Atc tower
1. Page 1
Hira Ejaz Ahmed Shaikh
Project Management- Group A
10th February 2015
ATC TOWER
Activity on Node Diagram:
Paths:
A, B, C, D, E
F, G, H, I, J, M, D, E
F, K, L, M, D, E
Critical Path:
A, B, C, D, E
Expected Time for Completion of the Project:
A, B, C, D, E
3 weeks + 2 weeks + 16 weeks + 2 weeks + 4 weeks = 27 weeks
Delay in Designing of Tower:
Delay of up to 5 weeks will not cause any delays in the overall project since the critical path
of the project is 27 weeks and within those 27 weeks all the parallel activities will be
completed even after the delay of 5 weeks.
A B C D
F
G H
K L M
I J
E