From:    Brandon Valdez                  To: David Ficklin - OnGoal
                                                                          Rory O’Connor – OnGoal
                             Office: Kansas City                          Lee Turner – OnGoal
                             Date:    7.28.2010                           Andy Heitmann – Turner
                                                                          Dave Dudzik - Turner
                             Re:      Wizards Stadium Project
                                      Update – Week of
                                      7.26.2010



 Current Activities this Week:

 Mass Excavation:
 Backfilling of on-grade seating is ongoing in Area 2
 and Area 3.

 Site Utilities:
 Storm Sewer Installation (Line 6000) is ongoing             Area 3 – Installation of Storm Line 6000 is
 on the east side of France Family Drive.                    ongoing on the east side of France Family
                                                             Drive.
  Foundations:
 Area 3 Field Level – Foundation installation continues on
 the east side of the site.

 Concrete Flatwork:
 Area 1 – Slab-on-grade is placed at field level from
 Column line 25-23. Slab-on grade for player’s field
 Entrance is placed. “Ribbon” slab is placed over precast
                                                             Field Level Area 1 – Cast-in-place concrete
 Seating tubs on Suite Level.
                                                             riser installation is ongoing at west
                                                             elevation. Forming of intermediate stairs
 Structural Steel Erection:
                                                             has also started.
 Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8)
 Area 2 – Decking is being installed Sequence 2-1 is
 ongoing. Area 3 – Structural Steel Erection Sequence
 3-1 is nearly complete.

 Underground MEP:
 Electrical Secondary Distribution is ongoing in Areas 2.



                                                             Suite Level Area 1 – Concrete “Ribbon” Slab
                                                             is placed over the precast seating tubs.

Building the Future
MEP Rough-in:
 Area 1 – Shallow electrical and plumbing rough-in is
 ongoing. Ductwork installation on Suite Level is ongoing.
 Plumbing installation is ongoing on Suite Level.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Suite and Press
 Levels are ongoing. Metal stud framing has started on
 Main Concourse West Building.                                  Field Level Area 3 – Steel Erection is nearly
                                                                complete. Rakers are currently being set.
 Projected Activities occurring next Week:

 Mass Excavation:
 Backfilling of on-grade seating areas will continue in Area
 3. Grading in Area 3 (east of A-Line) will continue.

 Site Utilities:
 Installation of the Storm Line 6000 on the East Side (France
 Family Drive) of the site will be complete. Sanitary Sewer
 installation will begin at locations where Storm Line 6000
 is complete.
                                                                Area 1 – Shot of the West Building from the
 Deep Underground MEP:                                          North East corner of the Project Site.
 Deep Electrical Distribution installation will start again
 in Area 3.

 Foundations:
 Area 3 Field Level – Foundation installation will continue.

 Concrete Flatwork:
 Area 2 Field Level – Concrete placement for Slab-on-Grade
 will be completed to Column Line 14.

 Area 1 Field Level – Installation of on-grade seating risers
 will continue.
                                                                Press Level Area 1 – Metal stud framing is
 Structural Steel Erection:                                     ongoing.
 Erection of Structural Steel in Sequence 3-2 will
 begin. Decking installation will begin in Steel Sequence
 3-1.



Building the Future
Erection of the Canopy Trusses will continue in
 Sequence 1-8.

 Underground MEP:
 Electrical Secondary will continue in Area 3.

 MEP Rough-in:
 Plumbing and Electrical rough-in for Area 1/2 Field Level slab
 on grade will continue. MEP Rough-in at Suite Level will         Area 1 – Shot of “Wing” at Roof Canopy
 continue.                                                        being installed.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Concourse, Suite and Press
 Levels will continue.




                                                                  Suite Level Area 1 – Metal Stud Framing and
                                                                  Ductwork installation is ongoing.




Building the Future
Additional Photos:




Suite Level Area 1 – In wall plumbing rough-   Area 1 – Installation of formwork for
in has started.                                intermediate stairs.




Field Level Area 1 – Player Field Entrance     Field Level Area 1 – Slab-on-Grade placed
Vomitory slab prepped for concrete.
                                               and being finished from Column Lines 25-23.




Area 3 – Backfill of east side on-grade        Area 1 – Caulking of precast risers is
seating is ongoing.                            ongoing.




Building the Future

More Related Content

Similar to Construction Update 07-28-2010

Memo wizards 05-12-2010
Memo wizards 05-12-2010Memo wizards 05-12-2010
Memo wizards 05-12-2010KyleLRogers
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportHonolulu Civil Beat
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Fairfax County
 

Similar to Construction Update 07-28-2010 (7)

KC Soccer Stadium
KC Soccer Stadium KC Soccer Stadium
KC Soccer Stadium
 
Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
 
Memo wizards 05-12-2010
Memo wizards 05-12-2010Memo wizards 05-12-2010
Memo wizards 05-12-2010
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily Report
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 

Construction Update 07-28-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 7.28.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 7.26.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer Installation (Line 6000) is ongoing Area 3 – Installation of Storm Line 6000 is on the east side of France Family Drive. ongoing on the east side of France Family Drive. Foundations: Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork: Area 1 – Slab-on-grade is placed at field level from Column line 25-23. Slab-on grade for player’s field Entrance is placed. “Ribbon” slab is placed over precast Field Level Area 1 – Cast-in-place concrete Seating tubs on Suite Level. riser installation is ongoing at west elevation. Forming of intermediate stairs Structural Steel Erection: has also started. Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8) Area 2 – Decking is being installed Sequence 2-1 is ongoing. Area 3 – Structural Steel Erection Sequence 3-1 is nearly complete. Underground MEP: Electrical Secondary Distribution is ongoing in Areas 2. Suite Level Area 1 – Concrete “Ribbon” Slab is placed over the precast seating tubs. Building the Future
  • 2. MEP Rough-in: Area 1 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite Level is ongoing. Plumbing installation is ongoing on Suite Level. Metal Stud Framing: Area 1 – Metal stud framing for Suite and Press Levels are ongoing. Metal stud framing has started on Main Concourse West Building. Field Level Area 3 – Steel Erection is nearly complete. Rakers are currently being set. Projected Activities occurring next Week: Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Grading in Area 3 (east of A-Line) will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will be complete. Sanitary Sewer installation will begin at locations where Storm Line 6000 is complete. Area 1 – Shot of the West Building from the Deep Underground MEP: North East corner of the Project Site. Deep Electrical Distribution installation will start again in Area 3. Foundations: Area 3 Field Level – Foundation installation will continue. Concrete Flatwork: Area 2 Field Level – Concrete placement for Slab-on-Grade will be completed to Column Line 14. Area 1 Field Level – Installation of on-grade seating risers will continue. Press Level Area 1 – Metal stud framing is Structural Steel Erection: ongoing. Erection of Structural Steel in Sequence 3-2 will begin. Decking installation will begin in Steel Sequence 3-1. Building the Future
  • 3. Erection of the Canopy Trusses will continue in Sequence 1-8. Underground MEP: Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 1/2 Field Level slab on grade will continue. MEP Rough-in at Suite Level will Area 1 – Shot of “Wing” at Roof Canopy continue. being installed. Metal Stud Framing: Area 1 – Metal stud framing for Concourse, Suite and Press Levels will continue. Suite Level Area 1 – Metal Stud Framing and Ductwork installation is ongoing. Building the Future
  • 4. Additional Photos: Suite Level Area 1 – In wall plumbing rough- Area 1 – Installation of formwork for in has started. intermediate stairs. Field Level Area 1 – Player Field Entrance Field Level Area 1 – Slab-on-Grade placed Vomitory slab prepped for concrete. and being finished from Column Lines 25-23. Area 3 – Backfill of east side on-grade Area 1 – Caulking of precast risers is seating is ongoing. ongoing. Building the Future