SlideShare a Scribd company logo
1 of 46
Download to read offline
SIPA Capstone Team
James Doone, William Hernandez, Harsh Vijay Singh, Varun Soni & Vivian Xu
M a y 1 3 , 2 0 1 5
Wind in a Post-PTC Market
2
Table of Contents
Acknowledgements............................................................................................................................3
1.0 Introduction ..................................................................................................................................4
2.0 Executive Summary ....................................................................................................................6
2.1 Objective of the Project ........................................................................................................................6
2.2 Planning for Variability........................................................................................................................6
2.3 Exogenous Factors .................................................................................................................................7
2.4 Avoided Costs...........................................................................................................................................8
2.5 Recommendations..................................................................................................................................9
3.0 Background ................................................................................................................................ 12
3.1 Overview of utility...............................................................................................................................12
4.0 Planning for Variability.......................................................................................................... 14
4.1 Existing Assets ......................................................................................................................................14
4.2 Wind Scheduling ..................................................................................................................................15
4.3 Reserve Margin & Capacity Value.................................................................................................16
4.4 Pricing.......................................................................................................................................................18
5.0 Exogenous Factors ................................................................................................................... 20
5.1 Underdeveloped Transmission Infrastructure .......................................................................20
5.2 Regulation...............................................................................................................................................22
6.0 Avoided Cost............................................................................................................................... 25
6.1 Regulations on Avoided Costs........................................................................................................29
7.0 Recommendations ................................................................................................................... 35
7.1 Address asymmetry in fuel price risk allocation....................................................................35
7.2 Standardized Avoided Cost Methodologies..............................................................................35
7.3 Resource Specific Avoided Costs...................................................................................................36
7.4 Forward Capacity Markets...............................................................................................................37
7.5 Security Constraint Economic Dispatch.....................................................................................38
7.6 Increased Geographic Network .....................................................................................................39
7.7 Externalities...........................................................................................................................................41
APPENDIX........................................................................................................................................... 43
Bibliography............................................................................................................................ 44
3
Acknowledgements
The SIPA capstone team would like to express our deep gratitude to the following
subject matter experts, who provided insight and expertise that greatly assisted in
the research presented in this document.
John Olsen, Executive Director, Power Marketing, Westar Energy
Jay Caspary, Director R&D and Special Studies, OG&E
Cody VandeVelde, Supervisor, Market Resource Planning, Westar Energy
Richard Cornelis, Project Manager and Economic Development, OG&E
Dana Murphy, Commissioner, Oklahoma Corporation Commission
David Springe,	
  Consumer	
  Counsel,	
  Kansas	
  Citizens’	
  Utility	
  Ratepayer	
  Board
Dale Osborn, Transmissions Planning Technical Director, Midwest ISO
Paul Suskie, Executive Vice President and General Counsel, Southwest Power Pool
Kevin Porter, Principal, Exeter Associates
Charles Smith, Executive Director, Utility Variable-Generation Integration Group
Mark Alhstrom, CEO, WindLogics
Jacob Sussman, CEO, OWN Energy
A.J. Goulding, Professor, Columbia University and Principal, LEI
Alfred Griffin, Professor, Columbia University and President, NY Green Bank
Daniel Gross, Professor, Columbia University and MD, Oaktree Capital Management
Jeanne Fox, Professor, Columbia University and Ex-Commissioner, NJ Board of Public
Utilities
4
1.0 Introduction
In the US, wind energy has grown rapidly in recent years. At the end of 2014,
installed capacity reached 65,879 megawatts, a 145% increase since 2008.1 Much of
this growth has been fueled by incentives provided at both the state and federal
levels, which allow wind generation to compete with traditional generation
technologies. In particular, the Production Tax Credit (PTC) offered a strong incentive
by providing an inflation-adjusted per kilowatt-hour tax credit of $0.023 to wind
generators for the first 10 years of generation. However, conditional expiration of the
PTC began at the end of 2014.
As a leading manufacturer of wind turbines, our client, GE Power & Water,
would like to gain a better understanding of how utilities will evaluate wind
generation in a post-PTC market. As such, GE has asked our capstone team to:
1. Identify and analyze the factors utilities consider when evaluating wind
generation against other generation assets;
2. Analyze the alternative methodologies currently being used by utilities to
evaluate generation assets and determine the extent to which they might be
indefensible.
3. Identify and outline opportunities for GE to overcome barriers for wind
generation amongst target utilities.
The scope of this project was limited to investigating two vertically-integrated
utilities operating in the regulated Southwest Power Pool Regional Transmission
Organization – Oklahoma Gas & Electric (OG&E) and Westar Energy of Kansas. In
order to achieve the objectives of this project, the capstone team conducted research
on	
  each	
  utility’s	
  regulatory	
  environment	
  and	
  electric	
  supply	
  and	
  demand	
  portfolios.	
  
In addition, the team also researched various avoided cost methodologies that are
commonly used by utilities. Based on this knowledge, the team conducted a series of
1 (American Wind Energy Association, 2015)
5
interviews with relevant stakeholders in order to gain a deeper understanding of the
decision making criteria and avoided cost methodologies being used by OG&E and
Westar Energy. This included speaking with officials at both utilities as well as various
subject matter experts from the power sector.2 After synthesizing and analyzing the
information gathered from the desk research and interviews, the team came up with
recommendations that will help GE overcome barriers to wind deployment in a post-
PTC marketplace.
In general, the capstone team focused on the following key areas:
1. Variability:
A. Existing assets
B. Wind scheduling
C. Capacity margin vs. reserve margin
D. Pricing
2. Exogenous factors
A. Transmission
B. Regulation
3. Avoided cost methodologies
In this report, Section 4 and 5 describe the factors that utilities consider when
evaluating wind against other generating assets, whereas Section 6 covers
information gathered on avoided cost methodologies. Section 7 consists of
recommendations that might help GE overcome barriers that prevent utilities from
deploying wind assets in a post-PTC market.
2 A complete list of interviewees can be found in the Acknowledgements section
6
2.0 Executive Summary
2.1 Objective of the Project
In the US, wind energy has grown rapidly in recent years. At the end of 2014,
installed capacity reached 61,327 megawatts, a 145% increase since 2008. Much of
this growth has been fueled by incentives provided at both the state and federal
levels, which allow wind generation to compete with traditional generation
technologies. In particular, the Production Tax Credit (PTC) offered a strong incentive
by providing an inflation-adjusted per kilowatt-hour tax credit of $0.023 to wind
generators for the first 10 years of generation. However, conditional expiration of the
PTC began at the end of 2014.
1. Identify and analyze the factors utilities consider when evaluating wind
generation against other generation assets;
2. Analyze the alternative methodologies currently being used by utilities to
evaluate generation assets and determine the extent to which they might be
indefensible.
3. Identify and outline opportunities for GE to overcome barriers for wind
generation amongst target utilities.
2.2 Planning for Variability
Research and interviews conducted with stakeholders at both Westar Energy
and OG&E revealed that utilities regard variability and intermittency to be the most
significant vulnerabilities to wind generation. The subsequent issues that utilities
consider when evaluating wind against other generating technologies are as follows:
1. Existing Assets: Since wind is variable resource, other generating assets often
have to be dispatched in order to fill the gap between supply and load. When
planning for wind integration, utilities have to consider the dispatchability or
flexibility of existing assets, and decide whether or not to increase their
portfolio of traditional generation, so as to address the issues of wind
7
variability and intermittency. In the absence of forward capacity markets at
SPP, utilities do not have sufficient incentives to add new generation assets to
maintain appropriate reserve capacity in order to mitigate the variability
component of wind farms.
2. Wind Scheduling: Through discussions with utilities, it was revealed that
strong winds can pose a critical threat to reliability due to high wind cut out.
However, further discussions with subject matter experts suggest that high
wind cut out is not a significant barrier due to advances in wind forecasting,
technological improvements, greater	
   balancing	
   areas,	
   and	
   SPP’s	
   Integrated	
  
Marketplace.
3. Reserve Margin and Capacity Value: Utilities are required to to maintain the
reserve margin standard assigned by SPP, to demonstrate resource adequacy.
Since wind is variable, it is accredited a small percentage of nameplate
capacity	
  under	
  SPP’s	
  methodology.	
  	
  The	
  low	
  capacity	
  value	
  of	
  wind	
  and	
  its	
  
limited	
  contribution	
  to	
  reserve	
  margin	
  reduce	
  utilities’	
  incentive	
  to	
  add	
  wind.
4. Pricing: From	
   a	
   utility’s	
   perspective,	
   limitations	
   associated	
   with	
   wind	
  
predictability in the short-term put wind at a disadvantage when compared to
more conventional assets. In particular this aspect of wind limits the ability of
a utility to offer power in day-ahead markets. This exposes utilities to greater
price risk.
2.3 Exogenous Factors
In addition to considering factors related to variability and vulnerability, utilities
also consider various other criteria when evaluating wind against other generating
technologies. These criteria include:
1. Transmission constraints: Underdeveloped transmission infrastructure has
been cited as a major deterrent of wind growth in the Plains region. However,
8
with SPPs creation of the Integrated Marketplace and the Highway Byway cost
sharing methodology, utilities are more incentivized to rate-base these
transmission projects and earn a return on their investments. Greater
transmission infrastructure will help to reduce barriers to wind generation.
Through interviews with stakeholders from SPP, we discovered that the
component of transmission cost in the rate base is applied on an average basis
to	
  customers	
  across	
  SPP’s	
  balancing	
  area,	
  irrespective	
  of	
  the	
  location	
  of	
  the	
  
source and the load.
2. Regulation: Conversations with officials at both utilities and other subject
matter experts in the power sector suggest that regulation has been a primary
driver for the deployment of wind resources in the SPP. Specifically, the three
programs that have had the greatest impact are the Renewable Portfolio
Standard (RPS), PTC and Clean Power Plan (CPP). However, from the utilities
perspective an uncertain regulatory environment introduces the risk of
stranded assets.
2.4 Avoided Costs
Utilities assess the value of electricity and capacity offered by independent
power producers on the basis of avoided costs. A	
  utility’s assessment of avoided cost
borrows from its Integrated Resource Plan (IRP). Among the factors that influence
avoided costs, utilities account for projections of resource sufficiency and deficiency,
fuel price projections, load growth and load shape forecasts, costs of compliance to
current and expected future compliance standards, etc. Avoided costs for small power
producers, those with less than 100 kW of capacity 3 , are defined by standard
purchase contracts, which are vetted by state regulatory commissions. However, for
qualifying facilities (QFs) that are not eligible for standard purchase agreements, the
avoided costs assessment depends upon the assumptions made by the utility for its
3 Eligibility criteria varies by state
9
IRP. Consequently, there are a variety of methods used to estimate avoided costs,
none more or less defensible than the others. On a general note, some of the common
variables that feed into avoided costs are avoided costs of energy, capacity,
transmission and distribution, line losses and environmental compliance, etc.
2.5 Recommendations
From	
  a	
  utility’s	
  perspective,	
  greater	
  wind	
  adoption	
  faces several barriers in a
post-PTC market. Foremost among them are issues related to variability, uncertain
regulation and limitations in transmission infrastructure. Although new
developments in the SPP alleviate some of these issues for OG&E and Westar Energy,
other issues will persist. The following recommendations are put forward to help GE
address these issues, and are based on information gleaned from desk research and
stakeholder interviews.
Address asymmetry in allocation of fuel price risk: Unlike traditional generating
assets, such as coal and gas plants, wind generation has negligible fuel price risk.
However, the Fuel Adjustment Clause (FAC) in both Oklahoma and Kansas leads to
market distortions that cause utilities to overlook this critical aspect of wind
generation. In order to provide a level playing field for wind generation, it would be
prudent for GE to help address distortions created by the FAC. Since the FAC allocates
fuel price risk to ratepayers, one way for GE to address this issue is through
consumer-motivated regulation.
Standardize Avoided Cost Methods: The avoided cost methodologies approved across
different states are consistent with their respective policy objectives. However, there
is a considerable lack of transparency with regards to these methodologies. This
creates uncertainty for QF investors and limits their ability to make investments in
the long term. As such, GE would benefit if FERC were to commission an evaluation of
avoided costs methods used across different states, assessing their strengths and
weaknesses from the perspective of small power producers.
10
Resource Specific Avoided Costs: A recent order by FERC on a petition filed by the
California Public Utilities Commission permitted multi-tiered avoided cost
calculations within a jurisdiction. Depending on the characteristics of the specific
resource, such as dispatchability, intermittency, efficiency, environmental
performance and location etc., the avoided cost of a QF should be calculated by
comparison with an operating QF with similar characteristics. Such a comparison will
determine the full extent of avoided costs. It would help equipment manufacturers
like GE, as well as wind energy developers alike to engage in discussion with state
regulatory commissions and advocate for resource specific avoided cost assessment.
Forward Capacity Markets: SPP requires a reserve capacity margin of approximately
12 percent. However, the reserve capacity margin does not offer enough incentive to
incumbent utilities to add additional conventional generation capacity beyond the
reserve margin, to compensate for the intermittency induced by variable generation
assets. A forward capacity market, on the lines of PJM, will offer the utilities a regular
stream of revenue from capacity, and improve the system's overall reliability. With
this in mind, we believe stakeholders from conventional utilities, equipment
manufacturers, wind generators, consumer forums and SPP should explore the
possibility of implementing a forward capacity market.
Security Constrained Economic Dispatch: This is a process that takes cost and liability
when optimizing a system every 5 minutes to match load. This process takes into
account the whole power system with all its different types of generators and
characteristics (failure modes, lack of certainty, etc.). So, When Dispatch nullifies the
problems associated with cut out and other associated problems caused by
variability. Therefore, we believe GE can reduce the barriers associated with
variability by informing utilities that these problems can be nullified by using the
tools already in place—primarily the Security Constrained Economic Dispatch.
Integrated Marketplace: The expansion of the Integrated Marketplace through the
growth of the SPP will reduce the variability of wind and the congestion-related
11
issues surrounding geographic areas highly concentrated with wind farms. The
inclusion of more stakeholders, as participants in this marketplace, will further the
development of high-voltage transmissions lines paid for through the
Highway/Byway shared-cost methodology. This would reduce integration costs and
promote further development of wind farms.
Externalities: While	
  there	
  isn’t	
  a	
  carbon	
  pricing	
  system	
  in	
  the	
  SPP, it is expected that
tighter regulation on carbon emission will eventually lead to a price on externalities
caused by greenhouse gas (GHG) emission. Since the generating assets that utilities
invest in today will endure for a several years into the future, it is important to ensure
that the generating portfolio can meet a future tighter standard on carbon emission.
Thus,	
  GE	
  could	
  engage	
  in	
  raising	
  utilities’	
  awareness	
  of the possibility of future carbon
pricing, and suggest utilities to factor in a carbon price in economic analysis.
12
3.0 Background
3.1 Overview of utility
3.1.1 Oklahoma Gas and Electric
OG&E was incorporated in 1902 in Oklahoma, and currently operates as a
regulated investor-owned public utility holding company. As an energy services
provider it offers physical delivery and related services for both electricity and
natural gas, primarily in the south-central United States. The company conducts these
activities through two business segments: (i) an electric utility and (ii) natural gas
midstream operations. The electric utility segment generates, transmits, distributes
and sells electric energy in Oklahoma and western Arkansas. The service area covers
30,000 square miles in Oklahoma and western Arkansas, including Oklahoma City,
the largest city in Oklahoma, and Fort Smith, Arkansas.4
OG&E’s	
  stated	
  mission	
  is	
  “to fulfill its critical role in the nation's electric utility
and natural gas midstream pipeline infrastructure and meet individual customers'
needs for energy and related services focusing on safety, efficiency, reliability,
customer service and risk management.”5 OG&E is focused on increased investment
to preserve system reliability and to meet load growth by adding and maintaining
infrastructure equipment and replacing aging transmission and distribution systems.
OG&E expects to maintain a diverse generation portfolio while remaining
environmentally responsible. Through its various initiatives, OG&E believes it may be
able to defer the construction or acquisition of any incremental fossil fuel generation
capacity until 2020. 6
4 (OG&E, 2014)
5 (OG&E, 2014)
6 (OG&E, 2014)
13
3.1.2 Westar Energy
A Kansas corporation incorporated in 1924, Westar Energy, Inc. (Westar) is a
vertically-integrated investor-owned utility operating in south-central and northeast
Kansas. Within these two geographic areas of Kansas, Westar Energy operates as two
separate companies – Kansas Gas and Electric (Westar South) and Westar Energy
(Westar North). As the largest electric utility in Kansas, Westar provides electric
generation, transmission and distribution services to approximately 693,000
customers in Kansas.7 Although technically comprised of two separate companies,
Westar’s	
  entire	
  system	
  is	
  dispatched	
  as	
  one	
  system	
  unit, and therefore there has been
a movement to consolidate electric rates with the ultimate goal of uniform rates
across the two entities.8
Significant	
   elements	
   of	
   Westar’s	
   corporate	
   strategy	
   involves	
   maintaining	
   a	
  
flexible and diverse energy supply portfolio. In doing so, Westar has made
environmental upgrades to their coal-fired power plants, developed renewable
generation, built and upgraded their electrical infrastructure, and developed systems
and programs with regard to how their customers use energy.9
7 (Westar Energy, 2014)
8 (Kansas Corporation Commission, 2015)
9 (Westar Energy, 2013)
14
4.0 Planning for Variability
While utilities consider various factors when evaluating wind against other
generation technologies, research and interviews conducted with stakeholders at
both Westar and OG&E revealed that utilities regard variability and intermittency to
be the most significant vulnerabilities to wind generation. As such, variability is a key
aspect that utilities factor into their decision making process, when comparing wind
to traditional generation assets. This section describes the subsequent issues that
utilities face due to these vulnerabilities.
4.1 Existing Assets
The extent to which utilities can add new wind assets is in part determined by
the dispatchability of their existing generation portfolio. Since wind is a variable
resource, other generating assets often have to be dispatched in order to fill the gaps
between supply and load. This issue becomes more acute in times of light load. During
periods of light load, an increase in wind generation can quickly lead to a surplus of
power in the market. In such situations utilities are forced to curtail generation from
other assets, as wind	
  generation’s low variable cost allows it to be dispatched before
other baseload assets in the bid stack. Those utilities with a portfolio of assets with a
low dispatchability find it more difficult to integrate wind. Broadly speaking, utilities
that have a greater percentage of gas generation are better off, since gas turbines are
highly dispatchable, or flexible to changing load conditions. Conversely, those utilities
with predominantly nuclear or coal assets find it more difficult to integrate wind as
these assets are less flexible.
When planning for wind integration, utilities have to consider whether or not
to also increase their portfolio of traditional generation, so as to address the issues of
wind variability and intermittency. For instance, the resource planning department
of Westar mentioned that it had to invest in 600MW of gas turbines to offset an
anticipated increase in wind generation. Of the 600MW, 150MW consisted of aero-
derivative turbines, which have very high dispatchability. These variable backup
15
generators amount to additional costs for the utility. Thus, wind variability and
intermittency	
  with	
  regards	
  to	
  the	
  existing	
  portfolio	
  of	
  a	
  utility’s	
  generating	
  assets	
  can	
  
present a barrier to adding wind generation.
4.2 Wind Scheduling
Variability is not just a problem when wind speeds drop to low levels. In a
discussion with a former director of resource planning at one utility, he described a
situation where strong winds, not light or even no wind scenarios, pose the biggest
threat to operators. He informed us that at 8 mph, wind turbines begin to produce
power; at 20 mph, they achieve maximum output; but between 40 and 55 mph
turbines hit their cut out point. For an operator, this scenario threatens the reliability
of a utility to meet demand. If a wind farm is running at full output and then shuts off
due to high wind, the utility will have to immediately make up for the shortfall. From
the point of view of a director of resource planning, strong winds can pose a critical
threat to a	
  utility’s	
  reliability.
However, other subject matter experts undermined the threat of high wind cut
out. It was pointed out that high wind cut out is only associated with high intensity
storms that result from wind speeds in excess of 55 mph. In most cases, utilities can
predict storms of this magnitude well in advance, allowing them adequate time to
prepare their supply needs. Furthermore, high wind cut out typically impacts only a
small fraction of wind turbines in a wind generation facility, and as soon as the wind
dies down, the turbines start generating again. With current technology and
modeling, wind scheduling is capable of significantly lowering the risk that a cut out
scenario poses to an operator. By utilizing wind-scheduling technology, operators
can plan for a cut out scenario, in some cases up to 48 hours before a weather system
hits its region. Finally, new turbine technology, which can mitigate the risk posed by
high winds, and the creation of the Integrated Marketplace in SPP, raises further
questions as to whether high wind cut out is a serious issue for utilities.
16
4.3 Reserve Margin & Capacity Value
In order to ensure grid reliability, utilities have to demonstrate that they have
enough installed capacity to meet peak load requirements. SPP ensures resource
capacity by mandating that each utility in its jurisdiction maintain a reserve margin
of at least 13.6%. As such, utilities need to accredit the capacity value of all their
generating assets, making sure that they adhere to this standard in their resource
planning.
Due to the variability of wind, the capacity value that is assigned to wind
generators is a smaller fraction of nameplate capacity than that associated with other
generation technologies. From the point of view of a utility, the low capacity value of
wind imposes a barrier to developing wind generation, because wind only makes a
limited contribution to reserve margin, compared with traditional generating assets.
Thus, when considering alternative generation technologies with regards to meeting
capacity requirements, utilities are more likely to choose technologies that have a
higher accreditation value.
The variability associated with wind also results in greater subjectivity in the
accreditation process. As such, each region may choose to adopt its own methodology
and assumptions when accrediting wind farms, giving wind varying degrees of
capacity value. Proponents of wind have longstanding concerns that the SPP deters
wind development by assigning a particularly low value to wind. Based on 2011 EIA
estimate of wind profiles, within NERC regions, the wind capacity value in SPP was
8.2%. Only the Midwest ISO MRO had a lower value of 8%.10
One reason that SPP assigns a low capacity value to wind is that wind speed is
negatively correlated with load in this region.11 However, in cases where output from
wind generators closely correlates with load, wind generation assets might be
10 (EIA, 2011)
11 (Southwest Power Pool Generation Working Group , 2004)
17
assigned a higher capacity credit. 12 Furthermore, SPP is revising its wind
accreditation methodology this year. The new methodology is expected to improve
wind capacity value to 12.1%.13 From	
  a	
  utility’s	
  perspective,	
  this increased capacity
credit is likely to reduce barriers associated with wind generation.
Originally in 2004, the SPP Generation Working Group (GWG) developed a
statistical-based method to accredit capacity value of wind. It first examined the
highest 10% of load hours in a month, and ranked wind generation during these hours
from high to low. The value that exceeded 85% of these values was used as the wind
capacity value. When possible, the methodology takes 10 years of data into account.14
In	
   April	
   2014,	
   Mitchell	
   Williams,	
   of	
   Western	
   Farmers	
   Electric	
   Cooperative’s	
  
Generation Working Group, proposed a revision of the wind accreditation. This
revised version is more favorable to wind for the following reasons:
1. It reduces data requirements from 10% load hours to 3%.
2. It reduces confidence interval from 85% to 60%.
3. It accepts 5% capacity for a new project instead of 3% for up to 3 years.15
In	
   June	
   2014,	
   SPP’s	
   Cost	
   Allocation	
   Working	
   Group	
   decided	
   to	
   maintain	
   this	
  
proposed revision, and planned to pay close attention to future reports on the
performance of wind assets. 16 Not only is wind accreditation becoming more
favorable to wind development, but also utilities in SPP are expecting to see more
relaxed reserve margin standards. These standards will also favor wind in an indirect
manner, since they place fewer requirements on utilities in terms of increasing
capacity value of generating assets.
12 (Milligan & Porter, 2006)
13 (Argus, 2015)
14 (Milligan & Porter, 2006)
15 (Southwest Power Pool CAWG, 2014)
16 (Southwest Power Pool CAWG, 2014)
18
Considering that approximately $1 billion could be saved over a 30-year
period for every 1% reduction in the reserve margin, SPP formed the Capacity Margin
Task Force to research the potential of reducing capacity margin or reserve margin
while still ensuring the same level of reliability.17 Due to the high potential for
conserving capital, refining reserve margin	
  is	
  currently	
  one	
  of	
  SPP’s	
  highest	
  stated	
  
priorities.18
4.4 Pricing
Utilities claim that variability and intermittency can significantly increase
price volatility in energy markets. Although wind forecasts can provide reliable
estimates of generation over long periods of time, such as on a monthly or annual
basis, they are inaccurate over shorter	
   periods.	
   From	
   a	
   utility’s	
   perspective,	
  
limitations associated with wind predictability in the short-term put wind at a
disadvantage when compared to more conventional assets, such as gas turbines,
which are predictable and far more dispatchable.
When a utility seeks to offer its generated power into the marketplace, it has
two channels: through the day-ahead markets, or in the real-time markets. In the day-
ahead market, a utility determines the price and quantity at which it will offer its
power the following day. The day-ahead market in the SPP is scheduled in five-minute
increments. Consequently, each day consists of a total of 288 price points.
Furthermore, the utility can provide up to 10 discrete prices for each five-minute
increment, depending on the heat rate, which in turn depends on how much of an
asset is bid into the market.
By contracting in the day-ahead market, a utility gains price-assurance;
however, the quantity of power that the market purchases is dependent on the bid
17 (Nickell, 2014)
18 (Nickell, 2014)
19
stack, which in turn depends on two variables: load and price competition.
Conversely, real-time market prices vary based on demand and supply, and thus, a
utility can only determine the quantity it is willing to offer for the real-time price.
Due to the short-term variability and intermittency associated with wind
assets, the ability of a utility to offer wind in the day-ahead market is compromised.
It is all but impossible for a utility to determine the power generation of a wind asset
during a certain five-minute increment the following day. Utilities have limited choice
but to offer a large portion of their wind power in real-time markets. This increases
price risk. Furthermore, in geographies that are highly concentrated with wind
turbines, such as in the southwest of Kansas, the market experiences increased price
volatility. When wind is available, all the wind turbines in a given area produce power,
leading to a surplus of power in the real-time market. This surplus causes prices to
drop. As such, the extent of the change in price is determined by the capacity of wind
assets in that area. With continued wind development in an already highly
concentrated area, price volatility persists.
The issue of price volatility due to wind variability is further complicated by
the market distortions caused by the PTC. Wind generators who can avail the PTC can
occasionally offer power into the market at negative prices. Consequently, utilities
that are contemplating the addition of wind assets after the expiration of the PTC are
at a distinct disadvantage, since it would be impossible for them to compete with
generators that have negative marginal costs. This is one of the reasons why wind
deployment has plummeted in the post-PTC market.
The issue of price volatility can be somewhat mitigated through the use of
balancing areas and robust transmission infrastructure. There is potential to benefit
from economies of scale if several balancing areas develop cooperative arrangements
or markets for ancillary services, as SPP has created through the Integrated
Marketplace.
20
5.0 Exogenous Factors
5.1 Underdeveloped Transmission Infrastructure
Through conversations with participants in the Integrated Marketplace, the
need to rehabilitate and build new transmission infrastructure has been cited as a
major deterrent of wind growth in the Plains region. Aging infrastructure, unable to
handle the supply variations of wind along with a sparse transmissions network in
wind-abundant areas are believed to be major sources of resistance for wind
development.
One explanation for lackluster infrastructure development is historically low
load growth. Yet, in recent years, population growth in Oklahoma’s	
  two	
  largest	
  cities,	
  
Oklahoma City and Tulsa, has caused electricity demand to increase. This influx of
population is changing demographics in the OG&E service area. As such, customers
are demanding more clean energy options, in particularly wind options, as part of
their electricity fuel make-up. These demands are forcing OG&E and other utilities to
make preparatory infrastructure investments.
Prior to 2014, transmission projects in the SPP region were implemented on a
utility-by-utility basis. However, the creation of the Integrated Marketplace has given
utilities a new incentive to implement transmission renovation projects. The
“Highway/Byway”	
  cost	
  sharing	
  methodology	
  assigns	
  costs	
  regionally	
  and	
  locally	
  to	
  
those	
  benefiting	
  most	
  from	
  the	
  project.	
  “Highways”	
  are	
  high-voltage transmission
lines	
   above	
   300	
   kV,	
   while	
   “Byways”	
   are	
   lower-voltage (300 kv and below)
transmission lines. Costs are assigned to electric utilities across the entire SPP
footprint	
  based	
  on	
  their	
  historic	
  use	
  of	
  the	
  region’s	
  transmission	
  system.	
  The	
  SPP	
  uses	
  
a formula to assign costs more directly to the utility in whose service territory (zone)
21
the project is located. The chart below outlines the breakdown of the Highway/Byway
method.19
Voltage Paid for by Region Paid for by Local Zone
“Electricity	
  Highways”
(300 kV and above)
100% 0%
“Electricity	
  Byways”
(100 kV to 300 kV)
33% 67%
“Electricity	
  Byways”
(100 kV and below)
0% 100%
The Highway/Byway method significantly reduces the amount of capital
required for transmission projects. Utilities are incentivized to expand their
transmissions infrastructure through incorporation into their rate-base in order to
earn an annual return. The new system also increases the overall reliability of the grid
by improving the efficiency by which electricity flows throughout the RTO. The
combination of these changes in the SPP has led to an increase in completed
transmission projects, totaling $8 billion in 10 years, and solving the apparent
vulnerability of transmission development.
One recent success of the Highway/Byway is the Prairie Wind Transmission
Project. In 2014, Westar completed the Prairie Wind Transmission Project to build
108 miles of extra-high-voltage 345 kV transmission lines. The project links an
existing 345-kV substation near Wichita, Kansas to a new 345-kV substation
northeast of Medicine Lodge, Kansas near the Flat Ridge I Wind Farm, and then south
to the Kansas/Oklahoma border. This project will support future generation assets
joining the grid in the region.20
Stakeholder interviews suggest that had the ability to share transmission costs
been created in earlier, utilities would likely have avoided issues related to
curtailment payments. For instance, OG&E may have avoided a $4.3 million
19 (Pennel, 2010)
20 (Westar Energy, 2014)
22
settlement with wind developer Competitive Power Ventures, surrounding a
disagreement on curtailment payments caused by unreliable transmissions lines. In
August 2013, the wind developer filed a lawsuit against OG&E claiming the utility
failed to pay curtailment charges when their Keenan wind farm was in operation but
transmission issues limited it from supplying electricity onto the grid. The two parties
settled for $4.3 million and OG&E plans to recover this cost through a fuel adjustment
clause, transferring the burden of the faulty transmission system onto its rate-payers.
Underdeveloped transmission infrastructure might have been a deterrent of wind in
the past, but recent innovations such as the Highway/Byway and the Integrated
Marketplace have brought solutions to all stakeholders within the SPP territory. 21
5.2 Regulation
Conversations with both utilities and other subject matter experts in the
power sector provide consensus that regulation has been a primary driver for the
deployment of wind resources in the SPP. First, both OG&E and Westar were forced
to comply with the Renewable Portfolio Standards (RPS) in their respective states.
Second, the Production Tax Credit (PTC) offered a significant incentive for deploying
wind assets by improving wind economics. Finally, the Clean Power Plan is forcing
both utilities to rethink their resource planning objectives for the coming years.
Meanwhile, uncertainty surrounding future policy legislation introduces a certain
amount of risk. For instance, if a utility takes on additional wind assets in order to
comply with legislation, and the legislation is later repealed, the utility runs the risk
of creating stranded assets. The following sections elaborate on these aspects of
regulation and their impact on wind generation.
21 (Monies, 2015)
23
5.2.1 Renewable Portfolio Standard (RPS)
Officials at both OG&E and Westar confirmed that the RPS was a primary
driving force behind wind adoption in their respective states. In May 2010, the
Oklahoma Legislature set a suggested RPS goal that 15% of total installed generation
capacity be derived from renewable sources. There are no interim targets and the
goal is not extending past 2015.22 This RPS standard in Oklahoma is not a mandatory
regulation, but only a call for voluntary compliance. As it stands, wind capacity at
OG&E accounts for about 12% of generation capacity.23
In Kansas, the RPS was established in 2009, aiming for 15% by 2015-2019,
and 20% by 2020.24 Due	
  to	
  Kansas’	
  low load growth, as well as additional purchased
wind energy, Westar has achieved its 2020 RPS target of 20%. Although Westar has
technically met its RPS goals until 2020, the utility continues to weigh the economic
advantages of adding wind generation now with the PTC or possibly in the future
should wind generation technology continue to become more cost competitive. An
uncertain regulatory environment exacerbates the risk of adding wind. For example,
in a conversation with the resource planning team at Westar Energy, the concern for
creating stranded assets was communicated. However, should the utility wait until
the regulatory environment is certain, then the utility will likely face higher charges
as greater demand for wind assets will increase the price at which developers provide
wind assets.
With that said, a	
   utility’s ability to rate-base assets offers them greater
incentive to expand their wind portfolio, as any investment costs approved by state
regulators are able to be recovered. If utilities are forced to bear an unfair higher cost
because of a sudden change in state legislation, it has been suggested that utilities will
have a strong legal case for reparations.
22 (National Conference of State Legislatures, 2015)
23 (OG&E, 2014)
24 (OG&E, 2014)
24
5.2.2 Clean Power Plan
In 2014, the EPA proposed emissions guidelines for states to reduce GHG
emissions from tradition, fossil-fuel generation plants. Although the proposal has yet
to be enacted, the CPP has the potential to significantly impact utilities throughout
the SPP.
Insight gained from experts in the SPP and MISO suggest that the most
significant impact of the CPP will manifest through a conversion from traditional coal
generating units to more flexible, cheaper natural gas ones. For OG&E and Westar,
this means converting around 50% of coal assets to natural gas. The utility-by-utility
reaction to this will vary; it has been observed that some utilities are willing to make
slightly larger investments to lock-in longer-term contracts for their clean assets.
In the short-run, the current industry consensus is that the transition to
natural gas plants will expand wind and solar markets by determining the shadow
price for carbon in the market. Stakeholders believe that studies to analyze the impact
of the CPP are underestimating how much wind will be installed over the next few
years. Even with this favorable future, this conversion is still highly vulnerable to
policies that state regulatory authorities will enact to either facilitate or add
resistance to this process.
25
6.0 Avoided Cost
FERC’s	
   enactment	
   of	
   PURPA	
   left the calculation of avoided costs open to
interpretation, and there are several methodologies used by state utility commissions
across	
  the	
  US.	
  Developers	
  are	
  often	
  unable	
  to	
  fully	
  capitalize	
  on	
  PURPA’s	
  benefits,	
  due	
  
to complexity of avoided cost ratemaking at the state level. Under the constraints of
maintaining consistency and reliability of electricity supply, and due to the multitude
of sources used for energy production, the calculation of avoided costs is invariably
complicated.
Added to the complexity of avoided costs is the necessity of confidentiality.
Since utilities need to compete in the open market for goods and services, the
respective inputs to avoided costs and the price points need to be masked from
potential vendors, otherwise the bids will naturally gravitate towards the highest bid,
thus setting an artificial floor and forcing other utilities to meet this price point. In
our attempt to understand how OG&E and Westar Energy calculate avoided cost, the
capstone team first conducted general desk research on the most commonly used
avoided cost methodologies in the sector. This information was helpful in guiding our
conversations with officials at both utilities. That said, although the team was able to
get a general sense of how the target utilities approach avoided cost, we were unable
to get specific information for the reasons stated above.
Availability of information on avoided costs methodologies varies among
states. While information on avoided cost for some states might be more easily
accessible in public records, reliable information is not available for most states25. To
the extent possible, we collected information from publically available information,
such as testimonies in utility case filings, news reports, and rate case proceedings.
25 18 CFR § 292.302 requires utilities to submit data from which avoided costs were calculated to the
state regulatory commissions every two years.
26
From testimonies and interviews of personnel from OG&E and public records at
the Oklahoma Corporation Commission, the following information gives some insight
into	
  OG&E’s	
  avoided	
  cost	
  calculation	
  methodology.	
  OG&E’s	
  decision	
  making	
  on	
  QF	
  
power purchases are based on their forecasts from a production cost model, for which
they	
  use	
  Power	
  Cost	
  Inc.’s	
  GenTrader	
  software.26 The following are some of the key
components	
  of	
  OG&E’s	
  avoided	
  cost	
  methodology:
1. OG&E’s	
  avoided	
  cost	
  calculation	
  includes purchases of wholesale energy that
would be purchased in the absence of purchase from the wind farms.
2. Due to the establishment of regional transmission operator, Southwest Power
Pool,	
  all	
  wind	
  QF’s	
  have	
  non-discriminatory access to the grid. Hence the QF’s	
  
bid into the integrated marketplace.
3. In the regional SPP market, the hourly costs are calculated at specific nodes.
This implies that at a given point of time, there are several avoided costs for
each utility.
4. The avoided capacity cost calculation is based on the assumption that OG&E's
next incremental capacity need would be fulfilled with a combustion turbine
(peaking capacity). OG&E assumes avoided capacity cost to be zero in years it
does not need an additional capacity to maintain the minimum required
capacity margin of 12% specified in section 2.1.9 of the SPP criteria. OG&E's
avoided cost calculation do not include any forecasts of capacity prices in the
region. Moreover, OG&E does not include any costs with compliance with
present or future environmental regulations in avoided capacity cost
calculations, as environmental regulations are geared towards the
preservation of existing capacity, and not the incremental need.
26 Docket No. 07-075-TF
27
5. Planned shutdowns, retirements, and retrofits of existing fossil fuel generating
facilities are usually included in the production cost analysis used to calculate
avoided costs. For instance, the O&M costs associated with retrofitting coal
and gas units with Low NOX burners was included in the production cost
model, and used to calculate the avoided energy costs.
6. OG&E includes the need and timing of future capacity needs to determine
avoided capacity costs, which takes inputs from planned shutdowns, retrofits,
and retirements.
7. Average line losses, and not marginal, are included in forecasting annual load,
which is then used to determine the forecasted reserve margin and energy
equivalents	
  for	
  each	
  year.	
  Generation	
  used	
  to	
  fulfil	
  OG&E’s	
  reserve	
  margin	
  is	
  
also included in the production cost analysis, and hence is an input for avoided
cost calculation
8. The production cost model also includes the assumption that OG&E will
comply with regional haze regulations in the manner specified in the
Oklahoma State Implementation Plan (SIP). The EPA rejected Oklahoma's SIP
and imposed a Federal Implementation Plan (FIP) on Oklahoma and OG&E.
The FIP would require OG&E to install very costly scrubbers on some of its
coal fired generators. The order has been challenged in 10th Circuit Court of
Appeals. There is some uncertainty about the requirements and costs
associated with Regional Haze and other environmental rules at the moment.
9. In addition to factors such as environmental compliance, reserve margins, line
losses, planned shutdowns, retrofits and retirements, the production cost
model is sensitive to natural gas price forecasts. OG&E does not assume any
transmission constraints in its avoided cost analysis.
28
From this information we can infer that	
  OG&E’s	
  assessment	
  of	
  long-term avoided
costs depends on the assumptions in their IRP, such as projections of fuel prices, load
growth forecasts and diurnal as well as seasonal load shape projections, planned
shutdowns, retirements and retrofits of existing generation assets, timing and type of
planned capacity additions, etc. With respect to resource sufficiency, OG&E does not
consider avoided capacity costs beyond the reserve margin of 12% as determined by
SPP, and avoided energy costs are calculated on the basis of the cost of service
incurred by OG&E to generate the power themselves from their existing generation
assets. If the resource planning considers periods of resource deficiency, the avoided
capacity payments are determined by referring to a proxy combustion turbine
generation unit (discussed below), and avoided energy costs are indicated by the
wholesale market price that OG&E might incur for purchasing the power from the
integrated marketplace. However, the above information has been obtained through
secondary	
   sources,	
   and	
   might	
   be	
   dated.	
   	
   Insight	
   into	
   Westar’s	
   avoided	
   cost	
  
methodology was briefly	
  shared	
  during	
  a	
  conversation	
  with	
  officials	
  from	
  Westar’s	
  
Market Resource Planning department. The highlights of the conversation are
outlined below:
To determine whether a project is cost-competitive to traditional assets, the
team first uses a quantitative-based model, created by a third-party, and enters hour-
by-hour factors such as fuel price curves, load growth, and other operating
parameters. This initial model helps the team determine the optimal way to best
serve the load. Based on the potential wind generation from a wind farm, the cost of
the wind farm is compared with the cost generated from the model. The analysis looks
at 100% operation of the wind farms along with complimentary generation from
other assets. After comparing the combined system, a break-even price is determined
that establishes the basis of the economic competitiveness of the wind farm.
Additional costs such as transmission and congestion costs are factored into the
process after generating the base price. The combination of these various costs create
an avoided cost necessary to beat to purchase the wind asset.
29
6.1 Regulations on Avoided Costs
The rationale behind PURPA is to balance the interests of independent power
producers,	
  customers,	
  and	
  utilities.	
  IPP’s	
  lacks	
  the	
  market	
  power	
  to	
  compete	
  in	
  the	
  
open market with long established utilities. Customers need to be protected from
overpriced electricity tariffs, and utilities need to keep into consideration the
reliability and quality of power supply, air quality standards and their guaranteed
rate of return. The nature of transaction between utilities and IPPs, termed as
Qualifying	
   Facilities	
   (QF’s),	
   are	
   determined	
   by	
   the	
   avoided costs. PURPA defines
avoided	
   costs	
   as	
   the	
   “incremental costs to an electric utility for electric energy or
capacity or both, but for the purchase from the qualifying facility or qualifying facilities,
such utility would generate itself or purchase from another source”	
   (Section	
   210,	
  
PURPA, 1978).
Despite	
  the	
  mention	
  of	
  “incremental	
  costs”,	
  avoided	
  costs	
  differ	
  from	
  marginal	
  
costs. Marginal costs do not consider the size of the load over which changes in costs
are measured. Avoided Costs, on the other hand, require explicit consideration of the
change in costs associated with a finite change in the load, hence depending on both
timing as well as magnitude of the load changes. The incremental costs act as the price
ceilings, so that the consumer is largely indifferent to the source from which the
power is being delivered to them.
Among the various inputs that are considered in calculation of avoided costs, the
following find application in most methods:
1. Avoided purchase of energy
2. Avoided purchase of resources, such as natural gas, coal, oil etc. (and the cost
of storing and transportation of the resources)
3. Avoided transmission line costs, including construction, maintenance and line
losses
4. Avoided cost of maintenance, retrofit, and replacement, as determined by the
utility’s	
  integrated	
  resource	
  planning
30
5. Avoided cost of compliance with current and expected environmental
regulations
6. Avoided cost of externalities, such as health costs, benefits from improved air
quality and visibility, less noise pollution, etc.
7. Avoided	
  RPS	
  costs	
  (for	
  clean	
  energy	
  QF’s)
8. Avoided property taxes
Apart	
  from	
  the	
  above	
  mentioned	
  inputs,	
  the	
  utility’s	
  decision	
  making	
  finally	
  rests	
  
upon their resource planning, future load forecasts, and the quality of the QF power
supply.	
  FERC’s	
  regulations list the following qualitative factors which states should
consider	
  while	
  evaluating	
  bids	
  by	
  QF’s:	
  
1. The ability of the utility to dispatch the QF
2. The expected and demonstrated reliability of the QF
3. The duration of the contract
4. The extent of coordination	
  between	
  the	
  QF	
  and	
  utility’s	
  planned	
  /	
  unplanned	
  
outages
5. Costs and savings from changes in line losses as a result of QF purchases
6. The relationship of the availability of energy or capacity from the QF to the
ability of the electric utility to avoid costs, including deferral of capacity
additions and reduction in fossil fuel use.
6.3 Methodologies:
Surveys of avoided cost calculation methodologies have documented a variety of
methods being used across different states in the US 27 . The methods vary by
complexity,
Proxy unit:
The proxy unit method assumes that the QF enables the utility to defer a future
generation unit; and the avoided costs are hence the projected energy and capacity
27 (Porter, Fink, Buckley, Rogers, & Hodge, 2013)
31
costs of the specified proxy unit, which is usually a combustion turbine power
generation asset.
The capacity costs are the fixed costs of the proxy unit, and the estimated
variable costs are used to calculate avoided energy costs. Factors such as debt
financing, tax burdens, equity costs, etc. are considered in calculate avoided capacity
costs.	
  The	
  choice	
  of	
  proxy	
  unit	
  may	
  either	
  be	
  in	
  accordance	
  to	
  the	
  utility’s	
  IRP	
  in	
  terms	
  
of the timing that the proxy unit comes online, capacity and type of technology, or it
may be a hypothetical unit as determined by the state utility commission.
The avoided cost hence calculated depends on the type of proxy unit selected.
Choosing a higher cost base load plant as proxy will result in higher avoided cost, and
a lower cost combustion turbine will have lower avoided cost. Although this method
lacks sound scientific basis, it is most widely used across different states in the US,
because of its simplicity.
Peaker Method:
In a Peaker method of calculating avoided costs, it is assumed that the power
supplied by the QF reduced the marginal generation requirement of the utility, and
hence avoids the construction of a peaking plant. The cost if the energy component is
based on marginal costs over the life of the contract, calculated on an hourly or longer
period, as opposed to the next planned units as in the case of proxy unit method. The
production cost simulation of marginal costs with and without the QF yields the
difference between the two scenarios, which is the avoided energy cost.
The capacity component is of avoided cost is based on the annual equivalent
of	
  utility’s	
  least	
  cost	
  capacity	
  option	
  (pealing	
  unit),	
  which	
  is	
  typically	
  a	
  combustion	
  
turbine. Since these generation assets have less upfront capital requirement, they
minimize the avoided capacity costs, whereas the generation costs are high, as they
are assessed in a marginal generation basis. The argument in favor of this method is
32
that the sum of lower capacity costs and higher (marginal) energy costs is equivalent
to the higher capacity cost and lower fuel costs of a base load.
Since the capacity component of the contract is availed by the utility only when
required, this method assumes that the QF will recover its investment only through
energy component, whose payments vary by the hour. In case of intermittent
technologies, the payments for energy component is not only dependent on the
hourly load profile, but the resource availability as well. A recent petition at Georgia
Public Service Commission28 about this limitation of the peaker method prompted the
commission to modify the avoided cost calculation formula, with inclusion of avoided
costs of environmental compliance, and avoided start-up costs.
Differential revenue requirement (DRR)
The	
  QF	
  capacity	
  reduces	
  the	
  utility’s	
  revenue	
  requirement.	
  The	
  present	
  value	
  
of	
  the	
  difference	
  between	
  the	
  utility’s	
  revenue	
  requirement	
  in	
  the	
  two	
  scenarios	
  of	
  
IRP, with and without QF capacity, represents the avoided cost.
While DRR method utilizes sophisticated modeling and forecasting technologies
in projecting the revenue requirement with and without QF output, the IRP is
sensitive to inputs considered by the utility, such as fuel price forecasts and load
forecasts. DRR assumes	
   that	
   the	
   QF’s	
   are	
   perpetually	
   marginal	
   resources,	
   and	
   is	
  
suitable only for short-term avoided cost calculation. Moreover, DRR method suffers
from a lack of transparency.
Market based pricing
PURPA was amended in 2005, authorizing FERC to grant an exception from
mandatory obligation for purchase of QF power, if the QF has a non-discriminatory
access to competitive markets and open access to the transmission system provided
by the regional transmission operator. Lower natural gas prices and increased
28 (Georgia Public Service Commission, 2004)
33
competition in the wholesale markets, including competitive bidding as a way to set
avoided costs in some jurisdictions, has reduced avoided cost payments to renewable
generation	
  QF’s,	
  and	
  is	
  applicable	
  only	
  for	
  short	
  term	
  planning.	
  	
  Some	
  jurisdictions
apply locational marginal price (LMP) as determined at the integrated marketplace
as	
  the	
  avoided	
  energy	
  cost.	
  However,	
  the	
  use	
  of	
  current	
  or	
  even	
  historical	
  LMP’s	
  does	
  
not allow the QF to estimate the future prices, due to variability in load shape, and
because	
   there	
   are	
   multiple	
   avoided	
   costs	
   (LMP’s)	
   at	
   any	
   given	
   point	
   of	
   time,	
  
depending upon the location of the node at which the cost is measured. The lack of
long	
   term	
   price	
   projections	
   makes	
   the	
   returns	
   on	
   investment	
   by	
   the	
   QF	
   owner’s	
  
uncertain, and acts as a barrier towards promotion of small power producers.
Moreover,	
  LMP’s	
  do	
  not	
  reflect	
  the	
  full	
  cost	
  of	
  owning	
  and	
  operating	
  the	
  generation	
  
facility, more specifically, the costs related to long term planning, costs of
transmission line losses, costs of maintaining reserves, etc., and hence offer an
undervalued estimate of the avoided costs.
Competitive bidding
In some states, after determining the power needs based on the IRP, utilities
establish	
   benchmark	
   prices	
   and	
   allow	
   QF’s	
   to	
   bid	
   to	
   meet	
   the	
   benchmark. The
winning bids reflect the cost at which the utility would have procured power, and are
regarded	
  as	
  the	
  utility’s	
  avoided	
  costs.	
  
The benchmark prices set by the utilities depends on the forecasts of load and
fuel prices, resource mix as determined by the utility, term of the contract between
winning bidder and the utility and future policy projections. Theoretically,
competitive bidding rewards the QF with most efficient power generation. However,
in an open market, it places renewable energy generation facilities, especially those
with higher capacity, at a disadvantage.
All of the above-described avoided cost methodologies have their own merits
as well as merits, and none of them can yield most accurate avoided cost estimates.
34
Utilities have a broad discretion over many of the assumptions that go into calculation
of avoided costs. The choice of a specific method for avoided cost calculation in a state
is generally dictated by the policy objective, such as to promote small power
producers, incentivize particular technology, environmental considerations,
maintaining	
  ratepayer	
  neutrality	
  or	
  spreading	
  the	
  risks	
  of	
  QF	
  contracts	
  between	
  QF’s	
  
and ratepayers non-discriminately29.
Apart from the these calculation methodologies, states are required to
maintain	
  standard	
  purchase	
  contracts	
  for	
  purchase	
  of	
  QF’s	
  of	
  capacity	
  100	
  kW	
  or	
  less.	
  
In standard contracts, either the state commission establishes methodology for
calculation of avoided costs, or utilities propose both rates as well as methodologies
before the	
  state	
  commission.	
  Some	
  states	
  have	
  allowed	
  standard	
  contracts	
  for	
  QF’s	
  of	
  
higher capacity as well. For example, California allows standard contracts for facilities
of maximum capacity 20 MW, and Utah, Montana and Oregon make standard
contracts available for facilities of 10 MW capacity. Standard contracts would lend
certainty to the business of power generation from the perspective of the QF, and
enable them to plan for future investments.
29 (Elefant, 2011)
35
7.0 Recommendations
7.1 Address asymmetry in fuel price risk allocation
Unlike traditional generating assets, such as coal and gas plants, wind
generation has almost no fuel price risk. However, the Fuel Adjustment Clause (FAC)
in both Kansas and Oklahoma leads to market distortions that cause utilities to
overlook this critical aspect of wind generation when evaluating it against traditional
generating technologies.
Both Westar and OG&E are subject to the FAC. This is a mechanism that
permits jurisdictional utilities to regularly adjust the price of electricity to reflect
fluctuations in the cost of fuel, or purchased power, used to supply that electricity. By
allowing utilities to reflect fluctuations in fuel prices in electricity rates, the FAC
insulates utilities from changes in the price of fuel. Both Westar and OG&E pass the
risk of fuel price volatility straight through to their ratepayers through the FAC.
Consequently, when evaluating wind generation against traditional generation these
utilities do not factor in the benefit of mitigating fuel price risk.
The FAC encourages the use of fuel intensive technologies over renewables
since fuel price volatility is passed through to the ratepayers. In order to provide a
level playing field for wind generation, it would be prudent for GE to help address the
distortions created by the FAC. One way for GE to accomplish this goal is to facilitate
consumer-motivated regulation.
7.2 Standardized Avoided Cost Methodologies
The	
  guidelines	
  for	
  compensation	
  to	
  QF’s	
  as	
  defined	
  by	
  PURPA	
  allow	
  the	
  states	
  
to choose methods that are consistent with their policy objectives. Consequently, the
choice made by the states has significant implications on the prospects of alternative
generation technologies within their jurisdictions. However, the inputs that
constitute the models for estimation of avoided costs are not transparent, and hence
36
the methods are heterogeneous between, and sometimes within states. In such a
situation, there is a lack of support for long term investment planning on part of the
QF’s.	
  	
  In	
  order	
  to	
  introduce	
  certainty,	
  an	
  authority	
  such	
  as	
  FERC,	
  with	
  the	
  mandate	
  of	
  
ensuring	
   national	
   electricity	
   reliability	
   and	
   quality	
   along	
   with	
   PURPA’s	
   goal	
   of	
  
encouraging alternative power producers, should conduct an evaluation of avoided
cost methodologies used across different states and quantify the merits and demerits
thereof. Such an evaluation will be useful in helping states choose the appropriate
methods for measuring avoided costs. Moreover, with the consolidation of multiple
jurisdictions under integrated market places, standardization of avoided cost
calculation methods will lend efficiency to the power market.
Standardization of avoided costs can be approached to some extent by
utilizing	
   PURPA’s	
   mandate	
   guaranteed	
   purchase	
   of	
   power	
   from	
   small	
   power	
  
producers. Although PURPA specifies the upper limit of such small power producers
at 100 kW, some states have increased this limit to include higher capacity
independent power producers to be eligible for standard purchase contracts, which
are vetted by the respective state regulatory commission, and provide relatively long
term certainty to small power producers. The standard purchase contracts in
Oklahoma are however fixed at 100	
  kW,	
  whereas	
  California	
  allows	
  for	
  QF’s	
  up	
  to	
  20	
  
MW to be eligible for standard purchase contracts. Similar figures were not available
for	
   Kansas.	
   The	
   recommendation	
   of	
   increasing	
   the	
   eligibility	
   criteria	
   of	
   QF’s	
   for	
  
standard purchase contracts can be taken up with the state regulatory commissions,
in the interest of encouraging small power producers.
7.3 Resource Specific Avoided Costs
Some of the methods of estimating avoided costs discussed above compare the
QF to a different generation asset, from which the utility might have purchased or
generated power in absence of the QF. These assets, categorized as proxies,
surrogates, or peakers, depending upon the method used, are usually either least cost
capacity additions or marginal units that use natural gas. The avoided cost estimates
37
resulting from comparisons of these units with wind farms do not reflect the full
extent of the avoided costs. Comparisons, if any, should be made between units with
similar supply characteristics. In a recent order on California Public Utility
Commission’s	
   petition 30 , FERC determined that multi-tiered avoided cost rate
structure can be deemed consistent with PURPA’s	
  requirements.	
  This	
  implies	
  that	
  
variables specific to a QF, such as capacity, reliability, availability, efficiency,
environmental	
   performance,	
   and	
   fuel	
   resource	
   used	
   can	
   differentiate	
   the	
   QF’s	
  
avoided	
   cost	
   from	
   other	
   generation	
   assets’	
   avoided	
   Allowing flexibility in pricing
mechanism will allow to include factors such as benefits of long-term contracts
between utility and QF, location of the QF, and external benefits such as creation of
employment opportunities and less reliance on local natural resources. Effectively,
the avoided cost for a wind energy QF should be compared to the costs of an existing
wind farm, including the non O&M components of the cost.
7.4 Forward Capacity Markets
An argument against addition of more renewable generation to the portfolio
has been the low capacity value that these assets offer, and hence the negative
impacts from a resource adequacy perspective. Moreover, incentives offered to
renewable generation, such as RPS and PTC for wind can sometimes lead to negative
clearing price in the integrated marketplace, and hence impair the ability of
conventional generation plants to recover their costs through the energy market
alone. This might force some of them to early retirement, hence adversely impacting
the resource adequacy of the power market. The Southwest Power Pool maintains
the resource adequacy through a capacity reserve margin, which is fixed at 12%. The
capacity margin can be met either by a particular utility on a standalone basis, or
through a reserve sharing pool.31
30 (FERC, 2010)
31 (Southwest Power Pool, 2011)
38
However, the capacity margin alone does not incentivize the generation
utilities to add more plants to their existing portfolio, as the capacity value in itself is
not monetized. A forward capacity market, such as that at PJM32, will help to maintain
resource adequacy on a forward basis for a defined period of time (three years in
PJM’s	
  Reliability	
  Pricing	
  Model),	
  by	
  providing	
  incentive	
  to	
  procure	
  capacity	
  for	
  a	
  long	
  
term. Forward capacity markets will offer an additional stream of revenues to
conventional generation assets, reflecting the value of their reliability, and hence will
improve their financial performance by offering stable prices for an extended period
of time. Stakeholders from equipment manufacturers (such as GE), variable power
generators, conventional utilities and SPP should explore the possibility of
implementing a forward capacity market.
7.5 Security Constraint Economic Dispatch
High	
  wind	
  speed	
  cut	
  out	
  came	
  to	
  our	
  team’s	
  attention	
  during	
  a	
  conversation	
  
with a former director of resource planning. Accordingly, we identified high winds as
a barrier for wind power generation. Mark Ahlstrom of Wind Logics proposed two
recommendations for rectifying the problem of high wind speed cut out. As noted
before, in a high wind scenario, to prevent damage to the equipment, an operator will
need to shut it down or feather the blades. Besides wind scheduling that will give
operators a reasonable amount of time to plan for a scenario of high wind (50-60
mph), Mark discussed how there are turbines in the market with the technology that
can change the forecast of uncertainty. New Turbines will back off even before they
get to that cut off point. With the new technology, individual blades can be turned to
take in less energy and protect it.
As our	
  recommendation	
  to	
  GE,	
  Mark’s	
  experience	
  and	
  work	
  with	
  an	
  optimizing	
  
tool that already is being used by SPP is instructive. In his experience, the cut out
problem	
   is	
   mostly	
   a	
   problem	
   for	
   people	
   who	
   don’t	
   really	
   think	
   about	
   the	
   larger	
  
39
system but only think about it as a single wind turbine problem. To integrate wind
into the market, it should be forecasted as well as it possibly can; and the forecast
should go in the overall system operational plans, the data unit commitment, and the
real time dispatch of all units in the system. But most importantly, cut off as well as
the other problems associated with wind power go away when using a process called
Security Constraint Economic Dispatch, a process that takes cost and liability when
optimizing a system every 5 minutes to match load. This process takes into account
the whole power system with all its different types of generators and characteristics
(failure modes, lack certainty, etc). So when it is integrated in the system, the process
of Security Constraint Economic Dispatch really nullifies the problems associated
with cut out and other associated problems caused by variability. Therefore, we
believe GE can reduce the barriers associated with variability by informing utilities
that these problems can be nullified by using the tools already in place—primarily
the Security Constraint Economic Dispatch.
7.6 Increased Geographic Network
Recently planned changes to the Southwest Power Pool have opened new
doors for wind growth. One area where the team sees opportunity for GE deals with
future transmission investments and the expansion of the SPP. In 2014, the Upper
Great Plains Region of the Western Area Power Administration was approved to join
the regional transmission organization. This inclusion would stretch	
   the	
   SPP’s	
  
footprint to the Canadian border. We see this as highly beneficial to future wind
growth because of the correlation between its future boundary and the abundance of
wind	
  resources	
  in	
  the	
  Plains	
  region	
  as	
  well	
  as	
  SPP’s	
  goals	
  to	
  develop	
  its	
  connected
energy market. The expansion of the RTO combined with the already progressive
actions made to integrate the energy market via the Integrated Marketplace offer a
promising future for wind development.
The expansion of the SPP footprint will promote transmission infrastructure
development, while increasing the interconnectedness of several states. However, the
40
growth of the marketplace will require more advanced infrastructure to balance and
ensure the reliability of the grid. As more wind farms are connected, the variability of
wind will significantly reduce, as abundant wind in one part of the region will be able
to be shared with other areas where wind is scarce. The inclusion of more
stakeholders -- as participants in this marketplace – will further the development of
high-voltage transmissions lines paid for through the Highway/Byway shared-cost
methodology. In a similar way, increased interconnectedness of the marketplace will
enable the SPP to dissipate power in congested areas and deliver wind resources from
their source to their need, reducing integration costs and providing greater incentive
for future wind farms.
Benefits obtained through greater adoption of wind have been shown in a
recent study by the U.S. Energy Information Agency (EIA) analyzing the reduction of
base load capacity due to higher wind generation in the SPP. The graph below shows
the reduction in base load use since 2010.
Figure 1 – September 5, 2013
The reduction in base load use is due to higher volumes of wind energy
generation supplanting generation from traditional base load units. This reduction
effect will be catalytic with the expansion of the SPP RTO, furthering the cost
41
competitiveness and the defensibility of wind as an energy option for resource
planning	
   decisions.	
   The	
   SPP’s	
   outlook	
   for	
   the	
   Integrated	
   Marketplace	
   and	
   the	
  
Highway/Byway cost was best summarized by Regional State Committee member
and Arkansas Public Service Commission Chairman Paul	
  Suskie,	
  “SPP	
  needed	
  a	
  cost	
  
allocation policy for transmission projects that not only enhance reliability, but also
have the potential to reduce costs for utilities and their customers. Building new
transmission will bring many benefits, such as reducing	
  congested	
  „bottlenecks‟ on
the electric grid, increasing grid reliability and efficiency, and creating jobs during the
construction and operating phases. This Highway/Byway cost sharing methodology
will provide a regional solution for building out the regional electric grid that will
meet	
  our	
  needs	
  into	
  the	
  future.”
7.7 Externalities
While	
  there	
  isn’t	
  a	
  carbon	
  pricing	
  system	
  in	
  the	
  US,	
  it	
  is	
  expected	
  to	
  see	
  a	
  future	
  
with stricter regulation on carbon emissions. Since utilities are mainly engaged in
long term investment decisions on generating assets, they will make better informed
decision by factoring in the coming tighter regulation of greenhouse gases and
including carbon pricing in its economic analysis.
As regulation gets tighter in cutting carbon emission, it is likely to have carbon
pricing as a regulatory tool in the US. Almost 40 countries and more than 20 cities,
states and provinces already use carbon pricing mechanisms or are planning to
implement them.33 Meanwhile, private sector has become more acceptable to carbon
pricing. And many companies are preparing for tighter regulation by including an
“internal	
  carbon	
  price”	
  in	
  business	
  planning.34
A landmark judgment by FERC on petition by California Public Utilities
Commission35 specifies	
  that	
   if	
  an	
  externality	
  factor	
  represents	
  “real	
  costs”	
  for	
  the	
  
33 (World Bank, 2015)
34 (CDP, 2013 )
35 (FERC, 2010)
42
incumbent utility, it may be deemed as a valid avoided cost under PURPA. This implies
that in the event of imposition of external costs associated with the environment, the
avoided cost methodology currently applied by utilities will need to be revised to
regard these external costs as penalties for conventional generation assets, which can
be avoided by renewable energy generation facilities. Subsequently, calculation of
these external costs on a life cycle basis will yield a more scientifically accurate
estimate of the impacts on the environment, integrating emission from upstream to
downstream operations.
Currently, neither Westar nor OG&E have considered the possibility of
pricing carbon or other pollutants such as SOX, NOX, particulate matter, etc. when
comparing renewable with fossil fuel generating assets. However, once they make an
investment decision today, they will have an asset that lasts for decades. Thus, it is
important to make sure that the portfolio of generating assets designed today could
comply with the tight regulation on carbon emission.
Adding carbon pricing in economic analysis will allow utilities to better evaluate
the comparative advantage of renewable and fossil fuel generating assets, and get
better prepared for future challenges in greenhouse gas regulation.
43
APPENDIX
SPP’s	
  Reliability	
  Impact	
  Assessment	
  of	
  EPA’s	
  Proposed	
  CPP:
http://www.spp.org/publications/CPP%20Reliability%20Analysis%20Results%20
Final%20Version.pdf
Kansas Corporation Commission Report on Electricity Demand and Supply,
2014:
http://www.kcc.state.ks.us/pi/2015_electric_supply_and_demand_report.pdf
EIA Levelized Cost and Levelized Avoided Cost of New Generation Resources,
2014:
http://www.eia.gov/forecasts/aeo/pdf/electricity_generation.pdf
44
Bibliography
1. American Wind Energy Association. (2015). Wind Energy Facts at a Glance.
(Retrieved from
http://www.awea.org/Resources/Content.aspx?ItemNumber=5059)
2. Argus. (2015, April 8). Analysis: SPP sees adequate summer reserve margin.
(Retrieved from http://www.argusmedia.com/News/Article?id=1019635)
3. CDP. (2013 , December). Use of internal carbon price by companies as
incentive and strategic planning tool.
(Retrieved from https://www.cdp.net/CDPResults/companies-carbon-pricing-
2013.pdf)
4. EIA. (2011, May 13). Electricity resource planners credit only a fraction of
potential wind capacity.
(Retrieved from http://www.eia.gov/todayinenergy/detail.cfm?id=1370)
5. EIA. (2014, April). Levelized Cost and Levelized Avoided Cost of New
Generation Resources in the Annual Energy Outlook 2014. (Retrieved from
http://www.eia.gov/forecasts/aeo/pdf/electricity_generation.pdf)
6. Elefant, C. (2011). Reviving PURPA's Purpose . (Law Offices of Carolyn Elefant)
(Retrieved from http://www.recycled-energy.com/images/uploads/Reviving-
PURPA.pdf)
7. FERC. (2010, October 21). 133 FERC ¶ 61,059. (Retrieved from
http://www.ferc.gov/whats-new/comm-meet/2010/102110/E-2.pdf)
8. Georgia Public Service Commission. (2004). Docket No. 4822-U. (Retrieved
from http://www.psc.state.ga.us/factsv2/Docket.aspx?docketNumber=36499)
9. Kansas Corporation Commission. (2015). Report on Electric Supply and
Demand. (Retrieved from
http://www.kcc.state.ks.us/pi/2015_electric_supply_and_demand_report.pdf)
10. Milligan, M., & Porter, K. (2006). The Capacity Value of Wind in the United
States: Methods and Implementation. The Electricity Journal , 19 (2).
11. Monies, P. (2015, April 2). Oklahoma Gas and Electric Co. plans to pass on $4.3
million wind legal settlement to customers. (Retrieved from
http://newsok.com/oklahoma-gas-and-electric-co.-plans-to-pass-on-4.3-
million-wind-legal-settlement-to-customers/article/5406550/?page=1)
45
12. National Conference of State Legislatures. (2015, February 19). State
Renewable Portfolio Standards and Goals.
(Retrieved from http://www.ncsl.org/research/energy/renewable-portfolio-
standards.aspx#ok)
13. Nickell, L. (2014). A Nickell for Your Thoughts. (Retrieved from
http://www.spp.org/publications/Resource%20Adequacy%20in%20SPP%20P
art%201%20Blog.pdf)
14. OG&E. (2014). 2014 Annual Report. OG&E.
15. OG&E. (2014). CDP 2014 Investor CDP 2014 Information Request. (Retrieved
from https://oge.com/wps/wcm/connect/d907496d-94c8-47d8-9cf6-
b6e11c88751f/140529+2014+OGE+CDP+Response.pdf?MOD=AJPERES&CACHE
ID=d907496d-94c8-47d8-9cf6-b6e11c88751f)
16. OG&E. (2014). OG&E Integrated Resource Plan (IRP). (Retrieved from
https://oge.com/wps/wcm/connect/342cf742-9bb6-48f1-aaa9-
34a4174b8c16/2014+IRP+-
+Oklahoma+Report.pdf?MOD=AJPERES&CACHEID=342cf742-9bb6-48f1-aaa9-
34a4174b8c16)
17. Pennel, E. (2010, April 19). SPP Proposes New Cost Sharing Method for
Expanding the Regional Electric Transmission Grid. (Retrieved from
http://www.spp.org/publications/spp_proposes_new_cost_sharing_method_for
_transmission.pdf)
18. Porter, K., Fink, S., Buckley, M., Rogers, J., & Hodge, B. (2013, March). A Review
of Variable Generation Integration Charges. Retrieved from National
Renewable Energy Laboratory (Retrieved from
http://www.nrel.gov/docs/fy13osti/57583.pdf)
19. Southwest Power Pool CAWG. (2014, April 17). CAWG Agenda & Background
Material. (Retrieved from
http://www.spp.org/section.asp?group=381&pageID=27)
20. Southwest Power Pool CAWG. (2014, June). CAWG Minutes & Attachments.
(Retrieved from http://www.spp.org/section.asp?group=381&pageID=27)
21. Southwest Power Pool Generation Working Group . (2004, September 29).
Wind Power Capacity Accreditation White Paper. (Retrieved from
http://www.spp.org/publications/WindWhite04Sept8_rev5.pdf)
22. Southwest Power Pool. (2011, January). Southwest Power Pool Criteria: Latest
Revision. (Retrieved from
46
http://www.spp.org/publications/Criteria%20and%20Appendices%20July%2
025,%202011.pdf)
23. Southwest Power Pool. (2014, October 8). SPP’S	
   RELIABILITY	
   IMPACT
ASSESSMENT	
  OF	
  THE	
  EPA’S	
  PROPOSED	
  CLEAN	
  POWER	
  PLAN. (Retrieved from
http://www.spp.org/publications/CPP%20Reliability%20Analysis%20Results
%20Final%20Version.pdf )
24. Westar Energy. (2013). 2013 Annual Report. (Retrieved from
http://www.annualreports.com/Click/3744?_SID_=20150512175718-
a4667f0b40ee9ec677a46b05b23f305e)
25. Westar Energy. (2014). 2014 Annual Report on Form 10K. (Retrieved from
http://phx.corporate-
ir.net/External.File?item=UGFyZW50SUQ9Mjc0NDkxfENoaWxkSUQ9LTF8VHl
wZT0z&t=1)
26. Westar Energy. (2014, October 30). Prairie	
  Wind	
  transmission’s	
  high-capacity
transmission line completed ahead of schedule, more than $60 million under
budget. (Retrieved from https://www.westarenergy.com/content/about-
us/news/2014-news-releases/pwt-energized)
27. World Bank. (2015). What Is Carbon Pricing? (Retrieved from
http://www.worldbank.org/en/programs/pricing-carbon)

More Related Content

What's hot

Business Innovation of Grid Connection & Power Quality in Renewable Energies
Business Innovation of Grid Connection & Power Quality in Renewable EnergiesBusiness Innovation of Grid Connection & Power Quality in Renewable Energies
Business Innovation of Grid Connection & Power Quality in Renewable EnergiesMaxwell Venture Service LLC
 
Feasibility Study of Solar Power in India
Feasibility Study of Solar Power in IndiaFeasibility Study of Solar Power in India
Feasibility Study of Solar Power in IndiaiData Insights
 
PLU General Presentation (Sept 2019)
PLU General Presentation (Sept 2019)PLU General Presentation (Sept 2019)
PLU General Presentation (Sept 2019)Bianca Pisciola
 
PLU General Presentation (November 2019)
PLU General Presentation (November 2019)PLU General Presentation (November 2019)
PLU General Presentation (November 2019)Bianca Pisciola
 
public serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencepublic serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencefinance20
 
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...ScottMadden, Inc.
 
Washington State Policy Roadmap
Washington State Policy RoadmapWashington State Policy Roadmap
Washington State Policy RoadmapAutodidact
 
ESF_StudyReport_SAND2016-8109
ESF_StudyReport_SAND2016-8109ESF_StudyReport_SAND2016-8109
ESF_StudyReport_SAND2016-8109richardbaxter1
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuidePrivate Consultants
 
Solar PV Financials
Solar PV FinancialsSolar PV Financials
Solar PV Financialstarunku08
 
Financing and Appraisal of a Power Project
Financing and Appraisal of a Power ProjectFinancing and Appraisal of a Power Project
Financing and Appraisal of a Power ProjectShaurya Vikram Singh
 
Indian Renewable Energy Status Report
Indian Renewable Energy Status ReportIndian Renewable Energy Status Report
Indian Renewable Energy Status ReportREN21
 
IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant Ashish Verma
 
Wind Industry Offers Ideas to Improve South African Wind Policy
Wind Industry Offers Ideas to Improve South African Wind PolicyWind Industry Offers Ideas to Improve South African Wind Policy
Wind Industry Offers Ideas to Improve South African Wind PolicyWind Energy Update
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden, Inc.
 
The 50 States of Solar_FINAL
The 50 States of Solar_FINALThe 50 States of Solar_FINAL
The 50 States of Solar_FINALJim Kennerly
 

What's hot (20)

Business Innovation of Grid Connection & Power Quality in Renewable Energies
Business Innovation of Grid Connection & Power Quality in Renewable EnergiesBusiness Innovation of Grid Connection & Power Quality in Renewable Energies
Business Innovation of Grid Connection & Power Quality in Renewable Energies
 
Feasibility Study of Solar Power in India
Feasibility Study of Solar Power in IndiaFeasibility Study of Solar Power in India
Feasibility Study of Solar Power in India
 
PLU General Presentation (Sept 2019)
PLU General Presentation (Sept 2019)PLU General Presentation (Sept 2019)
PLU General Presentation (Sept 2019)
 
PLU General Presentation (November 2019)
PLU General Presentation (November 2019)PLU General Presentation (November 2019)
PLU General Presentation (November 2019)
 
public serviceenterprise group LehmanConference
public serviceenterprise group LehmanConferencepublic serviceenterprise group LehmanConference
public serviceenterprise group LehmanConference
 
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
 
Washington State Policy Roadmap
Washington State Policy RoadmapWashington State Policy Roadmap
Washington State Policy Roadmap
 
ESF_StudyReport_SAND2016-8109
ESF_StudyReport_SAND2016-8109ESF_StudyReport_SAND2016-8109
ESF_StudyReport_SAND2016-8109
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
 
Solar PV Financials
Solar PV FinancialsSolar PV Financials
Solar PV Financials
 
AXY - 10 June
AXY - 10 JuneAXY - 10 June
AXY - 10 June
 
The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...
The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...
The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...
 
Financing and Appraisal of a Power Project
Financing and Appraisal of a Power ProjectFinancing and Appraisal of a Power Project
Financing and Appraisal of a Power Project
 
SunBurn Test
SunBurn TestSunBurn Test
SunBurn Test
 
Indian Renewable Energy Status Report
Indian Renewable Energy Status ReportIndian Renewable Energy Status Report
Indian Renewable Energy Status Report
 
IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant
 
Wind Industry Offers Ideas to Improve South African Wind Policy
Wind Industry Offers Ideas to Improve South African Wind PolicyWind Industry Offers Ideas to Improve South African Wind Policy
Wind Industry Offers Ideas to Improve South African Wind Policy
 
Wps4197
Wps4197Wps4197
Wps4197
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State Roadmap
 
The 50 States of Solar_FINAL
The 50 States of Solar_FINALThe 50 States of Solar_FINAL
The 50 States of Solar_FINAL
 

Similar to GE Capstone Final Report

Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...
Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...
Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...Eamon Keane
 
1000-1250 wordsTable of ContentsAbstract2Introduction3.docx
1000-1250 wordsTable of ContentsAbstract2Introduction3.docx1000-1250 wordsTable of ContentsAbstract2Introduction3.docx
1000-1250 wordsTable of ContentsAbstract2Introduction3.docxhyacinthshackley2629
 
Integrating Renewable Energy into the Electricity Grid
Integrating Renewable Energy into the Electricity GridIntegrating Renewable Energy into the Electricity Grid
Integrating Renewable Energy into the Electricity GridPower System Operation
 
Delay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionDelay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionCharles Fournier
 
R42576, PTC 2012
R42576, PTC 2012R42576, PTC 2012
R42576, PTC 2012Keri
 
Current US Policies and Future R&D Directions
Current US Policies and Future R&D Directions Current US Policies and Future R&D Directions
Current US Policies and Future R&D Directions Iceland Geothermal
 
Hawaii PUC Decision and Order No. 34696, July 14, 1017
Hawaii PUC Decision and Order No. 34696, July 14, 1017Hawaii PUC Decision and Order No. 34696, July 14, 1017
Hawaii PUC Decision and Order No. 34696, July 14, 1017Honolulu Civil Beat
 
ACORE_USEPA_111(d)_Comments_12-1-2014
ACORE_USEPA_111(d)_Comments_12-1-2014ACORE_USEPA_111(d)_Comments_12-1-2014
ACORE_USEPA_111(d)_Comments_12-1-2014Scott Clausen
 
60230 nrel securiyzation
60230 nrel securiyzation60230 nrel securiyzation
60230 nrel securiyzationEdwin Santiago
 
Independent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketIndependent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketTurlough Guerin GAICD FGIA
 
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Scott Clausen
 
Solar powering your community, a guide for local governments
Solar powering your community, a guide for local governmentsSolar powering your community, a guide for local governments
Solar powering your community, a guide for local governmentsJustin Bean
 
Rauluk Testimony Final no pics
Rauluk Testimony Final no picsRauluk Testimony Final no pics
Rauluk Testimony Final no picsValerie Rauluk
 
Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System Power System Operation
 
Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Finnish_Energy_Hub
 
Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011UCSD-Strategic-Energy
 
Connecticut Self Storage Association Presentation
Connecticut Self Storage Association PresentationConnecticut Self Storage Association Presentation
Connecticut Self Storage Association PresentationRRinc
 

Similar to GE Capstone Final Report (20)

Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...
Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...
Sandia National Laboratories, "Energy Storage for the Electricity Grid: Benef...
 
1000-1250 wordsTable of ContentsAbstract2Introduction3.docx
1000-1250 wordsTable of ContentsAbstract2Introduction3.docx1000-1250 wordsTable of ContentsAbstract2Introduction3.docx
1000-1250 wordsTable of ContentsAbstract2Introduction3.docx
 
Integrating Renewable Energy into the Electricity Grid
Integrating Renewable Energy into the Electricity GridIntegrating Renewable Energy into the Electricity Grid
Integrating Renewable Energy into the Electricity Grid
 
Delay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionDelay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant Construction
 
R42576, PTC 2012
R42576, PTC 2012R42576, PTC 2012
R42576, PTC 2012
 
Current US Policies and Future R&D Directions
Current US Policies and Future R&D Directions Current US Policies and Future R&D Directions
Current US Policies and Future R&D Directions
 
Hawaii PUC Decision and Order No. 34696, July 14, 1017
Hawaii PUC Decision and Order No. 34696, July 14, 1017Hawaii PUC Decision and Order No. 34696, July 14, 1017
Hawaii PUC Decision and Order No. 34696, July 14, 1017
 
PUC PSIP Order
PUC PSIP OrderPUC PSIP Order
PUC PSIP Order
 
ACORE_USEPA_111(d)_Comments_12-1-2014
ACORE_USEPA_111(d)_Comments_12-1-2014ACORE_USEPA_111(d)_Comments_12-1-2014
ACORE_USEPA_111(d)_Comments_12-1-2014
 
60230 nrel securiyzation
60230 nrel securiyzation60230 nrel securiyzation
60230 nrel securiyzation
 
TASK FORCE TO INVESTIGATE HAWAII ELECTRIC COMPANY (HECO)
TASK FORCE TO INVESTIGATE HAWAII ELECTRIC COMPANY (HECO)TASK FORCE TO INVESTIGATE HAWAII ELECTRIC COMPANY (HECO)
TASK FORCE TO INVESTIGATE HAWAII ELECTRIC COMPANY (HECO)
 
Independent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketIndependent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity Market
 
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
 
Solar powering your community, a guide for local governments
Solar powering your community, a guide for local governmentsSolar powering your community, a guide for local governments
Solar powering your community, a guide for local governments
 
Rauluk Testimony Final no pics
Rauluk Testimony Final no picsRauluk Testimony Final no pics
Rauluk Testimony Final no pics
 
Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System
 
Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)Future proofing energy storage - a greensmith white paper (EN)
Future proofing energy storage - a greensmith white paper (EN)
 
Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011Cpuc changes to adv energy storage incentives sep 2011
Cpuc changes to adv energy storage incentives sep 2011
 
Connecticut Self Storage Association Presentation
Connecticut Self Storage Association PresentationConnecticut Self Storage Association Presentation
Connecticut Self Storage Association Presentation
 
2015 08 Power Engineering
2015 08 Power Engineering2015 08 Power Engineering
2015 08 Power Engineering
 

GE Capstone Final Report

  • 1. SIPA Capstone Team James Doone, William Hernandez, Harsh Vijay Singh, Varun Soni & Vivian Xu M a y 1 3 , 2 0 1 5 Wind in a Post-PTC Market
  • 2. 2 Table of Contents Acknowledgements............................................................................................................................3 1.0 Introduction ..................................................................................................................................4 2.0 Executive Summary ....................................................................................................................6 2.1 Objective of the Project ........................................................................................................................6 2.2 Planning for Variability........................................................................................................................6 2.3 Exogenous Factors .................................................................................................................................7 2.4 Avoided Costs...........................................................................................................................................8 2.5 Recommendations..................................................................................................................................9 3.0 Background ................................................................................................................................ 12 3.1 Overview of utility...............................................................................................................................12 4.0 Planning for Variability.......................................................................................................... 14 4.1 Existing Assets ......................................................................................................................................14 4.2 Wind Scheduling ..................................................................................................................................15 4.3 Reserve Margin & Capacity Value.................................................................................................16 4.4 Pricing.......................................................................................................................................................18 5.0 Exogenous Factors ................................................................................................................... 20 5.1 Underdeveloped Transmission Infrastructure .......................................................................20 5.2 Regulation...............................................................................................................................................22 6.0 Avoided Cost............................................................................................................................... 25 6.1 Regulations on Avoided Costs........................................................................................................29 7.0 Recommendations ................................................................................................................... 35 7.1 Address asymmetry in fuel price risk allocation....................................................................35 7.2 Standardized Avoided Cost Methodologies..............................................................................35 7.3 Resource Specific Avoided Costs...................................................................................................36 7.4 Forward Capacity Markets...............................................................................................................37 7.5 Security Constraint Economic Dispatch.....................................................................................38 7.6 Increased Geographic Network .....................................................................................................39 7.7 Externalities...........................................................................................................................................41 APPENDIX........................................................................................................................................... 43 Bibliography............................................................................................................................ 44
  • 3. 3 Acknowledgements The SIPA capstone team would like to express our deep gratitude to the following subject matter experts, who provided insight and expertise that greatly assisted in the research presented in this document. John Olsen, Executive Director, Power Marketing, Westar Energy Jay Caspary, Director R&D and Special Studies, OG&E Cody VandeVelde, Supervisor, Market Resource Planning, Westar Energy Richard Cornelis, Project Manager and Economic Development, OG&E Dana Murphy, Commissioner, Oklahoma Corporation Commission David Springe,  Consumer  Counsel,  Kansas  Citizens’  Utility  Ratepayer  Board Dale Osborn, Transmissions Planning Technical Director, Midwest ISO Paul Suskie, Executive Vice President and General Counsel, Southwest Power Pool Kevin Porter, Principal, Exeter Associates Charles Smith, Executive Director, Utility Variable-Generation Integration Group Mark Alhstrom, CEO, WindLogics Jacob Sussman, CEO, OWN Energy A.J. Goulding, Professor, Columbia University and Principal, LEI Alfred Griffin, Professor, Columbia University and President, NY Green Bank Daniel Gross, Professor, Columbia University and MD, Oaktree Capital Management Jeanne Fox, Professor, Columbia University and Ex-Commissioner, NJ Board of Public Utilities
  • 4. 4 1.0 Introduction In the US, wind energy has grown rapidly in recent years. At the end of 2014, installed capacity reached 65,879 megawatts, a 145% increase since 2008.1 Much of this growth has been fueled by incentives provided at both the state and federal levels, which allow wind generation to compete with traditional generation technologies. In particular, the Production Tax Credit (PTC) offered a strong incentive by providing an inflation-adjusted per kilowatt-hour tax credit of $0.023 to wind generators for the first 10 years of generation. However, conditional expiration of the PTC began at the end of 2014. As a leading manufacturer of wind turbines, our client, GE Power & Water, would like to gain a better understanding of how utilities will evaluate wind generation in a post-PTC market. As such, GE has asked our capstone team to: 1. Identify and analyze the factors utilities consider when evaluating wind generation against other generation assets; 2. Analyze the alternative methodologies currently being used by utilities to evaluate generation assets and determine the extent to which they might be indefensible. 3. Identify and outline opportunities for GE to overcome barriers for wind generation amongst target utilities. The scope of this project was limited to investigating two vertically-integrated utilities operating in the regulated Southwest Power Pool Regional Transmission Organization – Oklahoma Gas & Electric (OG&E) and Westar Energy of Kansas. In order to achieve the objectives of this project, the capstone team conducted research on  each  utility’s  regulatory  environment  and  electric  supply  and  demand  portfolios.   In addition, the team also researched various avoided cost methodologies that are commonly used by utilities. Based on this knowledge, the team conducted a series of 1 (American Wind Energy Association, 2015)
  • 5. 5 interviews with relevant stakeholders in order to gain a deeper understanding of the decision making criteria and avoided cost methodologies being used by OG&E and Westar Energy. This included speaking with officials at both utilities as well as various subject matter experts from the power sector.2 After synthesizing and analyzing the information gathered from the desk research and interviews, the team came up with recommendations that will help GE overcome barriers to wind deployment in a post- PTC marketplace. In general, the capstone team focused on the following key areas: 1. Variability: A. Existing assets B. Wind scheduling C. Capacity margin vs. reserve margin D. Pricing 2. Exogenous factors A. Transmission B. Regulation 3. Avoided cost methodologies In this report, Section 4 and 5 describe the factors that utilities consider when evaluating wind against other generating assets, whereas Section 6 covers information gathered on avoided cost methodologies. Section 7 consists of recommendations that might help GE overcome barriers that prevent utilities from deploying wind assets in a post-PTC market. 2 A complete list of interviewees can be found in the Acknowledgements section
  • 6. 6 2.0 Executive Summary 2.1 Objective of the Project In the US, wind energy has grown rapidly in recent years. At the end of 2014, installed capacity reached 61,327 megawatts, a 145% increase since 2008. Much of this growth has been fueled by incentives provided at both the state and federal levels, which allow wind generation to compete with traditional generation technologies. In particular, the Production Tax Credit (PTC) offered a strong incentive by providing an inflation-adjusted per kilowatt-hour tax credit of $0.023 to wind generators for the first 10 years of generation. However, conditional expiration of the PTC began at the end of 2014. 1. Identify and analyze the factors utilities consider when evaluating wind generation against other generation assets; 2. Analyze the alternative methodologies currently being used by utilities to evaluate generation assets and determine the extent to which they might be indefensible. 3. Identify and outline opportunities for GE to overcome barriers for wind generation amongst target utilities. 2.2 Planning for Variability Research and interviews conducted with stakeholders at both Westar Energy and OG&E revealed that utilities regard variability and intermittency to be the most significant vulnerabilities to wind generation. The subsequent issues that utilities consider when evaluating wind against other generating technologies are as follows: 1. Existing Assets: Since wind is variable resource, other generating assets often have to be dispatched in order to fill the gap between supply and load. When planning for wind integration, utilities have to consider the dispatchability or flexibility of existing assets, and decide whether or not to increase their portfolio of traditional generation, so as to address the issues of wind
  • 7. 7 variability and intermittency. In the absence of forward capacity markets at SPP, utilities do not have sufficient incentives to add new generation assets to maintain appropriate reserve capacity in order to mitigate the variability component of wind farms. 2. Wind Scheduling: Through discussions with utilities, it was revealed that strong winds can pose a critical threat to reliability due to high wind cut out. However, further discussions with subject matter experts suggest that high wind cut out is not a significant barrier due to advances in wind forecasting, technological improvements, greater   balancing   areas,   and   SPP’s   Integrated   Marketplace. 3. Reserve Margin and Capacity Value: Utilities are required to to maintain the reserve margin standard assigned by SPP, to demonstrate resource adequacy. Since wind is variable, it is accredited a small percentage of nameplate capacity  under  SPP’s  methodology.    The  low  capacity  value  of  wind  and  its   limited  contribution  to  reserve  margin  reduce  utilities’  incentive  to  add  wind. 4. Pricing: From   a   utility’s   perspective,   limitations   associated   with   wind   predictability in the short-term put wind at a disadvantage when compared to more conventional assets. In particular this aspect of wind limits the ability of a utility to offer power in day-ahead markets. This exposes utilities to greater price risk. 2.3 Exogenous Factors In addition to considering factors related to variability and vulnerability, utilities also consider various other criteria when evaluating wind against other generating technologies. These criteria include: 1. Transmission constraints: Underdeveloped transmission infrastructure has been cited as a major deterrent of wind growth in the Plains region. However,
  • 8. 8 with SPPs creation of the Integrated Marketplace and the Highway Byway cost sharing methodology, utilities are more incentivized to rate-base these transmission projects and earn a return on their investments. Greater transmission infrastructure will help to reduce barriers to wind generation. Through interviews with stakeholders from SPP, we discovered that the component of transmission cost in the rate base is applied on an average basis to  customers  across  SPP’s  balancing  area,  irrespective  of  the  location  of  the   source and the load. 2. Regulation: Conversations with officials at both utilities and other subject matter experts in the power sector suggest that regulation has been a primary driver for the deployment of wind resources in the SPP. Specifically, the three programs that have had the greatest impact are the Renewable Portfolio Standard (RPS), PTC and Clean Power Plan (CPP). However, from the utilities perspective an uncertain regulatory environment introduces the risk of stranded assets. 2.4 Avoided Costs Utilities assess the value of electricity and capacity offered by independent power producers on the basis of avoided costs. A  utility’s assessment of avoided cost borrows from its Integrated Resource Plan (IRP). Among the factors that influence avoided costs, utilities account for projections of resource sufficiency and deficiency, fuel price projections, load growth and load shape forecasts, costs of compliance to current and expected future compliance standards, etc. Avoided costs for small power producers, those with less than 100 kW of capacity 3 , are defined by standard purchase contracts, which are vetted by state regulatory commissions. However, for qualifying facilities (QFs) that are not eligible for standard purchase agreements, the avoided costs assessment depends upon the assumptions made by the utility for its 3 Eligibility criteria varies by state
  • 9. 9 IRP. Consequently, there are a variety of methods used to estimate avoided costs, none more or less defensible than the others. On a general note, some of the common variables that feed into avoided costs are avoided costs of energy, capacity, transmission and distribution, line losses and environmental compliance, etc. 2.5 Recommendations From  a  utility’s  perspective,  greater  wind  adoption  faces several barriers in a post-PTC market. Foremost among them are issues related to variability, uncertain regulation and limitations in transmission infrastructure. Although new developments in the SPP alleviate some of these issues for OG&E and Westar Energy, other issues will persist. The following recommendations are put forward to help GE address these issues, and are based on information gleaned from desk research and stakeholder interviews. Address asymmetry in allocation of fuel price risk: Unlike traditional generating assets, such as coal and gas plants, wind generation has negligible fuel price risk. However, the Fuel Adjustment Clause (FAC) in both Oklahoma and Kansas leads to market distortions that cause utilities to overlook this critical aspect of wind generation. In order to provide a level playing field for wind generation, it would be prudent for GE to help address distortions created by the FAC. Since the FAC allocates fuel price risk to ratepayers, one way for GE to address this issue is through consumer-motivated regulation. Standardize Avoided Cost Methods: The avoided cost methodologies approved across different states are consistent with their respective policy objectives. However, there is a considerable lack of transparency with regards to these methodologies. This creates uncertainty for QF investors and limits their ability to make investments in the long term. As such, GE would benefit if FERC were to commission an evaluation of avoided costs methods used across different states, assessing their strengths and weaknesses from the perspective of small power producers.
  • 10. 10 Resource Specific Avoided Costs: A recent order by FERC on a petition filed by the California Public Utilities Commission permitted multi-tiered avoided cost calculations within a jurisdiction. Depending on the characteristics of the specific resource, such as dispatchability, intermittency, efficiency, environmental performance and location etc., the avoided cost of a QF should be calculated by comparison with an operating QF with similar characteristics. Such a comparison will determine the full extent of avoided costs. It would help equipment manufacturers like GE, as well as wind energy developers alike to engage in discussion with state regulatory commissions and advocate for resource specific avoided cost assessment. Forward Capacity Markets: SPP requires a reserve capacity margin of approximately 12 percent. However, the reserve capacity margin does not offer enough incentive to incumbent utilities to add additional conventional generation capacity beyond the reserve margin, to compensate for the intermittency induced by variable generation assets. A forward capacity market, on the lines of PJM, will offer the utilities a regular stream of revenue from capacity, and improve the system's overall reliability. With this in mind, we believe stakeholders from conventional utilities, equipment manufacturers, wind generators, consumer forums and SPP should explore the possibility of implementing a forward capacity market. Security Constrained Economic Dispatch: This is a process that takes cost and liability when optimizing a system every 5 minutes to match load. This process takes into account the whole power system with all its different types of generators and characteristics (failure modes, lack of certainty, etc.). So, When Dispatch nullifies the problems associated with cut out and other associated problems caused by variability. Therefore, we believe GE can reduce the barriers associated with variability by informing utilities that these problems can be nullified by using the tools already in place—primarily the Security Constrained Economic Dispatch. Integrated Marketplace: The expansion of the Integrated Marketplace through the growth of the SPP will reduce the variability of wind and the congestion-related
  • 11. 11 issues surrounding geographic areas highly concentrated with wind farms. The inclusion of more stakeholders, as participants in this marketplace, will further the development of high-voltage transmissions lines paid for through the Highway/Byway shared-cost methodology. This would reduce integration costs and promote further development of wind farms. Externalities: While  there  isn’t  a  carbon  pricing  system  in  the  SPP, it is expected that tighter regulation on carbon emission will eventually lead to a price on externalities caused by greenhouse gas (GHG) emission. Since the generating assets that utilities invest in today will endure for a several years into the future, it is important to ensure that the generating portfolio can meet a future tighter standard on carbon emission. Thus,  GE  could  engage  in  raising  utilities’  awareness  of the possibility of future carbon pricing, and suggest utilities to factor in a carbon price in economic analysis.
  • 12. 12 3.0 Background 3.1 Overview of utility 3.1.1 Oklahoma Gas and Electric OG&E was incorporated in 1902 in Oklahoma, and currently operates as a regulated investor-owned public utility holding company. As an energy services provider it offers physical delivery and related services for both electricity and natural gas, primarily in the south-central United States. The company conducts these activities through two business segments: (i) an electric utility and (ii) natural gas midstream operations. The electric utility segment generates, transmits, distributes and sells electric energy in Oklahoma and western Arkansas. The service area covers 30,000 square miles in Oklahoma and western Arkansas, including Oklahoma City, the largest city in Oklahoma, and Fort Smith, Arkansas.4 OG&E’s  stated  mission  is  “to fulfill its critical role in the nation's electric utility and natural gas midstream pipeline infrastructure and meet individual customers' needs for energy and related services focusing on safety, efficiency, reliability, customer service and risk management.”5 OG&E is focused on increased investment to preserve system reliability and to meet load growth by adding and maintaining infrastructure equipment and replacing aging transmission and distribution systems. OG&E expects to maintain a diverse generation portfolio while remaining environmentally responsible. Through its various initiatives, OG&E believes it may be able to defer the construction or acquisition of any incremental fossil fuel generation capacity until 2020. 6 4 (OG&E, 2014) 5 (OG&E, 2014) 6 (OG&E, 2014)
  • 13. 13 3.1.2 Westar Energy A Kansas corporation incorporated in 1924, Westar Energy, Inc. (Westar) is a vertically-integrated investor-owned utility operating in south-central and northeast Kansas. Within these two geographic areas of Kansas, Westar Energy operates as two separate companies – Kansas Gas and Electric (Westar South) and Westar Energy (Westar North). As the largest electric utility in Kansas, Westar provides electric generation, transmission and distribution services to approximately 693,000 customers in Kansas.7 Although technically comprised of two separate companies, Westar’s  entire  system  is  dispatched  as  one  system  unit, and therefore there has been a movement to consolidate electric rates with the ultimate goal of uniform rates across the two entities.8 Significant   elements   of   Westar’s   corporate   strategy   involves   maintaining   a   flexible and diverse energy supply portfolio. In doing so, Westar has made environmental upgrades to their coal-fired power plants, developed renewable generation, built and upgraded their electrical infrastructure, and developed systems and programs with regard to how their customers use energy.9 7 (Westar Energy, 2014) 8 (Kansas Corporation Commission, 2015) 9 (Westar Energy, 2013)
  • 14. 14 4.0 Planning for Variability While utilities consider various factors when evaluating wind against other generation technologies, research and interviews conducted with stakeholders at both Westar and OG&E revealed that utilities regard variability and intermittency to be the most significant vulnerabilities to wind generation. As such, variability is a key aspect that utilities factor into their decision making process, when comparing wind to traditional generation assets. This section describes the subsequent issues that utilities face due to these vulnerabilities. 4.1 Existing Assets The extent to which utilities can add new wind assets is in part determined by the dispatchability of their existing generation portfolio. Since wind is a variable resource, other generating assets often have to be dispatched in order to fill the gaps between supply and load. This issue becomes more acute in times of light load. During periods of light load, an increase in wind generation can quickly lead to a surplus of power in the market. In such situations utilities are forced to curtail generation from other assets, as wind  generation’s low variable cost allows it to be dispatched before other baseload assets in the bid stack. Those utilities with a portfolio of assets with a low dispatchability find it more difficult to integrate wind. Broadly speaking, utilities that have a greater percentage of gas generation are better off, since gas turbines are highly dispatchable, or flexible to changing load conditions. Conversely, those utilities with predominantly nuclear or coal assets find it more difficult to integrate wind as these assets are less flexible. When planning for wind integration, utilities have to consider whether or not to also increase their portfolio of traditional generation, so as to address the issues of wind variability and intermittency. For instance, the resource planning department of Westar mentioned that it had to invest in 600MW of gas turbines to offset an anticipated increase in wind generation. Of the 600MW, 150MW consisted of aero- derivative turbines, which have very high dispatchability. These variable backup
  • 15. 15 generators amount to additional costs for the utility. Thus, wind variability and intermittency  with  regards  to  the  existing  portfolio  of  a  utility’s  generating  assets  can   present a barrier to adding wind generation. 4.2 Wind Scheduling Variability is not just a problem when wind speeds drop to low levels. In a discussion with a former director of resource planning at one utility, he described a situation where strong winds, not light or even no wind scenarios, pose the biggest threat to operators. He informed us that at 8 mph, wind turbines begin to produce power; at 20 mph, they achieve maximum output; but between 40 and 55 mph turbines hit their cut out point. For an operator, this scenario threatens the reliability of a utility to meet demand. If a wind farm is running at full output and then shuts off due to high wind, the utility will have to immediately make up for the shortfall. From the point of view of a director of resource planning, strong winds can pose a critical threat to a  utility’s  reliability. However, other subject matter experts undermined the threat of high wind cut out. It was pointed out that high wind cut out is only associated with high intensity storms that result from wind speeds in excess of 55 mph. In most cases, utilities can predict storms of this magnitude well in advance, allowing them adequate time to prepare their supply needs. Furthermore, high wind cut out typically impacts only a small fraction of wind turbines in a wind generation facility, and as soon as the wind dies down, the turbines start generating again. With current technology and modeling, wind scheduling is capable of significantly lowering the risk that a cut out scenario poses to an operator. By utilizing wind-scheduling technology, operators can plan for a cut out scenario, in some cases up to 48 hours before a weather system hits its region. Finally, new turbine technology, which can mitigate the risk posed by high winds, and the creation of the Integrated Marketplace in SPP, raises further questions as to whether high wind cut out is a serious issue for utilities.
  • 16. 16 4.3 Reserve Margin & Capacity Value In order to ensure grid reliability, utilities have to demonstrate that they have enough installed capacity to meet peak load requirements. SPP ensures resource capacity by mandating that each utility in its jurisdiction maintain a reserve margin of at least 13.6%. As such, utilities need to accredit the capacity value of all their generating assets, making sure that they adhere to this standard in their resource planning. Due to the variability of wind, the capacity value that is assigned to wind generators is a smaller fraction of nameplate capacity than that associated with other generation technologies. From the point of view of a utility, the low capacity value of wind imposes a barrier to developing wind generation, because wind only makes a limited contribution to reserve margin, compared with traditional generating assets. Thus, when considering alternative generation technologies with regards to meeting capacity requirements, utilities are more likely to choose technologies that have a higher accreditation value. The variability associated with wind also results in greater subjectivity in the accreditation process. As such, each region may choose to adopt its own methodology and assumptions when accrediting wind farms, giving wind varying degrees of capacity value. Proponents of wind have longstanding concerns that the SPP deters wind development by assigning a particularly low value to wind. Based on 2011 EIA estimate of wind profiles, within NERC regions, the wind capacity value in SPP was 8.2%. Only the Midwest ISO MRO had a lower value of 8%.10 One reason that SPP assigns a low capacity value to wind is that wind speed is negatively correlated with load in this region.11 However, in cases where output from wind generators closely correlates with load, wind generation assets might be 10 (EIA, 2011) 11 (Southwest Power Pool Generation Working Group , 2004)
  • 17. 17 assigned a higher capacity credit. 12 Furthermore, SPP is revising its wind accreditation methodology this year. The new methodology is expected to improve wind capacity value to 12.1%.13 From  a  utility’s  perspective,  this increased capacity credit is likely to reduce barriers associated with wind generation. Originally in 2004, the SPP Generation Working Group (GWG) developed a statistical-based method to accredit capacity value of wind. It first examined the highest 10% of load hours in a month, and ranked wind generation during these hours from high to low. The value that exceeded 85% of these values was used as the wind capacity value. When possible, the methodology takes 10 years of data into account.14 In   April   2014,   Mitchell   Williams,   of   Western   Farmers   Electric   Cooperative’s   Generation Working Group, proposed a revision of the wind accreditation. This revised version is more favorable to wind for the following reasons: 1. It reduces data requirements from 10% load hours to 3%. 2. It reduces confidence interval from 85% to 60%. 3. It accepts 5% capacity for a new project instead of 3% for up to 3 years.15 In   June   2014,   SPP’s   Cost   Allocation   Working   Group   decided   to   maintain   this   proposed revision, and planned to pay close attention to future reports on the performance of wind assets. 16 Not only is wind accreditation becoming more favorable to wind development, but also utilities in SPP are expecting to see more relaxed reserve margin standards. These standards will also favor wind in an indirect manner, since they place fewer requirements on utilities in terms of increasing capacity value of generating assets. 12 (Milligan & Porter, 2006) 13 (Argus, 2015) 14 (Milligan & Porter, 2006) 15 (Southwest Power Pool CAWG, 2014) 16 (Southwest Power Pool CAWG, 2014)
  • 18. 18 Considering that approximately $1 billion could be saved over a 30-year period for every 1% reduction in the reserve margin, SPP formed the Capacity Margin Task Force to research the potential of reducing capacity margin or reserve margin while still ensuring the same level of reliability.17 Due to the high potential for conserving capital, refining reserve margin  is  currently  one  of  SPP’s  highest  stated   priorities.18 4.4 Pricing Utilities claim that variability and intermittency can significantly increase price volatility in energy markets. Although wind forecasts can provide reliable estimates of generation over long periods of time, such as on a monthly or annual basis, they are inaccurate over shorter   periods.   From   a   utility’s   perspective,   limitations associated with wind predictability in the short-term put wind at a disadvantage when compared to more conventional assets, such as gas turbines, which are predictable and far more dispatchable. When a utility seeks to offer its generated power into the marketplace, it has two channels: through the day-ahead markets, or in the real-time markets. In the day- ahead market, a utility determines the price and quantity at which it will offer its power the following day. The day-ahead market in the SPP is scheduled in five-minute increments. Consequently, each day consists of a total of 288 price points. Furthermore, the utility can provide up to 10 discrete prices for each five-minute increment, depending on the heat rate, which in turn depends on how much of an asset is bid into the market. By contracting in the day-ahead market, a utility gains price-assurance; however, the quantity of power that the market purchases is dependent on the bid 17 (Nickell, 2014) 18 (Nickell, 2014)
  • 19. 19 stack, which in turn depends on two variables: load and price competition. Conversely, real-time market prices vary based on demand and supply, and thus, a utility can only determine the quantity it is willing to offer for the real-time price. Due to the short-term variability and intermittency associated with wind assets, the ability of a utility to offer wind in the day-ahead market is compromised. It is all but impossible for a utility to determine the power generation of a wind asset during a certain five-minute increment the following day. Utilities have limited choice but to offer a large portion of their wind power in real-time markets. This increases price risk. Furthermore, in geographies that are highly concentrated with wind turbines, such as in the southwest of Kansas, the market experiences increased price volatility. When wind is available, all the wind turbines in a given area produce power, leading to a surplus of power in the real-time market. This surplus causes prices to drop. As such, the extent of the change in price is determined by the capacity of wind assets in that area. With continued wind development in an already highly concentrated area, price volatility persists. The issue of price volatility due to wind variability is further complicated by the market distortions caused by the PTC. Wind generators who can avail the PTC can occasionally offer power into the market at negative prices. Consequently, utilities that are contemplating the addition of wind assets after the expiration of the PTC are at a distinct disadvantage, since it would be impossible for them to compete with generators that have negative marginal costs. This is one of the reasons why wind deployment has plummeted in the post-PTC market. The issue of price volatility can be somewhat mitigated through the use of balancing areas and robust transmission infrastructure. There is potential to benefit from economies of scale if several balancing areas develop cooperative arrangements or markets for ancillary services, as SPP has created through the Integrated Marketplace.
  • 20. 20 5.0 Exogenous Factors 5.1 Underdeveloped Transmission Infrastructure Through conversations with participants in the Integrated Marketplace, the need to rehabilitate and build new transmission infrastructure has been cited as a major deterrent of wind growth in the Plains region. Aging infrastructure, unable to handle the supply variations of wind along with a sparse transmissions network in wind-abundant areas are believed to be major sources of resistance for wind development. One explanation for lackluster infrastructure development is historically low load growth. Yet, in recent years, population growth in Oklahoma’s  two  largest  cities,   Oklahoma City and Tulsa, has caused electricity demand to increase. This influx of population is changing demographics in the OG&E service area. As such, customers are demanding more clean energy options, in particularly wind options, as part of their electricity fuel make-up. These demands are forcing OG&E and other utilities to make preparatory infrastructure investments. Prior to 2014, transmission projects in the SPP region were implemented on a utility-by-utility basis. However, the creation of the Integrated Marketplace has given utilities a new incentive to implement transmission renovation projects. The “Highway/Byway”  cost  sharing  methodology  assigns  costs  regionally  and  locally  to   those  benefiting  most  from  the  project.  “Highways”  are  high-voltage transmission lines   above   300   kV,   while   “Byways”   are   lower-voltage (300 kv and below) transmission lines. Costs are assigned to electric utilities across the entire SPP footprint  based  on  their  historic  use  of  the  region’s  transmission  system.  The  SPP  uses   a formula to assign costs more directly to the utility in whose service territory (zone)
  • 21. 21 the project is located. The chart below outlines the breakdown of the Highway/Byway method.19 Voltage Paid for by Region Paid for by Local Zone “Electricity  Highways” (300 kV and above) 100% 0% “Electricity  Byways” (100 kV to 300 kV) 33% 67% “Electricity  Byways” (100 kV and below) 0% 100% The Highway/Byway method significantly reduces the amount of capital required for transmission projects. Utilities are incentivized to expand their transmissions infrastructure through incorporation into their rate-base in order to earn an annual return. The new system also increases the overall reliability of the grid by improving the efficiency by which electricity flows throughout the RTO. The combination of these changes in the SPP has led to an increase in completed transmission projects, totaling $8 billion in 10 years, and solving the apparent vulnerability of transmission development. One recent success of the Highway/Byway is the Prairie Wind Transmission Project. In 2014, Westar completed the Prairie Wind Transmission Project to build 108 miles of extra-high-voltage 345 kV transmission lines. The project links an existing 345-kV substation near Wichita, Kansas to a new 345-kV substation northeast of Medicine Lodge, Kansas near the Flat Ridge I Wind Farm, and then south to the Kansas/Oklahoma border. This project will support future generation assets joining the grid in the region.20 Stakeholder interviews suggest that had the ability to share transmission costs been created in earlier, utilities would likely have avoided issues related to curtailment payments. For instance, OG&E may have avoided a $4.3 million 19 (Pennel, 2010) 20 (Westar Energy, 2014)
  • 22. 22 settlement with wind developer Competitive Power Ventures, surrounding a disagreement on curtailment payments caused by unreliable transmissions lines. In August 2013, the wind developer filed a lawsuit against OG&E claiming the utility failed to pay curtailment charges when their Keenan wind farm was in operation but transmission issues limited it from supplying electricity onto the grid. The two parties settled for $4.3 million and OG&E plans to recover this cost through a fuel adjustment clause, transferring the burden of the faulty transmission system onto its rate-payers. Underdeveloped transmission infrastructure might have been a deterrent of wind in the past, but recent innovations such as the Highway/Byway and the Integrated Marketplace have brought solutions to all stakeholders within the SPP territory. 21 5.2 Regulation Conversations with both utilities and other subject matter experts in the power sector provide consensus that regulation has been a primary driver for the deployment of wind resources in the SPP. First, both OG&E and Westar were forced to comply with the Renewable Portfolio Standards (RPS) in their respective states. Second, the Production Tax Credit (PTC) offered a significant incentive for deploying wind assets by improving wind economics. Finally, the Clean Power Plan is forcing both utilities to rethink their resource planning objectives for the coming years. Meanwhile, uncertainty surrounding future policy legislation introduces a certain amount of risk. For instance, if a utility takes on additional wind assets in order to comply with legislation, and the legislation is later repealed, the utility runs the risk of creating stranded assets. The following sections elaborate on these aspects of regulation and their impact on wind generation. 21 (Monies, 2015)
  • 23. 23 5.2.1 Renewable Portfolio Standard (RPS) Officials at both OG&E and Westar confirmed that the RPS was a primary driving force behind wind adoption in their respective states. In May 2010, the Oklahoma Legislature set a suggested RPS goal that 15% of total installed generation capacity be derived from renewable sources. There are no interim targets and the goal is not extending past 2015.22 This RPS standard in Oklahoma is not a mandatory regulation, but only a call for voluntary compliance. As it stands, wind capacity at OG&E accounts for about 12% of generation capacity.23 In Kansas, the RPS was established in 2009, aiming for 15% by 2015-2019, and 20% by 2020.24 Due  to  Kansas’  low load growth, as well as additional purchased wind energy, Westar has achieved its 2020 RPS target of 20%. Although Westar has technically met its RPS goals until 2020, the utility continues to weigh the economic advantages of adding wind generation now with the PTC or possibly in the future should wind generation technology continue to become more cost competitive. An uncertain regulatory environment exacerbates the risk of adding wind. For example, in a conversation with the resource planning team at Westar Energy, the concern for creating stranded assets was communicated. However, should the utility wait until the regulatory environment is certain, then the utility will likely face higher charges as greater demand for wind assets will increase the price at which developers provide wind assets. With that said, a   utility’s ability to rate-base assets offers them greater incentive to expand their wind portfolio, as any investment costs approved by state regulators are able to be recovered. If utilities are forced to bear an unfair higher cost because of a sudden change in state legislation, it has been suggested that utilities will have a strong legal case for reparations. 22 (National Conference of State Legislatures, 2015) 23 (OG&E, 2014) 24 (OG&E, 2014)
  • 24. 24 5.2.2 Clean Power Plan In 2014, the EPA proposed emissions guidelines for states to reduce GHG emissions from tradition, fossil-fuel generation plants. Although the proposal has yet to be enacted, the CPP has the potential to significantly impact utilities throughout the SPP. Insight gained from experts in the SPP and MISO suggest that the most significant impact of the CPP will manifest through a conversion from traditional coal generating units to more flexible, cheaper natural gas ones. For OG&E and Westar, this means converting around 50% of coal assets to natural gas. The utility-by-utility reaction to this will vary; it has been observed that some utilities are willing to make slightly larger investments to lock-in longer-term contracts for their clean assets. In the short-run, the current industry consensus is that the transition to natural gas plants will expand wind and solar markets by determining the shadow price for carbon in the market. Stakeholders believe that studies to analyze the impact of the CPP are underestimating how much wind will be installed over the next few years. Even with this favorable future, this conversion is still highly vulnerable to policies that state regulatory authorities will enact to either facilitate or add resistance to this process.
  • 25. 25 6.0 Avoided Cost FERC’s   enactment   of   PURPA   left the calculation of avoided costs open to interpretation, and there are several methodologies used by state utility commissions across  the  US.  Developers  are  often  unable  to  fully  capitalize  on  PURPA’s  benefits,  due   to complexity of avoided cost ratemaking at the state level. Under the constraints of maintaining consistency and reliability of electricity supply, and due to the multitude of sources used for energy production, the calculation of avoided costs is invariably complicated. Added to the complexity of avoided costs is the necessity of confidentiality. Since utilities need to compete in the open market for goods and services, the respective inputs to avoided costs and the price points need to be masked from potential vendors, otherwise the bids will naturally gravitate towards the highest bid, thus setting an artificial floor and forcing other utilities to meet this price point. In our attempt to understand how OG&E and Westar Energy calculate avoided cost, the capstone team first conducted general desk research on the most commonly used avoided cost methodologies in the sector. This information was helpful in guiding our conversations with officials at both utilities. That said, although the team was able to get a general sense of how the target utilities approach avoided cost, we were unable to get specific information for the reasons stated above. Availability of information on avoided costs methodologies varies among states. While information on avoided cost for some states might be more easily accessible in public records, reliable information is not available for most states25. To the extent possible, we collected information from publically available information, such as testimonies in utility case filings, news reports, and rate case proceedings. 25 18 CFR § 292.302 requires utilities to submit data from which avoided costs were calculated to the state regulatory commissions every two years.
  • 26. 26 From testimonies and interviews of personnel from OG&E and public records at the Oklahoma Corporation Commission, the following information gives some insight into  OG&E’s  avoided  cost  calculation  methodology.  OG&E’s  decision  making  on  QF   power purchases are based on their forecasts from a production cost model, for which they  use  Power  Cost  Inc.’s  GenTrader  software.26 The following are some of the key components  of  OG&E’s  avoided  cost  methodology: 1. OG&E’s  avoided  cost  calculation  includes purchases of wholesale energy that would be purchased in the absence of purchase from the wind farms. 2. Due to the establishment of regional transmission operator, Southwest Power Pool,  all  wind  QF’s  have  non-discriminatory access to the grid. Hence the QF’s   bid into the integrated marketplace. 3. In the regional SPP market, the hourly costs are calculated at specific nodes. This implies that at a given point of time, there are several avoided costs for each utility. 4. The avoided capacity cost calculation is based on the assumption that OG&E's next incremental capacity need would be fulfilled with a combustion turbine (peaking capacity). OG&E assumes avoided capacity cost to be zero in years it does not need an additional capacity to maintain the minimum required capacity margin of 12% specified in section 2.1.9 of the SPP criteria. OG&E's avoided cost calculation do not include any forecasts of capacity prices in the region. Moreover, OG&E does not include any costs with compliance with present or future environmental regulations in avoided capacity cost calculations, as environmental regulations are geared towards the preservation of existing capacity, and not the incremental need. 26 Docket No. 07-075-TF
  • 27. 27 5. Planned shutdowns, retirements, and retrofits of existing fossil fuel generating facilities are usually included in the production cost analysis used to calculate avoided costs. For instance, the O&M costs associated with retrofitting coal and gas units with Low NOX burners was included in the production cost model, and used to calculate the avoided energy costs. 6. OG&E includes the need and timing of future capacity needs to determine avoided capacity costs, which takes inputs from planned shutdowns, retrofits, and retirements. 7. Average line losses, and not marginal, are included in forecasting annual load, which is then used to determine the forecasted reserve margin and energy equivalents  for  each  year.  Generation  used  to  fulfil  OG&E’s  reserve  margin  is   also included in the production cost analysis, and hence is an input for avoided cost calculation 8. The production cost model also includes the assumption that OG&E will comply with regional haze regulations in the manner specified in the Oklahoma State Implementation Plan (SIP). The EPA rejected Oklahoma's SIP and imposed a Federal Implementation Plan (FIP) on Oklahoma and OG&E. The FIP would require OG&E to install very costly scrubbers on some of its coal fired generators. The order has been challenged in 10th Circuit Court of Appeals. There is some uncertainty about the requirements and costs associated with Regional Haze and other environmental rules at the moment. 9. In addition to factors such as environmental compliance, reserve margins, line losses, planned shutdowns, retrofits and retirements, the production cost model is sensitive to natural gas price forecasts. OG&E does not assume any transmission constraints in its avoided cost analysis.
  • 28. 28 From this information we can infer that  OG&E’s  assessment  of  long-term avoided costs depends on the assumptions in their IRP, such as projections of fuel prices, load growth forecasts and diurnal as well as seasonal load shape projections, planned shutdowns, retirements and retrofits of existing generation assets, timing and type of planned capacity additions, etc. With respect to resource sufficiency, OG&E does not consider avoided capacity costs beyond the reserve margin of 12% as determined by SPP, and avoided energy costs are calculated on the basis of the cost of service incurred by OG&E to generate the power themselves from their existing generation assets. If the resource planning considers periods of resource deficiency, the avoided capacity payments are determined by referring to a proxy combustion turbine generation unit (discussed below), and avoided energy costs are indicated by the wholesale market price that OG&E might incur for purchasing the power from the integrated marketplace. However, the above information has been obtained through secondary   sources,   and   might   be   dated.     Insight   into   Westar’s   avoided   cost   methodology was briefly  shared  during  a  conversation  with  officials  from  Westar’s   Market Resource Planning department. The highlights of the conversation are outlined below: To determine whether a project is cost-competitive to traditional assets, the team first uses a quantitative-based model, created by a third-party, and enters hour- by-hour factors such as fuel price curves, load growth, and other operating parameters. This initial model helps the team determine the optimal way to best serve the load. Based on the potential wind generation from a wind farm, the cost of the wind farm is compared with the cost generated from the model. The analysis looks at 100% operation of the wind farms along with complimentary generation from other assets. After comparing the combined system, a break-even price is determined that establishes the basis of the economic competitiveness of the wind farm. Additional costs such as transmission and congestion costs are factored into the process after generating the base price. The combination of these various costs create an avoided cost necessary to beat to purchase the wind asset.
  • 29. 29 6.1 Regulations on Avoided Costs The rationale behind PURPA is to balance the interests of independent power producers,  customers,  and  utilities.  IPP’s  lacks  the  market  power  to  compete  in  the   open market with long established utilities. Customers need to be protected from overpriced electricity tariffs, and utilities need to keep into consideration the reliability and quality of power supply, air quality standards and their guaranteed rate of return. The nature of transaction between utilities and IPPs, termed as Qualifying   Facilities   (QF’s),   are   determined   by   the   avoided costs. PURPA defines avoided   costs   as   the   “incremental costs to an electric utility for electric energy or capacity or both, but for the purchase from the qualifying facility or qualifying facilities, such utility would generate itself or purchase from another source”   (Section   210,   PURPA, 1978). Despite  the  mention  of  “incremental  costs”,  avoided  costs  differ  from  marginal   costs. Marginal costs do not consider the size of the load over which changes in costs are measured. Avoided Costs, on the other hand, require explicit consideration of the change in costs associated with a finite change in the load, hence depending on both timing as well as magnitude of the load changes. The incremental costs act as the price ceilings, so that the consumer is largely indifferent to the source from which the power is being delivered to them. Among the various inputs that are considered in calculation of avoided costs, the following find application in most methods: 1. Avoided purchase of energy 2. Avoided purchase of resources, such as natural gas, coal, oil etc. (and the cost of storing and transportation of the resources) 3. Avoided transmission line costs, including construction, maintenance and line losses 4. Avoided cost of maintenance, retrofit, and replacement, as determined by the utility’s  integrated  resource  planning
  • 30. 30 5. Avoided cost of compliance with current and expected environmental regulations 6. Avoided cost of externalities, such as health costs, benefits from improved air quality and visibility, less noise pollution, etc. 7. Avoided  RPS  costs  (for  clean  energy  QF’s) 8. Avoided property taxes Apart  from  the  above  mentioned  inputs,  the  utility’s  decision  making  finally  rests   upon their resource planning, future load forecasts, and the quality of the QF power supply.  FERC’s  regulations list the following qualitative factors which states should consider  while  evaluating  bids  by  QF’s:   1. The ability of the utility to dispatch the QF 2. The expected and demonstrated reliability of the QF 3. The duration of the contract 4. The extent of coordination  between  the  QF  and  utility’s  planned  /  unplanned   outages 5. Costs and savings from changes in line losses as a result of QF purchases 6. The relationship of the availability of energy or capacity from the QF to the ability of the electric utility to avoid costs, including deferral of capacity additions and reduction in fossil fuel use. 6.3 Methodologies: Surveys of avoided cost calculation methodologies have documented a variety of methods being used across different states in the US 27 . The methods vary by complexity, Proxy unit: The proxy unit method assumes that the QF enables the utility to defer a future generation unit; and the avoided costs are hence the projected energy and capacity 27 (Porter, Fink, Buckley, Rogers, & Hodge, 2013)
  • 31. 31 costs of the specified proxy unit, which is usually a combustion turbine power generation asset. The capacity costs are the fixed costs of the proxy unit, and the estimated variable costs are used to calculate avoided energy costs. Factors such as debt financing, tax burdens, equity costs, etc. are considered in calculate avoided capacity costs.  The  choice  of  proxy  unit  may  either  be  in  accordance  to  the  utility’s  IRP  in  terms   of the timing that the proxy unit comes online, capacity and type of technology, or it may be a hypothetical unit as determined by the state utility commission. The avoided cost hence calculated depends on the type of proxy unit selected. Choosing a higher cost base load plant as proxy will result in higher avoided cost, and a lower cost combustion turbine will have lower avoided cost. Although this method lacks sound scientific basis, it is most widely used across different states in the US, because of its simplicity. Peaker Method: In a Peaker method of calculating avoided costs, it is assumed that the power supplied by the QF reduced the marginal generation requirement of the utility, and hence avoids the construction of a peaking plant. The cost if the energy component is based on marginal costs over the life of the contract, calculated on an hourly or longer period, as opposed to the next planned units as in the case of proxy unit method. The production cost simulation of marginal costs with and without the QF yields the difference between the two scenarios, which is the avoided energy cost. The capacity component is of avoided cost is based on the annual equivalent of  utility’s  least  cost  capacity  option  (pealing  unit),  which  is  typically  a  combustion   turbine. Since these generation assets have less upfront capital requirement, they minimize the avoided capacity costs, whereas the generation costs are high, as they are assessed in a marginal generation basis. The argument in favor of this method is
  • 32. 32 that the sum of lower capacity costs and higher (marginal) energy costs is equivalent to the higher capacity cost and lower fuel costs of a base load. Since the capacity component of the contract is availed by the utility only when required, this method assumes that the QF will recover its investment only through energy component, whose payments vary by the hour. In case of intermittent technologies, the payments for energy component is not only dependent on the hourly load profile, but the resource availability as well. A recent petition at Georgia Public Service Commission28 about this limitation of the peaker method prompted the commission to modify the avoided cost calculation formula, with inclusion of avoided costs of environmental compliance, and avoided start-up costs. Differential revenue requirement (DRR) The  QF  capacity  reduces  the  utility’s  revenue  requirement.  The  present  value   of  the  difference  between  the  utility’s  revenue  requirement  in  the  two  scenarios  of   IRP, with and without QF capacity, represents the avoided cost. While DRR method utilizes sophisticated modeling and forecasting technologies in projecting the revenue requirement with and without QF output, the IRP is sensitive to inputs considered by the utility, such as fuel price forecasts and load forecasts. DRR assumes   that   the   QF’s   are   perpetually   marginal   resources,   and   is   suitable only for short-term avoided cost calculation. Moreover, DRR method suffers from a lack of transparency. Market based pricing PURPA was amended in 2005, authorizing FERC to grant an exception from mandatory obligation for purchase of QF power, if the QF has a non-discriminatory access to competitive markets and open access to the transmission system provided by the regional transmission operator. Lower natural gas prices and increased 28 (Georgia Public Service Commission, 2004)
  • 33. 33 competition in the wholesale markets, including competitive bidding as a way to set avoided costs in some jurisdictions, has reduced avoided cost payments to renewable generation  QF’s,  and  is  applicable  only  for  short  term  planning.    Some  jurisdictions apply locational marginal price (LMP) as determined at the integrated marketplace as  the  avoided  energy  cost.  However,  the  use  of  current  or  even  historical  LMP’s  does   not allow the QF to estimate the future prices, due to variability in load shape, and because   there   are   multiple   avoided   costs   (LMP’s)   at   any   given   point   of   time,   depending upon the location of the node at which the cost is measured. The lack of long   term   price   projections   makes   the   returns   on   investment   by   the   QF   owner’s   uncertain, and acts as a barrier towards promotion of small power producers. Moreover,  LMP’s  do  not  reflect  the  full  cost  of  owning  and  operating  the  generation   facility, more specifically, the costs related to long term planning, costs of transmission line losses, costs of maintaining reserves, etc., and hence offer an undervalued estimate of the avoided costs. Competitive bidding In some states, after determining the power needs based on the IRP, utilities establish   benchmark   prices   and   allow   QF’s   to   bid   to   meet   the   benchmark. The winning bids reflect the cost at which the utility would have procured power, and are regarded  as  the  utility’s  avoided  costs.   The benchmark prices set by the utilities depends on the forecasts of load and fuel prices, resource mix as determined by the utility, term of the contract between winning bidder and the utility and future policy projections. Theoretically, competitive bidding rewards the QF with most efficient power generation. However, in an open market, it places renewable energy generation facilities, especially those with higher capacity, at a disadvantage. All of the above-described avoided cost methodologies have their own merits as well as merits, and none of them can yield most accurate avoided cost estimates.
  • 34. 34 Utilities have a broad discretion over many of the assumptions that go into calculation of avoided costs. The choice of a specific method for avoided cost calculation in a state is generally dictated by the policy objective, such as to promote small power producers, incentivize particular technology, environmental considerations, maintaining  ratepayer  neutrality  or  spreading  the  risks  of  QF  contracts  between  QF’s   and ratepayers non-discriminately29. Apart from the these calculation methodologies, states are required to maintain  standard  purchase  contracts  for  purchase  of  QF’s  of  capacity  100  kW  or  less.   In standard contracts, either the state commission establishes methodology for calculation of avoided costs, or utilities propose both rates as well as methodologies before the  state  commission.  Some  states  have  allowed  standard  contracts  for  QF’s  of   higher capacity as well. For example, California allows standard contracts for facilities of maximum capacity 20 MW, and Utah, Montana and Oregon make standard contracts available for facilities of 10 MW capacity. Standard contracts would lend certainty to the business of power generation from the perspective of the QF, and enable them to plan for future investments. 29 (Elefant, 2011)
  • 35. 35 7.0 Recommendations 7.1 Address asymmetry in fuel price risk allocation Unlike traditional generating assets, such as coal and gas plants, wind generation has almost no fuel price risk. However, the Fuel Adjustment Clause (FAC) in both Kansas and Oklahoma leads to market distortions that cause utilities to overlook this critical aspect of wind generation when evaluating it against traditional generating technologies. Both Westar and OG&E are subject to the FAC. This is a mechanism that permits jurisdictional utilities to regularly adjust the price of electricity to reflect fluctuations in the cost of fuel, or purchased power, used to supply that electricity. By allowing utilities to reflect fluctuations in fuel prices in electricity rates, the FAC insulates utilities from changes in the price of fuel. Both Westar and OG&E pass the risk of fuel price volatility straight through to their ratepayers through the FAC. Consequently, when evaluating wind generation against traditional generation these utilities do not factor in the benefit of mitigating fuel price risk. The FAC encourages the use of fuel intensive technologies over renewables since fuel price volatility is passed through to the ratepayers. In order to provide a level playing field for wind generation, it would be prudent for GE to help address the distortions created by the FAC. One way for GE to accomplish this goal is to facilitate consumer-motivated regulation. 7.2 Standardized Avoided Cost Methodologies The  guidelines  for  compensation  to  QF’s  as  defined  by  PURPA  allow  the  states   to choose methods that are consistent with their policy objectives. Consequently, the choice made by the states has significant implications on the prospects of alternative generation technologies within their jurisdictions. However, the inputs that constitute the models for estimation of avoided costs are not transparent, and hence
  • 36. 36 the methods are heterogeneous between, and sometimes within states. In such a situation, there is a lack of support for long term investment planning on part of the QF’s.    In  order  to  introduce  certainty,  an  authority  such  as  FERC,  with  the  mandate  of   ensuring   national   electricity   reliability   and   quality   along   with   PURPA’s   goal   of   encouraging alternative power producers, should conduct an evaluation of avoided cost methodologies used across different states and quantify the merits and demerits thereof. Such an evaluation will be useful in helping states choose the appropriate methods for measuring avoided costs. Moreover, with the consolidation of multiple jurisdictions under integrated market places, standardization of avoided cost calculation methods will lend efficiency to the power market. Standardization of avoided costs can be approached to some extent by utilizing   PURPA’s   mandate   guaranteed   purchase   of   power   from   small   power   producers. Although PURPA specifies the upper limit of such small power producers at 100 kW, some states have increased this limit to include higher capacity independent power producers to be eligible for standard purchase contracts, which are vetted by the respective state regulatory commission, and provide relatively long term certainty to small power producers. The standard purchase contracts in Oklahoma are however fixed at 100  kW,  whereas  California  allows  for  QF’s  up  to  20   MW to be eligible for standard purchase contracts. Similar figures were not available for   Kansas.   The   recommendation   of   increasing   the   eligibility   criteria   of   QF’s   for   standard purchase contracts can be taken up with the state regulatory commissions, in the interest of encouraging small power producers. 7.3 Resource Specific Avoided Costs Some of the methods of estimating avoided costs discussed above compare the QF to a different generation asset, from which the utility might have purchased or generated power in absence of the QF. These assets, categorized as proxies, surrogates, or peakers, depending upon the method used, are usually either least cost capacity additions or marginal units that use natural gas. The avoided cost estimates
  • 37. 37 resulting from comparisons of these units with wind farms do not reflect the full extent of the avoided costs. Comparisons, if any, should be made between units with similar supply characteristics. In a recent order on California Public Utility Commission’s   petition 30 , FERC determined that multi-tiered avoided cost rate structure can be deemed consistent with PURPA’s  requirements.  This  implies  that   variables specific to a QF, such as capacity, reliability, availability, efficiency, environmental   performance,   and   fuel   resource   used   can   differentiate   the   QF’s   avoided   cost   from   other   generation   assets’   avoided   Allowing flexibility in pricing mechanism will allow to include factors such as benefits of long-term contracts between utility and QF, location of the QF, and external benefits such as creation of employment opportunities and less reliance on local natural resources. Effectively, the avoided cost for a wind energy QF should be compared to the costs of an existing wind farm, including the non O&M components of the cost. 7.4 Forward Capacity Markets An argument against addition of more renewable generation to the portfolio has been the low capacity value that these assets offer, and hence the negative impacts from a resource adequacy perspective. Moreover, incentives offered to renewable generation, such as RPS and PTC for wind can sometimes lead to negative clearing price in the integrated marketplace, and hence impair the ability of conventional generation plants to recover their costs through the energy market alone. This might force some of them to early retirement, hence adversely impacting the resource adequacy of the power market. The Southwest Power Pool maintains the resource adequacy through a capacity reserve margin, which is fixed at 12%. The capacity margin can be met either by a particular utility on a standalone basis, or through a reserve sharing pool.31 30 (FERC, 2010) 31 (Southwest Power Pool, 2011)
  • 38. 38 However, the capacity margin alone does not incentivize the generation utilities to add more plants to their existing portfolio, as the capacity value in itself is not monetized. A forward capacity market, such as that at PJM32, will help to maintain resource adequacy on a forward basis for a defined period of time (three years in PJM’s  Reliability  Pricing  Model),  by  providing  incentive  to  procure  capacity  for  a  long   term. Forward capacity markets will offer an additional stream of revenues to conventional generation assets, reflecting the value of their reliability, and hence will improve their financial performance by offering stable prices for an extended period of time. Stakeholders from equipment manufacturers (such as GE), variable power generators, conventional utilities and SPP should explore the possibility of implementing a forward capacity market. 7.5 Security Constraint Economic Dispatch High  wind  speed  cut  out  came  to  our  team’s  attention  during  a  conversation   with a former director of resource planning. Accordingly, we identified high winds as a barrier for wind power generation. Mark Ahlstrom of Wind Logics proposed two recommendations for rectifying the problem of high wind speed cut out. As noted before, in a high wind scenario, to prevent damage to the equipment, an operator will need to shut it down or feather the blades. Besides wind scheduling that will give operators a reasonable amount of time to plan for a scenario of high wind (50-60 mph), Mark discussed how there are turbines in the market with the technology that can change the forecast of uncertainty. New Turbines will back off even before they get to that cut off point. With the new technology, individual blades can be turned to take in less energy and protect it. As our  recommendation  to  GE,  Mark’s  experience  and  work  with  an  optimizing   tool that already is being used by SPP is instructive. In his experience, the cut out problem   is   mostly   a   problem   for   people   who   don’t   really   think   about   the   larger  
  • 39. 39 system but only think about it as a single wind turbine problem. To integrate wind into the market, it should be forecasted as well as it possibly can; and the forecast should go in the overall system operational plans, the data unit commitment, and the real time dispatch of all units in the system. But most importantly, cut off as well as the other problems associated with wind power go away when using a process called Security Constraint Economic Dispatch, a process that takes cost and liability when optimizing a system every 5 minutes to match load. This process takes into account the whole power system with all its different types of generators and characteristics (failure modes, lack certainty, etc). So when it is integrated in the system, the process of Security Constraint Economic Dispatch really nullifies the problems associated with cut out and other associated problems caused by variability. Therefore, we believe GE can reduce the barriers associated with variability by informing utilities that these problems can be nullified by using the tools already in place—primarily the Security Constraint Economic Dispatch. 7.6 Increased Geographic Network Recently planned changes to the Southwest Power Pool have opened new doors for wind growth. One area where the team sees opportunity for GE deals with future transmission investments and the expansion of the SPP. In 2014, the Upper Great Plains Region of the Western Area Power Administration was approved to join the regional transmission organization. This inclusion would stretch   the   SPP’s   footprint to the Canadian border. We see this as highly beneficial to future wind growth because of the correlation between its future boundary and the abundance of wind  resources  in  the  Plains  region  as  well  as  SPP’s  goals  to  develop  its  connected energy market. The expansion of the RTO combined with the already progressive actions made to integrate the energy market via the Integrated Marketplace offer a promising future for wind development. The expansion of the SPP footprint will promote transmission infrastructure development, while increasing the interconnectedness of several states. However, the
  • 40. 40 growth of the marketplace will require more advanced infrastructure to balance and ensure the reliability of the grid. As more wind farms are connected, the variability of wind will significantly reduce, as abundant wind in one part of the region will be able to be shared with other areas where wind is scarce. The inclusion of more stakeholders -- as participants in this marketplace – will further the development of high-voltage transmissions lines paid for through the Highway/Byway shared-cost methodology. In a similar way, increased interconnectedness of the marketplace will enable the SPP to dissipate power in congested areas and deliver wind resources from their source to their need, reducing integration costs and providing greater incentive for future wind farms. Benefits obtained through greater adoption of wind have been shown in a recent study by the U.S. Energy Information Agency (EIA) analyzing the reduction of base load capacity due to higher wind generation in the SPP. The graph below shows the reduction in base load use since 2010. Figure 1 – September 5, 2013 The reduction in base load use is due to higher volumes of wind energy generation supplanting generation from traditional base load units. This reduction effect will be catalytic with the expansion of the SPP RTO, furthering the cost
  • 41. 41 competitiveness and the defensibility of wind as an energy option for resource planning   decisions.   The   SPP’s   outlook   for   the   Integrated   Marketplace   and   the   Highway/Byway cost was best summarized by Regional State Committee member and Arkansas Public Service Commission Chairman Paul  Suskie,  “SPP  needed  a  cost   allocation policy for transmission projects that not only enhance reliability, but also have the potential to reduce costs for utilities and their customers. Building new transmission will bring many benefits, such as reducing  congested  „bottlenecks‟ on the electric grid, increasing grid reliability and efficiency, and creating jobs during the construction and operating phases. This Highway/Byway cost sharing methodology will provide a regional solution for building out the regional electric grid that will meet  our  needs  into  the  future.” 7.7 Externalities While  there  isn’t  a  carbon  pricing  system  in  the  US,  it  is  expected  to  see  a  future   with stricter regulation on carbon emissions. Since utilities are mainly engaged in long term investment decisions on generating assets, they will make better informed decision by factoring in the coming tighter regulation of greenhouse gases and including carbon pricing in its economic analysis. As regulation gets tighter in cutting carbon emission, it is likely to have carbon pricing as a regulatory tool in the US. Almost 40 countries and more than 20 cities, states and provinces already use carbon pricing mechanisms or are planning to implement them.33 Meanwhile, private sector has become more acceptable to carbon pricing. And many companies are preparing for tighter regulation by including an “internal  carbon  price”  in  business  planning.34 A landmark judgment by FERC on petition by California Public Utilities Commission35 specifies  that   if  an  externality  factor  represents  “real  costs”  for  the   33 (World Bank, 2015) 34 (CDP, 2013 ) 35 (FERC, 2010)
  • 42. 42 incumbent utility, it may be deemed as a valid avoided cost under PURPA. This implies that in the event of imposition of external costs associated with the environment, the avoided cost methodology currently applied by utilities will need to be revised to regard these external costs as penalties for conventional generation assets, which can be avoided by renewable energy generation facilities. Subsequently, calculation of these external costs on a life cycle basis will yield a more scientifically accurate estimate of the impacts on the environment, integrating emission from upstream to downstream operations. Currently, neither Westar nor OG&E have considered the possibility of pricing carbon or other pollutants such as SOX, NOX, particulate matter, etc. when comparing renewable with fossil fuel generating assets. However, once they make an investment decision today, they will have an asset that lasts for decades. Thus, it is important to make sure that the portfolio of generating assets designed today could comply with the tight regulation on carbon emission. Adding carbon pricing in economic analysis will allow utilities to better evaluate the comparative advantage of renewable and fossil fuel generating assets, and get better prepared for future challenges in greenhouse gas regulation.
  • 43. 43 APPENDIX SPP’s  Reliability  Impact  Assessment  of  EPA’s  Proposed  CPP: http://www.spp.org/publications/CPP%20Reliability%20Analysis%20Results%20 Final%20Version.pdf Kansas Corporation Commission Report on Electricity Demand and Supply, 2014: http://www.kcc.state.ks.us/pi/2015_electric_supply_and_demand_report.pdf EIA Levelized Cost and Levelized Avoided Cost of New Generation Resources, 2014: http://www.eia.gov/forecasts/aeo/pdf/electricity_generation.pdf
  • 44. 44 Bibliography 1. American Wind Energy Association. (2015). Wind Energy Facts at a Glance. (Retrieved from http://www.awea.org/Resources/Content.aspx?ItemNumber=5059) 2. Argus. (2015, April 8). Analysis: SPP sees adequate summer reserve margin. (Retrieved from http://www.argusmedia.com/News/Article?id=1019635) 3. CDP. (2013 , December). Use of internal carbon price by companies as incentive and strategic planning tool. (Retrieved from https://www.cdp.net/CDPResults/companies-carbon-pricing- 2013.pdf) 4. EIA. (2011, May 13). Electricity resource planners credit only a fraction of potential wind capacity. (Retrieved from http://www.eia.gov/todayinenergy/detail.cfm?id=1370) 5. EIA. (2014, April). Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2014. (Retrieved from http://www.eia.gov/forecasts/aeo/pdf/electricity_generation.pdf) 6. Elefant, C. (2011). Reviving PURPA's Purpose . (Law Offices of Carolyn Elefant) (Retrieved from http://www.recycled-energy.com/images/uploads/Reviving- PURPA.pdf) 7. FERC. (2010, October 21). 133 FERC ¶ 61,059. (Retrieved from http://www.ferc.gov/whats-new/comm-meet/2010/102110/E-2.pdf) 8. Georgia Public Service Commission. (2004). Docket No. 4822-U. (Retrieved from http://www.psc.state.ga.us/factsv2/Docket.aspx?docketNumber=36499) 9. Kansas Corporation Commission. (2015). Report on Electric Supply and Demand. (Retrieved from http://www.kcc.state.ks.us/pi/2015_electric_supply_and_demand_report.pdf) 10. Milligan, M., & Porter, K. (2006). The Capacity Value of Wind in the United States: Methods and Implementation. The Electricity Journal , 19 (2). 11. Monies, P. (2015, April 2). Oklahoma Gas and Electric Co. plans to pass on $4.3 million wind legal settlement to customers. (Retrieved from http://newsok.com/oklahoma-gas-and-electric-co.-plans-to-pass-on-4.3- million-wind-legal-settlement-to-customers/article/5406550/?page=1)
  • 45. 45 12. National Conference of State Legislatures. (2015, February 19). State Renewable Portfolio Standards and Goals. (Retrieved from http://www.ncsl.org/research/energy/renewable-portfolio- standards.aspx#ok) 13. Nickell, L. (2014). A Nickell for Your Thoughts. (Retrieved from http://www.spp.org/publications/Resource%20Adequacy%20in%20SPP%20P art%201%20Blog.pdf) 14. OG&E. (2014). 2014 Annual Report. OG&E. 15. OG&E. (2014). CDP 2014 Investor CDP 2014 Information Request. (Retrieved from https://oge.com/wps/wcm/connect/d907496d-94c8-47d8-9cf6- b6e11c88751f/140529+2014+OGE+CDP+Response.pdf?MOD=AJPERES&CACHE ID=d907496d-94c8-47d8-9cf6-b6e11c88751f) 16. OG&E. (2014). OG&E Integrated Resource Plan (IRP). (Retrieved from https://oge.com/wps/wcm/connect/342cf742-9bb6-48f1-aaa9- 34a4174b8c16/2014+IRP+- +Oklahoma+Report.pdf?MOD=AJPERES&CACHEID=342cf742-9bb6-48f1-aaa9- 34a4174b8c16) 17. Pennel, E. (2010, April 19). SPP Proposes New Cost Sharing Method for Expanding the Regional Electric Transmission Grid. (Retrieved from http://www.spp.org/publications/spp_proposes_new_cost_sharing_method_for _transmission.pdf) 18. Porter, K., Fink, S., Buckley, M., Rogers, J., & Hodge, B. (2013, March). A Review of Variable Generation Integration Charges. Retrieved from National Renewable Energy Laboratory (Retrieved from http://www.nrel.gov/docs/fy13osti/57583.pdf) 19. Southwest Power Pool CAWG. (2014, April 17). CAWG Agenda & Background Material. (Retrieved from http://www.spp.org/section.asp?group=381&pageID=27) 20. Southwest Power Pool CAWG. (2014, June). CAWG Minutes & Attachments. (Retrieved from http://www.spp.org/section.asp?group=381&pageID=27) 21. Southwest Power Pool Generation Working Group . (2004, September 29). Wind Power Capacity Accreditation White Paper. (Retrieved from http://www.spp.org/publications/WindWhite04Sept8_rev5.pdf) 22. Southwest Power Pool. (2011, January). Southwest Power Pool Criteria: Latest Revision. (Retrieved from
  • 46. 46 http://www.spp.org/publications/Criteria%20and%20Appendices%20July%2 025,%202011.pdf) 23. Southwest Power Pool. (2014, October 8). SPP’S   RELIABILITY   IMPACT ASSESSMENT  OF  THE  EPA’S  PROPOSED  CLEAN  POWER  PLAN. (Retrieved from http://www.spp.org/publications/CPP%20Reliability%20Analysis%20Results %20Final%20Version.pdf ) 24. Westar Energy. (2013). 2013 Annual Report. (Retrieved from http://www.annualreports.com/Click/3744?_SID_=20150512175718- a4667f0b40ee9ec677a46b05b23f305e) 25. Westar Energy. (2014). 2014 Annual Report on Form 10K. (Retrieved from http://phx.corporate- ir.net/External.File?item=UGFyZW50SUQ9Mjc0NDkxfENoaWxkSUQ9LTF8VHl wZT0z&t=1) 26. Westar Energy. (2014, October 30). Prairie  Wind  transmission’s  high-capacity transmission line completed ahead of schedule, more than $60 million under budget. (Retrieved from https://www.westarenergy.com/content/about- us/news/2014-news-releases/pwt-energized) 27. World Bank. (2015). What Is Carbon Pricing? (Retrieved from http://www.worldbank.org/en/programs/pricing-carbon)