Programme Review
James Pesnichak
Calf State Auto Association
2
STAR Program Update
• Organization
• Tools
• Plan and Work Order Process
• Resource / Staffing Management
• Project Plan Management
• Work Order Management
• Scope, Assumptions & Constraints
• Change Management
• Issue Management
• Risk Mitigation Process
• Financial Management
• Project Status Management
• Project Health Check
3
STAR program organization
Project management
Financial management
Resource management
CCCM
Brooke Smith
PSO
Applications
Database
Mainframe
Platforms (MR, DT, SAN)
Network
Security
Management systems
Configuration management
Test & Performance
BJ Joshi
Architecture
Interface integration
App decommissioning
Cost recovery
Legacy
SW Install / Config
Integration
Interface builds
Data conversion
Testing & certification
HelpDesk integration &
Operational Readiness
Database
Job automation
Reporting
STAR
Michele Farnsworth
Applications
W2K server builds
Unix server builds
Desktop cert/deploy
Network support
Security platform
Job automation
Engineering
Server operations
Network & Security operations
Systems management
Test / Lab support
Operations
Disaster recovery
Facilities
SLAs / Reporting
Monte Ziola
Infrastructure
John Brownlow
Program Manager
Jim Pesnichak
Enterprise Prog Mngr
4
Customer STAR organization
PMO Liaison
Resources Management
Outside Liaison
Project Plan Mgmt.
Contracting
Program Mgmt.
Steve Dunn
Architecture / Engineering
Integration
Conversion
UI/Portal Engineering
Shared Services
Mike Knibbs
Project Management
Design / Business Rqmts.
Software Config. / Dvlpmt.
IT Transition
Deployment
Core Delivery
Linda Greifenstein
Project Management
Design / Business Rqmts.
Software Config. / Dvlpmt.
IT Transition
Deployment
CRM Delivery
Satish Weber
Project Management
Design / Business Rqmts.
Software Config. / Dvlpmt.
IT Transition
Deployment
Technical Deployment
& Information Mgmt.
Dave Graybeal
Config. Mgmt.
Release Mgmt.
Requirements Mgmt.
Testing / Performance
QA
Testing / QA
Victor Macias
Applications
Telephony
Desktop
Midrange
Mainframe
Infrastructure
David Lamm
STAR IT Executive
Daniel St. John
PSO
Architecture Infrastructure
Applications
Configuration Management
5
Program Tools Used
Risks & Mitigation Plan
• Microsoft Project - Schedule project activities, dependencies, and
estimate effort
• GSMS/PM2 Project Management Methodology - Standard PM
methodology
• PIV – Timekeeping, collect & track actuals, support CM of documents
• Presage - Reporting project actuals and status to the enterprise
• PMO Templates for client deliverables and work products, such as
Communication Plan, Risk Plan, Configuration Management Plan,
Acceptance Deliverable Signoff sheet
• CM tools - Rational ClearCase & CA-Endevor - version control /
configuration management for Midrange & Mainframe objects
respectively
6
How we develop plans & work orders
Staffing Plan
Statement of Work
Work Breakdown Structure (WBS) .mpp
Work Order Resource Allocation
Request / Scope document
Resource Plan (BAC)
7
Resource plan / BAC (Budget at Completion)
8
Staffing plan
9
Project Schedule
Example Project Plan
STAR Infrastructure
10
Statement of Work / Work Order
11
Scope, Assumptions, and Constraints
Example
Project Scope,
Assumptions,
& Constraints
document
12
Change management plan
CSAA
Change
Process
CSAA
Proposal
SOW / Scope
Process flow
13
Issues list
Example
STAR logs
14
Risks & Mitigation Plan
15
Financials – Budget vs Actuals
16
Financials
17
Status Reporting
18
Project Health Check Status
100 %
CommunicationManagement
RiskManagement
ScopeManagement
ScheduleManagement
Overall Compliance
ResourceManagement
Financial&ContractMgmt.
QualityManagement
CompliancebyKnowledgeArea(%)
22%
78%
11%
22%
56%
0%
60%
35 %
Of applicable items
P234 - STAR ProjectProject Health Check Action Plan Status - 03/09/04
Page 3 of3
Items are listed in the same order as they
w ere on the first Health Check report.
63.8%
77.8%
52.7%
50.0%
77.8%
58.3%
95.0%
67.3 %
Last
Check
Current
Status
Communication
Management
Resource
Management
Financial&
Contract
Management
Quality
Management
Schedule
Management
Scope
Management
Risk
Management Overall
10 %
40 %
30 %
20 %
70 %
60 %
50 %
90 %
80 %
Last Check
Current Status
0%

More Related Content

Viewers also liked

MaestríA Siendo Objetivos Contenidos
MaestríA Siendo Objetivos   ContenidosMaestríA Siendo Objetivos   Contenidos
MaestríA Siendo Objetivos Contenidos
Adalberto
 
MaestríA Pasos Para El Texto Paralelo
MaestríA Pasos Para El Texto ParaleloMaestríA Pasos Para El Texto Paralelo
MaestríA Pasos Para El Texto Paralelo
Adalberto
 

Viewers also liked (16)

Education%203 a%20walker%20final%20slides[1]
Education%203 a%20walker%20final%20slides[1]Education%203 a%20walker%20final%20slides[1]
Education%203 a%20walker%20final%20slides[1]
 
operating system structures
operating system structuresoperating system structures
operating system structures
 
Danuelo Arroyo Longitud de una curva
Danuelo Arroyo Longitud de una curvaDanuelo Arroyo Longitud de una curva
Danuelo Arroyo Longitud de una curva
 
Ute lorena lopez,dr.gonzalo remache.fortalecer las capacidades y potencialida...
Ute lorena lopez,dr.gonzalo remache.fortalecer las capacidades y potencialida...Ute lorena lopez,dr.gonzalo remache.fortalecer las capacidades y potencialida...
Ute lorena lopez,dr.gonzalo remache.fortalecer las capacidades y potencialida...
 
Estamos Con Ustedes
Estamos Con UstedesEstamos Con Ustedes
Estamos Con Ustedes
 
Domingo 6 resurrección c 2013 reflexión evangélica
Domingo 6 resurrección c 2013 reflexión evangélicaDomingo 6 resurrección c 2013 reflexión evangélica
Domingo 6 resurrección c 2013 reflexión evangélica
 
Ute plan de investigación en la modalidad de proyectos dr remache_l_uis aguas
Ute plan de investigación en la modalidad de proyectos dr remache_l_uis aguasUte plan de investigación en la modalidad de proyectos dr remache_l_uis aguas
Ute plan de investigación en la modalidad de proyectos dr remache_l_uis aguas
 
MaestríA Siendo Objetivos Contenidos
MaestríA Siendo Objetivos   ContenidosMaestríA Siendo Objetivos   Contenidos
MaestríA Siendo Objetivos Contenidos
 
Tp psicología general UBA
Tp psicología general UBATp psicología general UBA
Tp psicología general UBA
 
Guia de trabajo creativo semaforo
Guia de trabajo creativo semaforoGuia de trabajo creativo semaforo
Guia de trabajo creativo semaforo
 
MaestríA Pasos Para El Texto Paralelo
MaestríA Pasos Para El Texto ParaleloMaestríA Pasos Para El Texto Paralelo
MaestríA Pasos Para El Texto Paralelo
 
Ch23
Ch23Ch23
Ch23
 
Biological Bases of Behavior
Biological Bases of BehaviorBiological Bases of Behavior
Biological Bases of Behavior
 
Curso hfc aprendices
Curso hfc aprendicesCurso hfc aprendices
Curso hfc aprendices
 
Tipos de suelos
Tipos de suelosTipos de suelos
Tipos de suelos
 
StreamOnline
StreamOnline StreamOnline
StreamOnline
 

Similar to JP PM Review2

Project Management_c
Project Management_cProject Management_c
Project Management_c
rynmif
 
The Powerof One+Pmo Overview
The Powerof One+Pmo OverviewThe Powerof One+Pmo Overview
The Powerof One+Pmo Overview
DJ EVERETTE
 
Project Management
Project ManagementProject Management
Project Management
jdhakkan
 
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
shofiulalom
 
V Edelstein Resume Progenics 12 10
V Edelstein Resume Progenics 12 10V Edelstein Resume Progenics 12 10
V Edelstein Resume Progenics 12 10
dverae
 

Similar to JP PM Review2 (20)

Carden carrieresume2016
Carden carrieresume2016Carden carrieresume2016
Carden carrieresume2016
 
Cloudbyz PPM - Integrated Enterprise PPM, ALM and APM on force.com cloud
Cloudbyz PPM - Integrated Enterprise PPM, ALM and APM on force.com cloudCloudbyz PPM - Integrated Enterprise PPM, ALM and APM on force.com cloud
Cloudbyz PPM - Integrated Enterprise PPM, ALM and APM on force.com cloud
 
Project Management_c
Project Management_cProject Management_c
Project Management_c
 
Rachana Resume To be sent
Rachana Resume To be sentRachana Resume To be sent
Rachana Resume To be sent
 
Project Management - Ghayal Resume -1
Project Management - Ghayal Resume -1Project Management - Ghayal Resume -1
Project Management - Ghayal Resume -1
 
Surender Reddy
Surender ReddySurender Reddy
Surender Reddy
 
PMP CAPM Study Guide Time Management
PMP CAPM Study Guide Time ManagementPMP CAPM Study Guide Time Management
PMP CAPM Study Guide Time Management
 
The Powerof One+Pmo Overview
The Powerof One+Pmo OverviewThe Powerof One+Pmo Overview
The Powerof One+Pmo Overview
 
Introduction to the project managment
Introduction to the project managment Introduction to the project managment
Introduction to the project managment
 
Project Management
Project ManagementProject Management
Project Management
 
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
 
Resume
ResumeResume
Resume
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
Integrated Enterprise PPM, ALM and APM on force.com cloud
Integrated Enterprise PPM, ALM and APM on force.com cloudIntegrated Enterprise PPM, ALM and APM on force.com cloud
Integrated Enterprise PPM, ALM and APM on force.com cloud
 
V Edelstein Resume Progenics 12 10
V Edelstein Resume Progenics 12 10V Edelstein Resume Progenics 12 10
V Edelstein Resume Progenics 12 10
 
E Resume
E ResumeE Resume
E Resume
 
Resume margaret plass - 2016
Resume   margaret plass - 2016Resume   margaret plass - 2016
Resume margaret plass - 2016
 
Resume - Margaret Plass - 2016
Resume - Margaret Plass - 2016Resume - Margaret Plass - 2016
Resume - Margaret Plass - 2016
 
Pm training (planning and tracking) - Project Leader Ramp-Up
Pm training (planning and tracking) - Project Leader Ramp-Up Pm training (planning and tracking) - Project Leader Ramp-Up
Pm training (planning and tracking) - Project Leader Ramp-Up
 
Cloudbyz ppm, integrated enterprise ppm-alm-apm on force.com
Cloudbyz ppm,   integrated enterprise ppm-alm-apm on force.comCloudbyz ppm,   integrated enterprise ppm-alm-apm on force.com
Cloudbyz ppm, integrated enterprise ppm-alm-apm on force.com
 

JP PM Review2

  • 2. 2 STAR Program Update • Organization • Tools • Plan and Work Order Process • Resource / Staffing Management • Project Plan Management • Work Order Management • Scope, Assumptions & Constraints • Change Management • Issue Management • Risk Mitigation Process • Financial Management • Project Status Management • Project Health Check
  • 3. 3 STAR program organization Project management Financial management Resource management CCCM Brooke Smith PSO Applications Database Mainframe Platforms (MR, DT, SAN) Network Security Management systems Configuration management Test & Performance BJ Joshi Architecture Interface integration App decommissioning Cost recovery Legacy SW Install / Config Integration Interface builds Data conversion Testing & certification HelpDesk integration & Operational Readiness Database Job automation Reporting STAR Michele Farnsworth Applications W2K server builds Unix server builds Desktop cert/deploy Network support Security platform Job automation Engineering Server operations Network & Security operations Systems management Test / Lab support Operations Disaster recovery Facilities SLAs / Reporting Monte Ziola Infrastructure John Brownlow Program Manager Jim Pesnichak Enterprise Prog Mngr
  • 4. 4 Customer STAR organization PMO Liaison Resources Management Outside Liaison Project Plan Mgmt. Contracting Program Mgmt. Steve Dunn Architecture / Engineering Integration Conversion UI/Portal Engineering Shared Services Mike Knibbs Project Management Design / Business Rqmts. Software Config. / Dvlpmt. IT Transition Deployment Core Delivery Linda Greifenstein Project Management Design / Business Rqmts. Software Config. / Dvlpmt. IT Transition Deployment CRM Delivery Satish Weber Project Management Design / Business Rqmts. Software Config. / Dvlpmt. IT Transition Deployment Technical Deployment & Information Mgmt. Dave Graybeal Config. Mgmt. Release Mgmt. Requirements Mgmt. Testing / Performance QA Testing / QA Victor Macias Applications Telephony Desktop Midrange Mainframe Infrastructure David Lamm STAR IT Executive Daniel St. John PSO Architecture Infrastructure Applications Configuration Management
  • 5. 5 Program Tools Used Risks & Mitigation Plan • Microsoft Project - Schedule project activities, dependencies, and estimate effort • GSMS/PM2 Project Management Methodology - Standard PM methodology • PIV – Timekeeping, collect & track actuals, support CM of documents • Presage - Reporting project actuals and status to the enterprise • PMO Templates for client deliverables and work products, such as Communication Plan, Risk Plan, Configuration Management Plan, Acceptance Deliverable Signoff sheet • CM tools - Rational ClearCase & CA-Endevor - version control / configuration management for Midrange & Mainframe objects respectively
  • 6. 6 How we develop plans & work orders Staffing Plan Statement of Work Work Breakdown Structure (WBS) .mpp Work Order Resource Allocation Request / Scope document Resource Plan (BAC)
  • 7. 7 Resource plan / BAC (Budget at Completion)
  • 9. 9 Project Schedule Example Project Plan STAR Infrastructure
  • 10. 10 Statement of Work / Work Order
  • 11. 11 Scope, Assumptions, and Constraints Example Project Scope, Assumptions, & Constraints document
  • 18. 18 Project Health Check Status 100 % CommunicationManagement RiskManagement ScopeManagement ScheduleManagement Overall Compliance ResourceManagement Financial&ContractMgmt. QualityManagement CompliancebyKnowledgeArea(%) 22% 78% 11% 22% 56% 0% 60% 35 % Of applicable items P234 - STAR ProjectProject Health Check Action Plan Status - 03/09/04 Page 3 of3 Items are listed in the same order as they w ere on the first Health Check report. 63.8% 77.8% 52.7% 50.0% 77.8% 58.3% 95.0% 67.3 % Last Check Current Status Communication Management Resource Management Financial& Contract Management Quality Management Schedule Management Scope Management Risk Management Overall 10 % 40 % 30 % 20 % 70 % 60 % 50 % 90 % 80 % Last Check Current Status 0%