2. Project Photo History
-Contractual-
POP – 67 days
Start- 18 Dec 10
Finish –23 Feb 11
-Actual-
POP – 52 days
Start- 28 Dec 10
Finish – 18 Feb 11
- Construction -
16,000 Square Foot
Site Work
Power Generation
Force Protection
4. Project Photo History
-Actual-
POP – 23 days
Start- 01Nov10
Finish – 23 Nov 10
- Construction -
36’ x 100’ Hygiene unit
Septic System
Pressurized Pump Unit
Power Generation
5. Project Photo History
-Actual-
POP – 43 day
Start- 17 Oct 10
Power Generation
Force Protection
- Construction -
34’ x 120’ PEB
Power Generation
Force Protection
6. Project Photo History
-Actual-
POP – 49 days
Start- 21 Sep 10
Finish – 09 Nov 10
- Construction -
34’ x 120’ PEB
Site Development
Power Generation
Force Protection