Weekly Construction Update 06-06-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 5.26.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
5.24.2010
Current Activities this Week:
Mass Excavation:
Grading is ongoing in Area 3. Backfilling of on-grade
is ongoing in Area 1 and Area 2.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on France Family Drive – Storm Line 6000
east side of France Family Drive. installation is ongoing. Currently at station
4+00.
Foundations:
Area 2 Concourse Level – E-Line footing excavation has
started and is currently to Column Line 18.
Area 3 Field Level – Wall Form installation is ongoing
on A-Line and is currently to Column Line 9.
Area 3 Field Level – Installation of Drilled Piers
are ongoing.
Field Level Area 2 – South East Vomitory
Area 4 Mezzanine Level – D-Line grade beam excavation Wall installation is ongoing (Column Lines
has begun. 11-12).
Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-4 is ongoing and
Is currently to Column Line 31.
Decking/Detailing/Studs/Edge Angle is ongoing in
sequence 1-2 on Mezzanine, Concourse and Suite Levels.
Area 4 – Drilled Pier installation is ongoing
near Column Line 1.
Building the Future
2. Underground MEP:
Deep Sanitary installation has started in Area 2.
MEP Rough-in:
Plumbing and Electrical rough-in on Concourse Level has
started.
Projected Activities occurring next Week:
Field Level Area 2 – Deep Sanitary Line
Mass Excavation: installation has started near Column Line 15.
Grading at Area 3 will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 5000 and
4000 will begin.
Deep Underground Plumbing:
Deep Sanitary installation in Area 2 will continue.
Foundations: Area 1 – Structural Steel Erection at West
Area 2 Concourse Level – Footing/Grade Beam installation Building is ongoing in Sequence 1-4 (bays
will begin. 28-31 shown).
Area 3 Field Level – A-Line wall placement will begin
Area 3 Mezzanine Level – Grade beam installation will
begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-4 will continue.
Decking/Detailing/Studs/Edge Plates will continue in
Sequence 1-2.
Field Level Area 1 – Shot looking north from
Concourse Level.
Building the Future
3. Additional Photos:
Suite Level Area 1 – Edge plate being
Concourse Level Area 1 – Plumbing rough-in
installed between Column Lines 26 - 27.
has started at north end.
Mezzanine Level Area 4 – Grade Beam
installation has started at Column Line 33 Press Level Area 1 – Steel being set in place
(North Supporter’s Seating Area). that holds the precast seating tubs.
Field Level Area 1 – Hydrotherapy Pit poured Field Level Area 1 – Column encasement and
and backfilled. backfilling ongoing.