Project Proposal
New C2C Site for Digital
Terrestrial Television (DTT) Niche
Market Penetration
Project Manager: Eze Igwe
Creation Date: 04/02/2015
Last Revised: 06/02/2015
Version: 1.0
ORtv Nigeria Ltd.
TABLE OF CONTENTS
INTRODUCTION.........................................................................................................................................................3
PURPOSE OF PLAN................................................................................................................................................... 3
BACKGROUND INFORMATION...................................................................................................................................3
PROJECT APPROACH................................................................................................................................................ 4
PHASE X: STAKEHOLDERS’ CONTRIBUTION..............................................................................................................4
GOALS AND OBJECTIVES......................................................................................................................................5
BUSINESS GOALS AND OBJECTIVES..........................................................................................................................5
PROJECT GOALS AND OBJECTIVES...........................................................................................................................5
SCOPE...........................................................................................................................................................................6
SCOPE DEFINITION.................................................................................................................................................. 6
PROJECTED BUDGET................................................................................................................................................ 8
RISK ASSESSMENT................................................................................................................................................. 10
INITIAL PROJECT RISK ASSESSMENT......................................................................................................................11
MILESTONES......................................................................................................................................................... 14
ASSUMPTIONS..........................................................................................................................................................15
PROJECT ASSUMPTIONS.........................................................................................................................................15
CONSTRAINTS..........................................................................................................................................................16
PROJECT CONSTRAINTS.........................................................................................................................................16
RELATED PROJECTS .............................................................................................................................................. 16
CRITICAL PROJECT BARRIERS................................................................................................................................16
PROJECT MANAGEMENT APPROACH.............................................................................................................17
PROJECT ROLES AND RESPONSIBILITIES.................................................................................................................17
ISSUE MANAGEMENT............................................................................................................................................. 18
COMMUNICATIONS PLAN.......................................................................................................................................19
ATTACHMENTS/APPENDICES.............................................................................................................................21
APPROVALS..............................................................................................................................................................22
SIGN-OFF SHEET...................................................................................................................................................22
2
INTRODUCTION
Purpose of Plan
The proposed Analogue Switch-Off (ASO) transition roll-out by the Nigerian
Broadcasting Corporation (NBC) has created a huge opportunity for Pay-tv
service providers to penetrate the large Nigerian Mass Market. To dominate this
niche market and riding on the over 100 million Mobile Phone penetration by the
GSM service providers, a Consumer-To-Consumer site will provide ORTV the
right platform to gain a substantive market share as well as use the same tool to
create and retain customers. Using this site, Subscribers can cross-market ORtv
products and services and earn a nominal income by accumulating points which
can be redeemed as subscription to their accounts or gift items from the ORtv
gift catalog. This Proposal will provide a definition of the project, including the
project’s goals and objectives. Additionally, the Proposal will serve as an
agreement between the following parties: Steering Committee, Project
Coordinator, Project Owner, Project Manager, Project Team, and other
personnel associated with and/or affected by the project.
The Project Plan defines the following:
− Project purpose
− Business and project goals and objectives
− Scope and expectations
− Roles and responsibilities
− Assumptions and constraints
− Project management approach
− Ground rules for the project
− Project budget
− Project timeline and execution
− The conceptual design of new technology
Background Information
The Broadcasting Revolution is well underway in Nigeria and the transition from
Analogue to Digital broadcasting is not only in conformance with the guidelines and
resolutions of the ITU and NBC but also creating opportunities for Oraqtech Nigeria
Limited to achieve a 10 million subscriber base and exponential profitability targets.
The ORtv brand provides the DTT platform needed to achieve the required
coverage and penetration to keep our targets in perspective and achievable.
There is need for concerted effort to be deployed by all facets of the ORtv business
to enable a seamless transition through innovative technology and achieve a
sustainable competitive advantage. We recognize that the transition will benefit our
business extensively but it is a complex process given our business terrain and our
regulatory environment
Our Business Strategy would rely on a C2C site as a marketing and retention tool to
create subscriber base with huge multiplier potential
3
C2C DTT Penetration Project
Project Approach
The Project will be executed in phases using a proactive approach through
informed and accurate projections to stay ahead of competition and on top of
target markets’ preference. The different phases can happen within over-lapping
timelines as execution is imminent.
Phase I: Constitute and Inaugurate project Team to ease co-
ordination
Phase II: Activate a Research and Advisory team to conduct a market
survey to determine prospective customer TV preferences
Phase III: Design a C2C Site creating existing subscribers on the
platform as activation agents who will earn points that can
be converted to subscription or redeemed as gifts
Phase IV: Test-run Site with internal customers to identify gaps and
measure efficiency
Phase V: Marketing campaign to create awareness and traction to the
C2C site
Phase VI: Launch Site
Phase VII: Train and support a robust operation for Subscriber
Management
Phase VIII: Post Launch evaluation and performance audit
Phase X: Stakeholders’ Contribution
1. ORtv Management
2. Finance Department
3. Research and Development Department
-
4. Marketing Department
5. IT Department
6. Human Resources Department
7. Credit Control and Operations
8. Sales Department
4
C2C DTT Penetration Project
GOALS AND OBJECTIVES
Business Goals and Objectives
The business goals and objectives of the Project is to achieve a 10 million
subscriber base over a 24 Months period using a C2C Site as a customer
acquisition and subscriber management tool
− Achieve extensive DTT coverage and penetration in accordance with the
ORtv Roll-out plan
− Build a 10 million subscriber base
− Distribution and value-chain management at required trade and sales
capacity
− Grow revenue by 100% in 12 Months through C2C mutually beneficial
innovations
− Reduce operational cost by using IT alternatives to providing services
Project Goals and Objectives
These are
− Design and Deploy a user friendly C2C Site with growing benefits for
subscribers and huge returns for the Company
− Facilitates coordination of transition activities, site roll-out plan and
information sharing both internal and external to all stakeholders
− Ensure stock adequacy and inventory management to meet the expected
increase in demand for Set-Top-Boxes (STB) created by the C2C site
− Cost effective budget
− Marketing campaign with deep penetration
− Provides an open, flexible, reliable DTT technology base for the future.
− Build a virtual supply chain and sales force
− Invest in an operational platform that guarantees ease of activation,
subscriber management and user friendly devices
− Accomplish project business goals and objectives within defined budget
and time parameters.
− Minimize impact to business operations within the transition period
− Gather demographic and market intelligence data to guarantee competitive
edge
5
C2C DTT Penetration Project
SCOPE
Scope Definition
The Project will achieve an interactive platform that will enable customers act
as ORtv agents to resell STBs through direct referrals to prospective
customers, registration of deals, fulfillment of transactions and earning of
points which can be earned as subscription or gifts
− Identify areas of research and investigation to determine customer TV
preferences and sales referrals incentives
− Identify and deploy the right subscriber management tools as payment and
redemption interfaces on a C2C site
− Build and Launch a customer friendly C2C e-commerce solution for
subscribers to earn their subscription payments
− Monitor the volume of trade generated using this portal and measuring the
impact on the company bottom-line
− Plan and execute marketing campaigns that will reach over 100m GSM
users in Nigeria
− Grow subscriber base exponentially through this innovative technology and
deploy the right retention tools
− Provide Training and Support to the operations and subscriber
management department
− Integrate the billing system into the C2C site
− Achieve business goals and objectives within set timelines and budget
− Periodic evaluation of site performance and maintenance and constant
improvements
Including the following interfaces:
− Nigerian Broadcasting Corporation (NBC)
− GSM Service Providers (MTN, Etisalat, Airtel)
− Internet Service Providers (Swift, Smile, ICSL)
− Advertising Media (BTL and ATL)
Desired Enhancements
− Information Technology in-house infrastructure
− Warehouse and Stock Holding Capacity
− DTT Coverage Area
− Distribution and Logistics
− Competitive intelligence and Demographic data
− Value-chain penetration and market reach
− Management and financial support
− Alternative Payment Options
− Operational tools and training deployments
6
C2C DTT Penetration Project
7
C2C DTT Penetration Project
Projected Budget
$000's
ORTV NIG LTD
C2C DTT MARKET PENETRATION
Labour 2,533
Monitoring Equipment Installation - Labour 22
Business input into specs and testing & System Design Approval 20
Research and Market Survey - Materials 20
Connections - Billing System 65
Connections - Customer Relationship Management 241
Dissemination - Customer engagement via email & training 28
Implementation of PowerOn Fusion 709
Maintenance & Support for PowerOn Fusion 187
Project Management - Website Design 351
Project Management - ePayment Solution 790
Involvement in developing Future Network Planning/Operational
Standard 15
Circuit Selection 32
Developing Future Network Planning/Operational Standard 53
Equipment 3,077
Publicity Materials - Informational Pamphlets & postage & packaging 18
Remote Control Installation - Head Office 1,954
Monitoring Equipment Installation - Project Office 112
Remote Control Installation - Materials 563
Commissioning SWIFT link to Remote Control Devices 31
Delivery and configuration of SWIFT IT hardware and software 399
Contractors 2,214
Demand Side Response Customer Survey 391
Project Management - Market Survey 115
Remote Control Installation - Labour 844
Remote Control Installation at Project Office 159
Contractors Travel & Publicity - Informing Affected Customers 42
Connections - Connections Design 303
Data Analysis and Economic Modelling 185
Power System and Technical Modelling 175
IT 739
Data Capture and Cleanse 55
Database Licenses 100 8
C2C DTT Penetration Project
Develop CRMS Reporting Capability 11
Develop CRMS/PowerOn (SOP) Interface 87
Develop New Interface to PowerOn Fusion 87
Develop Real-time Data Update Functionality 55
Develop Visual Display Functionality for CRMS 73
Initial Data Load Functionality 55
System Integration & Testing 66
Testing and Development Workstation 10
Upload and Store Estimates (into historian) 85
Upload CRMS Diagram and Managed Loads 55
Project Manager - Remuneration 100
Travel & Expenses 50
Payments to users 300
Demand Side Response 300
Contingency 967
Development and Preparation 44
Remote Control Installation 284
Publicity, Training and Dissemination - Operations 125
DSR and Interruptions 100
Project Management 28
Connections 102
Monitoring Equipment 77
Installation and configuration of IT and Implementation of PowerOn
Fusion
109
Circuit selection and data upload 24
Analysis, Modelling and Development of Standards 41
System Integration & Testing 13
Decommissioning 20
Other 444
Publicity and Dissemination 257
Accommodation 160
Unplanned interruptions during trial 27
TOTAL PROJECT COST – $10,424,000
9
C2C DTT Penetration Project
Risk Assessment
The initial Risk Assessment attempts to identify, characterize, prioritize and
document a mitigation approach relative to those risks which can be identified
prior to the start of the project.
The Risk Assessment will be continuously monitored and updated throughout
the life of the project, with monthly assessments included in the status report
(see Communications Plan) and open to amendment by the Project Owner and
Project Manager.
Because mitigation approaches must be agreed upon by project leadership
(based on the assessed impact of the risk, the project’s ability to accept the risk,
and the feasibility of mitigating the risk), it is necessary to allocate time into each
Steering Committee meeting, dedicated to identifying new risks and discussing
mitigation strategies.
The Project Manager will convey amendments and recommended contingencies
to the Steering Committee monthly, or more frequently, as conditions may
warrant.
10
C2C DTT Penetration Project
Initial Project Risk Assessment
Risk Risk Level
L/M/H
Likelihood
of Event
Mitigation Strategy
Project Size
Person Hours H: Over 20,000 Certainty Assigned Project Manager,
Site Engineers and hands-on
project team, comprehensive
project management
approach and
communications plan
Estimated Project
Schedule
H: Over 12 months Certainty Created comprehensive
project timeline with frequent
baseline reviews
Team Size at Peak H: Over 15
members
Certainty Comprehensive
communications plan,
frequent meetings, tight
project management
oversight
Number of Interfaces to
Existing Systems
Affected
H: Over 4 Certainty Develop interface control
document immediately
Project Definition
Narrow Knowledge
Level of Users
M: Knowledgeable
of user area only
Likely Assigned Project Manager(s)
and Team members to assess
global implications
Available
documentation and
data clouds
establishment of
baseline
M: More than 75%
complete/current
Likely Balance of information to be
gathered by team and
Customer Insight
Project Scope Creep L: Scope generally
defined, subject to
revision
Unlikely Scope intially defined in
project plan, reviewed
monthly by three groups
(Project Manager and
Steering Committee) to
prevent undetected scope
creep
Project Deliverables
unclear
L: Well defined Unlikely Included in project plan,
subject to amendment
Technical Team Project
Deliverables
M: Estimated, not
clearly defined
Somewhat
likely
Included in project plan but
requires more information,
subject to amendment
Cost Estimates
Unrealistic
L: Thoroughly
predicted by finance
experts using
proven practices to
less than 15%
margin of error
Unlikely Included in project plan,
subject to amendment as new
details regarding project
scope are revealed
11
C2C DTT Penetration Project
Risk Risk Level
L/M/H
Likelihood
of Event
Mitigation Strategy
Timeline Estimates
Unrealistic
M: Timeline
assumes no
derailment
Somewhat
likely
Timeline reviewed monthly by
three groups (Project
Manager and Steering
Committee) to prevent
undetected timeline
departures
Number of Team
Members
Unknowledgeable of
Business
L: Team well versed
in business
operations impacted
by technology
Unlikely Project Manager to identify
knowledge gaps and provide
training, as necessary
Project Leadership
Steering Committee
existence
L: Identified and
enthusiastic
Unlikely Frequently seek feedback to
ensure continued support
Absence of
Commitment
Level/Attitude of
Management
L: Understands
value & supports
project
Unlikely Frequently seek feedback to
ensure continued support
Absence of
Commitment
Level/Attitude of
Project Team
L: Understands
value & supports
project
Unlikely Frequently seek feedback to
ensure continued support
Absence of Mid-
Management and Staff
Commitment
L: Most understand
value & support
project
Unlikely Frequently seek feedback to
ensure continued support
Staffing & Funding
Project Team
Availability
M: Diverse team
makes availability
questionable
Somewhat
likely
Continuous review of project
momentum by all levels. HR to
identify any impacts caused
by unavailability. If necessary,
increase committmment by
participants to full time status
Physical Location and
primary responsibility
of Team prevents
effective management
M: Team is
dispersed among
several functions
Likely Use of Intranet project website
on pundit, comprehensive
Communications Plan
Project Team’s Shared
Work Experience
creates poor working
relationship
M: Some have
worked together
before
Somewhat
likely
Comprehensive
Communications Plan
Weak User Participation
on Project Team
L: Users are part-
time team members
Unlikely User Group Participants
coordinated by full time
employee
Project Management
Funding
Methodology Used
unknown to team
L: Procurement
Methodology
familiar to team
Unlikely N/A
Change Management
Procedures undefined
L: Well-defined Unlikely N/A
Quality Management
Procedures unclear
L: Well-defined and
accepted
Unlikely N/A
IT Team
Number of Times Team
Has Done Prior Work
with Vendor Creates
M: Project Owner
has always worked
with the Technical
Likely Comprehensive briefing by
previous participants will bring
the rest of the Team to speed12
C2C DTT Penetration Project
Risk Risk Level
L/M/H
Likelihood
of Event
Mitigation Strategy
Foreign Relationship Team on Work-In-Progress (WIP)
Project Team’s Lack of
Knowledge of C2C
relevant experience
M: Conceptual
understanding
Somewhat
likely
Comprehensive briefing by
previous participants will bring
the rest of the Team to speed
on Work-In-Progress (WIP)
Poor Coverage of
Transmitters in existing
DTT cities
H: Emphasis on
metropolis as
against mass
market dwellings
Certainty Additional transmitters will
need to be constructed and
deployed in such cities e.g
Abuja and Port Harcourt
Team’s Involvement in
Transmission sites
Selection Impacts
Success of
Implementation
L: High involvement
in selection
Unlikely Periodic meetings to identify
high opportunity markets and
prioritize resources for
transmitter deployments
13
C2C DTT Penetration Project
Milestones
Description of Milestone Sub Steps (if any)
#1. Conduct extensive Research on Customer TV
Preferences to determine areas of content creation and
investments in strong selling points.
Sub Step #1 - Delineate the Nigerian Market
Sub Step #2 - Determine size of target market
Sub Step #3 - Focus on existing customers using android
devices
#2. Invest in a Robust Subscriber Management Tool and
Billing System to enable database updates and cleansing.
Partner epayment solution providers to create a payment
and points management platform
Sub Step #1 - Ensure all customer data are captured
Sub Step #2 - Increase the size and speed of Billing Tool
Sub Step #3 - Integrate a viable and efficient payment
and point capturing platform
#1. Recruit Web Design Consultant and determine DIY
functionalities to enable subscribers manage their
accounts from their mobile devices
Sub Step #1 - Recruit Consultant and sign Agreements
Sub Step #2 - Present Web design and Online Account
User profiles
Sub Step #3 - Upload customer profiles from Subscriber
Management platform to Website
#2. Completion of Web design and presentation to Senior
Management for critic and adoption
Sub Step #1 - Completion of Web Design
Sub Step #2 - Presentation to Senior Management
Sub Step #3 - Adoption and Approval by Project Owner
and Sponsors
#1. Test Run of Web Site with Internal Customers and
Select Subscribers from diverse markets
Sub Step #1 - Create all Internal Customers on Web Portal
Sub Step #2 - Include select Subscribers from diverse
markets
Sub Step #3 -Close Customer to Customer deals and
measure Turn Around Time and Satisfaction Rating
#2. Train Operations and IT Staff who will monitor and
manage C2C Interface
Sub Step #1 - Create a Support Team
Sub Step #2 - Train and Retrain Operations and IT Staff
Sub Step #3 - Provide Product Knowledge Training to all
Customer facing staff
#3. Deploy BTL and ATL Campaign across diverse markets
especially using GSM Service Providers Marketing
platforms to reach existing and prospective Subscribers
Sub Step #1 - Choose a Marketing Campaign Slogan (Sell
& Smile)
Sub Step #2 - Adopt a staff and customer sensitization
and awareness campaign
Sub Step #3 - Deploy Marketing conccepts across BTL and
ATL platforms
#1. LAUNCH C2C WEBSITE
Sub Step #1 - Launch New C2C Site with Stakeholders
Sub Step #2 - Launch in Regional Markets
Sub Step #3 - Sustain Aggressive campaign across
platforms
15 months
#1 Conduct Post Launch Performance Audit and Evaluations
Sub Step #1 - Measure customer satisfaction
Sub Step #2 - Measure Market Penetration sucess
Sub Step #3 - Measure Impact on Revenue
6 months
9 months
12 months
3 months
14
C2C DTT Penetration Project
ASSUMPTIONS
Project Assumptions
The following assumptions were made in preparing the Project Plan:
− ORTV management and staff are informed and willing to take advantage
of the opportunity offered by the Analogue Switch-Off (ASO) transition
programme led by NBC
− Management will ensure that project team members are available as
needed to complete project tasks and objectives.
− The Steering Committee will participate in the timely execution of the
Project Plan (i.e., timely approval cycles and meeting when required).
− Failure to identify changes to draft deliverables within the time specified
in the project timeline will result in project delays.
− Project team members will adhere to the Communications Plan.
− Mid and upper management will foster support and “buy-in” of project
goals and objectives.
− The business will ensure the existence of a technological and
transmission infrastructure that can support the C2C site Roll-out.
− All project participants will abide by the guidelines identified within this
plan.
− The Project Plan may change as new information and issues are
revealed.
15
C2C DTT Penetration Project
CONSTRAINTS
Project Constraints
The following represent known constraints to the C2C DTT Penetration Project:
− Project funding could be limited, with no contingency.
− Due to the nature of regulatory enforcement and Government
bureaucracies the Digital Transition Roll-out might be inconsistent
− Online web usage knowledge among subscribers might be limited
− A large number of GSM users do not use Android devices
− Poor Sells incentives for Customers
Related Projects
- DTT Transmitters Roll-out Project
- Consumer Behaviour Research Projects
- STB Manufacturing Project
Critical Project Barriers
Unlike risks, critical project barriers are insurmountable issues that can be
destructive to a project’s initiative. In this project, the following are possible
critical barriers:
− Inefficient Internet Services by ISPs
− NBC Regulatory bottlenecks
Should any of these events occur, the Project execution could be threatened
16
C2C DTT Penetration Project
PROJECT MANAGEMENT APPROACH
Project Roles and Responsibilities
Role Responsibilities Participant(s)
Project Sponsor
 Ultimate decision-maker and tie-breaker
 Provide project oversight and guidance
 Review/approve some project elements
ORtv Management
Steering
Committee
 Commits department resources
 Approves major funding and resource
allocation strategies, and significant
changes to funding/resource allocation
 Resolves conflicts and issues
 Provides direction to the Project Manager
 Review project deliverables
VP – Marketing
VP – Operations
VP – HRM
VP – IT
VP – Sales
VP – R&D/Strategy
VP – Finance
Project Manager  Manages project in accordance to the
project plan
 Serves as liaison to the Steering Committee
 Receive guidance from Steering Committee
 Supervises consultants
 Supervise vendor(s)
 Provide overall project direction
 Direct/lead team members toward project
objectives
 Handle problem resolution
 Manages the project budget
Eze Igwe
Project Participants
(Team)
 Understand the user needs and business
processes of their area
 Act as consumer advocate in representing
their area
 Communicate project goals, status and
progress throughout the project to
personnel in their area
 Review and approve project deliverables
 Creates or helps create work products
 Coordinates participation of work groups,
individuals and stakeholders
 Provide knowledge and recommendations
 Helps identify and remove project barriers
 Assure quality of products that will meet
the project goals and objectives
 Identify risks and issues and help in
resolutions
Team Member – Marketing
Team Member – Operations
Team Member – HRM
Team Member – IT
Team Member – Sales
Team Member – R&D
Team Member - Finance
Consultants  Lend expertise and guidance as needed Web Design Consultant
17
C2C DTT Penetration Project
Issue Management
The information contained within the Project Proposal will likely change as the
project progresses. While change is both certain and required, it is important to
note that any changes to the Project Plan will impact at least one of three critical
success factors: Available Time, Available Resources (Financial, Personnel), or
Project Quality. The decision by which to make modifications to the Project Plan
(including project scope and resources) should be coordinated using the
following process:
Step 1: As soon as a change which impacts project scope, schedule,
staffing or spending is identified, the Project Manager will
document the issue.
Step 2: The Project Manager will review the change and determine the associated
impact to the project and will forward the issue, along with a recommendation, to
the Steering Committee for review and decision.
Step 3: Upon receipt, the Steering Committee should reach a consensus
opinion on whether to approve, reject or modify the request based
upon the information contained within the project scope, the Project
Manager’s recommendation and their own judgment. Should the Steering
Committee be unable to reach consensus on the approval or denial of a change,
the issue will be forwarded to the Project Sponsor, with a written summation of
the issue, for ultimate resolution.
Step 4: If required under the decision matrix or due to a lack of consensus, the Project
Sponsor shall review the issue(s) and render a final decision on the approval or
denial of a change.
Step 5: Following an approval or denial (by the Steering Committee or Project Sponsor),
the Project Manager will notify the original requestor of the action taken. There is
no appeal process.
18
C2C DTT Penetration Project
Communications Plan
Disseminating knowledge about the project is essential to the project’s success.
Project participants desire knowledge of what the status of the project is and how
they are affected. Furthermore, they are anxious to participate. The more that
people are educated about the progress of the project and how it will help them
in the future, the more they are likely to participate and benefit.
This plan provides a framework for informing, involving, and obtaining buy-in
from all participants throughout the duration of the project.
Audience This communication plan is for the following audiences:
− Project Sponsor
− Steering Committee
− Project Manager
− Project Team
− Subject Matter Experts
Communications Methodology The communications methodology utilizes
three directions for effective communication:
Top-Down It is absolutely crucial that all participants in this project sense
the executive support and guidance for this effort. The executive
leadership of the organization needs to speak with a unified, enthusiastic
voice about the project and what it holds for everyone involved. This will
be 'hands-on' change management, if it is to be successful. Not only will
the executives need to speak directly to all levels of the organization, they
will also need to listen directly to all levels of the organization, as well.
The transition from the project management practices of today to the
practices envisioned for tomorrow will be driven by a sure and convinced
leadership focused on a vision and guided by clearly defined, strategic,
measurable goals.
Bottom-Up To ensure the buy-in and confidence of the personnel
involved in bringing the proposed changes to reality, it will be important to
communicate the way in which the solutions were created. If the
perception in the organization is that only the Steering Committee created
the proposed changes, resistance is likely to occur. However, if it is
understood that all participants were consulted, acceptance seems more
promising.
19
C2C DTT Penetration Project
Middle-Out Full support at all levels, where the changes will have to be
implemented, is important to sustainable improvement. At this level (as
with all levels), there must be an effort to find and communicate the
specific benefits of the changes. People need a personal stake in the
success of the project management practices.
Communications Outreach The following is a list of communication events that
are established for this project:
Monthly Status Reports The Project Manager shall provide monthly
written status reports to the Steering Committee. The reports shall include
the following information tracked against the Project Plan:
- Summary of tasks completed in previous month
- Summary of tasks scheduled for completion in the next month
- Summary of issue status and resolutions
Monthly Steering Committee Meeting These status meetings are held
at least once per month and are coordinated by the Project Manager.
Every member of the Steering Committee participates in the meeting. The
Project Manager sends the status report to each member of the team prior
to the meeting time so everyone can review it in advance.
Bi-Monthly Project Team Status Meeting These status meetings are
held every other month. Every member of the Project Team will be invited
to participate in the meeting. Project Manager sends the status report to
each member of the team prior to the meeting so everyone can review it
in advance.
20
C2C DTT Penetration Project
ATTACHMENTS/APPENDICES
21
Project Sponsor – ORTV
Management
Steering Committee
Project Manager
Eze Igwe
Team Member
- Marketing
Team
Member -
Operations
Team Member
- HRM
Team
Member - IT
Team
Member -
Sales
Team
Member –
R&D
Team Member -
Finance
C2C DTT Penetration Project
APPROVALS
Sign-off Sheet
I have read the above Project Proposal and hereby append my approval and
support to the Project
Project Sponsor:
Date
Project Manager:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
22

More Related Content

Similar to NEW C2C SITE FOR DTT NICHE MARKET PENETRATION

akhan_CareerProfile.doc1
akhan_CareerProfile.doc1akhan_CareerProfile.doc1
akhan_CareerProfile.doc1
Asadullah Khan
 
City campus proj
City campus projCity campus proj
City campus proj
Hira Warsi
 
Application enablement stephan massalt (kpn netco)
Application enablement   stephan massalt (kpn netco)Application enablement   stephan massalt (kpn netco)
Application enablement stephan massalt (kpn netco)
Stephan Massalt
 

Similar to NEW C2C SITE FOR DTT NICHE MARKET PENETRATION (20)

DIGITAL TRANSFORMATION MAP FOR STREAM IT MEDIA.docx
DIGITAL TRANSFORMATION MAP FOR STREAM IT MEDIA.docxDIGITAL TRANSFORMATION MAP FOR STREAM IT MEDIA.docx
DIGITAL TRANSFORMATION MAP FOR STREAM IT MEDIA.docx
 
DIGIT North 2022
DIGIT North 2022DIGIT North 2022
DIGIT North 2022
 
DIGITAL COMPETENCIES SM DIPATANE.pdf
DIGITAL COMPETENCIES SM DIPATANE.pdfDIGITAL COMPETENCIES SM DIPATANE.pdf
DIGITAL COMPETENCIES SM DIPATANE.pdf
 
Cliona O Hanrahan Introduction 2011
Cliona O Hanrahan Introduction 2011Cliona O Hanrahan Introduction 2011
Cliona O Hanrahan Introduction 2011
 
Optare Solutions Network Applications BU Brochure
Optare Solutions Network Applications BU BrochureOptare Solutions Network Applications BU Brochure
Optare Solutions Network Applications BU Brochure
 
Reimagining the Technology of Tomorrow
Reimagining the Technology of Tomorrow Reimagining the Technology of Tomorrow
Reimagining the Technology of Tomorrow
 
akhan_CareerProfile.doc1
akhan_CareerProfile.doc1akhan_CareerProfile.doc1
akhan_CareerProfile.doc1
 
Managed Services: Yielding Excellent Results at Videocon
Managed Services: Yielding Excellent Results at VideoconManaged Services: Yielding Excellent Results at Videocon
Managed Services: Yielding Excellent Results at Videocon
 
Connected digital additive manufacturing competition briefing
Connected digital additive manufacturing competition briefingConnected digital additive manufacturing competition briefing
Connected digital additive manufacturing competition briefing
 
Connected digital additive manufacturing competition briefing
Connected digital additive manufacturing competition briefingConnected digital additive manufacturing competition briefing
Connected digital additive manufacturing competition briefing
 
Guiding a Product Roadmap in a Chaotic World
Guiding a Product Roadmap in a Chaotic WorldGuiding a Product Roadmap in a Chaotic World
Guiding a Product Roadmap in a Chaotic World
 
Work Proposal for Project Management and Invoicing System
Work Proposal for Project Management and Invoicing SystemWork Proposal for Project Management and Invoicing System
Work Proposal for Project Management and Invoicing System
 
Digital Transformation Map
Digital Transformation MapDigital Transformation Map
Digital Transformation Map
 
City campus proj
City campus projCity campus proj
City campus proj
 
Iveda (OTCQB:IVDA) - Investor Presentation
Iveda (OTCQB:IVDA) - Investor PresentationIveda (OTCQB:IVDA) - Investor Presentation
Iveda (OTCQB:IVDA) - Investor Presentation
 
Iveda Investor Presentation
Iveda Investor PresentationIveda Investor Presentation
Iveda Investor Presentation
 
Application enablement stephan massalt (kpn netco)
Application enablement   stephan massalt (kpn netco)Application enablement   stephan massalt (kpn netco)
Application enablement stephan massalt (kpn netco)
 
BBC DMI Project Info for Backstage (Part 1)
BBC DMI Project Info for Backstage (Part 1)BBC DMI Project Info for Backstage (Part 1)
BBC DMI Project Info for Backstage (Part 1)
 
Brief
BriefBrief
Brief
 
2012 Global Awards for Excellence in BPM and Workflow
2012 Global Awards for Excellence in BPM and Workflow2012 Global Awards for Excellence in BPM and Workflow
2012 Global Awards for Excellence in BPM and Workflow
 

NEW C2C SITE FOR DTT NICHE MARKET PENETRATION

  • 1. ORtv Limited Project Proposal New C2C Site for Digital Terrestrial Television (DTT) Niche Market Penetration Project Manager: Eze Igwe Creation Date: 04/02/2015 Last Revised: 06/02/2015 Version: 1.0
  • 2. ORtv Nigeria Ltd. TABLE OF CONTENTS INTRODUCTION.........................................................................................................................................................3 PURPOSE OF PLAN................................................................................................................................................... 3 BACKGROUND INFORMATION...................................................................................................................................3 PROJECT APPROACH................................................................................................................................................ 4 PHASE X: STAKEHOLDERS’ CONTRIBUTION..............................................................................................................4 GOALS AND OBJECTIVES......................................................................................................................................5 BUSINESS GOALS AND OBJECTIVES..........................................................................................................................5 PROJECT GOALS AND OBJECTIVES...........................................................................................................................5 SCOPE...........................................................................................................................................................................6 SCOPE DEFINITION.................................................................................................................................................. 6 PROJECTED BUDGET................................................................................................................................................ 8 RISK ASSESSMENT................................................................................................................................................. 10 INITIAL PROJECT RISK ASSESSMENT......................................................................................................................11 MILESTONES......................................................................................................................................................... 14 ASSUMPTIONS..........................................................................................................................................................15 PROJECT ASSUMPTIONS.........................................................................................................................................15 CONSTRAINTS..........................................................................................................................................................16 PROJECT CONSTRAINTS.........................................................................................................................................16 RELATED PROJECTS .............................................................................................................................................. 16 CRITICAL PROJECT BARRIERS................................................................................................................................16 PROJECT MANAGEMENT APPROACH.............................................................................................................17 PROJECT ROLES AND RESPONSIBILITIES.................................................................................................................17 ISSUE MANAGEMENT............................................................................................................................................. 18 COMMUNICATIONS PLAN.......................................................................................................................................19 ATTACHMENTS/APPENDICES.............................................................................................................................21 APPROVALS..............................................................................................................................................................22 SIGN-OFF SHEET...................................................................................................................................................22 2
  • 3. INTRODUCTION Purpose of Plan The proposed Analogue Switch-Off (ASO) transition roll-out by the Nigerian Broadcasting Corporation (NBC) has created a huge opportunity for Pay-tv service providers to penetrate the large Nigerian Mass Market. To dominate this niche market and riding on the over 100 million Mobile Phone penetration by the GSM service providers, a Consumer-To-Consumer site will provide ORTV the right platform to gain a substantive market share as well as use the same tool to create and retain customers. Using this site, Subscribers can cross-market ORtv products and services and earn a nominal income by accumulating points which can be redeemed as subscription to their accounts or gift items from the ORtv gift catalog. This Proposal will provide a definition of the project, including the project’s goals and objectives. Additionally, the Proposal will serve as an agreement between the following parties: Steering Committee, Project Coordinator, Project Owner, Project Manager, Project Team, and other personnel associated with and/or affected by the project. The Project Plan defines the following: − Project purpose − Business and project goals and objectives − Scope and expectations − Roles and responsibilities − Assumptions and constraints − Project management approach − Ground rules for the project − Project budget − Project timeline and execution − The conceptual design of new technology Background Information The Broadcasting Revolution is well underway in Nigeria and the transition from Analogue to Digital broadcasting is not only in conformance with the guidelines and resolutions of the ITU and NBC but also creating opportunities for Oraqtech Nigeria Limited to achieve a 10 million subscriber base and exponential profitability targets. The ORtv brand provides the DTT platform needed to achieve the required coverage and penetration to keep our targets in perspective and achievable. There is need for concerted effort to be deployed by all facets of the ORtv business to enable a seamless transition through innovative technology and achieve a sustainable competitive advantage. We recognize that the transition will benefit our business extensively but it is a complex process given our business terrain and our regulatory environment Our Business Strategy would rely on a C2C site as a marketing and retention tool to create subscriber base with huge multiplier potential 3
  • 4. C2C DTT Penetration Project Project Approach The Project will be executed in phases using a proactive approach through informed and accurate projections to stay ahead of competition and on top of target markets’ preference. The different phases can happen within over-lapping timelines as execution is imminent. Phase I: Constitute and Inaugurate project Team to ease co- ordination Phase II: Activate a Research and Advisory team to conduct a market survey to determine prospective customer TV preferences Phase III: Design a C2C Site creating existing subscribers on the platform as activation agents who will earn points that can be converted to subscription or redeemed as gifts Phase IV: Test-run Site with internal customers to identify gaps and measure efficiency Phase V: Marketing campaign to create awareness and traction to the C2C site Phase VI: Launch Site Phase VII: Train and support a robust operation for Subscriber Management Phase VIII: Post Launch evaluation and performance audit Phase X: Stakeholders’ Contribution 1. ORtv Management 2. Finance Department 3. Research and Development Department - 4. Marketing Department 5. IT Department 6. Human Resources Department 7. Credit Control and Operations 8. Sales Department 4
  • 5. C2C DTT Penetration Project GOALS AND OBJECTIVES Business Goals and Objectives The business goals and objectives of the Project is to achieve a 10 million subscriber base over a 24 Months period using a C2C Site as a customer acquisition and subscriber management tool − Achieve extensive DTT coverage and penetration in accordance with the ORtv Roll-out plan − Build a 10 million subscriber base − Distribution and value-chain management at required trade and sales capacity − Grow revenue by 100% in 12 Months through C2C mutually beneficial innovations − Reduce operational cost by using IT alternatives to providing services Project Goals and Objectives These are − Design and Deploy a user friendly C2C Site with growing benefits for subscribers and huge returns for the Company − Facilitates coordination of transition activities, site roll-out plan and information sharing both internal and external to all stakeholders − Ensure stock adequacy and inventory management to meet the expected increase in demand for Set-Top-Boxes (STB) created by the C2C site − Cost effective budget − Marketing campaign with deep penetration − Provides an open, flexible, reliable DTT technology base for the future. − Build a virtual supply chain and sales force − Invest in an operational platform that guarantees ease of activation, subscriber management and user friendly devices − Accomplish project business goals and objectives within defined budget and time parameters. − Minimize impact to business operations within the transition period − Gather demographic and market intelligence data to guarantee competitive edge 5
  • 6. C2C DTT Penetration Project SCOPE Scope Definition The Project will achieve an interactive platform that will enable customers act as ORtv agents to resell STBs through direct referrals to prospective customers, registration of deals, fulfillment of transactions and earning of points which can be earned as subscription or gifts − Identify areas of research and investigation to determine customer TV preferences and sales referrals incentives − Identify and deploy the right subscriber management tools as payment and redemption interfaces on a C2C site − Build and Launch a customer friendly C2C e-commerce solution for subscribers to earn their subscription payments − Monitor the volume of trade generated using this portal and measuring the impact on the company bottom-line − Plan and execute marketing campaigns that will reach over 100m GSM users in Nigeria − Grow subscriber base exponentially through this innovative technology and deploy the right retention tools − Provide Training and Support to the operations and subscriber management department − Integrate the billing system into the C2C site − Achieve business goals and objectives within set timelines and budget − Periodic evaluation of site performance and maintenance and constant improvements Including the following interfaces: − Nigerian Broadcasting Corporation (NBC) − GSM Service Providers (MTN, Etisalat, Airtel) − Internet Service Providers (Swift, Smile, ICSL) − Advertising Media (BTL and ATL) Desired Enhancements − Information Technology in-house infrastructure − Warehouse and Stock Holding Capacity − DTT Coverage Area − Distribution and Logistics − Competitive intelligence and Demographic data − Value-chain penetration and market reach − Management and financial support − Alternative Payment Options − Operational tools and training deployments 6
  • 8. C2C DTT Penetration Project Projected Budget $000's ORTV NIG LTD C2C DTT MARKET PENETRATION Labour 2,533 Monitoring Equipment Installation - Labour 22 Business input into specs and testing & System Design Approval 20 Research and Market Survey - Materials 20 Connections - Billing System 65 Connections - Customer Relationship Management 241 Dissemination - Customer engagement via email & training 28 Implementation of PowerOn Fusion 709 Maintenance & Support for PowerOn Fusion 187 Project Management - Website Design 351 Project Management - ePayment Solution 790 Involvement in developing Future Network Planning/Operational Standard 15 Circuit Selection 32 Developing Future Network Planning/Operational Standard 53 Equipment 3,077 Publicity Materials - Informational Pamphlets & postage & packaging 18 Remote Control Installation - Head Office 1,954 Monitoring Equipment Installation - Project Office 112 Remote Control Installation - Materials 563 Commissioning SWIFT link to Remote Control Devices 31 Delivery and configuration of SWIFT IT hardware and software 399 Contractors 2,214 Demand Side Response Customer Survey 391 Project Management - Market Survey 115 Remote Control Installation - Labour 844 Remote Control Installation at Project Office 159 Contractors Travel & Publicity - Informing Affected Customers 42 Connections - Connections Design 303 Data Analysis and Economic Modelling 185 Power System and Technical Modelling 175 IT 739 Data Capture and Cleanse 55 Database Licenses 100 8
  • 9. C2C DTT Penetration Project Develop CRMS Reporting Capability 11 Develop CRMS/PowerOn (SOP) Interface 87 Develop New Interface to PowerOn Fusion 87 Develop Real-time Data Update Functionality 55 Develop Visual Display Functionality for CRMS 73 Initial Data Load Functionality 55 System Integration & Testing 66 Testing and Development Workstation 10 Upload and Store Estimates (into historian) 85 Upload CRMS Diagram and Managed Loads 55 Project Manager - Remuneration 100 Travel & Expenses 50 Payments to users 300 Demand Side Response 300 Contingency 967 Development and Preparation 44 Remote Control Installation 284 Publicity, Training and Dissemination - Operations 125 DSR and Interruptions 100 Project Management 28 Connections 102 Monitoring Equipment 77 Installation and configuration of IT and Implementation of PowerOn Fusion 109 Circuit selection and data upload 24 Analysis, Modelling and Development of Standards 41 System Integration & Testing 13 Decommissioning 20 Other 444 Publicity and Dissemination 257 Accommodation 160 Unplanned interruptions during trial 27 TOTAL PROJECT COST – $10,424,000 9
  • 10. C2C DTT Penetration Project Risk Assessment The initial Risk Assessment attempts to identify, characterize, prioritize and document a mitigation approach relative to those risks which can be identified prior to the start of the project. The Risk Assessment will be continuously monitored and updated throughout the life of the project, with monthly assessments included in the status report (see Communications Plan) and open to amendment by the Project Owner and Project Manager. Because mitigation approaches must be agreed upon by project leadership (based on the assessed impact of the risk, the project’s ability to accept the risk, and the feasibility of mitigating the risk), it is necessary to allocate time into each Steering Committee meeting, dedicated to identifying new risks and discussing mitigation strategies. The Project Manager will convey amendments and recommended contingencies to the Steering Committee monthly, or more frequently, as conditions may warrant. 10
  • 11. C2C DTT Penetration Project Initial Project Risk Assessment Risk Risk Level L/M/H Likelihood of Event Mitigation Strategy Project Size Person Hours H: Over 20,000 Certainty Assigned Project Manager, Site Engineers and hands-on project team, comprehensive project management approach and communications plan Estimated Project Schedule H: Over 12 months Certainty Created comprehensive project timeline with frequent baseline reviews Team Size at Peak H: Over 15 members Certainty Comprehensive communications plan, frequent meetings, tight project management oversight Number of Interfaces to Existing Systems Affected H: Over 4 Certainty Develop interface control document immediately Project Definition Narrow Knowledge Level of Users M: Knowledgeable of user area only Likely Assigned Project Manager(s) and Team members to assess global implications Available documentation and data clouds establishment of baseline M: More than 75% complete/current Likely Balance of information to be gathered by team and Customer Insight Project Scope Creep L: Scope generally defined, subject to revision Unlikely Scope intially defined in project plan, reviewed monthly by three groups (Project Manager and Steering Committee) to prevent undetected scope creep Project Deliverables unclear L: Well defined Unlikely Included in project plan, subject to amendment Technical Team Project Deliverables M: Estimated, not clearly defined Somewhat likely Included in project plan but requires more information, subject to amendment Cost Estimates Unrealistic L: Thoroughly predicted by finance experts using proven practices to less than 15% margin of error Unlikely Included in project plan, subject to amendment as new details regarding project scope are revealed 11
  • 12. C2C DTT Penetration Project Risk Risk Level L/M/H Likelihood of Event Mitigation Strategy Timeline Estimates Unrealistic M: Timeline assumes no derailment Somewhat likely Timeline reviewed monthly by three groups (Project Manager and Steering Committee) to prevent undetected timeline departures Number of Team Members Unknowledgeable of Business L: Team well versed in business operations impacted by technology Unlikely Project Manager to identify knowledge gaps and provide training, as necessary Project Leadership Steering Committee existence L: Identified and enthusiastic Unlikely Frequently seek feedback to ensure continued support Absence of Commitment Level/Attitude of Management L: Understands value & supports project Unlikely Frequently seek feedback to ensure continued support Absence of Commitment Level/Attitude of Project Team L: Understands value & supports project Unlikely Frequently seek feedback to ensure continued support Absence of Mid- Management and Staff Commitment L: Most understand value & support project Unlikely Frequently seek feedback to ensure continued support Staffing & Funding Project Team Availability M: Diverse team makes availability questionable Somewhat likely Continuous review of project momentum by all levels. HR to identify any impacts caused by unavailability. If necessary, increase committmment by participants to full time status Physical Location and primary responsibility of Team prevents effective management M: Team is dispersed among several functions Likely Use of Intranet project website on pundit, comprehensive Communications Plan Project Team’s Shared Work Experience creates poor working relationship M: Some have worked together before Somewhat likely Comprehensive Communications Plan Weak User Participation on Project Team L: Users are part- time team members Unlikely User Group Participants coordinated by full time employee Project Management Funding Methodology Used unknown to team L: Procurement Methodology familiar to team Unlikely N/A Change Management Procedures undefined L: Well-defined Unlikely N/A Quality Management Procedures unclear L: Well-defined and accepted Unlikely N/A IT Team Number of Times Team Has Done Prior Work with Vendor Creates M: Project Owner has always worked with the Technical Likely Comprehensive briefing by previous participants will bring the rest of the Team to speed12
  • 13. C2C DTT Penetration Project Risk Risk Level L/M/H Likelihood of Event Mitigation Strategy Foreign Relationship Team on Work-In-Progress (WIP) Project Team’s Lack of Knowledge of C2C relevant experience M: Conceptual understanding Somewhat likely Comprehensive briefing by previous participants will bring the rest of the Team to speed on Work-In-Progress (WIP) Poor Coverage of Transmitters in existing DTT cities H: Emphasis on metropolis as against mass market dwellings Certainty Additional transmitters will need to be constructed and deployed in such cities e.g Abuja and Port Harcourt Team’s Involvement in Transmission sites Selection Impacts Success of Implementation L: High involvement in selection Unlikely Periodic meetings to identify high opportunity markets and prioritize resources for transmitter deployments 13
  • 14. C2C DTT Penetration Project Milestones Description of Milestone Sub Steps (if any) #1. Conduct extensive Research on Customer TV Preferences to determine areas of content creation and investments in strong selling points. Sub Step #1 - Delineate the Nigerian Market Sub Step #2 - Determine size of target market Sub Step #3 - Focus on existing customers using android devices #2. Invest in a Robust Subscriber Management Tool and Billing System to enable database updates and cleansing. Partner epayment solution providers to create a payment and points management platform Sub Step #1 - Ensure all customer data are captured Sub Step #2 - Increase the size and speed of Billing Tool Sub Step #3 - Integrate a viable and efficient payment and point capturing platform #1. Recruit Web Design Consultant and determine DIY functionalities to enable subscribers manage their accounts from their mobile devices Sub Step #1 - Recruit Consultant and sign Agreements Sub Step #2 - Present Web design and Online Account User profiles Sub Step #3 - Upload customer profiles from Subscriber Management platform to Website #2. Completion of Web design and presentation to Senior Management for critic and adoption Sub Step #1 - Completion of Web Design Sub Step #2 - Presentation to Senior Management Sub Step #3 - Adoption and Approval by Project Owner and Sponsors #1. Test Run of Web Site with Internal Customers and Select Subscribers from diverse markets Sub Step #1 - Create all Internal Customers on Web Portal Sub Step #2 - Include select Subscribers from diverse markets Sub Step #3 -Close Customer to Customer deals and measure Turn Around Time and Satisfaction Rating #2. Train Operations and IT Staff who will monitor and manage C2C Interface Sub Step #1 - Create a Support Team Sub Step #2 - Train and Retrain Operations and IT Staff Sub Step #3 - Provide Product Knowledge Training to all Customer facing staff #3. Deploy BTL and ATL Campaign across diverse markets especially using GSM Service Providers Marketing platforms to reach existing and prospective Subscribers Sub Step #1 - Choose a Marketing Campaign Slogan (Sell & Smile) Sub Step #2 - Adopt a staff and customer sensitization and awareness campaign Sub Step #3 - Deploy Marketing conccepts across BTL and ATL platforms #1. LAUNCH C2C WEBSITE Sub Step #1 - Launch New C2C Site with Stakeholders Sub Step #2 - Launch in Regional Markets Sub Step #3 - Sustain Aggressive campaign across platforms 15 months #1 Conduct Post Launch Performance Audit and Evaluations Sub Step #1 - Measure customer satisfaction Sub Step #2 - Measure Market Penetration sucess Sub Step #3 - Measure Impact on Revenue 6 months 9 months 12 months 3 months 14
  • 15. C2C DTT Penetration Project ASSUMPTIONS Project Assumptions The following assumptions were made in preparing the Project Plan: − ORTV management and staff are informed and willing to take advantage of the opportunity offered by the Analogue Switch-Off (ASO) transition programme led by NBC − Management will ensure that project team members are available as needed to complete project tasks and objectives. − The Steering Committee will participate in the timely execution of the Project Plan (i.e., timely approval cycles and meeting when required). − Failure to identify changes to draft deliverables within the time specified in the project timeline will result in project delays. − Project team members will adhere to the Communications Plan. − Mid and upper management will foster support and “buy-in” of project goals and objectives. − The business will ensure the existence of a technological and transmission infrastructure that can support the C2C site Roll-out. − All project participants will abide by the guidelines identified within this plan. − The Project Plan may change as new information and issues are revealed. 15
  • 16. C2C DTT Penetration Project CONSTRAINTS Project Constraints The following represent known constraints to the C2C DTT Penetration Project: − Project funding could be limited, with no contingency. − Due to the nature of regulatory enforcement and Government bureaucracies the Digital Transition Roll-out might be inconsistent − Online web usage knowledge among subscribers might be limited − A large number of GSM users do not use Android devices − Poor Sells incentives for Customers Related Projects - DTT Transmitters Roll-out Project - Consumer Behaviour Research Projects - STB Manufacturing Project Critical Project Barriers Unlike risks, critical project barriers are insurmountable issues that can be destructive to a project’s initiative. In this project, the following are possible critical barriers: − Inefficient Internet Services by ISPs − NBC Regulatory bottlenecks Should any of these events occur, the Project execution could be threatened 16
  • 17. C2C DTT Penetration Project PROJECT MANAGEMENT APPROACH Project Roles and Responsibilities Role Responsibilities Participant(s) Project Sponsor  Ultimate decision-maker and tie-breaker  Provide project oversight and guidance  Review/approve some project elements ORtv Management Steering Committee  Commits department resources  Approves major funding and resource allocation strategies, and significant changes to funding/resource allocation  Resolves conflicts and issues  Provides direction to the Project Manager  Review project deliverables VP – Marketing VP – Operations VP – HRM VP – IT VP – Sales VP – R&D/Strategy VP – Finance Project Manager  Manages project in accordance to the project plan  Serves as liaison to the Steering Committee  Receive guidance from Steering Committee  Supervises consultants  Supervise vendor(s)  Provide overall project direction  Direct/lead team members toward project objectives  Handle problem resolution  Manages the project budget Eze Igwe Project Participants (Team)  Understand the user needs and business processes of their area  Act as consumer advocate in representing their area  Communicate project goals, status and progress throughout the project to personnel in their area  Review and approve project deliverables  Creates or helps create work products  Coordinates participation of work groups, individuals and stakeholders  Provide knowledge and recommendations  Helps identify and remove project barriers  Assure quality of products that will meet the project goals and objectives  Identify risks and issues and help in resolutions Team Member – Marketing Team Member – Operations Team Member – HRM Team Member – IT Team Member – Sales Team Member – R&D Team Member - Finance Consultants  Lend expertise and guidance as needed Web Design Consultant 17
  • 18. C2C DTT Penetration Project Issue Management The information contained within the Project Proposal will likely change as the project progresses. While change is both certain and required, it is important to note that any changes to the Project Plan will impact at least one of three critical success factors: Available Time, Available Resources (Financial, Personnel), or Project Quality. The decision by which to make modifications to the Project Plan (including project scope and resources) should be coordinated using the following process: Step 1: As soon as a change which impacts project scope, schedule, staffing or spending is identified, the Project Manager will document the issue. Step 2: The Project Manager will review the change and determine the associated impact to the project and will forward the issue, along with a recommendation, to the Steering Committee for review and decision. Step 3: Upon receipt, the Steering Committee should reach a consensus opinion on whether to approve, reject or modify the request based upon the information contained within the project scope, the Project Manager’s recommendation and their own judgment. Should the Steering Committee be unable to reach consensus on the approval or denial of a change, the issue will be forwarded to the Project Sponsor, with a written summation of the issue, for ultimate resolution. Step 4: If required under the decision matrix or due to a lack of consensus, the Project Sponsor shall review the issue(s) and render a final decision on the approval or denial of a change. Step 5: Following an approval or denial (by the Steering Committee or Project Sponsor), the Project Manager will notify the original requestor of the action taken. There is no appeal process. 18
  • 19. C2C DTT Penetration Project Communications Plan Disseminating knowledge about the project is essential to the project’s success. Project participants desire knowledge of what the status of the project is and how they are affected. Furthermore, they are anxious to participate. The more that people are educated about the progress of the project and how it will help them in the future, the more they are likely to participate and benefit. This plan provides a framework for informing, involving, and obtaining buy-in from all participants throughout the duration of the project. Audience This communication plan is for the following audiences: − Project Sponsor − Steering Committee − Project Manager − Project Team − Subject Matter Experts Communications Methodology The communications methodology utilizes three directions for effective communication: Top-Down It is absolutely crucial that all participants in this project sense the executive support and guidance for this effort. The executive leadership of the organization needs to speak with a unified, enthusiastic voice about the project and what it holds for everyone involved. This will be 'hands-on' change management, if it is to be successful. Not only will the executives need to speak directly to all levels of the organization, they will also need to listen directly to all levels of the organization, as well. The transition from the project management practices of today to the practices envisioned for tomorrow will be driven by a sure and convinced leadership focused on a vision and guided by clearly defined, strategic, measurable goals. Bottom-Up To ensure the buy-in and confidence of the personnel involved in bringing the proposed changes to reality, it will be important to communicate the way in which the solutions were created. If the perception in the organization is that only the Steering Committee created the proposed changes, resistance is likely to occur. However, if it is understood that all participants were consulted, acceptance seems more promising. 19
  • 20. C2C DTT Penetration Project Middle-Out Full support at all levels, where the changes will have to be implemented, is important to sustainable improvement. At this level (as with all levels), there must be an effort to find and communicate the specific benefits of the changes. People need a personal stake in the success of the project management practices. Communications Outreach The following is a list of communication events that are established for this project: Monthly Status Reports The Project Manager shall provide monthly written status reports to the Steering Committee. The reports shall include the following information tracked against the Project Plan: - Summary of tasks completed in previous month - Summary of tasks scheduled for completion in the next month - Summary of issue status and resolutions Monthly Steering Committee Meeting These status meetings are held at least once per month and are coordinated by the Project Manager. Every member of the Steering Committee participates in the meeting. The Project Manager sends the status report to each member of the team prior to the meeting time so everyone can review it in advance. Bi-Monthly Project Team Status Meeting These status meetings are held every other month. Every member of the Project Team will be invited to participate in the meeting. Project Manager sends the status report to each member of the team prior to the meeting so everyone can review it in advance. 20
  • 21. C2C DTT Penetration Project ATTACHMENTS/APPENDICES 21 Project Sponsor – ORTV Management Steering Committee Project Manager Eze Igwe Team Member - Marketing Team Member - Operations Team Member - HRM Team Member - IT Team Member - Sales Team Member – R&D Team Member - Finance
  • 22. C2C DTT Penetration Project APPROVALS Sign-off Sheet I have read the above Project Proposal and hereby append my approval and support to the Project Project Sponsor: Date Project Manager: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date 22