SlideShare a Scribd company logo
1 of 25
Download to read offline
Optimization of ATV Erector Set
Thomas Malloy
April Bouquard
Abdulrahman Mohammed Nuhuli
Leonard Arambam
Agenda
● Time Standards
● Line Balancing
● Workstation Analysis
● Ergonomics
● Part Presentation
● Iterations
● 5S implementation
● Conclusion
Time Study
Part 1:
● Members worked alone on constructing entire ATV.
● Identified steps to be timed (Battery, 1-24)
● Timed each step in seconds
Part 2:
● Users’ times were averaged together to identify
standard assembly times.
Phase Time (hrs)
Average 2.53
Final 1.16
Line Balancing
Goal: We want all workers to have the same
amount of time spent working.
● Precedence constraints did not allow for
optimal usage of Largest Candidate Rule
○ Grouped steps were very restrictive
● Divided steps into 8 blocks to be divided
between 4 workers.
○ 4 Long blocks and 4 short blocks
Worker # Time (sec)
1 2207
2 1973
3 2217
4 2710
Line Balancing (cont.)
● We reallocated steps from longer times to shorter times, but as the assembly
progressed we could not have all workers actively working on the same
product.
● Idle times between blocks allowed for flexibility.
○ Workers could help others when they lagged behind
Workstation Analysis
● Due to kitting and task analysis, workers
needed to be close together.
● Ordered 360 Degree Rotational Vices for
each workstation.
● Separated black screws and ¼” nuts into
separate containers.
● Kept tools in order
● Materials lay flat on the workstation (nothing
above the head)
● No foreign objects permitted
Workstation Analysis (cont.)
● Seated work aided in fine assembly and
allowed for necessary communication
● All materials were within 24 inches of the
worker
● Most used materials were within 14 inches
● Adjustable chairs with wheels provide
ergonomic benefits for workers of all heights as
well as ability to move laterally along
workstation
● Elevated tables for larger workers
Workstation Design Benefits
● Promotes a social atmosphere.
● Task order automatically designates idle times for workers
● Allows for quick passing of assembly
● Provides help from idle workers
Tooling
● Magnetized Allen Wrench
● Standard C-Frame Wrench (stock with set)
● 360 Degree Rotational Vice
● Spring Clips
● Power tools were bulky and too powerful
○ Stripped screws/nuts
○ Caused hand cramps/aches
● Hand tools allowed for precision and accuracy
Part Presentation
● Kitted parts rather than binning
○ Reduced time spent searching for parts.
○ Logical order to the steps
● All parts for worker job were within reach
● Kits had picture instructions as well as
what to do when a set of steps was
finished.
5S Implementation
● Sort: Separate the unnecessary from the necessary parts
● Shine: Place for every part - labelling
● Set to order: Clean the workplace before manufacturing start of shift
● Standardize: SOPs
● Sustain : implement and execute
Ergonomic Evaluation Methods
● ACGIH TLV for Hand Activity
● Lighting Conditions
● Posture and repetitive work
● Mechanical Safety
● Job rotation.
ACGIH TLV Evaluation
Purpose: To asses the risk of hand injury in performing physically continuous
demanding jobs
Methods: Conducting ACGIH TLV for Hand Activity by accurately observing the
steps through videotaping
Results: Our results indicated that most of the work done by our right hand
needed some modification.
Implemented Improvements
● Ordered two 360 degree rotational vices to reduce TLV scores
● Magnetic Allen wrenches reduce overall movement during tightening the
screws and decreased the number of lost screws due to dropping
● Holding the assembly in with the vice reduced the strain on the dominant
hand while increasing nondominant hand usage
Lighting Conditions
OSHA Recommended:
● Illumination needed: >1500-2000 lux(lumen/m^2)
● Installation of overhead florescent lamp in the workstation with > 40 watt
● Incandescent lamp in the room with > 20 watt
Posture and Repetitive Work
● Total work per day: 8 hours with one hour lunch
● System capability: 16 ATVs
● Height adjustable chairs
● Elevated tables for comfortable leg room
Job Rotation
● Eliminate monotonous jobs and potentially harmful posture
● Cross functional training leads to a fully flexible workforce
● Isolate worker strengths
● Increase satisfaction and decrease muscle weakening rate
● Motivate employees to deal with new challenges
Iteration #1: Assembly Line/Binning
● Assembly line with binning at each station
● No change in step order
● Precedence constraints were severe
● No drastic change in time from single worker method
Iteration #2: Binning/Current Workstation Layout
● Allowed workers to work simultaneously
● Confusion during part selection
● Increased work time/lack of idle time
● Implemented magnetic c-wrenches and allen wrenches
Iteration #3: Kitting/Current Workstation Layout
● Easy part selection
● Low precedence constraint effect
● Workers had idle time to reorganize workstations
● Provided quickest assembly time
● Removed magnetized c-wrench tool after it was found to be ineffective
Quality Assurance
● Worker checklist to ensure
all steps are performed
● Signoff sheet to link worker
with steps performed as
well as determine routings
● Standard Operating
Procedures were developed
to standardize the way
steps were performed.
Workstation Recommendations
● Drawers or overhead hangers for tool storage
● Lightweight automated tools calibrated to output a set pressure/rotation
● Flow racks to allow for kits to roll towards and away from worker
● Cross training workers to better utilize skills
Idle Time
● Work on wheel assemblies or other small tasks
● Organize workstations
● Restock materials
● Help other workers
● Perform quality checks
● Start on a new kit
Conclusions
● Average Takt Time of 29 min
● Layout provided a “team” mentality
● Kitting reduced time spent searching for parts
● Magnetized tooling aided in assembly process
● 360 Degree Rotational vice freed non-dominant hand
● Cross training workers allows for flexibility and cost efficiency

More Related Content

Viewers also liked

Mr Naga Chaitanya Resume
Mr Naga Chaitanya Resume Mr Naga Chaitanya Resume
Mr Naga Chaitanya Resume chaitanya naga
 
El sena mision y vision
El sena mision y vision El sena mision y vision
El sena mision y vision yuliehtKaren
 
Analysis of audience questionnaire
Analysis of audience questionnaireAnalysis of audience questionnaire
Analysis of audience questionnaireLaila Jaleel
 
Rendicion de cuentas vocal patricio vasquez año 2015
Rendicion de cuentas vocal patricio vasquez  año 2015Rendicion de cuentas vocal patricio vasquez  año 2015
Rendicion de cuentas vocal patricio vasquez año 2015Wilson Limaico
 
Building learner disposition parent workshop for margaret
Building learner disposition   parent workshop for margaretBuilding learner disposition   parent workshop for margaret
Building learner disposition parent workshop for margaretColliar
 
Interpellanza Mappatura della rete di condutture e tubature in cemento amianto
Interpellanza Mappatura della rete di condutture e tubature in cemento amiantoInterpellanza Mappatura della rete di condutture e tubature in cemento amianto
Interpellanza Mappatura della rete di condutture e tubature in cemento amiantoMarco Campanini
 
Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...
Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...
Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...Radio Télévision Caraibes
 
The Male Gaze Theory
The Male Gaze TheoryThe Male Gaze Theory
The Male Gaze TheoryMJackson1010
 
Raph Koster — The Core of Fun
Raph Koster — The Core of FunRaph Koster — The Core of Fun
Raph Koster — The Core of FunChristopher Allen
 
Spanish Omelette
Spanish OmeletteSpanish Omelette
Spanish OmeletteRoci_rocio
 
Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16
Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16 Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16
Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16 Panayotis Sofianopoulos
 
HRC-Conference-Abstracts-2014
HRC-Conference-Abstracts-2014HRC-Conference-Abstracts-2014
HRC-Conference-Abstracts-2014Mary Beth Levin
 
Radhan profile 2015
Radhan profile 2015Radhan profile 2015
Radhan profile 2015RadhanTLV
 
NO BULLSHIT MARKETING
NO BULLSHIT MARKETINGNO BULLSHIT MARKETING
NO BULLSHIT MARKETINGPiXSELLS
 

Viewers also liked (18)

Catalog file
Catalog fileCatalog file
Catalog file
 
Mr Naga Chaitanya Resume
Mr Naga Chaitanya Resume Mr Naga Chaitanya Resume
Mr Naga Chaitanya Resume
 
El sena mision y vision
El sena mision y vision El sena mision y vision
El sena mision y vision
 
Analysis of audience questionnaire
Analysis of audience questionnaireAnalysis of audience questionnaire
Analysis of audience questionnaire
 
Rendicion de cuentas vocal patricio vasquez año 2015
Rendicion de cuentas vocal patricio vasquez  año 2015Rendicion de cuentas vocal patricio vasquez  año 2015
Rendicion de cuentas vocal patricio vasquez año 2015
 
XSNano2014
XSNano2014XSNano2014
XSNano2014
 
Building learner disposition parent workshop for margaret
Building learner disposition   parent workshop for margaretBuilding learner disposition   parent workshop for margaret
Building learner disposition parent workshop for margaret
 
Interpellanza Mappatura della rete di condutture e tubature in cemento amianto
Interpellanza Mappatura della rete di condutture e tubature in cemento amiantoInterpellanza Mappatura della rete di condutture e tubature in cemento amianto
Interpellanza Mappatura della rete di condutture e tubature in cemento amianto
 
Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...
Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...
Verification/Déclaration de l'Observateur en-chef de la MOE-UE en Haiti Elena...
 
The Male Gaze Theory
The Male Gaze TheoryThe Male Gaze Theory
The Male Gaze Theory
 
Raph Koster — The Core of Fun
Raph Koster — The Core of FunRaph Koster — The Core of Fun
Raph Koster — The Core of Fun
 
Spanish Omelette
Spanish OmeletteSpanish Omelette
Spanish Omelette
 
Odn strategic planfinal
Odn strategic planfinalOdn strategic planfinal
Odn strategic planfinal
 
ΠΟΛ.1012/17
ΠΟΛ.1012/17ΠΟΛ.1012/17
ΠΟΛ.1012/17
 
Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16
Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16 Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16
Έρευνα Απασχόλησης Εργατικού Δυναμικού - Ιούλ. '16
 
HRC-Conference-Abstracts-2014
HRC-Conference-Abstracts-2014HRC-Conference-Abstracts-2014
HRC-Conference-Abstracts-2014
 
Radhan profile 2015
Radhan profile 2015Radhan profile 2015
Radhan profile 2015
 
NO BULLSHIT MARKETING
NO BULLSHIT MARKETINGNO BULLSHIT MARKETING
NO BULLSHIT MARKETING
 

Similar to IE 420 Presentation

Work Sampling in the excavator
Work Sampling in the excavatorWork Sampling in the excavator
Work Sampling in the excavatorSriguru Aithal
 
Midterm presentation rough
Midterm presentation   rough Midterm presentation   rough
Midterm presentation rough supermanu22
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.pptSandipanMaji3
 
Scrum. A brief introduction
Scrum. A brief introductionScrum. A brief introduction
Scrum. A brief introductionUptech
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUSTInternship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUSTHamza Nasir
 
Scooter india,sip presentation
Scooter india,sip presentationScooter india,sip presentation
Scooter india,sip presentationDeepak Gautam
 
GUI & Modern UI Design
GUI & Modern UI DesignGUI & Modern UI Design
GUI & Modern UI DesignMalik Zahid
 
Introduction To Agile
Introduction To AgileIntroduction To Agile
Introduction To AgileKnoldus Inc.
 
APPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNETAPPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNETMdRakibHasan27
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingJitesh Gaurav
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingJitesh Gaurav
 
Agile scrum fundamentals
Agile scrum fundamentalsAgile scrum fundamentals
Agile scrum fundamentalsDeniz Gungor
 

Similar to IE 420 Presentation (20)

Work Sampling in the excavator
Work Sampling in the excavatorWork Sampling in the excavator
Work Sampling in the excavator
 
Midterm presentation rough
Midterm presentation   rough Midterm presentation   rough
Midterm presentation rough
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
Scrum. A brief introduction
Scrum. A brief introductionScrum. A brief introduction
Scrum. A brief introduction
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Work Measurement
Work MeasurementWork Measurement
Work Measurement
 
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUSTInternship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
 
Scooter india,sip presentation
Scooter india,sip presentationScooter india,sip presentation
Scooter india,sip presentation
 
GUI & Modern UI Design
GUI & Modern UI DesignGUI & Modern UI Design
GUI & Modern UI Design
 
Os prj ppt
Os prj pptOs prj ppt
Os prj ppt
 
Introduction To Agile
Introduction To AgileIntroduction To Agile
Introduction To Agile
 
5 Steps to implementing Lean
5  Steps to implementing Lean5  Steps to implementing Lean
5 Steps to implementing Lean
 
APPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNETAPPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNET
 
Scrum master
Scrum masterScrum master
Scrum master
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
IE training
IE training IE training
IE training
 
IE Training
IE Training IE Training
IE Training
 
Scrum (2)
Scrum (2)Scrum (2)
Scrum (2)
 
Agile scrum fundamentals
Agile scrum fundamentalsAgile scrum fundamentals
Agile scrum fundamentals
 

IE 420 Presentation

  • 1. Optimization of ATV Erector Set Thomas Malloy April Bouquard Abdulrahman Mohammed Nuhuli Leonard Arambam
  • 2. Agenda ● Time Standards ● Line Balancing ● Workstation Analysis ● Ergonomics ● Part Presentation ● Iterations ● 5S implementation ● Conclusion
  • 3. Time Study Part 1: ● Members worked alone on constructing entire ATV. ● Identified steps to be timed (Battery, 1-24) ● Timed each step in seconds Part 2: ● Users’ times were averaged together to identify standard assembly times. Phase Time (hrs) Average 2.53 Final 1.16
  • 4. Line Balancing Goal: We want all workers to have the same amount of time spent working. ● Precedence constraints did not allow for optimal usage of Largest Candidate Rule ○ Grouped steps were very restrictive ● Divided steps into 8 blocks to be divided between 4 workers. ○ 4 Long blocks and 4 short blocks Worker # Time (sec) 1 2207 2 1973 3 2217 4 2710
  • 5. Line Balancing (cont.) ● We reallocated steps from longer times to shorter times, but as the assembly progressed we could not have all workers actively working on the same product. ● Idle times between blocks allowed for flexibility. ○ Workers could help others when they lagged behind
  • 6. Workstation Analysis ● Due to kitting and task analysis, workers needed to be close together. ● Ordered 360 Degree Rotational Vices for each workstation. ● Separated black screws and ¼” nuts into separate containers. ● Kept tools in order ● Materials lay flat on the workstation (nothing above the head) ● No foreign objects permitted
  • 7. Workstation Analysis (cont.) ● Seated work aided in fine assembly and allowed for necessary communication ● All materials were within 24 inches of the worker ● Most used materials were within 14 inches ● Adjustable chairs with wheels provide ergonomic benefits for workers of all heights as well as ability to move laterally along workstation ● Elevated tables for larger workers
  • 8. Workstation Design Benefits ● Promotes a social atmosphere. ● Task order automatically designates idle times for workers ● Allows for quick passing of assembly ● Provides help from idle workers
  • 9. Tooling ● Magnetized Allen Wrench ● Standard C-Frame Wrench (stock with set) ● 360 Degree Rotational Vice ● Spring Clips ● Power tools were bulky and too powerful ○ Stripped screws/nuts ○ Caused hand cramps/aches ● Hand tools allowed for precision and accuracy
  • 10. Part Presentation ● Kitted parts rather than binning ○ Reduced time spent searching for parts. ○ Logical order to the steps ● All parts for worker job were within reach ● Kits had picture instructions as well as what to do when a set of steps was finished.
  • 11. 5S Implementation ● Sort: Separate the unnecessary from the necessary parts ● Shine: Place for every part - labelling ● Set to order: Clean the workplace before manufacturing start of shift ● Standardize: SOPs ● Sustain : implement and execute
  • 12. Ergonomic Evaluation Methods ● ACGIH TLV for Hand Activity ● Lighting Conditions ● Posture and repetitive work ● Mechanical Safety ● Job rotation.
  • 13. ACGIH TLV Evaluation Purpose: To asses the risk of hand injury in performing physically continuous demanding jobs Methods: Conducting ACGIH TLV for Hand Activity by accurately observing the steps through videotaping Results: Our results indicated that most of the work done by our right hand needed some modification.
  • 14.
  • 15. Implemented Improvements ● Ordered two 360 degree rotational vices to reduce TLV scores ● Magnetic Allen wrenches reduce overall movement during tightening the screws and decreased the number of lost screws due to dropping ● Holding the assembly in with the vice reduced the strain on the dominant hand while increasing nondominant hand usage
  • 16. Lighting Conditions OSHA Recommended: ● Illumination needed: >1500-2000 lux(lumen/m^2) ● Installation of overhead florescent lamp in the workstation with > 40 watt ● Incandescent lamp in the room with > 20 watt
  • 17. Posture and Repetitive Work ● Total work per day: 8 hours with one hour lunch ● System capability: 16 ATVs ● Height adjustable chairs ● Elevated tables for comfortable leg room
  • 18. Job Rotation ● Eliminate monotonous jobs and potentially harmful posture ● Cross functional training leads to a fully flexible workforce ● Isolate worker strengths ● Increase satisfaction and decrease muscle weakening rate ● Motivate employees to deal with new challenges
  • 19. Iteration #1: Assembly Line/Binning ● Assembly line with binning at each station ● No change in step order ● Precedence constraints were severe ● No drastic change in time from single worker method
  • 20. Iteration #2: Binning/Current Workstation Layout ● Allowed workers to work simultaneously ● Confusion during part selection ● Increased work time/lack of idle time ● Implemented magnetic c-wrenches and allen wrenches
  • 21. Iteration #3: Kitting/Current Workstation Layout ● Easy part selection ● Low precedence constraint effect ● Workers had idle time to reorganize workstations ● Provided quickest assembly time ● Removed magnetized c-wrench tool after it was found to be ineffective
  • 22. Quality Assurance ● Worker checklist to ensure all steps are performed ● Signoff sheet to link worker with steps performed as well as determine routings ● Standard Operating Procedures were developed to standardize the way steps were performed.
  • 23. Workstation Recommendations ● Drawers or overhead hangers for tool storage ● Lightweight automated tools calibrated to output a set pressure/rotation ● Flow racks to allow for kits to roll towards and away from worker ● Cross training workers to better utilize skills
  • 24. Idle Time ● Work on wheel assemblies or other small tasks ● Organize workstations ● Restock materials ● Help other workers ● Perform quality checks ● Start on a new kit
  • 25. Conclusions ● Average Takt Time of 29 min ● Layout provided a “team” mentality ● Kitting reduced time spent searching for parts ● Magnetized tooling aided in assembly process ● 360 Degree Rotational vice freed non-dominant hand ● Cross training workers allows for flexibility and cost efficiency