SlideShare a Scribd company logo
1 of 4
Download to read offline
From:    Brandon Valdez                  To: David Ficklin - OnGoal
                                                                          Rory O’Connor – OnGoal
                             Office: Kansas City                          Lee Turner – OnGoal
                             Date:    7.21.2010                           Andy Heitmann – Turner
                                                                          Dave Dudzik - Turner
                             Re:      Wizards Stadium Project
                                      Update – Week of
                                      7.19.2010



 Current Activities this Week:

 Mass Excavation:
 Backfilling of on-grade seating is ongoing in Area 2
 and Area 3.

 Site Utilities:
 Storm Sewer Installation (Line 6000) is ongoing             Area 3 – Installation of Storm Line 6000 is
 on the east side of France Family Drive.                    ongoing on the east side of France Family
                                                             Drive.
  Foundations:
 Area 3 Field Level – Foundation installation continues on
 the east side of the site.

 Concrete Flatwork:
 Area 1 – North Mezzanine concrete placement is
 Complete at VIP Entrance. Prep work is ongoing for
 Next Slab-on-Grade pour (Column Line 26-24). Prep
 work is ongoing for Main Club topping slab placement.
                                                             Field Level Area 1 – Cast-in-place concrete
 Structural Steel Erection:                                  riser installation is ongoing.
 Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-7)
 Area 2 - Structural Steel Erection Sequence 2-1 is
 ongoing. Area 3 – Structural Steel Erection Sequence
 3-1 has started.

 Underground MEP:
 Electrical Secondary Distribution is ongoing in Areas 2.


                                                             Mezzanine Level Area 1 – Concrete for slab-
                                                             on-grade at VIP Entrance is placed at North
                                                             Mezzanine.

Building the Future
MEP Rough-in:
 Area 1 – Shallow electrical and plumbing rough-in is
 ongoing. Ductwork installation on Suite Level is ongoing.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Suite and Press
 Levels are ongoing.
                                                                Field Level Area 1/2 – Steel Erection ongoing
 Projected Activities occurring next Week:                      in both Sequence 2-1 (right side of picture)
                                                                and 3-1 (left side of picture).
 Mass Excavation:
 Backfilling of on-grade seating areas will continue in Area
 3. Grading in Area 3 (east of A-Line) will continue.

 Site Utilities:
 Installation of the Storm Line 6000 on the East Side (France
 Family Drive) of the site will be complete.

 Deep Underground MEP:
 Deep Electrical Distribution installation will start again
 in Area 3.

 Foundations:                                                   Area 1 – Shot of the West Building from the
 Area 3 Field Level – Foundation installation will continue.    south concourse area.

 Concrete Flatwork:
 Area 1 Field Level – Concrete placement for Slab-on-Grade
 will be completed to 24 Line.

 Area 1 Field Level – Installation of on-grade seating risers
 will continue.

 Structural Steel Erection:
 Erection of Structural Steel in Sequence 2-1 will
 continue. Erection of Structural Steel Sequence 3-1
 will continue.
                                                                Suite Level Area 1 – Shot at the front of the
 Erection of the Canopy Trusses will begin in Sequence 1-8.     Suites of metal stud framing progress.




Building the Future
Underground MEP:
 Electrical Secondary will continue in Area 3.

 MEP Rough-in:
 Plumbing and Electrical rough-in for Area 1 Field Level slab
 on grade will continue. MEP Rough-in at Suite Level will
 continue.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Suite and Press Levels will    Area 1 – Shot from Roof Level showing the
 continue.                                                      installation of the Canopy Roof Trusses.




                                                                Suite Level Area 1 – Ductwork installation is
                                                                ongoing.




Building the Future
Additional Photos:




Roof Level Area 1 – Shot looking between        Area 1 – Shot of the West Building showing
Canopy Trusses at 29 and 30 showing the         Canopy Trusses, Stadium Suite and Suites
bridging trusses, purlins and chevron braces.   metal stud framing.




Concourse Level Area 1 – Main Club slab-on-     Field Level Area 1 – Shot looking north of
grade is placed.                                on-grade seating.




Area 1 – Metal decking installation is          Field Level Area 1 – Shot of Supporter’s Club
ongoing at Terrace Seating Area.                Seating Area and Cauldron Club entrances.




Building the Future

More Related Content

More from Kansas City Wizards

More from Kansas City Wizards (9)

Memo wizards 08-25-2010
Memo wizards 08-25-2010Memo wizards 08-25-2010
Memo wizards 08-25-2010
 
KC Soccer Stadium
KC Soccer Stadium KC Soccer Stadium
KC Soccer Stadium
 
Construction Update 7-6-2010
Construction Update 7-6-2010Construction Update 7-6-2010
Construction Update 7-6-2010
 
Weekly Construction Update 06-14-10
Weekly Construction Update 06-14-10Weekly Construction Update 06-14-10
Weekly Construction Update 06-14-10
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Weekly Construction Update 05-19-2010
Weekly Construction Update 05-19-2010Weekly Construction Update 05-19-2010
Weekly Construction Update 05-19-2010
 
Construction Update 5-5-2010
Construction Update 5-5-2010Construction Update 5-5-2010
Construction Update 5-5-2010
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
 
Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
 

Construction Update 07-21-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 7.21.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 7.19.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer Installation (Line 6000) is ongoing Area 3 – Installation of Storm Line 6000 is on the east side of France Family Drive. ongoing on the east side of France Family Drive. Foundations: Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork: Area 1 – North Mezzanine concrete placement is Complete at VIP Entrance. Prep work is ongoing for Next Slab-on-Grade pour (Column Line 26-24). Prep work is ongoing for Main Club topping slab placement. Field Level Area 1 – Cast-in-place concrete Structural Steel Erection: riser installation is ongoing. Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-7) Area 2 - Structural Steel Erection Sequence 2-1 is ongoing. Area 3 – Structural Steel Erection Sequence 3-1 has started. Underground MEP: Electrical Secondary Distribution is ongoing in Areas 2. Mezzanine Level Area 1 – Concrete for slab- on-grade at VIP Entrance is placed at North Mezzanine. Building the Future
  • 2. MEP Rough-in: Area 1 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite Level is ongoing. Metal Stud Framing: Area 1 – Metal stud framing for Suite and Press Levels are ongoing. Field Level Area 1/2 – Steel Erection ongoing Projected Activities occurring next Week: in both Sequence 2-1 (right side of picture) and 3-1 (left side of picture). Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Grading in Area 3 (east of A-Line) will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will be complete. Deep Underground MEP: Deep Electrical Distribution installation will start again in Area 3. Foundations: Area 1 – Shot of the West Building from the Area 3 Field Level – Foundation installation will continue. south concourse area. Concrete Flatwork: Area 1 Field Level – Concrete placement for Slab-on-Grade will be completed to 24 Line. Area 1 Field Level – Installation of on-grade seating risers will continue. Structural Steel Erection: Erection of Structural Steel in Sequence 2-1 will continue. Erection of Structural Steel Sequence 3-1 will continue. Suite Level Area 1 – Shot at the front of the Erection of the Canopy Trusses will begin in Sequence 1-8. Suites of metal stud framing progress. Building the Future
  • 3. Underground MEP: Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 1 Field Level slab on grade will continue. MEP Rough-in at Suite Level will continue. Metal Stud Framing: Area 1 – Metal stud framing for Suite and Press Levels will Area 1 – Shot from Roof Level showing the continue. installation of the Canopy Roof Trusses. Suite Level Area 1 – Ductwork installation is ongoing. Building the Future
  • 4. Additional Photos: Roof Level Area 1 – Shot looking between Area 1 – Shot of the West Building showing Canopy Trusses at 29 and 30 showing the Canopy Trusses, Stadium Suite and Suites bridging trusses, purlins and chevron braces. metal stud framing. Concourse Level Area 1 – Main Club slab-on- Field Level Area 1 – Shot looking north of grade is placed. on-grade seating. Area 1 – Metal decking installation is Field Level Area 1 – Shot of Supporter’s Club ongoing at Terrace Seating Area. Seating Area and Cauldron Club entrances. Building the Future