3. The way it used to be:
1 batch would take 6 - 8 people
3 – 4 hours to fill & pack
•Bad GMP and not safe
•Repetitive strain from doing the same
thing again and again
•Stressed and tired
4. The way it is now:
1 batch can be filled & packed
by 4 people in 30 mins -1 hr
•Much better GMP
•Safer
•Relaxed and not tired
5. The Math
8 people taking 4 hours to produce 800 units =
25 units per man-hour
4 people taking 1 hour to produce 800 units =
200 units per man-hour