1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 7.21.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
7.19.2010
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer Installation (Line 6000) is ongoing Area 3 – Installation of Storm Line 6000 is
on the east side of France Family Drive. ongoing on the east side of France Family
Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site.
Concrete Flatwork:
Area 1 – North Mezzanine concrete placement is
Complete at VIP Entrance. Prep work is ongoing for
Next Slab-on-Grade pour (Column Line 26-24). Prep
work is ongoing for Main Club topping slab placement.
Field Level Area 1 – Cast-in-place concrete
Structural Steel Erection: riser installation is ongoing.
Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-7)
Area 2 - Structural Steel Erection Sequence 2-1 is
ongoing. Area 3 – Structural Steel Erection Sequence
3-1 has started.
Underground MEP:
Electrical Secondary Distribution is ongoing in Areas 2.
Mezzanine Level Area 1 – Concrete for slab-
on-grade at VIP Entrance is placed at North
Mezzanine.
Building the Future
2. MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite Level is ongoing.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press
Levels are ongoing.
Field Level Area 1/2 – Steel Erection ongoing
Projected Activities occurring next Week: in both Sequence 2-1 (right side of picture)
and 3-1 (left side of picture).
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Grading in Area 3 (east of A-Line) will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will be complete.
Deep Underground MEP:
Deep Electrical Distribution installation will start again
in Area 3.
Foundations: Area 1 – Shot of the West Building from the
Area 3 Field Level – Foundation installation will continue. south concourse area.
Concrete Flatwork:
Area 1 Field Level – Concrete placement for Slab-on-Grade
will be completed to 24 Line.
Area 1 Field Level – Installation of on-grade seating risers
will continue.
Structural Steel Erection:
Erection of Structural Steel in Sequence 2-1 will
continue. Erection of Structural Steel Sequence 3-1
will continue.
Suite Level Area 1 – Shot at the front of the
Erection of the Canopy Trusses will begin in Sequence 1-8. Suites of metal stud framing progress.
Building the Future
3. Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue. MEP Rough-in at Suite Level will
continue.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press Levels will Area 1 – Shot from Roof Level showing the
continue. installation of the Canopy Roof Trusses.
Suite Level Area 1 – Ductwork installation is
ongoing.
Building the Future
4. Additional Photos:
Roof Level Area 1 – Shot looking between Area 1 – Shot of the West Building showing
Canopy Trusses at 29 and 30 showing the Canopy Trusses, Stadium Suite and Suites
bridging trusses, purlins and chevron braces. metal stud framing.
Concourse Level Area 1 – Main Club slab-on- Field Level Area 1 – Shot looking north of
grade is placed. on-grade seating.
Area 1 – Metal decking installation is Field Level Area 1 – Shot of Supporter’s Club
ongoing at Terrace Seating Area. Seating Area and Cauldron Club entrances.
Building the Future