All exterior building components need to be properly designed to withstand the forces of nature. However, many of the buildings being constructed today are not properly designed or the responsibility has been improperly designated to a contractor. This has resulted in many failures, both minor and major, of various building envelope components.
Wind Uplift: The Next Big Lift will focus on the aspects of designing roofing to properly withstand the forces of wind that act upon the building. We will go through the NBC design requirements and how they relate to the CSA A123.21 testing standard. We will discuss the pitfalls of using FM Global references in our specs and how it interacts with our codes. We will also discuss the shortfalls of our current building code and the direction of the next code edition.
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
15 05-05 wind uplift - the next big lift - roof tech presentation
1. Wind Uplift: The Next Big Lift
Wind Uplift:
The Next Big Lift
Josh Jensen, AScT, CHI, RRO, RRC
2. Wind Uplift: The Next Big Lift
All building envelope components must be designed
to withstand the forces of wind.
Proper design of the roof and perimeter flashing is
often miss understood and not properly completed on
many buildings.
What can this lead to?
Wind Uplift Design
15. Wind Uplift: The Next Big Lift
Detachment of material
Rupture of membrane
Permanent deformation of materials
Any damage that results in a leak
With respect to full adhered systems, detachment of
insulation from underlying layers within the assembly
What is a failure?
16. Wind Uplift: The Next Big Lift
Proper construction to withstand wind uplift forces is
still not fully understood within the industry
A roof can fail through the forces of the wind acting
on the roof membrane surface.
Many of the roof membranes we use today can
withstand the forces of wind within Canada fairly easily
if designed properly.
Wind Uplift Performance
17. Wind Uplift: The Next Big Lift
So how do the codes deal with this?
• Part 5 – Environmental Separation
◦ Construction conforming to a design that resists the
loads of wind up-lift imposed on roofing and
associated components.
• Schedule B (BC Only)
◦ 1.18 Roofing and Flashings
◦ 1.22 Integration of BE components
◦ 1.06 Structural Capacity of Architectural Components
Wind Uplift Performance
18. Wind Uplift: The Next Big Lift
Section 4.1.7 of the BCBC / NBC provides direction on
calculations to be completed and refers to the NBC Structural
Commentary
p=IwqCeCgCp
p = specified external pressure
Iw = importance factor
q = reference velocity pressure
Ce = exposure factor
Cg = gust factor
Cp = external pressure coefficient
Wind Uplift Calculation
19. Wind Uplift: The Next Big Lift
Internal pressures must be accounted for
pi=IwqCeCgiCpi
pi = specified Pressure
Iw = importance factor
q = reference velocity pressure
Ce = exposure factor
Cgi = gust factor
Cpi = external pressure coefficient
Wind Uplift Calculation
20. Wind Uplift: The Next Big Lift
Internal and external forces are added together to
get the total pressure acting on the roof membrane
assembly.
Wind Uplift Calculation
21. Wind Uplift: The Next Big Lift
Importance Factor (Iw)
• Low 0.8
• Normal 1
• High 1.15
• Post-Disaster 1.25
Wind Uplift Calculation
22. Wind Uplift: The Next Big Lift
Reference Velocity (q)
1 in 50 wind velocity found in Appendix C
Check with local Authorities having Jurisdiction (AHJ)
to ensure correct pressure is used
Vancouver (City Hall) 0.45 kPa
Sandspit 0.78kPa
Wind Uplift Calculation
23. Wind Uplift: The Next Big Lift
Exposure Factor (Ce)
Depends on the terrain
Open Terrain = (h/10)0.2 not less than 0.9
Rough Terrain = 0.7(h/12)0.3 not less than 0.7
Interpolation for transitional areas
Wind Uplift Calculation
26. Wind Uplift: The Next Big Lift
Gust Factor (Cg) (Cgi)
Cladding and components use:
Cgi = 2.0*
*Unless a large single volume of internal air
For Cg, although a coefficient is given it must be looked
at with Cp as a larger coefficient for roofing
Wind Uplift Calculation
27. Wind Uplift: The Next Big Lift
Pressure Coefficients (Cpi)
Category 1 = Cpi = -0.15 to 0
• Buildings without large openings, but having small
uniformly distributed openings amounting to less than
0.1% of the total surface area.
• An opening is a window or door which can be expected to
be open during a storm, either though expected usage or
through damage.
• Such buildings include high-rise buildings with no operable
windows and are mechanically ventilated. Some less
common low rise buildings such as concrete tilt-up buildings
with storm proof doors.
Wind Uplift Calculation
28. Wind Uplift: The Next Big Lift
Pressure Coefficients (Cpi)
Category 2 = Cpi = -.45 to 0.3
• This category covers buildings in which significant
openings, if there are any, can be relied on to be
closed during storms but in which background leakage
may not by uniformly distributed.
• Most low-rise buildings fall into this category
provided that all elements – especially shipping doors
– are designed to be fully wind-resistant. Most high-
rise buildings with operable windows or balcony
doors also fall into this category.
Wind Uplift Calculation
29. Wind Uplift: The Next Big Lift
Pressure Coefficients (Cpi)
Category 3 = Cpi = -0.7 to 0.7
• This category covers buildings with large or significant
openings through which gusts are transmitted to the
interior.
• Examples of such buildings included sheds with one or
more open sides as well as industrial buildings with
shipping doors, ventilators or the like, which have a
high probability of being open during a storm or not
being fully resistant to design wind loads.
Wind Uplift Calculation
30. Wind Uplift: The Next Big Lift
Gust Factor and external pressure coefficient (CpCg)
Graphs are used to determine coefficients
Tributary area over a component must be taken into
account
Wind Uplift Calculation
34. Wind Uplift: The Next Big Lift
Online Calculator Available for Simple Generic
Buildings
www.nrc-cnrc.gc.ca/eng/services/windrci
Online Calculator
35. Wind Uplift: The Next Big Lift
Only Buildings up to 150’ high
Cannot be used for :
• buildings on a cliff or escarpment
• unusually shaped buildings
• Post Disaster Buildings
Limitations of Online Calculator
36. Wind Uplift: The Next Big Lift
This calculation provides an unfactored wind uplift
design pressure for the Corner, Perimeter, and Field
Some of the factors often overlooked:
• Are there overhangs?
• Window and door sizes and openings
• Tributary area
• True Exposure Factor
Wind Uplift Performance
37. Wind Uplift: The Next Big Lift
The calculation within the BCBC / NBC is based on
wind data taken from weather stations across the
country
The reference wind speed / velocity pressures is
based on an averaged hour.
Our US counterparts to the south uses 3-second gusts
to determine the reference wind speed
Wind Uplift Performance
38. Wind Uplift: The Next Big Lift
OK, we have a number now, what next?
Well…..
Wind Uplift Performance
39. Wind Uplift: The Next Big Lift
FM Global, formally Factory Mutual, is an
international full building insurance company.
Due to a number of insurable claims, FM took it upon
themselves to develop requirements that must be met for
them to be able to insure a building. These requirements
are based on claims made as well as testing of actual
assemblies.
This is a voluntary requirement and is not codified.
• There is a new standard in the US (ANSI FM 4474)
which is not relevant in Canada.
FM, What is FM?
40. Wind Uplift: The Next Big Lift
So what does it mean when you spec a roof to meet
FM 1-90?
• The prefix 1 means that the roof system has passed
the FM requirement for Calorimeter Testing.
• The second number is the field uplift pressure.
• The Canadian method of determining uplift pressures
is different and cannot be used to determine the
design pressure for use with FM systems.
FM 1-90 or 1-60 Ratings
41. Wind Uplift: The Next Big Lift
A Roof System that has a FM 1-90 rating means that
the roof membrane assembly is rated at 90 psf.
Assembly includes:
• Membrane
• Insulation
• Air / Vapour barrier
• Overlay boards
• Substrate
FM 1-90 or 1-60 Ratings
42. Wind Uplift: The Next Big Lift
The calculation within the FM requirements is based
on wind data taken from weather stations across the
USA
The reference wind speeds / velocity pressures is
based on a 3 second gust rather than an averaged hour.
Wind Uplift Performance
43. Wind Uplift: The Next Big Lift
To determine what FM rating is required for a
particular project a calculation must be performed.
• https://roofnav.fmglobal.com
By referencing the FM 1-90 requirement you may
unintentionally specify something else like:
• Steel Deck Gauge
• Nailer Attachment
• Steel Weld Sizes and Patterns
FMG Requirements
44. Wind Uplift: The Next Big Lift
What does the Designer, Roofer, General Contractor,
or Inspector need to know?
• By specifying these requirements you may
unintentionally contradict another part of the project
documents
• There is more to the requirements then just membrane
selections and uplift ratings
• Something that is “buried” in the roofing specification
may impact the forming contractor or steel welders
• Possible extra costs during construction?
FMG Requirements
45. Wind Uplift: The Next Big Lift
OK, so FM doesn’t work for us now what?
Our new option……
Wind Uplift Performance
46. Wind Uplift: The Next Big Lift
CSA standards have been developed to encompass all
aspects of roofing.
The CSA A123.21 Wind Uplift Standard is being
completed in phases.
This standard is different than American standards as in is
based on dynamic pressure differential rather than static
pressure.
Currently the completed phases include:
• mechanically attached roofing systems,
• adhesively applied roofing systems.
• Partially adhered roofing systems
CSA Standards for Wind Uplift?
48. Wind Uplift: The Next Big Lift
On March 29th, 2015 the Canadian Commission on
Building and Fire Codes accepted proposed change
525 in the 2015 version of the National Building Code.
Proposed Change 525 included adopting CSA
A123.21 as the national reference standard for which
roof membranes must be tested to comply with the wind
uplift requirements of the building code.
This version of the NBCC will go into full effect in at
the end of the year.
CSA A 123.21 - 14
49. Wind Uplift: The Next Big Lift
There are several testing labs conducting these tests.
Go to the testing lab website or ask the manufacturer
to provide test reports showing membrane uplift
performance.
Wind Uplift Performance
53. Wind Uplift: The Next Big Lift
Deck Type
• The majority of the tests are conducted using a Steel
Deck
Wind Uplift Performance
54. Wind Uplift: The Next Big Lift
The new code wording does allow for exceptions for
assemblies such as:
• Ballasted roofs
• Traditional BUR’s
• Sloped roofing
Wind Uplift Performance
55. Wind Uplift: The Next Big Lift
Design complete:
• Design pressure calculated
• Membrane Selected
• Done?
Wind Uplift Performance
56. Wind Uplift: The Next Big Lift
Improperly secured perimeter flashing is the leading
cause of roof failures through wind uplift.
Once the flashings are bent or torn off the wind can
act directly on the edge of the membrane.
Wind Uplift Performance
57. Wind Uplift: The Next Big Lift
BCBC Appendix A
A-5.6.2.1
• Roof Flashings guidelines
◦ Roofing Specifications, Canadian Roofing Contractors
Association
◦ Architectural Sheet Metal Manual – SMACNA
◦ Roofing and Waterproofing Manual, National Roofing
Contractors Association
Wind Uplift Performance
58. Wind Uplift: The Next Big Lift
There is currently no standard for the design of flashings
for wind uplift in Canada.
What Standards are in-place to aid with designing
flashing components?
• ANSI/SPRI ES-1 - http://www.spri.org/
• FMG Data Sheet 1-49 - http://www.fmglobal.com/default.aspx
Both documents are based on tested flashing assemblies
The FM requirement is intended to only be used on FM
insured buildings. It is not referenced in any building codes or
industry standards and therefore is a voluntary standard.
Wind Uplift Performance - Flashings
59. Wind Uplift: The Next Big Lift
RCABC has developed flashing attachment standards for
use by RCABC members.
These standards are based on SMACNA (Sheet Metal
and Air Conditioning Contractors` National Association)
details with some changes to meet BC’s specific requirements.
SMACNA’s current details are tested to meet the
ANSI/SPRI ES-1Standard
These flashing attachment details are meant for typical
details and thus cannot be used for unique or custom flashing
profiles.
Wind ratings for RCABC details are not provided
RCABC Flashing Standards
60. Wind Uplift: The Next Big Lift
Although the CSA A123.21 – 14 standard includes
testing for roofing it does not yet include perimeter
flashings.
Currently the committee is at the design guide stage
of the inclusion of perimeter flashings into the standard
Three different models of testing are currently being
pursued:
• Full system
• Specific parapet
• Modeling Verification
Where is the CSA?
61. Wind Uplift: The Next Big Lift
The draft design guide will be completed this year
The design guide will include:
• How to complete the calculations for pressures on
flashings
• Sample flashing profiles commonly used in Canada
along with design pressures
• Description of materials used within those flashing
profiles
Where is the CSA?
62. Wind Uplift: The Next Big Lift
Wind Design: Roofing and Flashings
• Ensure that any design is reviewed, use any available
standards to unsure due diligence is exercised.
• Follow-up in construction to ensure that the contractor
understood and has provided what was designed.
Conclusion
63. Wind Uplift: The Next Big Lift
Remember, when it comes to wind design, just
because it has worked for hundreds of years doesn’t
mean it can’t fail in a second.
Wind Performance