Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.

Construction Update 07-28-2010

1,149 views

Published on

  • Be the first to comment

  • Be the first to like this

Construction Update 07-28-2010

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 7.28.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 7.26.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer Installation (Line 6000) is ongoing Area 3 – Installation of Storm Line 6000 is on the east side of France Family Drive. ongoing on the east side of France Family Drive. Foundations: Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork: Area 1 – Slab-on-grade is placed at field level from Column line 25-23. Slab-on grade for player’s field Entrance is placed. “Ribbon” slab is placed over precast Field Level Area 1 – Cast-in-place concrete Seating tubs on Suite Level. riser installation is ongoing at west elevation. Forming of intermediate stairs Structural Steel Erection: has also started. Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8) Area 2 – Decking is being installed Sequence 2-1 is ongoing. Area 3 – Structural Steel Erection Sequence 3-1 is nearly complete. Underground MEP: Electrical Secondary Distribution is ongoing in Areas 2. Suite Level Area 1 – Concrete “Ribbon” Slab is placed over the precast seating tubs. Building the Future
  2. 2. MEP Rough-in: Area 1 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite Level is ongoing. Plumbing installation is ongoing on Suite Level. Metal Stud Framing: Area 1 – Metal stud framing for Suite and Press Levels are ongoing. Metal stud framing has started on Main Concourse West Building. Field Level Area 3 – Steel Erection is nearly complete. Rakers are currently being set. Projected Activities occurring next Week: Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Grading in Area 3 (east of A-Line) will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will be complete. Sanitary Sewer installation will begin at locations where Storm Line 6000 is complete. Area 1 – Shot of the West Building from the Deep Underground MEP: North East corner of the Project Site. Deep Electrical Distribution installation will start again in Area 3. Foundations: Area 3 Field Level – Foundation installation will continue. Concrete Flatwork: Area 2 Field Level – Concrete placement for Slab-on-Grade will be completed to Column Line 14. Area 1 Field Level – Installation of on-grade seating risers will continue. Press Level Area 1 – Metal stud framing is Structural Steel Erection: ongoing. Erection of Structural Steel in Sequence 3-2 will begin. Decking installation will begin in Steel Sequence 3-1. Building the Future
  3. 3. Erection of the Canopy Trusses will continue in Sequence 1-8. Underground MEP: Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 1/2 Field Level slab on grade will continue. MEP Rough-in at Suite Level will Area 1 – Shot of “Wing” at Roof Canopy continue. being installed. Metal Stud Framing: Area 1 – Metal stud framing for Concourse, Suite and Press Levels will continue. Suite Level Area 1 – Metal Stud Framing and Ductwork installation is ongoing. Building the Future
  4. 4. Additional Photos: Suite Level Area 1 – In wall plumbing rough- Area 1 – Installation of formwork for in has started. intermediate stairs. Field Level Area 1 – Player Field Entrance Field Level Area 1 – Slab-on-Grade placed Vomitory slab prepped for concrete. and being finished from Column Lines 25-23. Area 3 – Backfill of east side on-grade Area 1 – Caulking of precast risers is seating is ongoing. ongoing. Building the Future

×