SlideShare a Scribd company logo
1 of 42
Download to read offline
1275 Shiloh Road • Suite 2560
Kennesaw, GA 30144
770.794.7012
brewerengineering.com
Preliminary Design Submittal
Professional Design and Construction
Administration Services for:
Sewell Park Redevelopment
Cobb County Parks, Recreational, and
Cultural Affairs Department
April 19, 2013
Submittal Contents
Preliminary Base Sheets
Overall Site Plan
Site Plans
Grading Plans
Utility Plans
Architectural Plans
Architectural Elevations
Issues Lists
Updated Schedule
Permit Required List
Preliminary Cost Estimates
Sheet Title:
Drawn By:
Scale:
Date:
Job No.:
Sheet No.:
Revisions:
Sheet Title:
Drawn By:
Scale:
Date:
Job No.:
Sheet No.:
Revisions:
Sheet Title:
Drawn By:
Scale:
Date:
Job No.:
Sheet No.:
Revisions:
Sheet Title:
Drawn By:
Scale:
Date:
Job No.:
Sheet No.:
Revisions:
5855 Jimmy Carter Boulevard Suite 218 Norcross, Georgia 30071 770.729.8433 fax 770.729.8466
SEWELL PARK PRELIMINARY NOTES AND QUESTIONS
Notes
1. The asbestos report notes the tan tile has asbestos and will need to be remediated. Our
understanding is that this will be handled by the client before we begin demolition.
2. Geo Hydro recommends that the demolition contractor make a specific composite sample of
the demolition debris for the Concession/Restroom building and a combined sample from the
Field 3 Dugouts for Toxic Characteristic (TC) analysis for lead. According to their findings they do
not believe that they test will come back showing a high level of lead content. This test will cost
approximately $50.00 and is up to the owner. Please advise is you want to have us include this
in the specifications.
3. We will note in the specifications the recommendations for the fluorescent light fixtures.
Architectural:
1. The schematic notes added a door from the concession storage (was Youth Closet) to the
concession room. Is an exterior door needed for concession storage.
2. If a exterior door is needed to concession storage does it need to be 4'-0"?
3. In expanding the dugouts at field 3 to the requested size the two poles next to (and attached)
the existing dugouts will need to be relocated or demolished. Please advise.
4. There are wooded baseball bat holders at each of the dugout areas. Are those to be saved?
5. If the wooded bat holders are to be saved are they to be repainted?
6. According to Addendum 1 the dugouts at field 3 are to be brought up to grade. We are
currently showing that situation. if this is incorrect please let us know.
7. We are currently showing a 4' gate on one side of the Field 3 building by one of the redesigned
dugouts for access to the condenser in between the building and the field. If this is not
acceptable or you would like different access please advise.
8. The current benches have backs. We are current showing new benches without backs. Is that
acceptable.
9. We have provided a shelf in the dugouts in field 3 for helmets. Please advise if this is not
acceptable.
Plumbing:
1. In an attempt at meeting the latest State adopted water conservation requirements (i.e. use of
high-efficiency plumbing fixtures), it appears that the standard push-button styles typically used
do not meet the minimum ADA push requirements, therefore we are proposing use of hydraulic
flushometers for the water closets and urinals (see Attachments 1 & 2 for products by Sloan).
They can be ordered with accessories for metal push buttons in lieu of the plastic buttons
shown, and elbows for top-spud connections in lieu of the back-spud shown). Please advise if
acceptable.
2. For the 3-compartment sink a drop-in stainless steel fixture will be specified. To meet
requirements of Cobb Food Service Code where each compartment “shall be large enough to
accommodate immersion of the largest equipment and utensils” what are the minimum
compartment dimensions required.
5855 Jimmy Carter Boulevard Suite 218 Norcross, Georgia 30071 770.729.8433 fax 770.729.8466
HVAC:
1. For concession area we are providing a ductless split heat pump unit with programmable thermostat,
however, there is concern about concession storage room being hot during the summer months. To
solve this problem, In lieu of ductless split unit, we could put a floor mounted unit in the Concession
storage and duct this unit to serve both concession storage and concession room. Please advise.
2. In case it was decided not to provide any air-conditioning for concession storage, we can ventilate this
room along with baseball storage room by means of a roof mounted exhaust fan. The fan will be
controlled by means of wall mounted thermostat at Concession storage room. Please advise.
3. For Ventilation of restrooms, we plan to control the roof mounted exhaust fan serving the restrooms by
means of both programmed timer and motion sensor, that is, in the summer months; we program the
fan to run continuously on certain days and certain hours, and during the cold months, we let the fan to
be controlled by motion sensor. This way, we can lower the space temperature during the summer
months. Please advise.
ELECTRICAL:
1. Are we to provide any power or EC to the scoreboards? Notes indicate that this will be done under a
separate contract but the electrical will need to be coordinated.
2. Is any EC or power needed for sound systems?
3. Need direction on how to control the field lighting. Notes indicate a remote control and time clock.
What is needed for the remote connection for lighting controls?
4. Do we need any dedicated power outside the concessions building for fryers or will they be propane?
Description
Concealed Hydraulically Operated High Efficiency Water Closet Flushometer, for wall
hung concealed back spud bowls.
Flush Cycle
£ Model 952-1.28 High Efficiency (1.28 gpf/4.8 Lpf)
Specifications
Quiet, Concealed, Diaphragm Type, Rough Brass Closet Flushometer for either left or
right hand supply with the following features:
• PERMEX™ Synthetic Rubber Diaphragm with Dual Filtered Bypass
• ADA Compliant Non-Hold-Open feature type Actuator (specify Actuator type listed
below)
• 1" I.P.S. Wheel Handle Bak-Chek™ Angle Stop
• Adjustable Tailpiece
• Vacuum Breaker
• Double Slip Elbow Flush Connection and Spud Coupling for 1½" Concealed Back
Spud
• Sweat Solder Adapter
• Diaphragm, Stop Seat and Vacuum Breaker to be molded from
PERMEX™ rubber compound for Chloramine resistance
• High Copper, Low Zinc Brass Castings for Dezincification Resistance
• Non-Hold-Open Handle, Fixed Metering Bypass and No External Volume Adjustment
to Ensure Water Conservation.
• Flush Accuracy Controlled by CID™ Technology
• Diaphragm, Handle Packing, Stop Seat and Vacuum Breaker to be molded from
PERMEX™ Rubber Compound for Chloramine Resistance.
• 100% of the energy used in manufacturing is offset with Renewable Energy Sources
– Wind Energy
Valve Body, Cover, Tailpiece and Control Stop shall be in conformance with ASTM
Alloy Classification for Semi-Red Brass. Valve shall be in compliance to the
applicable sections of ASSE 1037, ANSI/ASME 112.19.2.
Actuator Types: (please check one)
£ FW Fixture Wall Actuator (HY-33-A) (rear access required)
£ MP Metal Partition Actuator (HY-49-A)
£ SW Side Wall Mounted Actuator (HY-72-A)
£ MBFW Metal Button Fixture Wall Actuator (HY-100-A) (rear access required)
£ MBPM Metal Button Panel Mount (HY-108-A)
See Actuator Specification pages in this section for details on Actuators.
Variations
£ TP Trap Primer
£ YO Two Wall Bumpers (for open front seat without cover)
See Accessories Section of the Sloan catalog for details on these and other
Flushometer variations.
Hydraulic Flushometer can also be provided in Regal®
Models. All rough-in
dimensions remain the same. Consult the factory.
SLOAN VALVE COMPANY • 10500 SEYMOUR AVE. • FRANKLIN PARK, IL. 60131
Ph: 1-800-9-VALVE-9 or 1-847-671-4300 • Fax: 1-800-447-8329 or 1-847-671-4380
http://www.sloanvalve.com
Hydraulic
Royal®
Model
Flushometer
u
u
u
u
This space for Architect/Engineer approval
The information contained in this document is subject to change without notice.
Royal Hydraulic 952-1.28 S.S. — Rev. X (03/10)
Copyright © 2010 SLOAN VALVE COMPANY Printed in the U.S.A.
Made in the U.S.A.
u
952-1.28
Description
Concealed hydraulically activated urinal flushometer, for ¾” rear spud high efficiency
urinals.
Flush Cycle
£	Model 995-0.125 (0.125 gpf/0.5 Lp)
£	Model 995-0.25 (0.25 gpf/1.0 Lpf)
£	Model 995-0.5 (0.5 gpf/1.9 Lpf)
Specifications
Quiet, Concealed, Diaphragm Type, Rough Brass Urinal Flushometer for either left or right
hand supply with the following features:
•	 For Flushing Volumes 0.125 and 0.25: Dual Linear Filtered Bypass Diaphragm
•	 For Flushing Volumes 0.5: Dual Filtered Bypass Diaphragm
•	 ADA Compliant Non-Hold-Open feature type Actuator (specify Actuator type listed below)
•	 ¾” I.P.S. Wheel Handle Bak-Chek®
Angle Stop
•	 Adjustable Tailpiece
•	 Vacuum Breaker
•	 Elbow Flush Connection and Spud Coupling for ¾” Concealed Back Spud
•	 Sweat Solder Adapter
•	 High Copper, Low Zinc Brass Castings for Dezincification Resistance
•	 Non-Hold-Open Handle, Fixed Metering Bypass and No External Volume Adjustment to
Ensure Water Conservation.
•	 Flush Accuracy Controlled by CID Technology
•	 Diaphragm, Handle Packing, Stop Seat and Vacuum Breaker to be molded from PERMEX®
Rubber Compound for Chloramine Resistance.
Valve Body, Cover, Tailpiece and Control Stop shall be in conformance with ASTM Alloy
Classification for Semi-Red Brass. Valve shall be in compliance to the applicable sections
of ASSE 1037 and ANSI/ASME 112.19.6.
L Dimension
Specify the “L” Dimension for the proper length of the Flush Connection. The “L”
Dimension is equal to the Wall Thickness (to the nearest whole inch) plus 2¾”.
Actuator Types: (Please Check One)
£ FW	 Fixture Wall Actuator (HY-33-A) (rear access required)
£ MP	 Metal Partition Actuator (HY-49-A)
£ SW	 Side Wall Mounted Actuator (HY-72-A)
£ MBFW	 Metal Button Fixture Wall Actuator (HY-100-A) (rear access required)
£ MBPM	 Metal Button Panel Mount (HY-108-A)
See actuator Specification pages in this section for details on Actuators.
See Accessories Section of the Sloan catalog for details on these and other flushometer
variations.
Hydraulic flushometers can also be provided in Regal®
and Sloan®
models. All rough-in
dimensions remain the same. Consult the factory.
SLOAN HEADQUARTERS • 10500 SEYMOUR AVENUE • FRANKLIN PARK, IL 60131
Ph: 1-800-9-VALVE-9 •  Fax: 1-847-671-4380 • http://www.sloanvalve.com
Hydraulic
Royal®
Model
Flushometer
This space for Architect/Engineer approval
The information contained in this document is subject to change without notice.
Royal Hydraulic 995 HEU  S.S. — Rev. 0 (03/12)
© 2012 SLOAN VALVE COMPANY      
Made with
Renewable Energy
Buy
America
n
Act•
•
C
om plian
t
Buy
America
n
Act•
•
C
om plian
t
Sloan Valve Company is buying renewable energy
certificates to meet 100% of the company’s purchased
electricity use at its Franklin Park, Illinois facility.
1275 Shiloh Road
Suite 2560
Kennesaw, GA 30144
Preliminary Design Questions/Issues
1. What playground surface and equipment is desired for the Commons Area? What age group should this area
be designed for?
2. Do we have as-builts or design drawings for the irrigation system recently installed for Fields 5A  5B?
3. Do we know where the existing septic field and tank is located for the existing concession stand?
4. Will the existing score keepers structure be retained for both Fields 1  2?
5. We have had several discussions with Cobb Stormwater to develop ways to incorporate the scope of the
project desired without requiring water quality measures  ponds. We are attempting to develop a plan that
will not generate an increase in stormwater runoff and thereby not require detention ponds or water quality
ponds. Paving scope will be a possible issue with water quality.
Sewell Park Project Schedule
Notice to Proceed 2-25-13
Begin Field Survey 3-04-13
Project Team Site Visit 3-04-13
Kick-off Meeting 2-25-13
Survey Completed 3-16-13
Schematic/Preliminary Design 4-19-13
Formal Presentation to County 4-26-13
Design Development Submittal 5-17-13
90% CD Submittal 6-26-13
100% CD Submittal 7-17-13
Submit for LDP 7-24-13
LDP Permit 9-02-13
Submit for Building Permit 9-02-13
Submit to Purchasing-Bid Set 9-18-13
Building Permit 9-30-13
Issue for Bid 9-27-13
Pre-Bid Meeting 10-08-13
Bid Date 10-24-13
BOC Award 11-12-13
Construction Begins 1-02-14
Sod Installed 5-08-14
Construction Completion 8-01-14
Permits Required
Land Disturbance Permit- Cobb County
Marietta Water  Sewer  Marietta Power Approvals
Building Permit-Cobb County
NPDES Permit
Units Qty Unit Rate Sub Total Total
244,231.00$           
‐$                        
LS 1 30,000.00$       30,000.00$            
LS 1 123,000.00$    123,000.00$          
LS 1 35,000.00$       35,000.00$            
LS 1 19,000.00$       19,000.00$            
LS 1 36,000.00$       36,000.00$            
243,000.00$         
SF 25600 0.25$                6,400.00$              
CY 75 15.00$              1,125.00$              
LF 686 5.00$                3,430.00$              
SF 400 2.00$                800.00$                 
LS 2 3,000.00$         6,000.00$              
CY 200 12.00$              2,400.00$              
CY 500 15.00$              7,500.00$              
SF 30000 0.10$                3,000.00$              
SF 30000 0.10$                3,000.00$              
SF 30000 0.10$                3,000.00$              
Re‐Development of Sewell Park
Cobb County Parks, Recreation,  Cultural Affairs
Preliminary Cost Estimate ‐ 4‐19‐13
Laser Grading Filling
Laser Grading before sod
Project Budget for Redevelopment of Fields #1, #2, #3, #4,  Common 
Area Between Field 3 and 5A  5B
Preliminary Cost Estimate‐ Baseball Concession/RR Bldg
Strip  Haul off sod
Demolition of existing building
New Concession Building
Electrical
HVAC
Plumbing
Field #1
Hazardous Material Abatement (
Total Preliminary Estimated Cost Concession/RR Bldg
 $          977,500.00 
Item ‐ Description
Project Budget for Baseball Concession/Restroom Building
Demolition‐Field 1
Remove existing infield mix
Remove existing fencing  posts
Remove existing concrete
Remove existing dugouts
Grading Field 1
Import fill
Import topsoil
Laser Grading Subgrade
Sewell Park Preliminary Cost Estimate 2
Units Qty Unit Rate Sub Total Total
TN 120 110.00$            13,200.00$            
TN 35 85.00$              2,975.00$              
TN 300 30.00$              9,000.00$              
‐$                        
‐$                        
‐$                        
‐$                        
EA 1 1,750.00$         1,750.00$              
LF 700 4.00$                2,800.00$              
EA 1 400.00$            400.00$                 
SF 10000 0.25$                2,500.00$              
‐$                        
SF 26500 0.50$                13,250.00$            
EA 1 1,250.00$         1,250.00$              
EA 1 400.00$            400.00$                 
EA 8 300.00$            2,400.00$              
EA 2 200.00$            400.00$                 
EA 28 75.00$              2,100.00$              
EA 1 3,000.00$         3,000.00$              
LF 400 15.00$              6,000.00$              
LF 400 12.00$              4,800.00$              
LF 200 10.00$              2,000.00$              
LF 200 10.00$              2,000.00$              
‐$                        
‐$                        
EA 1 3,000.00$         3,000.00$              
‐$                        
‐$                        
2 Irrigation Meter
2 PVC
1.5 PVC
1.25 PVC
1 PVC
Main Shut Off Valve
Scrubber Valves
Quick Coupling Valve
Falcon 6504 
Controller
Grassing
Landscaping  Irrigation Field 1
Sod
Backflow Preventer
Erosion Field 1
Temoporary construction entrance
Silt Fence
Inlet Protection
Sand
Existing Septic Field Removal
Infield Mix
Warning Track Mix
Item ‐ Description
Sewell Park Preliminary Cost Estimate 3
Units Qty Unit Rate Sub Total Total
SF 650 5.00$                3,250.00$              
LF 500 15.00$              7,500.00$              
LF 135 25.00$              3,375.00$              
LF 60 75.00$              4,500.00$              
LF ‐$                        
EA 1 1,750.00$         1,750.00$              
EA 4 300.00$            1,200.00$              
LF 300 3.00$                900.00$                 
LS 1 1,000.00$         1,000.00$              
‐$                        
EA 2 1,250.00$         2,500.00$              
LF 300 2.00$                600.00$                 
‐$                        
EA 2 250.00$            500.00$                 
EA 3 150.00$            450.00$                 
LS 2 15,000.00$       30,000.00$            
‐$                        
LS 1 70,000.00$       70,000.00$            
EA 1 2,000.00$         2,000.00$              
EA 1 2,000.00$         2,000.00$              
SY 365 25.00$              9,125.00$              
SF 180 50.00$              9,000.00$              
‐$                        
LF 50 35.00$              1,750.00$              
LF 40.00$              ‐$                        
LF 250 35.00$              8,750.00$              
LS 1 15,000.00$       15,000.00$            
285,030.00$         
Storm drainage
Fence Windscreen
Heavy Duty Rubber Backstop Netting
Outfield Distance Markers
Dugouts
4 FT Gate
Yellow Fence Capping
Homeplate  Bases
Pitching Mound
Foul Poles
6 FT Chain Link Fencing
Underground Power Service to Fields 1  2 to replace overhead
Total Preliminary Estimated Costs ‐ Field #1
Concrete Retaining Wall
Utilities Field 1
Water
Sanitary Sewer
Scoreboards
New Wiring for Light Poles
New wiring for Pitching Machines
Power to Pitching Mound
Asphalt Drive
10 FT Chain Link Fencing
20 FT Chain Link Fencing
24 FT Chain Link Fencing
12 FT Gate
Item ‐ Description
Site Improvements Field 1
Concrete Pad
Sewell Park Preliminary Cost Estimate 4
Units Qty Unit Rate Sub Total Total
SF 15500 0.25$                3,875.00$              
CY 100 15.00$              1,500.00$              
LF 498 5.00$                2,490.00$              
EA 2 3,000.00$         6,000.00$              
‐$                        
CY 500 15.00$              7,500.00$              
SF 20000 0.10$                2,000.00$              
SF 20000 0.20$                4,000.00$              
TN 120 110.00$            13,200.00$            
TN 20 85.00$              1,700.00$              
TN 150 30.00$              4,500.00$              
EA 1 1,750.00$         1,750.00$              
LF 600 4.00$                2,400.00$              
‐$                        
SF 10000 0.25$                2,500.00$              
SF 16000 0.50$                8,000.00$              
EA 1 800.00$            800.00$                 
EA 1 400.00$            400.00$                 
EA 6 300.00$            1,800.00$              
EA 2 200.00$            400.00$                 
EA 20 75.00$              1,500.00$              
EA 1 1,200.00$         1,200.00$              
LF 400 10.00$              4,000.00$              
LF 300 10.00$              3,000.00$              
LF 150 10.00$              1,500.00$              
LF 150 10.00$              1,500.00$              
‐$                        
1.25 PVC
1 PVC
Quick Coupling Valve
Falcon 6504 
Controller
2 PVC
1.5 PVC
Landscaping  Irrigation Field 2
Sod
Backflow Preventer
Main Shut Off Valve
Scrubber Valves
Erosion Field 2
Temoporary construction entrance
Silt Fence
Inlet Protection
Grassing
Laser Grading Subgrade
Laser Grading Filling  before sod
Infield Mix
Warning Track Mix
Sand
Remove existing fencing  posts
Demo and remove existing dugout
Grading Field 2
Import fill
Import topsoil
Item ‐ Description
Field #2
Demolition Field 2
Strip  Haul off sod
Remove existing infield mix
Sewell Park Preliminary Cost Estimate 5
Units Qty Unit Rate Sub Total Total
SF 650 5.00$                3,250.00$              
LF 435 15.00$              6,525.00$              
LF 120 25.00$              3,000.00$              
LF 65 75.00$              4,875.00$              
LF ‐$                        
EA 1 1,750.00$         1,750.00$              
EA 4 300.00$            1,200.00$              
LF 250 3.00$                750.00$                 
EA 1 1,000.00$         1,000.00$              
‐$                        
EA 2 1,250.00$         2,500.00$              
LF 250 2.00$                500.00$                 
‐$                        
EA 2 250.00$            500.00$                 
EA 3 150.00$            450.00$                 
EA 2 15,000.00$       30,000.00$            
‐$                        
LS 1 70,000.00$       70,000.00$            
LS 1 2,000.00$         2,000.00$              
‐$                        
‐$                        
‐$                        
LF 350 50.00$              17,500.00$            
‐$                        
223,315.00$         Total Preliminary Estimated Costs ‐ Field #2
Water
Sanitary Sewer
Storm drainage
Scoreboards
New Wiring for Light Poles
New wiring for Pitching Machines
Utilities Field 2
Fence Windscreen
Heavy Duty Rubber Backstop Netting
Outfield Distance Markers
Dugouts
4 FT Gate
Yellow Fence Capping
Homeplate  Bases
Pitching Mound
Foul Poles
6 FT Chain Link Fencing
10 FT Chain Link Fencing
20 FT Chain Link Fencing
24 FT Chain Link Fencing
12 FT Gate
Item ‐ Description
Site Improvements Field 2
Concrete Sidewalks
Sewell Park Preliminary Cost Estimate 6
Units Qty Unit Rate Sub Total Total
‐$                        
‐$                        
‐$                        
LS 2 6,000.00$         12,000.00$            
‐$                        
‐$                        
‐$                        
‐$                        
LS 2 25,000.00$       50,000.00$            
‐$                        
‐$                        
‐$                        
‐$                        
62,000.00$            
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
Total Preliminary Estimated Costs ‐ Field #3
New Dugout
Field #3
Demolition Field 3
Demolition of existing Dugout
Item ‐ Description
Sewell Park Preliminary Cost Estimate 7
Units Qty Unit Rate Sub Total Total
‐$                        
SF 55600 0.25$                13,900.00$            
CY 300 15.00$              4,500.00$              
LF 1000 5.00$                5,000.00$              
SF 600 2.00$                1,200.00$              
EA 6 1,600.00$         9,600.00$              
EA 2 3,000.00$         6,000.00$              
EA 6 400.00$            2,400.00$              
CY 2000 12.00$              24,000.00$            
CY 900 15.00$              13,500.00$            
EA 1 5,000.00$         5,000.00$              
EA 1 6,000.00$         6,000.00$              
TN 300 110.00$            33,000.00$            
LS 1 5,000.00$         5,000.00$              
TN 80 85.00$              6,800.00$              
TN 600 30.00$              18,000.00$            
‐$                        
EA 1 3,000.00$         3,000.00$              
SF 1500 4.00$                6,000.00$              
EA 3 400.00$            1,200.00$              
SF 43000 0.25$                10,750.00$            
‐$                        
LF ‐$                        
LF ‐$                        
LF 600 50.00$              30,000.00$            
Utilities Field 4
Water
Sanitary Sewer
Storm drainage
Erosion Field 4
Temoporary construction entrance
Silt Fence
Inlet Protection
Grassing
Laser Grading Filling  before sod
Infield Mix
Clear  Grub
Warning Track Mix
Sand
Selective Tree Removal
Grading Field 4
Earthwork
Import topsoil
Laser Grading Subgrade
Remove existing infield mix
Remove existing fencing  posts
Remove existing concrete
Remove and dispose of existing light poles
Demo and remove existing dugout
Item ‐ Description
Field #4
Demolition Field 4
Strip  Haul off sod
Sewell Park Preliminary Cost Estimate 8
Units Qty Unit Rate Sub Total Total
Landscaping  Irrigation Field 4
Sod SF 58000 0.50$                29,000.00$            
Backflow Preventer EA 1 1,200.00$         1,200.00$              
Main Shut Off Valve EA 1 400.00$            400.00$                 
Scrubber Valves EA 14 300.00$            4,200.00$              
Quick Coupling Valve EA 4 200.00$            800.00$                 
Falcon 6504  EA 40 75.00$              3,000.00$              
Controller EA 1 3,000.00$         3,000.00$              
2 PVC EA 800 10.00$              8,000.00$              
1.5 PVC LF 600 10.00$              6,000.00$              
1.25 PVC LF 300 10.00$              3,000.00$              
1 PVC LF 300 10.00$              3,000.00$              
‐$                        
‐$                        
Irrigation Meter EA 1 3,000.00$         3,000.00$              
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
Item ‐ Description
Sewell Park Preliminary Cost Estimate 9
Units Qty Unit Rate Sub Total Total
SF 650 5.00$                3,250.00$              
LF 580 15.00$              8,700.00$              
LF 120 25.00$              3,000.00$              
LF 180 75.00$              13,500.00$            
LF 120 125.00$            15,000.00$            
EA 2 1,750.00$         3,500.00$              
EA 4 300.00$            1,200.00$              
LF 275 3.00$                825.00$                 
EA 1 1,000.00$         1,000.00$              
‐$                        
EA 2 1,250.00$         2,500.00$              
SF 120 2.00$                240.00$                 
‐$                        
EA 3 250.00$            750.00$                 
EA 3 250.00$            750.00$                 
EA 2 15,000.00$       30,000.00$            
‐$                        
‐$                        
LS 1 25,000.00$       25,000.00$            
EA 6 20,000.00$       120,000.00$          
LS 1 2,000.00$         2,000.00$              
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
500,665.00$         
Item ‐ Description
Site Improvements Field 4
Concrete Sidewalks
6 FT Chain Link Fencing
10 FT Chain Link Fencing
20 FT Chain Link Fencing
30 FT Chain Link Fencing
12 FT Gate
4 FT Gate
Yellow Fence Capping
Homeplate  Bases
Pitching Mound
Foul Poles
Fence Windscreen
Heavy Duty Rubber Backstop Netting
Outfield Distance Markers
Dugouts
Scoreboards
Lighting Distribution Modifications Allowance
New Light Pole Fixtures ( Assuming Musco direct burial pole)
Power to Pitching Mound
Total Preliminary Estimated Costs ‐ Field #4
Sewell Park Preliminary Cost Estimate 10
Units Qty Unit Rate Sub Total Total
‐$                        
‐$                        
‐$                        
EA 10 450.00$            4,500.00$              
EA 9 190.00$            1,710.00$              
EA 9 175.00$            1,575.00$              
EA 25 45.00$              1,125.00$              
EA 25 25.00$              625.00$                 
EA 25 15.00$              375.00$                 
EA 21 16.00$              336.00$                 
‐$                        
TN 50 50.00$              2,500.00$              
TN 2 225.00$            450.00$                 
SF 1000 10.00$              10,000.00$            
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
23,196.00$            
Item ‐ Description
Common Area Between Field #3  #5A/5B
Large Trees
Evergreen Tree
Small Flowering Trees
Large Shrubs
Small Shrubs
Ground Cover
Oerebbuaks.Native Grasses
Slate Dust
Boulders
Play Surface
Total Preliminary Estimated Costs‐ Common Area
Sewell Park Preliminary Cost Estimate 11
Units Qty Unit Rate Sub Total Total
‐$                        
244,231.00$           
SY 1200 16.00$              19,200.00$            
SY 1200 8.00$                9,600.00$              
‐$                        
‐$                        
‐$                        
LF 420 10.00$              4,200.00$              
LS 1 2,500.00$         2,500.00$              
‐$                        
‐$                        
LS 1 8,000.00$         8,000.00$              
‐$                        
‐$                        
SY 8000 24.00$              192,000.00$          
‐$                        
‐$                        
‐$                        
235,500.00$         
‐$                        
1 20,000.00$       20,000.00$            
1 4,000.00$         4,000.00$              
‐$                        
‐$                        
‐$                        
‐$                        
‐$                        
24,000.00$            
Item ‐ Description
Project Budget for Paving
Site Paving
Soil Cement Stabilization
2 Asphalt Topping 
Storm Sewer
Curb  Gutter
Traffic Striping
Removal and Disposal of gravel
Landscaping
Additional Available for Site Paving (8,000 sy‐ 72,000 sf)
Total Preliminary Estimated Costs ‐ Site Paving
Alternates
Storage Shed
Electrical for Shed
Total Preliminary Estimated Costs‐ Storage Shed
Sewell Park Preliminary Cost Estimate 12
EST. COST DIFERENCE
244,231.00$         
243,000.00$         
1,231.00$               
285,030.00$   
223,315.00$   
62,000.00$     
500,665.00$   
23,196.00$     
1,094,206.00$      
(116,706.00)$         
244,231.00$         
43,500.00$     
192,000.00$   
235,500.00$         
8,731.00$               
24,000.00$            
977,500.00$         
SUMMARY
Project Budget for Baseball Concession/Restroom Building
Total Preliminary Estimated Cost Concession/RR Bldg
Variance
Field #1
Field #2
Field #3
Project Budget for Redevelopment of Fields #1, #2, #3, #4,  Common 
Area Between Field 3 and 5A  5B
Field #4
Commons Area
Total Preliminary Estimated Costs (Fields and Common Area)
Variance
Project Budget for Site Paving
Paving for Existing Gravel and Additional Parking Spaces
Additional 72,000 sf of Paving Resurfacing
Total Preliminary Estimated Costs for Site Paving
Variance
Storage Shed Alternate
Total Preliminary Estimated Cost for Storage Shed

More Related Content

What's hot

Universal seal brochure
Universal seal brochureUniversal seal brochure
Universal seal brochureEko Kiswanto
 
H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...
H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...
H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...UniqueIndoorComfortLibertyville
 
Updated Summary Lincoln Power Point Presentation
Updated Summary Lincoln Power Point PresentationUpdated Summary Lincoln Power Point Presentation
Updated Summary Lincoln Power Point PresentationDavid Page
 
Specialized Transmitter Isolation Valve
Specialized Transmitter Isolation ValveSpecialized Transmitter Isolation Valve
Specialized Transmitter Isolation ValveCTi Controltech
 
Nordeast Nest Project
Nordeast Nest ProjectNordeast Nest Project
Nordeast Nest ProjectTE Studio
 
Cooper Lighing Eco-Twist
Cooper Lighing Eco-TwistCooper Lighing Eco-Twist
Cooper Lighing Eco-TwistPatrick Smith
 
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYBUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYAgrima Garg
 
Vikingpump.catalog sec 141_12-06
Vikingpump.catalog sec 141_12-06Vikingpump.catalog sec 141_12-06
Vikingpump.catalog sec 141_12-06Eko Kiswanto
 
Gas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural GasGas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural GasGas Networks Ireland
 
2010 FASTECH BUILDING PROSPECTUS
2010  FASTECH BUILDING  PROSPECTUS2010  FASTECH BUILDING  PROSPECTUS
2010 FASTECH BUILDING PROSPECTUSRene I. Dela Cruz
 
Rheem Hot Water Brochure - The Heater Man
Rheem Hot Water Brochure - The Heater ManRheem Hot Water Brochure - The Heater Man
Rheem Hot Water Brochure - The Heater ManBrendan Smith
 

What's hot (18)

Universal seal brochure
Universal seal brochureUniversal seal brochure
Universal seal brochure
 
H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...
H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...
H2i Residential Cooling and Heating System Carried By Unique Indoor Comfort L...
 
Hobart dealer delhi Contact 91-9899332022
Hobart dealer delhi Contact 91-9899332022Hobart dealer delhi Contact 91-9899332022
Hobart dealer delhi Contact 91-9899332022
 
Product of the Week Showcase - May
Product of the Week Showcase - MayProduct of the Week Showcase - May
Product of the Week Showcase - May
 
Updated Summary Lincoln Power Point Presentation
Updated Summary Lincoln Power Point PresentationUpdated Summary Lincoln Power Point Presentation
Updated Summary Lincoln Power Point Presentation
 
Specialized Transmitter Isolation Valve
Specialized Transmitter Isolation ValveSpecialized Transmitter Isolation Valve
Specialized Transmitter Isolation Valve
 
Nordeast Nest Project
Nordeast Nest ProjectNordeast Nest Project
Nordeast Nest Project
 
Raypak
RaypakRaypak
Raypak
 
Pdwi event
Pdwi eventPdwi event
Pdwi event
 
Cooper Lighing Eco-Twist
Cooper Lighing Eco-TwistCooper Lighing Eco-Twist
Cooper Lighing Eco-Twist
 
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDYBUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
BUSINESS HOTEL CASE STUDY AND LITERATURE STUDY
 
Bba petroleo pesado
Bba petroleo pesadoBba petroleo pesado
Bba petroleo pesado
 
Vikingpump.catalog sec 141_12-06
Vikingpump.catalog sec 141_12-06Vikingpump.catalog sec 141_12-06
Vikingpump.catalog sec 141_12-06
 
Gas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural GasGas Networks Ireland Connecting your Home to Natural Gas
Gas Networks Ireland Connecting your Home to Natural Gas
 
2010 FASTECH BUILDING PROSPECTUS
2010  FASTECH BUILDING  PROSPECTUS2010  FASTECH BUILDING  PROSPECTUS
2010 FASTECH BUILDING PROSPECTUS
 
Rheem Hot Water Brochure - The Heater Man
Rheem Hot Water Brochure - The Heater ManRheem Hot Water Brochure - The Heater Man
Rheem Hot Water Brochure - The Heater Man
 
Water tank-standards
Water tank-standardsWater tank-standards
Water tank-standards
 
Gürcistan references
Gürcistan referencesGürcistan references
Gürcistan references
 

Viewers also liked

Viewers also liked (11)

12° império islâmico
12° império islâmico12° império islâmico
12° império islâmico
 
Chalk Dust Final PDF
Chalk Dust Final PDFChalk Dust Final PDF
Chalk Dust Final PDF
 
Di adiós messenger, hola skype(2)
Di adiós messenger, hola skype(2)Di adiós messenger, hola skype(2)
Di adiós messenger, hola skype(2)
 
Modelos informe-de-gestion (1)
Modelos informe-de-gestion (1)Modelos informe-de-gestion (1)
Modelos informe-de-gestion (1)
 
Los volcanes
Los volcanesLos volcanes
Los volcanes
 
Cv natasja de jong
Cv natasja de jongCv natasja de jong
Cv natasja de jong
 
Cronograma
CronogramaCronograma
Cronograma
 
Programa92
Programa92Programa92
Programa92
 
WOHAA
WOHAAWOHAA
WOHAA
 
13° feudalismo
13° feudalismo13° feudalismo
13° feudalismo
 
Actualidad tecnológica en las redes sociales
Actualidad tecnológica en las redes socialesActualidad tecnológica en las redes sociales
Actualidad tecnológica en las redes sociales
 

Similar to Sewell Park Redevelopment Preliminary Design Submittal

JDWW001v6evapcocondenser
JDWW001v6evapcocondenserJDWW001v6evapcocondenser
JDWW001v6evapcocondenserKelly Erwin
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Audubon Engineering Company
 
Pipe shields inc
Pipe shields incPipe shields inc
Pipe shields incopenmind56
 
What Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobWhat Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobjoseph william
 
Valvulas globo - Globe valves
Valvulas globo - Globe valvesValvulas globo - Globe valves
Valvulas globo - Globe valvesJLX Valve
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between SystemsVictor Ashkenazy
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasAshwin Gadgil
 
Plate Heat Exchanger-controller_design.pptx
Plate Heat Exchanger-controller_design.pptxPlate Heat Exchanger-controller_design.pptx
Plate Heat Exchanger-controller_design.pptxAmitYadav413774
 
48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrier48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrierRios Luis
 
AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.
AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.
AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.Steve Kolesar
 
Ivanpah Solar Thermal Project ACC1
Ivanpah Solar Thermal Project ACC1Ivanpah Solar Thermal Project ACC1
Ivanpah Solar Thermal Project ACC1Laura Sterk
 

Similar to Sewell Park Redevelopment Preliminary Design Submittal (20)

JDWW001v6evapcocondenser
JDWW001v6evapcocondenserJDWW001v6evapcocondenser
JDWW001v6evapcocondenser
 
Pipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case StudiesPipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case Studies
 
Service center solahart 081313462267
Service center solahart 081313462267Service center solahart 081313462267
Service center solahart 081313462267
 
Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010
 
Pipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case StudiesPipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case Studies
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
 
Ta y sa60_00
Ta y sa60_00Ta y sa60_00
Ta y sa60_00
 
Pipe shields inc
Pipe shields incPipe shields inc
Pipe shields inc
 
What Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning jobWhat Constittutes a Cuality Commissioning job
What Constittutes a Cuality Commissioning job
 
Valvulas globo - Globe valves
Valvulas globo - Globe valvesValvulas globo - Globe valves
Valvulas globo - Globe valves
 
US Bellows 101
US Bellows 101US Bellows 101
US Bellows 101
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between Systems
 
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_ThomasSubsea689_FinalSubmission_Ashwin_Kim_Thomas
Subsea689_FinalSubmission_Ashwin_Kim_Thomas
 
Powertech1
Powertech1Powertech1
Powertech1
 
Plate Heat Exchanger-controller_design.pptx
Plate Heat Exchanger-controller_design.pptxPlate Heat Exchanger-controller_design.pptx
Plate Heat Exchanger-controller_design.pptx
 
48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrier48 tc 04-16-03pd paquete carrier
48 tc 04-16-03pd paquete carrier
 
Field Services: Problem Resolution
Field Services: Problem ResolutionField Services: Problem Resolution
Field Services: Problem Resolution
 
AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.
AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.
AmSan Now Carries a Complete MRO Building Maintenance Supplies Product Offering.
 
Contech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial MarketsContech Slotted Drain for Commercial Markets
Contech Slotted Drain for Commercial Markets
 
Ivanpah Solar Thermal Project ACC1
Ivanpah Solar Thermal Project ACC1Ivanpah Solar Thermal Project ACC1
Ivanpah Solar Thermal Project ACC1
 

Sewell Park Redevelopment Preliminary Design Submittal

  • 1. 1275 Shiloh Road • Suite 2560 Kennesaw, GA 30144 770.794.7012 brewerengineering.com Preliminary Design Submittal Professional Design and Construction Administration Services for: Sewell Park Redevelopment Cobb County Parks, Recreational, and Cultural Affairs Department April 19, 2013
  • 2. Submittal Contents Preliminary Base Sheets Overall Site Plan Site Plans Grading Plans Utility Plans Architectural Plans Architectural Elevations Issues Lists Updated Schedule Permit Required List Preliminary Cost Estimates
  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20. Sheet Title: Drawn By: Scale: Date: Job No.: Sheet No.: Revisions:
  • 21. Sheet Title: Drawn By: Scale: Date: Job No.: Sheet No.: Revisions:
  • 22. Sheet Title: Drawn By: Scale: Date: Job No.: Sheet No.: Revisions:
  • 23. Sheet Title: Drawn By: Scale: Date: Job No.: Sheet No.: Revisions:
  • 24. 5855 Jimmy Carter Boulevard Suite 218 Norcross, Georgia 30071 770.729.8433 fax 770.729.8466 SEWELL PARK PRELIMINARY NOTES AND QUESTIONS Notes 1. The asbestos report notes the tan tile has asbestos and will need to be remediated. Our understanding is that this will be handled by the client before we begin demolition. 2. Geo Hydro recommends that the demolition contractor make a specific composite sample of the demolition debris for the Concession/Restroom building and a combined sample from the Field 3 Dugouts for Toxic Characteristic (TC) analysis for lead. According to their findings they do not believe that they test will come back showing a high level of lead content. This test will cost approximately $50.00 and is up to the owner. Please advise is you want to have us include this in the specifications. 3. We will note in the specifications the recommendations for the fluorescent light fixtures. Architectural: 1. The schematic notes added a door from the concession storage (was Youth Closet) to the concession room. Is an exterior door needed for concession storage. 2. If a exterior door is needed to concession storage does it need to be 4'-0"? 3. In expanding the dugouts at field 3 to the requested size the two poles next to (and attached) the existing dugouts will need to be relocated or demolished. Please advise. 4. There are wooded baseball bat holders at each of the dugout areas. Are those to be saved? 5. If the wooded bat holders are to be saved are they to be repainted? 6. According to Addendum 1 the dugouts at field 3 are to be brought up to grade. We are currently showing that situation. if this is incorrect please let us know. 7. We are currently showing a 4' gate on one side of the Field 3 building by one of the redesigned dugouts for access to the condenser in between the building and the field. If this is not acceptable or you would like different access please advise. 8. The current benches have backs. We are current showing new benches without backs. Is that acceptable. 9. We have provided a shelf in the dugouts in field 3 for helmets. Please advise if this is not acceptable. Plumbing: 1. In an attempt at meeting the latest State adopted water conservation requirements (i.e. use of high-efficiency plumbing fixtures), it appears that the standard push-button styles typically used do not meet the minimum ADA push requirements, therefore we are proposing use of hydraulic flushometers for the water closets and urinals (see Attachments 1 & 2 for products by Sloan). They can be ordered with accessories for metal push buttons in lieu of the plastic buttons shown, and elbows for top-spud connections in lieu of the back-spud shown). Please advise if acceptable. 2. For the 3-compartment sink a drop-in stainless steel fixture will be specified. To meet requirements of Cobb Food Service Code where each compartment “shall be large enough to accommodate immersion of the largest equipment and utensils” what are the minimum compartment dimensions required.
  • 25. 5855 Jimmy Carter Boulevard Suite 218 Norcross, Georgia 30071 770.729.8433 fax 770.729.8466 HVAC: 1. For concession area we are providing a ductless split heat pump unit with programmable thermostat, however, there is concern about concession storage room being hot during the summer months. To solve this problem, In lieu of ductless split unit, we could put a floor mounted unit in the Concession storage and duct this unit to serve both concession storage and concession room. Please advise. 2. In case it was decided not to provide any air-conditioning for concession storage, we can ventilate this room along with baseball storage room by means of a roof mounted exhaust fan. The fan will be controlled by means of wall mounted thermostat at Concession storage room. Please advise. 3. For Ventilation of restrooms, we plan to control the roof mounted exhaust fan serving the restrooms by means of both programmed timer and motion sensor, that is, in the summer months; we program the fan to run continuously on certain days and certain hours, and during the cold months, we let the fan to be controlled by motion sensor. This way, we can lower the space temperature during the summer months. Please advise. ELECTRICAL: 1. Are we to provide any power or EC to the scoreboards? Notes indicate that this will be done under a separate contract but the electrical will need to be coordinated. 2. Is any EC or power needed for sound systems? 3. Need direction on how to control the field lighting. Notes indicate a remote control and time clock. What is needed for the remote connection for lighting controls? 4. Do we need any dedicated power outside the concessions building for fryers or will they be propane?
  • 26. Description Concealed Hydraulically Operated High Efficiency Water Closet Flushometer, for wall hung concealed back spud bowls. Flush Cycle £ Model 952-1.28 High Efficiency (1.28 gpf/4.8 Lpf) Specifications Quiet, Concealed, Diaphragm Type, Rough Brass Closet Flushometer for either left or right hand supply with the following features: • PERMEX™ Synthetic Rubber Diaphragm with Dual Filtered Bypass • ADA Compliant Non-Hold-Open feature type Actuator (specify Actuator type listed below) • 1" I.P.S. Wheel Handle Bak-Chek™ Angle Stop • Adjustable Tailpiece • Vacuum Breaker • Double Slip Elbow Flush Connection and Spud Coupling for 1½" Concealed Back Spud • Sweat Solder Adapter • Diaphragm, Stop Seat and Vacuum Breaker to be molded from PERMEX™ rubber compound for Chloramine resistance • High Copper, Low Zinc Brass Castings for Dezincification Resistance • Non-Hold-Open Handle, Fixed Metering Bypass and No External Volume Adjustment to Ensure Water Conservation. • Flush Accuracy Controlled by CID™ Technology • Diaphragm, Handle Packing, Stop Seat and Vacuum Breaker to be molded from PERMEX™ Rubber Compound for Chloramine Resistance. • 100% of the energy used in manufacturing is offset with Renewable Energy Sources – Wind Energy Valve Body, Cover, Tailpiece and Control Stop shall be in conformance with ASTM Alloy Classification for Semi-Red Brass. Valve shall be in compliance to the applicable sections of ASSE 1037, ANSI/ASME 112.19.2. Actuator Types: (please check one) £ FW Fixture Wall Actuator (HY-33-A) (rear access required) £ MP Metal Partition Actuator (HY-49-A) £ SW Side Wall Mounted Actuator (HY-72-A) £ MBFW Metal Button Fixture Wall Actuator (HY-100-A) (rear access required) £ MBPM Metal Button Panel Mount (HY-108-A) See Actuator Specification pages in this section for details on Actuators. Variations £ TP Trap Primer £ YO Two Wall Bumpers (for open front seat without cover) See Accessories Section of the Sloan catalog for details on these and other Flushometer variations. Hydraulic Flushometer can also be provided in Regal® Models. All rough-in dimensions remain the same. Consult the factory. SLOAN VALVE COMPANY • 10500 SEYMOUR AVE. • FRANKLIN PARK, IL. 60131 Ph: 1-800-9-VALVE-9 or 1-847-671-4300 • Fax: 1-800-447-8329 or 1-847-671-4380 http://www.sloanvalve.com Hydraulic Royal® Model Flushometer u u u u This space for Architect/Engineer approval The information contained in this document is subject to change without notice. Royal Hydraulic 952-1.28 S.S. — Rev. X (03/10) Copyright © 2010 SLOAN VALVE COMPANY Printed in the U.S.A. Made in the U.S.A. u 952-1.28
  • 27. Description Concealed hydraulically activated urinal flushometer, for ¾” rear spud high efficiency urinals. Flush Cycle £ Model 995-0.125 (0.125 gpf/0.5 Lp) £ Model 995-0.25 (0.25 gpf/1.0 Lpf) £ Model 995-0.5 (0.5 gpf/1.9 Lpf) Specifications Quiet, Concealed, Diaphragm Type, Rough Brass Urinal Flushometer for either left or right hand supply with the following features: • For Flushing Volumes 0.125 and 0.25: Dual Linear Filtered Bypass Diaphragm • For Flushing Volumes 0.5: Dual Filtered Bypass Diaphragm • ADA Compliant Non-Hold-Open feature type Actuator (specify Actuator type listed below) • ¾” I.P.S. Wheel Handle Bak-Chek® Angle Stop • Adjustable Tailpiece • Vacuum Breaker • Elbow Flush Connection and Spud Coupling for ¾” Concealed Back Spud • Sweat Solder Adapter • High Copper, Low Zinc Brass Castings for Dezincification Resistance • Non-Hold-Open Handle, Fixed Metering Bypass and No External Volume Adjustment to Ensure Water Conservation. • Flush Accuracy Controlled by CID Technology • Diaphragm, Handle Packing, Stop Seat and Vacuum Breaker to be molded from PERMEX® Rubber Compound for Chloramine Resistance. Valve Body, Cover, Tailpiece and Control Stop shall be in conformance with ASTM Alloy Classification for Semi-Red Brass. Valve shall be in compliance to the applicable sections of ASSE 1037 and ANSI/ASME 112.19.6. L Dimension Specify the “L” Dimension for the proper length of the Flush Connection. The “L” Dimension is equal to the Wall Thickness (to the nearest whole inch) plus 2¾”. Actuator Types: (Please Check One) £ FW Fixture Wall Actuator (HY-33-A) (rear access required) £ MP Metal Partition Actuator (HY-49-A) £ SW Side Wall Mounted Actuator (HY-72-A) £ MBFW Metal Button Fixture Wall Actuator (HY-100-A) (rear access required) £ MBPM Metal Button Panel Mount (HY-108-A) See actuator Specification pages in this section for details on Actuators. See Accessories Section of the Sloan catalog for details on these and other flushometer variations. Hydraulic flushometers can also be provided in Regal® and Sloan® models. All rough-in dimensions remain the same. Consult the factory. SLOAN HEADQUARTERS • 10500 SEYMOUR AVENUE • FRANKLIN PARK, IL 60131 Ph: 1-800-9-VALVE-9 • Fax: 1-847-671-4380 • http://www.sloanvalve.com Hydraulic Royal® Model Flushometer This space for Architect/Engineer approval The information contained in this document is subject to change without notice. Royal Hydraulic 995 HEU S.S. — Rev. 0 (03/12) © 2012 SLOAN VALVE COMPANY Made with Renewable Energy Buy America n Act• • C om plian t Buy America n Act• • C om plian t Sloan Valve Company is buying renewable energy certificates to meet 100% of the company’s purchased electricity use at its Franklin Park, Illinois facility.
  • 28. 1275 Shiloh Road Suite 2560 Kennesaw, GA 30144 Preliminary Design Questions/Issues 1. What playground surface and equipment is desired for the Commons Area? What age group should this area be designed for? 2. Do we have as-builts or design drawings for the irrigation system recently installed for Fields 5A 5B? 3. Do we know where the existing septic field and tank is located for the existing concession stand? 4. Will the existing score keepers structure be retained for both Fields 1 2? 5. We have had several discussions with Cobb Stormwater to develop ways to incorporate the scope of the project desired without requiring water quality measures ponds. We are attempting to develop a plan that will not generate an increase in stormwater runoff and thereby not require detention ponds or water quality ponds. Paving scope will be a possible issue with water quality.
  • 29. Sewell Park Project Schedule Notice to Proceed 2-25-13 Begin Field Survey 3-04-13 Project Team Site Visit 3-04-13 Kick-off Meeting 2-25-13 Survey Completed 3-16-13 Schematic/Preliminary Design 4-19-13 Formal Presentation to County 4-26-13 Design Development Submittal 5-17-13 90% CD Submittal 6-26-13 100% CD Submittal 7-17-13 Submit for LDP 7-24-13 LDP Permit 9-02-13 Submit for Building Permit 9-02-13 Submit to Purchasing-Bid Set 9-18-13 Building Permit 9-30-13 Issue for Bid 9-27-13 Pre-Bid Meeting 10-08-13 Bid Date 10-24-13 BOC Award 11-12-13 Construction Begins 1-02-14 Sod Installed 5-08-14 Construction Completion 8-01-14
  • 30. Permits Required Land Disturbance Permit- Cobb County Marietta Water Sewer Marietta Power Approvals Building Permit-Cobb County NPDES Permit
  • 31. Units Qty Unit Rate Sub Total Total 244,231.00$            ‐$                         LS 1 30,000.00$       30,000.00$             LS 1 123,000.00$    123,000.00$           LS 1 35,000.00$       35,000.00$             LS 1 19,000.00$       19,000.00$             LS 1 36,000.00$       36,000.00$             243,000.00$          SF 25600 0.25$                6,400.00$               CY 75 15.00$              1,125.00$               LF 686 5.00$                3,430.00$               SF 400 2.00$                800.00$                  LS 2 3,000.00$         6,000.00$               CY 200 12.00$              2,400.00$               CY 500 15.00$              7,500.00$               SF 30000 0.10$                3,000.00$               SF 30000 0.10$                3,000.00$               SF 30000 0.10$                3,000.00$               Re‐Development of Sewell Park Cobb County Parks, Recreation,  Cultural Affairs Preliminary Cost Estimate ‐ 4‐19‐13 Laser Grading Filling Laser Grading before sod Project Budget for Redevelopment of Fields #1, #2, #3, #4,  Common  Area Between Field 3 and 5A  5B Preliminary Cost Estimate‐ Baseball Concession/RR Bldg Strip  Haul off sod Demolition of existing building New Concession Building Electrical HVAC Plumbing Field #1 Hazardous Material Abatement ( Total Preliminary Estimated Cost Concession/RR Bldg  $          977,500.00  Item ‐ Description Project Budget for Baseball Concession/Restroom Building Demolition‐Field 1 Remove existing infield mix Remove existing fencing  posts Remove existing concrete Remove existing dugouts Grading Field 1 Import fill Import topsoil Laser Grading Subgrade
  • 32. Sewell Park Preliminary Cost Estimate 2 Units Qty Unit Rate Sub Total Total TN 120 110.00$            13,200.00$             TN 35 85.00$              2,975.00$               TN 300 30.00$              9,000.00$               ‐$                         ‐$                         ‐$                         ‐$                         EA 1 1,750.00$         1,750.00$               LF 700 4.00$                2,800.00$               EA 1 400.00$            400.00$                  SF 10000 0.25$                2,500.00$               ‐$                         SF 26500 0.50$                13,250.00$             EA 1 1,250.00$         1,250.00$               EA 1 400.00$            400.00$                  EA 8 300.00$            2,400.00$               EA 2 200.00$            400.00$                  EA 28 75.00$              2,100.00$               EA 1 3,000.00$         3,000.00$               LF 400 15.00$              6,000.00$               LF 400 12.00$              4,800.00$               LF 200 10.00$              2,000.00$               LF 200 10.00$              2,000.00$               ‐$                         ‐$                         EA 1 3,000.00$         3,000.00$               ‐$                         ‐$                         2 Irrigation Meter 2 PVC 1.5 PVC 1.25 PVC 1 PVC Main Shut Off Valve Scrubber Valves Quick Coupling Valve Falcon 6504  Controller Grassing Landscaping  Irrigation Field 1 Sod Backflow Preventer Erosion Field 1 Temoporary construction entrance Silt Fence Inlet Protection Sand Existing Septic Field Removal Infield Mix Warning Track Mix Item ‐ Description
  • 33. Sewell Park Preliminary Cost Estimate 3 Units Qty Unit Rate Sub Total Total SF 650 5.00$                3,250.00$               LF 500 15.00$              7,500.00$               LF 135 25.00$              3,375.00$               LF 60 75.00$              4,500.00$               LF ‐$                         EA 1 1,750.00$         1,750.00$               EA 4 300.00$            1,200.00$               LF 300 3.00$                900.00$                  LS 1 1,000.00$         1,000.00$               ‐$                         EA 2 1,250.00$         2,500.00$               LF 300 2.00$                600.00$                  ‐$                         EA 2 250.00$            500.00$                  EA 3 150.00$            450.00$                  LS 2 15,000.00$       30,000.00$             ‐$                         LS 1 70,000.00$       70,000.00$             EA 1 2,000.00$         2,000.00$               EA 1 2,000.00$         2,000.00$               SY 365 25.00$              9,125.00$               SF 180 50.00$              9,000.00$               ‐$                         LF 50 35.00$              1,750.00$               LF 40.00$              ‐$                         LF 250 35.00$              8,750.00$               LS 1 15,000.00$       15,000.00$             285,030.00$          Storm drainage Fence Windscreen Heavy Duty Rubber Backstop Netting Outfield Distance Markers Dugouts 4 FT Gate Yellow Fence Capping Homeplate  Bases Pitching Mound Foul Poles 6 FT Chain Link Fencing Underground Power Service to Fields 1  2 to replace overhead Total Preliminary Estimated Costs ‐ Field #1 Concrete Retaining Wall Utilities Field 1 Water Sanitary Sewer Scoreboards New Wiring for Light Poles New wiring for Pitching Machines Power to Pitching Mound Asphalt Drive 10 FT Chain Link Fencing 20 FT Chain Link Fencing 24 FT Chain Link Fencing 12 FT Gate Item ‐ Description Site Improvements Field 1 Concrete Pad
  • 34. Sewell Park Preliminary Cost Estimate 4 Units Qty Unit Rate Sub Total Total SF 15500 0.25$                3,875.00$               CY 100 15.00$              1,500.00$               LF 498 5.00$                2,490.00$               EA 2 3,000.00$         6,000.00$               ‐$                         CY 500 15.00$              7,500.00$               SF 20000 0.10$                2,000.00$               SF 20000 0.20$                4,000.00$               TN 120 110.00$            13,200.00$             TN 20 85.00$              1,700.00$               TN 150 30.00$              4,500.00$               EA 1 1,750.00$         1,750.00$               LF 600 4.00$                2,400.00$               ‐$                         SF 10000 0.25$                2,500.00$               SF 16000 0.50$                8,000.00$               EA 1 800.00$            800.00$                  EA 1 400.00$            400.00$                  EA 6 300.00$            1,800.00$               EA 2 200.00$            400.00$                  EA 20 75.00$              1,500.00$               EA 1 1,200.00$         1,200.00$               LF 400 10.00$              4,000.00$               LF 300 10.00$              3,000.00$               LF 150 10.00$              1,500.00$               LF 150 10.00$              1,500.00$               ‐$                         1.25 PVC 1 PVC Quick Coupling Valve Falcon 6504  Controller 2 PVC 1.5 PVC Landscaping  Irrigation Field 2 Sod Backflow Preventer Main Shut Off Valve Scrubber Valves Erosion Field 2 Temoporary construction entrance Silt Fence Inlet Protection Grassing Laser Grading Subgrade Laser Grading Filling  before sod Infield Mix Warning Track Mix Sand Remove existing fencing  posts Demo and remove existing dugout Grading Field 2 Import fill Import topsoil Item ‐ Description Field #2 Demolition Field 2 Strip  Haul off sod Remove existing infield mix
  • 35. Sewell Park Preliminary Cost Estimate 5 Units Qty Unit Rate Sub Total Total SF 650 5.00$                3,250.00$               LF 435 15.00$              6,525.00$               LF 120 25.00$              3,000.00$               LF 65 75.00$              4,875.00$               LF ‐$                         EA 1 1,750.00$         1,750.00$               EA 4 300.00$            1,200.00$               LF 250 3.00$                750.00$                  EA 1 1,000.00$         1,000.00$               ‐$                         EA 2 1,250.00$         2,500.00$               LF 250 2.00$                500.00$                  ‐$                         EA 2 250.00$            500.00$                  EA 3 150.00$            450.00$                  EA 2 15,000.00$       30,000.00$             ‐$                         LS 1 70,000.00$       70,000.00$             LS 1 2,000.00$         2,000.00$               ‐$                         ‐$                         ‐$                         LF 350 50.00$              17,500.00$             ‐$                         223,315.00$         Total Preliminary Estimated Costs ‐ Field #2 Water Sanitary Sewer Storm drainage Scoreboards New Wiring for Light Poles New wiring for Pitching Machines Utilities Field 2 Fence Windscreen Heavy Duty Rubber Backstop Netting Outfield Distance Markers Dugouts 4 FT Gate Yellow Fence Capping Homeplate  Bases Pitching Mound Foul Poles 6 FT Chain Link Fencing 10 FT Chain Link Fencing 20 FT Chain Link Fencing 24 FT Chain Link Fencing 12 FT Gate Item ‐ Description Site Improvements Field 2 Concrete Sidewalks
  • 36. Sewell Park Preliminary Cost Estimate 6 Units Qty Unit Rate Sub Total Total ‐$                         ‐$                         ‐$                         LS 2 6,000.00$         12,000.00$             ‐$                         ‐$                         ‐$                         ‐$                         LS 2 25,000.00$       50,000.00$             ‐$                         ‐$                         ‐$                         ‐$                         62,000.00$             ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         Total Preliminary Estimated Costs ‐ Field #3 New Dugout Field #3 Demolition Field 3 Demolition of existing Dugout Item ‐ Description
  • 37. Sewell Park Preliminary Cost Estimate 7 Units Qty Unit Rate Sub Total Total ‐$                         SF 55600 0.25$                13,900.00$             CY 300 15.00$              4,500.00$               LF 1000 5.00$                5,000.00$               SF 600 2.00$                1,200.00$               EA 6 1,600.00$         9,600.00$               EA 2 3,000.00$         6,000.00$               EA 6 400.00$            2,400.00$               CY 2000 12.00$              24,000.00$             CY 900 15.00$              13,500.00$             EA 1 5,000.00$         5,000.00$               EA 1 6,000.00$         6,000.00$               TN 300 110.00$            33,000.00$             LS 1 5,000.00$         5,000.00$               TN 80 85.00$              6,800.00$               TN 600 30.00$              18,000.00$             ‐$                         EA 1 3,000.00$         3,000.00$               SF 1500 4.00$                6,000.00$               EA 3 400.00$            1,200.00$               SF 43000 0.25$                10,750.00$             ‐$                         LF ‐$                         LF ‐$                         LF 600 50.00$              30,000.00$             Utilities Field 4 Water Sanitary Sewer Storm drainage Erosion Field 4 Temoporary construction entrance Silt Fence Inlet Protection Grassing Laser Grading Filling  before sod Infield Mix Clear  Grub Warning Track Mix Sand Selective Tree Removal Grading Field 4 Earthwork Import topsoil Laser Grading Subgrade Remove existing infield mix Remove existing fencing  posts Remove existing concrete Remove and dispose of existing light poles Demo and remove existing dugout Item ‐ Description Field #4 Demolition Field 4 Strip  Haul off sod
  • 38. Sewell Park Preliminary Cost Estimate 8 Units Qty Unit Rate Sub Total Total Landscaping  Irrigation Field 4 Sod SF 58000 0.50$                29,000.00$             Backflow Preventer EA 1 1,200.00$         1,200.00$               Main Shut Off Valve EA 1 400.00$            400.00$                  Scrubber Valves EA 14 300.00$            4,200.00$               Quick Coupling Valve EA 4 200.00$            800.00$                  Falcon 6504  EA 40 75.00$              3,000.00$               Controller EA 1 3,000.00$         3,000.00$               2 PVC EA 800 10.00$              8,000.00$               1.5 PVC LF 600 10.00$              6,000.00$               1.25 PVC LF 300 10.00$              3,000.00$               1 PVC LF 300 10.00$              3,000.00$               ‐$                         ‐$                         Irrigation Meter EA 1 3,000.00$         3,000.00$               ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         Item ‐ Description
  • 39. Sewell Park Preliminary Cost Estimate 9 Units Qty Unit Rate Sub Total Total SF 650 5.00$                3,250.00$               LF 580 15.00$              8,700.00$               LF 120 25.00$              3,000.00$               LF 180 75.00$              13,500.00$             LF 120 125.00$            15,000.00$             EA 2 1,750.00$         3,500.00$               EA 4 300.00$            1,200.00$               LF 275 3.00$                825.00$                  EA 1 1,000.00$         1,000.00$               ‐$                         EA 2 1,250.00$         2,500.00$               SF 120 2.00$                240.00$                  ‐$                         EA 3 250.00$            750.00$                  EA 3 250.00$            750.00$                  EA 2 15,000.00$       30,000.00$             ‐$                         ‐$                         LS 1 25,000.00$       25,000.00$             EA 6 20,000.00$       120,000.00$           LS 1 2,000.00$         2,000.00$               ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         500,665.00$          Item ‐ Description Site Improvements Field 4 Concrete Sidewalks 6 FT Chain Link Fencing 10 FT Chain Link Fencing 20 FT Chain Link Fencing 30 FT Chain Link Fencing 12 FT Gate 4 FT Gate Yellow Fence Capping Homeplate  Bases Pitching Mound Foul Poles Fence Windscreen Heavy Duty Rubber Backstop Netting Outfield Distance Markers Dugouts Scoreboards Lighting Distribution Modifications Allowance New Light Pole Fixtures ( Assuming Musco direct burial pole) Power to Pitching Mound Total Preliminary Estimated Costs ‐ Field #4
  • 40. Sewell Park Preliminary Cost Estimate 10 Units Qty Unit Rate Sub Total Total ‐$                         ‐$                         ‐$                         EA 10 450.00$            4,500.00$               EA 9 190.00$            1,710.00$               EA 9 175.00$            1,575.00$               EA 25 45.00$              1,125.00$               EA 25 25.00$              625.00$                  EA 25 15.00$              375.00$                  EA 21 16.00$              336.00$                  ‐$                         TN 50 50.00$              2,500.00$               TN 2 225.00$            450.00$                  SF 1000 10.00$              10,000.00$             ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         23,196.00$             Item ‐ Description Common Area Between Field #3  #5A/5B Large Trees Evergreen Tree Small Flowering Trees Large Shrubs Small Shrubs Ground Cover Oerebbuaks.Native Grasses Slate Dust Boulders Play Surface Total Preliminary Estimated Costs‐ Common Area
  • 41. Sewell Park Preliminary Cost Estimate 11 Units Qty Unit Rate Sub Total Total ‐$                         244,231.00$            SY 1200 16.00$              19,200.00$             SY 1200 8.00$                9,600.00$               ‐$                         ‐$                         ‐$                         LF 420 10.00$              4,200.00$               LS 1 2,500.00$         2,500.00$               ‐$                         ‐$                         LS 1 8,000.00$         8,000.00$               ‐$                         ‐$                         SY 8000 24.00$              192,000.00$           ‐$                         ‐$                         ‐$                         235,500.00$          ‐$                         1 20,000.00$       20,000.00$             1 4,000.00$         4,000.00$               ‐$                         ‐$                         ‐$                         ‐$                         ‐$                         24,000.00$             Item ‐ Description Project Budget for Paving Site Paving Soil Cement Stabilization 2 Asphalt Topping  Storm Sewer Curb  Gutter Traffic Striping Removal and Disposal of gravel Landscaping Additional Available for Site Paving (8,000 sy‐ 72,000 sf) Total Preliminary Estimated Costs ‐ Site Paving Alternates Storage Shed Electrical for Shed Total Preliminary Estimated Costs‐ Storage Shed
  • 42. Sewell Park Preliminary Cost Estimate 12 EST. COST DIFERENCE 244,231.00$          243,000.00$          1,231.00$                285,030.00$    223,315.00$    62,000.00$      500,665.00$    23,196.00$      1,094,206.00$       (116,706.00)$          244,231.00$          43,500.00$      192,000.00$    235,500.00$          8,731.00$                24,000.00$             977,500.00$          SUMMARY Project Budget for Baseball Concession/Restroom Building Total Preliminary Estimated Cost Concession/RR Bldg Variance Field #1 Field #2 Field #3 Project Budget for Redevelopment of Fields #1, #2, #3, #4,  Common  Area Between Field 3 and 5A  5B Field #4 Commons Area Total Preliminary Estimated Costs (Fields and Common Area) Variance Project Budget for Site Paving Paving for Existing Gravel and Additional Parking Spaces Additional 72,000 sf of Paving Resurfacing Total Preliminary Estimated Costs for Site Paving Variance Storage Shed Alternate Total Preliminary Estimated Cost for Storage Shed