1. KP Weekly Report No 81, 15 December 2012 1
CONSTRUCTION OF THE TAILINGS STORAGE FACILITY
10 Dec 12 DSCN0369
Two days after 60 mm rain.
10 Dec 12 DSCN0368
High water level on sand stockpile after 60 mm rain event.
2. KP Weekly Report No 81, 15 December 2012 2
CONSTRUCTION OF THE TAILINGS STORAGE FACILITY
11 Dec 12 DSCN0371
Still draining area three days after 60 mm rain.
11 Dec 12 DSCN0372
Dewatering and cleaning out trench for LCRS outfall pipe for 3rd
time.
3. KP Weekly Report No 81, 15 December 2012 3
CONSTRUCTION OF THE TAILINGS STORAGE FACILITY
12 Dec 12 DSCN0375
Section of LCRS pipe installation completed 11th
Dec.
13 Dec 12 DSC01405
Basin works eastern side.
4. KP Weekly Report No 81, 15 December 2012 4
CONSTRUCTION OF THE TAILINGS STORAGE FACILITY
13 Dec 12 DSC01406
Installing LCRS outfall pipes through Divider Embankment.
13 Dec 12 DSC01410
Temporary decant and causeway construction.
5. KP Weekly Report No 81, 15 December 2012 5
CONSTRUCTION OF THE TAILINGS STORAGE FACILITY
14 Dec 12 DSCN0385
Placing fill over LCRS outfall pipes.
14 Dec 12 DSCN0387
LCRS construction.
6. KP Weekly Report No 81, 15 December 2012 6
CONSTRUCTION OF THE TAILINGS STORAGE FACILITY
14 Dec 12 DSC01427
Branch drain construction.
CONSTRUCTION OF WSD PIEZOMETER ACCESS
14 Dec 12 DSC01429
Constructing access stairs and handrails to WSD embankment
piezometers.