Processes and procedures for closing Guides or requirements to close projects Lessons learned Project audit requirements by required parties Project evaluations by required parties Product validations (by required parties) along with corresponding acceptance criteria 8 PMBOK, Fifth Edition, p. 27-28
  • 9. These are the categories which are specific to the performing organization to conduct project work (cont.) (2) Corporate Knowledge Base These are the knowledge bases that are necessary to archive and retrieve information Configuration management knowledge bases Financial databases (which can be systems) Historical information and lessons learned knowledge bases (e.g., SharePoint) Issue and defect management databases Process measurement databases Project files of previous projects 9 PMBOK, Fifth Edition, p. 27-28
  • 10. Enterprise environmental factors are outside PMI® standards but form part of and may be unique to organizations (e.g., culture, infrastructure, etc.). Enterprise environmental factors are important because they influence the recommended and necessary processes to develop a project. Note: Generally, each PMI® process group (initiating, planning, executing, monitoring, controlling and closing) makes reference to enterprise environmental factors (whatever they are). 10
  • 11. Enterprise environmental factors are NOT under the control of the project management team, but they do influence, constrain, or help direct a project. In other words, these environmental factors could improve or constrain project management options that in turn may influence the outcome of a project in a positive or negative manner. Enterprise environmental factors are necessary inputs to most PMI® planning processes. 11 PMBOK, Fifth Edition, p. 29
  • 12. Among others, the following enterprise environmental factors include:  Culture, infrastructure and governance of the organization  Geographic distribution of facilities and resources  Government or industry standards ◦ Regulatory agency regulations ◦ Codes of conduct ◦ Project standards ◦ Quality standards ◦ Workmanship standards  Infrastructure ◦ Existing facilities ◦ Capital equipment  Existing human resources ◦ Skills ◦ Disciplines and knowledge (design, dev, contracting, purchasing) 12 PMBOK, Fifth Edition, p. 29
  • 13. Among others, the following enterprise environmental factors include (cont.):  Personnel administration ◦ Guidelines in selecting and retaining personnel ◦ Employee performance reviews and training records ◦ Reward and overtime policy ◦ Time tracking  Work authorization systems  Market conditions  Stakeholder risk tolerances  Political climate 13 PMBOK, Fifth Edition, p. 29
  • 14. Among others, the following enterprise environmental factors include (cont.):  Established communication channels  Commercial databases (standardized cost estimating, industry risk study information, risk databases)  Project management information system ◦ Scheduling tool, configuration management system, repositories, web sites, etc. 14 PMBOK, Fifth Edition, p. 29