Pohick Stream Stabilization Phase II - Areas 2 and 3
Construction Update 07-28-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 7.28.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
7.26.2010
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer Installation (Line 6000) is ongoing Area 3 – Installation of Storm Line 6000 is
on the east side of France Family Drive. ongoing on the east side of France Family
Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site.
Concrete Flatwork:
Area 1 – Slab-on-grade is placed at field level from
Column line 25-23. Slab-on grade for player’s field
Entrance is placed. “Ribbon” slab is placed over precast
Field Level Area 1 – Cast-in-place concrete
Seating tubs on Suite Level.
riser installation is ongoing at west
elevation. Forming of intermediate stairs
Structural Steel Erection:
has also started.
Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8)
Area 2 – Decking is being installed Sequence 2-1 is
ongoing. Area 3 – Structural Steel Erection Sequence
3-1 is nearly complete.
Underground MEP:
Electrical Secondary Distribution is ongoing in Areas 2.
Suite Level Area 1 – Concrete “Ribbon” Slab
is placed over the precast seating tubs.
Building the Future
2. MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite Level is ongoing.
Plumbing installation is ongoing on Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press
Levels are ongoing. Metal stud framing has started on
Main Concourse West Building. Field Level Area 3 – Steel Erection is nearly
complete. Rakers are currently being set.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Grading in Area 3 (east of A-Line) will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will be complete. Sanitary Sewer
installation will begin at locations where Storm Line 6000
is complete.
Area 1 – Shot of the West Building from the
Deep Underground MEP: North East corner of the Project Site.
Deep Electrical Distribution installation will start again
in Area 3.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 2 Field Level – Concrete placement for Slab-on-Grade
will be completed to Column Line 14.
Area 1 Field Level – Installation of on-grade seating risers
will continue.
Press Level Area 1 – Metal stud framing is
Structural Steel Erection: ongoing.
Erection of Structural Steel in Sequence 3-2 will
begin. Decking installation will begin in Steel Sequence
3-1.
Building the Future
3. Erection of the Canopy Trusses will continue in
Sequence 1-8.
Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1/2 Field Level slab
on grade will continue. MEP Rough-in at Suite Level will Area 1 – Shot of “Wing” at Roof Canopy
continue. being installed.
Metal Stud Framing:
Area 1 – Metal stud framing for Concourse, Suite and Press
Levels will continue.
Suite Level Area 1 – Metal Stud Framing and
Ductwork installation is ongoing.
Building the Future
4. Additional Photos:
Suite Level Area 1 – In wall plumbing rough- Area 1 – Installation of formwork for
in has started. intermediate stairs.
Field Level Area 1 – Player Field Entrance Field Level Area 1 – Slab-on-Grade placed
Vomitory slab prepped for concrete.
and being finished from Column Lines 25-23.
Area 3 – Backfill of east side on-grade Area 1 – Caulking of precast risers is
seating is ongoing. ongoing.
Building the Future