SlideShare a Scribd company logo
1 of 1
Download to read offline
PROFILING OF FLOOD CONTROL PROJECTS
BASED ON QUANTITY AND COST
INDICATORS FOR PRIORITIZATION AND
RISK IMPLEMENTATION
Leovin-Rane D. Sanchez
Civil Engineer / Water Resources and Hydraulics
STUDY AREA FLOOD CONTROL PLAN
The major watershed areas were divided into
smaller sub-catchments through big interceptors
(RCBC). It contains the majority of the 50-year
flood and diverted to a bigger body of water such
as the Pasig River and Manila Bay. The remaining
volume of 50-year flood from the downstream side
of the proposed interceptors is contained by the
existing drainage channels. Thus, the remaining 50-
year flood could be said equivalent to a 10-year
flood. Restoration of the existing drainage network
and installation of new flood control facilities as
part of the overall flood control mitigation project
were considered.
CONCEPT
100
1,000
10,000
100,000
1 10 100 1000 10000
UnitCost(Php)
Volume (m3)
Declogging
Buendia
NAIA
Trend
0
10,000
20,000
30,000
40,000
50,000
60,000
0 2000 4000 6000 8000 10000 12000 14000 16000 18000
UnitCost/Barrel/Length/Width(Php)
Length (m)
Dredging
Buendia
Maricaban
NAIA
Parañaque
85,000
87,500
90,000
92,500
95,000
97,500
100,000
0 500 1000 1500 2000 2500 3000 3500 4000 4500
UnitCost(Php)
Length (m)
Interceptor
Box Culvert
Trend
This work item in the
Parañaque basin has the
most number of works in
terms of length but it
turned out as one of the
most economical project
in the long run.
Overall, the dredging
works for Buendia is the
most economical. This
could be prioritized for
budgeting.
QUANTITY AND COST INDICATORS
PRIORITY PROJECTS PER CATCHMENT AREA
In the long run, the declogging
work becomes cost efficient as
the quantity of work increases.
As a solution to the undersized drainage network of the study area, a flood control master plan has been updated. Due to economic or budget constraint, the flood control projects can’t be implemented all at the same time. For
urgent or small budget allocation, the following are suggested to be prioritized: (1) Declogging of existing drainage mains in the Buendia and NAIA basin, (2) and Dredging of channels in the Buendia basin. Also, construction of
interceptors(RCBC) is evidently costly but designing of culverts with big cross-section, that is sufficient for a higher design flood, is more cost-effective in the long run.
CONCLUSION
The present drainage network of Metro Manila is
only designed for 10-year flood and being not
maintained, the capacity of the drainages have
continuously decreased. The Department of Public
Works and Highways (DPWH), has released a new
memorandum that requires drainage systems be
designed for 25-year flood with a free board of 50-
year flood due to frequent high intensity rainfalls.
Being highly urbanized, increasing the capacity of
the existing channels is almost impossible. The
challenge is to introduce new flood control
structures and facilities that will help the
undersized drainage network to manage the flood.
PROBLEM
Design and construction
of culverts with big cross-
section is more cost-
efficient over a period of
time.
BP1-3
BP1-2
BP1-1
BP1-4
BP1-5
BP2-2
BP2-6
BP2-6
BP2-2
BP2-1
BP2-5
BP2-6
BP2-3
BP3-1
BP3-1
BP3-1
BP3-1
BP3-1
MP1-2
MP1-3
MP1-1
MP2-1
MP3-1
MP3-2
NP1-1
NP1-2
NP1-3
NP1-4
NP2-4
NP2-7
NP2-6
NP2-3
NP2-2
NP2-1
NP3-3
NP3-1
NP3-2
PP1
PP1-1
PP1-5
PP1-4
PP1-4
PP1-2
PP1-3
PP2-1
PP3-1
BUENDIA BASIN
Work Item Code and Specification
BP1 Declogging
BP1-1 Vito Cruz
BP1-2 Buendia
BP1-3 Libertad
BP1-4 EDSA
BP1-5 Zobel-Orbit
BP2 Dredging
BP2-1 Calatagan Creek
BP2-2 Makati Diversion Channel
BP2-3 Estero de Pandacan
BP2-4 Estero de Provisor
BP2-5 Estero de Paco
BP2-6 Estero de Tripa de Gallina
BP3 Box Culvert BP3-1 PNR Interceptor
MARICABAN BASIN
Work Item Code and Specification
MP1 Dredging
MP1-1 Maricaban Creek I
MP1-2 Maricaban Creek II
MP1-3 Maricaban Creek III
MP2 Box Culvert MP2-1 Maricaban Interceptor
MP3 Retarding Pond
MP3-1 Villamor Airbase
MP3-2 Philippine Navy
NAIA BASIN
Work Item Code and Specification
NP1 Declogging
NP1-1 Rivera
NP1-2 Airport Road
NP1-3 Librada
NP1-4 Seaside
NP2 Dredging
NP2-1 Inland Channel
NP2-2 Libertad Channel
NP2-3 Redemptorist Channel
NP2-4 Seaside Channel
NP2-5 Parañaque Channel
NP2-6 Cut-cut Creek
NP2-7 Ibayo Creek
NP3 Pumping Station
Np3-1 Redemptorist
NP3-2 Seaside
NP3-3 Parañaque
PARAÑAQUE BASIN
Work Item Code and Specification
PP1 Dredging
PP1-1 Baliwag River
PP1-2 South Parañaque River
PP1-3 San Dionisio River
PP1-4 San Isidro River
PP1-5 Don Bosco River
PP2 Pumping Station PP2-1 NAIA Relief
PP3 Parapet Wall PP3-1 Dongalo River

More Related Content

What's hot

Irrigation engineering
Irrigation engineeringIrrigation engineering
Irrigation engineeringNagma Modi
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Projectashkan ezazi
 
Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac
Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac
Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac Hanna Stahlberg
 
Sec15 cross county pipeline
Sec15 cross county pipelineSec15 cross county pipeline
Sec15 cross county pipelineru55e11
 
Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Mulugeta Abera
 
Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.Raj Bisen
 
California; Harvesting Rain: Addressing Water Needs of the Monterey Peninsu...
California;  Harvesting Rain:  Addressing Water Needs of the Monterey Peninsu...California;  Harvesting Rain:  Addressing Water Needs of the Monterey Peninsu...
California; Harvesting Rain: Addressing Water Needs of the Monterey Peninsu...D7Z
 
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONSLAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONSNamitha M R
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
Action taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of LakesAction taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of LakesEkonnect
 
WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemMitaliShelke
 
The hydrogeological risk asesment on the merti aquifer
The hydrogeological risk asesment on the merti aquiferThe hydrogeological risk asesment on the merti aquifer
The hydrogeological risk asesment on the merti aquiferWorld Agroforestry (ICRAF)
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Stephen Flood
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Ekonnect
 

What's hot (20)

Irrigation engineering
Irrigation engineeringIrrigation engineering
Irrigation engineering
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Project
 
Southmost Regional Water Authority, Judy Adams
Southmost Regional Water Authority, Judy AdamsSouthmost Regional Water Authority, Judy Adams
Southmost Regional Water Authority, Judy Adams
 
Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac
Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac
Water related issues in the Mekong Basin and Mekong Delta, Nguyen Tat Dac
 
Mc Quirk Sess1 101509
Mc Quirk Sess1 101509Mc Quirk Sess1 101509
Mc Quirk Sess1 101509
 
Sec15 cross county pipeline
Sec15 cross county pipelineSec15 cross county pipeline
Sec15 cross county pipeline
 
Hydrology and sediment initial baseline
Hydrology and sediment initial baselineHydrology and sediment initial baseline
Hydrology and sediment initial baseline
 
Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1
 
Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.Design of Kawlewada Dam and its Components.
Design of Kawlewada Dam and its Components.
 
Ppt( farakka barrage)
Ppt( farakka barrage)Ppt( farakka barrage)
Ppt( farakka barrage)
 
California; Harvesting Rain: Addressing Water Needs of the Monterey Peninsu...
California;  Harvesting Rain:  Addressing Water Needs of the Monterey Peninsu...California;  Harvesting Rain:  Addressing Water Needs of the Monterey Peninsu...
California; Harvesting Rain: Addressing Water Needs of the Monterey Peninsu...
 
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONSLAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
Action taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of LakesAction taken by BWSSB in preventing pollution of Lakes
Action taken by BWSSB in preventing pollution of Lakes
 
WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution system
 
The hydrogeological risk asesment on the merti aquifer
The hydrogeological risk asesment on the merti aquiferThe hydrogeological risk asesment on the merti aquifer
The hydrogeological risk asesment on the merti aquifer
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
 

Similar to POSTER_VIETNAM_BMNP_7

Towards A Sustainable Drainage Solution
Towards A Sustainable Drainage SolutionTowards A Sustainable Drainage Solution
Towards A Sustainable Drainage Solutionceal2005
 
Writing Sample - Draft EIR
Writing Sample - Draft EIRWriting Sample - Draft EIR
Writing Sample - Draft EIRSharanya Ganesh
 
Tubewell guideline(1)
Tubewell  guideline(1)Tubewell  guideline(1)
Tubewell guideline(1)Abdul Aziz
 
Reservoir Water Supply Planning for an Uncertain Future
Reservoir Water Supply Planning for an Uncertain FutureReservoir Water Supply Planning for an Uncertain Future
Reservoir Water Supply Planning for an Uncertain FutureDave Campbell
 
Simplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case studySimplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case studyAdam Berry
 
Water resources planning & environmental considerations
Water resources planning & environmental considerationsWater resources planning & environmental considerations
Water resources planning & environmental considerationsAMIE(I) Study Circle
 
Cape Cod Regional Wastewater Management Plan Overview
Cape Cod Regional Wastewater Management Plan OverviewCape Cod Regional Wastewater Management Plan Overview
Cape Cod Regional Wastewater Management Plan OverviewBuzzards Bay Coalition
 
Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014GreeNexus Consulting, LLC
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportFesto Wasukira
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGDEEPAK MALLICK
 
Hydropower Development on the Mekong and 3S
 Hydropower Development on the Mekong and 3S  Hydropower Development on the Mekong and 3S
Hydropower Development on the Mekong and 3S stimson
 
Abastecimento de agua y alcantarillado
Abastecimento de agua y alcantarilladoAbastecimento de agua y alcantarillado
Abastecimento de agua y alcantarilladoMaxAlejandro9
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Fairfax County
 
Midterm cu stormwater report.docx
Midterm cu stormwater report.docxMidterm cu stormwater report.docx
Midterm cu stormwater report.docxcbwalke
 
Guidelines on-flood-mgmt
Guidelines on-flood-mgmtGuidelines on-flood-mgmt
Guidelines on-flood-mgmtuyelinnbo
 
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IAASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IADavid Koser
 
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...Global Water Partnership
 

Similar to POSTER_VIETNAM_BMNP_7 (20)

Towards A Sustainable Drainage Solution
Towards A Sustainable Drainage SolutionTowards A Sustainable Drainage Solution
Towards A Sustainable Drainage Solution
 
Writing Sample - Draft EIR
Writing Sample - Draft EIRWriting Sample - Draft EIR
Writing Sample - Draft EIR
 
Tubewell guideline(1)
Tubewell  guideline(1)Tubewell  guideline(1)
Tubewell guideline(1)
 
Reservoir Water Supply Planning for an Uncertain Future
Reservoir Water Supply Planning for an Uncertain FutureReservoir Water Supply Planning for an Uncertain Future
Reservoir Water Supply Planning for an Uncertain Future
 
Simplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case studySimplifying stormwater design is costing us money - a short case study
Simplifying stormwater design is costing us money - a short case study
 
Water resources planning & environmental considerations
Water resources planning & environmental considerationsWater resources planning & environmental considerations
Water resources planning & environmental considerations
 
Rehab modernization
Rehab modernizationRehab modernization
Rehab modernization
 
Water Woes of Mumbai City by Mr.P.K.Charankar
Water Woes of Mumbai City by Mr.P.K.CharankarWater Woes of Mumbai City by Mr.P.K.Charankar
Water Woes of Mumbai City by Mr.P.K.Charankar
 
Cape Cod Regional Wastewater Management Plan Overview
Cape Cod Regional Wastewater Management Plan OverviewCape Cod Regional Wastewater Management Plan Overview
Cape Cod Regional Wastewater Management Plan Overview
 
Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014
 
Design manual chapter7_revjan_2013
Design manual chapter7_revjan_2013Design manual chapter7_revjan_2013
Design manual chapter7_revjan_2013
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
 
Hydropower Development on the Mekong and 3S
 Hydropower Development on the Mekong and 3S  Hydropower Development on the Mekong and 3S
Hydropower Development on the Mekong and 3S
 
Abastecimento de agua y alcantarillado
Abastecimento de agua y alcantarilladoAbastecimento de agua y alcantarillado
Abastecimento de agua y alcantarillado
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
 
Midterm cu stormwater report.docx
Midterm cu stormwater report.docxMidterm cu stormwater report.docx
Midterm cu stormwater report.docx
 
Guidelines on-flood-mgmt
Guidelines on-flood-mgmtGuidelines on-flood-mgmt
Guidelines on-flood-mgmt
 
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IAASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
ASSESSMENT OF FLOOD MITIGATION STRATEGIES FOR THE CITY OF KALONA, IA
 
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...
Sustainable Water Security at a time of Climate Change: India's 12th Five Yea...
 

POSTER_VIETNAM_BMNP_7

  • 1. PROFILING OF FLOOD CONTROL PROJECTS BASED ON QUANTITY AND COST INDICATORS FOR PRIORITIZATION AND RISK IMPLEMENTATION Leovin-Rane D. Sanchez Civil Engineer / Water Resources and Hydraulics STUDY AREA FLOOD CONTROL PLAN The major watershed areas were divided into smaller sub-catchments through big interceptors (RCBC). It contains the majority of the 50-year flood and diverted to a bigger body of water such as the Pasig River and Manila Bay. The remaining volume of 50-year flood from the downstream side of the proposed interceptors is contained by the existing drainage channels. Thus, the remaining 50- year flood could be said equivalent to a 10-year flood. Restoration of the existing drainage network and installation of new flood control facilities as part of the overall flood control mitigation project were considered. CONCEPT 100 1,000 10,000 100,000 1 10 100 1000 10000 UnitCost(Php) Volume (m3) Declogging Buendia NAIA Trend 0 10,000 20,000 30,000 40,000 50,000 60,000 0 2000 4000 6000 8000 10000 12000 14000 16000 18000 UnitCost/Barrel/Length/Width(Php) Length (m) Dredging Buendia Maricaban NAIA Parañaque 85,000 87,500 90,000 92,500 95,000 97,500 100,000 0 500 1000 1500 2000 2500 3000 3500 4000 4500 UnitCost(Php) Length (m) Interceptor Box Culvert Trend This work item in the Parañaque basin has the most number of works in terms of length but it turned out as one of the most economical project in the long run. Overall, the dredging works for Buendia is the most economical. This could be prioritized for budgeting. QUANTITY AND COST INDICATORS PRIORITY PROJECTS PER CATCHMENT AREA In the long run, the declogging work becomes cost efficient as the quantity of work increases. As a solution to the undersized drainage network of the study area, a flood control master plan has been updated. Due to economic or budget constraint, the flood control projects can’t be implemented all at the same time. For urgent or small budget allocation, the following are suggested to be prioritized: (1) Declogging of existing drainage mains in the Buendia and NAIA basin, (2) and Dredging of channels in the Buendia basin. Also, construction of interceptors(RCBC) is evidently costly but designing of culverts with big cross-section, that is sufficient for a higher design flood, is more cost-effective in the long run. CONCLUSION The present drainage network of Metro Manila is only designed for 10-year flood and being not maintained, the capacity of the drainages have continuously decreased. The Department of Public Works and Highways (DPWH), has released a new memorandum that requires drainage systems be designed for 25-year flood with a free board of 50- year flood due to frequent high intensity rainfalls. Being highly urbanized, increasing the capacity of the existing channels is almost impossible. The challenge is to introduce new flood control structures and facilities that will help the undersized drainage network to manage the flood. PROBLEM Design and construction of culverts with big cross- section is more cost- efficient over a period of time. BP1-3 BP1-2 BP1-1 BP1-4 BP1-5 BP2-2 BP2-6 BP2-6 BP2-2 BP2-1 BP2-5 BP2-6 BP2-3 BP3-1 BP3-1 BP3-1 BP3-1 BP3-1 MP1-2 MP1-3 MP1-1 MP2-1 MP3-1 MP3-2 NP1-1 NP1-2 NP1-3 NP1-4 NP2-4 NP2-7 NP2-6 NP2-3 NP2-2 NP2-1 NP3-3 NP3-1 NP3-2 PP1 PP1-1 PP1-5 PP1-4 PP1-4 PP1-2 PP1-3 PP2-1 PP3-1 BUENDIA BASIN Work Item Code and Specification BP1 Declogging BP1-1 Vito Cruz BP1-2 Buendia BP1-3 Libertad BP1-4 EDSA BP1-5 Zobel-Orbit BP2 Dredging BP2-1 Calatagan Creek BP2-2 Makati Diversion Channel BP2-3 Estero de Pandacan BP2-4 Estero de Provisor BP2-5 Estero de Paco BP2-6 Estero de Tripa de Gallina BP3 Box Culvert BP3-1 PNR Interceptor MARICABAN BASIN Work Item Code and Specification MP1 Dredging MP1-1 Maricaban Creek I MP1-2 Maricaban Creek II MP1-3 Maricaban Creek III MP2 Box Culvert MP2-1 Maricaban Interceptor MP3 Retarding Pond MP3-1 Villamor Airbase MP3-2 Philippine Navy NAIA BASIN Work Item Code and Specification NP1 Declogging NP1-1 Rivera NP1-2 Airport Road NP1-3 Librada NP1-4 Seaside NP2 Dredging NP2-1 Inland Channel NP2-2 Libertad Channel NP2-3 Redemptorist Channel NP2-4 Seaside Channel NP2-5 Parañaque Channel NP2-6 Cut-cut Creek NP2-7 Ibayo Creek NP3 Pumping Station Np3-1 Redemptorist NP3-2 Seaside NP3-3 Parañaque PARAÑAQUE BASIN Work Item Code and Specification PP1 Dredging PP1-1 Baliwag River PP1-2 South Parañaque River PP1-3 San Dionisio River PP1-4 San Isidro River PP1-5 Don Bosco River PP2 Pumping Station PP2-1 NAIA Relief PP3 Parapet Wall PP3-1 Dongalo River