2. EPRO Company Profile EPRO Company Profile
EPRO Power and Industrial Plants Inc. was founded in 1997 by five engineers and an economist, who as members of a management
team, have successfully managed and completed major industrial and power plant construction projects both in Turkey and abroad
between the years 1985-1997.
The main operational objective of EPRO Power and Industrial Plants Inc. to undertake and realize challenging construction and
fabrication projects in the following fields; We are pleased to announce that as of 3 January 2011, EPRO Power and Industrial Plants Inc. has become a subsidiary Company of
TML Construction Co. Istanbul.
TML Construction Co. (www.tml.com.tr) as a leading international construction Co. (ranking 219 th in “ENR-The Top 225 International
Contractors List-2010”) is currently active in Turkey, Libya and Azerbaijan and has recently extended its operations to the Gulf Region
by recently established companies “TML Saudia” at Dammam – KSA and a branch in Abu Dhabi UAE.
Having reinforced and strengthened its financial and operational structures with this new alliance, EPRO is looking forward to new
business opportunities in Turkey, Caspian Region, The Midde East, Europe and Africa.
Having optimized its physical and financial resources during the first thirteen years of its successful operations, EPRO Power and
Industrial Plants Inc. is now dynamically structured to employ all major erection and
fabrication disciplines including mechanical, piping, electrical, instrumentation, structural steel erection works and to perform detailed
engineering and procurement of project materials.
Having successfully completed Power Plant Projects in Azerbaijan, Dubai and Albania EPRO has become the first Turkish Company
ever to manufacture Heat Recovery Steam Generators (HRSG) abroad and now is aiming to enlarge its activities in the growing Power
Generation Sectors of the Europe, Middle East, Caspian Region and Africa.
POWER PLANTS
Combined Cycle and Cogeneration Plants
Gas Turbines
Thermal Power Plants
Hydraulic Power Plants
Diesel Power Plants
Desalination Plants
PIPELINES AND TERMINALS
Crude Oil and LNG Terminals
Crude Oil and Natural Gas Pipelines
Pumping Stations
Compressor Stations
Water Transmission Pipelines
FABRICATION OF POWER BOILERS AND
PRESSSURE VESSELS (ASME S & U)
HRSG Modules Fabrication
Boiler Piping
Pressure Vessels
STEEL STRUCTURE FABRICATION AND
ERECTION
Structural Steel for Industrial Buildings
Platforms, Decks, Towers, etc. Storage Tanks,
Stacks Secondary Steel Structures
INDUSTRIAL PLANTS
Iron and Steel Plants
Cement Plants
Glass and Ceramic Plants
Automotive Assembly Plants
Electronic Hardware Plants
Food, Beverage and Medicine Plants
Copper/Zinc Mills
ENVIRONMENT
Water Treatment Plants
Flue Gas Treatment Plants
Solid Waste Treatment Plants
POWER DISTRIBUTION
FACILITIES
Transformer Substations
PROCESS PLANTS
Petroleum Refineries
Petrochemical Plants
Fertilizer Plants
3. EPRO Organization Chart
EPRO Quality Management
System Certificates
BOARD OF DIRECTORS
GENERAL MANAGER
AGENCIES
ASST. GENERAL MNG.
Operations
Executive Assistant
Warehouse
Machinery &
Equipment
Superintendent Commercial Manager
Accounting Manager
Person & Admin. Chief
Const. Superintendent Const. Superintendent
Site Managers Site Managers
Business Develop.
Asst.
Plan. & Cost Cont.
Asst.
HRSG Module
Superintendent
St. Steel
Superintendent
Technical Manager
ADVISORS
QUALITY
MANAGEMENT
Legal Advisor
Technical Advisor
QA/QC Engineers
QA/QC Technicians
ASST. GENERAL MNG.
Operations
ASST. GENERAL MNG.
Planning & Logistic
ASST. GENERAL MNG.
Fabrication
ASST. GENERAL MNG.
Finance & Admin.
4. COMPLETED PROJECTS by EPRO
SUPSA ON-SHORE OIL TERMINAL
Supsa, GEORGIA
Owner : Georgian Pipeline Company
Consultant : Kvaerner John Brown
Main Contractor : TML – Borova Joint Venture
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : May 1998
Description of work : Underground and Aboveground Piping
Installation Works consisting of;
• 1800 meters of Storm Water, Oily Water and Foul Water Piping (DN 100 to DN 700).
• 3000 meters of Fire Fighting Pipework (DN 150 to DN 300)
• Both underground and aboveground including Hydrants and Monitors.
• 200 tons of Piperack and Pipe Supports
EEE GAS TURBINE POWER PLANT 1x40 MW
Eskişehir OSB, TURKEY
Owner : Eskişehir Industrial Power Generation Auto
Production Group Co.
Supplier of Main Equipment : European Gas Turbines – SA GEC ALSTHOM
Contractor : EPRO Power and Industrial Plants Inc.
Date of Completion : April 1998
Description of work : Complete Mechanical, Electrical and
Instrumentation Installation Works of a Frame
6 type Gas Turbine
Power Plant
The first stage of the Combined Cycle Power
Plant) including;
• 328 tons Mechanical and Electrical Equipment.
• 10 tons Piping.
• 3 tons Power & Control Cables.
• Complete NDT Services.
5. Owner : TEAS, Turkish Electricity Corp.
Main Contractor : SİMKO – SIEMENS
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : August 1998, Selimiye S/S - November 1998, Levent S/S
Description of work : Complete Electrical, Mechanical and Instrumentation
Installation Works of 170 kV GIS (Gas Insulated Switchgear)
Transformer Substations including;
• 17 no. 154 kV GIS Switchgear Feeders.
• 65 no. 34.5 kv Metal Enclosed Switchgear Feeders.
• 43 no. 11 kV Metal Clad Switchgear Feeders.
• 75 no. Control & Protection Panels for HV and LV Systems.
• 44 km. HV/MV/LV and Control Cables and Accessories.
• AC & DC and Auxiliary Systems.
170 kv GIS TRANSFORMER SUBSTATIONS - İstanbul, TURKEY
SELİMİYE TR. SUBSTATION, 154 / 34.5 / 11kV, 1x100 + 2x50 MVA LEVENT
TR. SUBSTATION 154 / 34.5 kV, 4 x 50 MVA
TENGIZCHEVROIL KTL 2.3 EXPANSION PROJECT
KAZAKHSTAN PIPE SPOOLS FABRICATION
İstanbul, TURKEY
Owner : Tengizchevroil
Main Contractor : BETCHEL ENKA J.V
Fabrication Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : November 1998
Description of work : Fabrication of Pipe Spools for the Interconnecting
Piping System of 4 no.’s of FM type Utility Boilers
and Pipe Connections to Water Deminerilazition
Plant including;
• 80 tons Pipe Spools (Pipe diameters.range from 2” to 14”).
• Complete NDT Services.
• Painting of Pipe Spools.
BIS ENERGY COMBINED CYCLE POWER PLANT
Bursa, TURKEY
Owner : Bis Energy
Main Contractor : Babcock & Wilcox GAMA (BWG)
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : July 1999
Description of work : Complete Mechanical, Electrical and Instrumentation
Installation
Works of two HRSG’s, one for Frame 6, and one for
LM 6000 type Gas Turbines and all External Piping
Work including;
• Frame 6 HRSG contains about 660 tons of Pressure Part and 300 tons of Non
Pressure Part.
• LM 6000 contains about 440 tons of Pressure Part and 200 tons of Non
Pressure Part.
• External Piping total weight (Alloy, SS and CS) is about 260 tons.
• Piperack and Pipe Support weight is about 240 tons.
• Heaviest Single Piece in this project was a Heating Module (173 tons) which was
handled by one 440 t. and one 330 t. Hydraulic Mobile Cranes together.
• Complete Electrical and Instrumentation Installations.
TOMSKNEFT GAS COMPRESSOR STATION
Leuginetskoye, Tomsk Area Western
Siberia, RUSSIAN FEDERATION
Owner : OAO TOMSKNEFT VNC
Main Contractor : Bateman International B.V, GAMA Industrial Plants
Manufacturing & Erection Corp.
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : November 1998
Description of work : Complete Electrical and Instrumentation Installation
Works of Main
Compressor Station and Booster Compressor Station
including;
• 6 no. Power Transformers and Diesel Generators.
• 134 no. MV, LV Switchgears and MCC’s and HT panels.
• 1315 no. Lighting Fixtures including Poles, Supports and Accessories.
• 262 km. Power & Control and Instrument Cables including Terminations.
• 22 km. Heat Tracing Cables and complete HT Systems.
• 25 km. Cable Ladders, Trays and Conduits.
• 3120 no. Field Instruments including Calibration and Loop Checks.
• 8 km. Instrument Impulse Piping.
• 30 no. Instrument Panels (DCS & ESD Systems).
• UPS, Power Metering and Monitoring Systems, Complete Lightning Protection &
Grounding Systems.
• Fire & Gas Detection Systems, Telephone
6. NUH ÇİMENTO COMBINED CYCLE POWER PLANT
Hereke, TURKEY
Owner : Nuh Çimento A.Ş.
Main Contractor : NEM - Netherlands
HRSG Subcontractor : Babcock & Wilcox GAMA (BWG)
Erection Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : October 1999
Description of work : Complete Mechanical, Electrical and Instrumentation
Works of one HRSG for
LM 2500+ type Gas Turbine and all External Piping
Work including;
• HRSG contains about 285 tons of Pressure Part and 253 tons of Non Pressure Part.
• External Piping total weight (alloy, SS and CS) is about 27 tons.
• Pipe Rack and Pipe Support weight is about 25 tons.
• Heaviest Single Piece in this project was the Heating Module (140 tons) which was
handled by one 440 t. and one 330 t. Hydraulic Mobile Cranes together.
• Complete Electrical and Instrumentation Installations.
ÇAYELİ COPPER WORKS INC. PASTEFILL PLANT
Rize, TURKEY
Owner : Çayeli Copper Works Inc.
Main Contractor : EPRO Power and Industrial Plants Inc.
Date of Completion : March 1999
Description of work : Civil Construction and Mechanical, Electrical and
Instrumentation Erection Works of Paste fill Plant including;
• Complete Civil Works.
• Supply, Fabrication and Erection of a Three Storied Steel Building.
• Supply, Fabrication and Erection of an Elevated Steel Thickener Tank and an
Agitated Storage tank.
• Mechanical Erection of all Plant Equipment.
• Supply and Erection of Victaulic Grooved Piping and Utility Piping Systems.
• Supply of Power & Control and Instrument Cables, complete Plant Instruments,
Lighting Fixtures.
• Complete Electrical and Instrumentation Erection Works.
• Modification Works to existing Thickeners and Tailings Disposal System.
TRAKYA ELEKTRİK A.Ş.
478 MW COMBINED CYCLE POWER PLANT
Marmara Ereğlisi, TURKEY
Owner : Trakya Elektrik A.Ş.
Main Contractor : NOOTER ERIKSEN - U.S.A.
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : June 1999
Description of work :
• Repair and replacement of internals on two silencers
• Supply of material, fabrication and erection of new Bundle
bypass plates inside Heat Recovery Steam Generators
Owner : Trakya Elektrik A.Ş.
Main Contractor : ENRON Engineering and
Construction Co. - U.S.A
Subcontractor : EPRO Power and Industrial
Plants Inc.
Date of Completion : September 1999
Description of work :
Various repair and new complementary works inside Steam and Gas
Turbines Building,
Heat Recovery Steam Generators and BOP. The works include ma-
terial supply and fabrication.
7. TRAKYA ELEKTRİK A.Ş.
478 MW COMBINED CYCLE POWER PLANT
Marmara Ereğlisi, TURKEY
Owner : Trakya Elektrik A.Ş.
Main Contractor : EPRO Power & Industrial Plants Inc.
Date of Completion : January 2000
Description of work : Underground and Aboveground fire water
piping installation.
• Stainless steel piping
• H.D.P.E. underground piping
• NDT Services
• Excavation, back filling and concrete works.
Owner : Trakya Elektrik A.Ş.
Main Contractor : EPRO Power & Industrial Plants Inc.
Date of Completion : February 2000
Description of work : Turnkey construction of one.. Warehouse & Weldingshop
building Engineering Design
• Fabrication, Painting and Erection of 22 tons steel Structures.
• Supply and Erection of 600 m² roof and sidewall cladding.
• Supply and Erection of Electrical Power & Lighting Systems and Fire Alarm System.
TÜPRAŞ CCR & ISOMERIZATION PLANT PROJECT
Aliağa, İZMİR, TURKEY
Owner : TÜPRAŞ, Turkish Petroleum Refineries Corp. İzmir Refinery
Consultant : Foster Wheeler Italiana
Main Contractor : GAMA Industrial Plants Manufacturing and Erection Corp.
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : September 2000
Description of work : CCR & Isomerization Plant project, Spool Fabrication and
Erection works of Underground and Aboveground Pipe
Lines including;
• 645 tons On site Aboveground Piping Erection
• 285 tons Off site Aboveground Piping Erection
• 215 tons On site Underground Piping fabrication and Erection
• 100 tons Pipe Support Fabrication and Erection
ÇAYELİ COPPER WORKS INC.
MILL PLANT MODIFICATION WORKS
Rize, TURKEY
Owner : Çayeli Copper Works Inc.
Consultant : Foster Wheeler Bimaş
Main Contractor : EPRO Power and Industrial Plants Inc.
Date of Completion : August 2000
Description of work : Civil Construction and Mechanical, Electrical and
Instrumentation Erection
Works of Mill Plant modifications including;
• Civil Construction works of a New Lime Storage Building and a Compressor Building.
• Civil Modification Works at the Mill Plant.
• Supply, fabrication and erection of Steel Structures.
• Installation of a New Filter Press at the Mill Plant.
• Supply and Installation of pipes, fittings valves, vessels etc. at the Mill Plant.
• Supply and Installation of Electrical and Instrumentation equipment and materials.
8. SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
“REROUTING WORKS OF MECHANICAL & ELECTRICAL
PORTION”Shuvelan, REPUBLIC OF AZERBAIJAN
Owner : Joint Stock Company AZERENERJİ
Consultant : Burns and Roe Enterprises, Inc.
Main Contractor : Mitsubishi Heavy Industries ,Ltd.
Civil and M/E/I Erection : TML - BOROVA
Works Subcontractor : EPRO Power and Industrial Plants, Inc.
Date of Completion : November 2000
Description of work : Rerouting of existing Power Plant active facilities such
as pipe lines.
(Fuel Gas, Fuel Oil, H2&CO2 Gas, Steam,
Raw/Condensate/Make-up Water, Chemical &
Hydrazinepipelines) and U/G cables which are run
through, new Power Plant area including;
• 163 tons Piping Fabrication and Erection.
• 22 tons Pipe Support Fabrication and Erection.
• 1,700 m U/G Power Cables Installation.
• 7,700 m² Painting including supply of Paint Material.
• 1,425 m² Insulation of pipelines.
EEE COMBINED CYCLE POWER PLANT
Eskişehir OSB, TURKEY
Owner : Eskişehir Industrial Power Generation
Autoproductor Group Co.
Supplier of Main Equipment : BABCOCK & WILCOX ESPANOLA S.A
Contractor : EPRO Power and Industrial Plants Inc.
Date of Completion : April 2001
Description of work : Complete Mechanical and Instrumentation
Erection Works of a Heat
Recovery Steam generator and associated
equipment.
• 523 tons Mechanical Equipment.
• 17 tons Piping including supports and valves.
• Complete Instrument Installation works including supply of cables, cabletrays,
• Conduits and junction boxes.
• Complete Inspection and Test. (i.e. NDT, PWHT, HT, Blow-out)
TÜPRAŞ ISOMERIZATION PLANT PROJECT
Körfez, KOCAELİ, TURKEY
Owner : TÜPRAŞ, Turkish Petroleum Refineries Corp. İzmit Refinery
Consultant : Technicas Reunidas
Main Contractor : Technicas Reunidas - ENTES A.Ş. Consortium
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : December 2001
Description of work : Fabrication, Erection Testings and Cleaning Works of
Process and Utility
Piping Both Above and Underground Inside Boundary
Limits of Isomerization Project.
• Piping Materials; Carbon Steel, Alloy Steel and Stainless Steel
• Pipe diameters ranging from ½” to 30”
• Total pipe quantity 1,320 tons.
• 144,720 dia-inch Welding Joints and 5,450 dia-inch threated joints
• 361 no. of test packages.
SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
Owner : Joint Stock Company AZERENERJİ
Consultant : Burns and Roe Enterprises, Inc.
EPC Main Contractor : Mitsui & Co. Ltd.
Sub - Contractors : Mitsubishi Heavy Industries ,Ltd. and ABB
Civil Works s/c : TML – BOROVA
M/E/I Erection Works s/c : EPRO Power and Industrial Plants, Inc.
Date of Start /Completion : M/E/I Works 01 August 2001 - 15 November 2002
Description of work : Complete Mechanical / Electrical / Control &
Instrumentation Erection Works of 400.MW
Single-Shaft
Combined Cycle Power Plant including Structural
Steel works of GT Building / Pump House and
Underground CW Pipeline.
9. SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
MITSUI & Co.Ltd. / MITSUBISHI HEAVY INDUSTRIES Ltd.
Prequalification Certificates
SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
BASIC TECHNICAL INFORMATION:
400MW, Single Unit, Combined-Cycle, Single-Shaft, Dual Fuel Plant
GT : One Mitsubishi M701 F Gas Turbine (made in Takasago, Japan)
ST : One Mitsubishi TC2F-35.4 Re-Heat Cycle Steam Turbine (made in Japan)
HRSG : One CMI Triple Pressure + Reheat, Natural Circulation (made in Belgium)
GEN : One ABB-ALSTOM 50WT21H-120, Hydrogen Cooled (made in Switzerland)
OTHERS : Water Treatment, Waste Water Treatment, Aux. Boiler, Storage Tanks, Water Intake Pumps, 110 kV GIS System
SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
ERECTION SCOPE OF WORKS:
MAJOR EQUIPMENT
Turbine & Aux. : 710 ton
Steam Turbine & Aux. : 960 ton
Main Transformer : 270 ton
Gas Compressor : 110 ton
Water Treatment Plant : 100 ton
Start-Up Boiler : 175 ton
Others : 800 ton
Total : 3125 ton
PIPING
Cooling Water Pipes : 2500 ton
Power House & Off-Sites : 1200 ton
Total : 3700 ton
STEEL STRUCTURE
Turbine - Gen. Building : 1200 ton
Others : 445 ton
Total : 1645 ton
STORAGE TANKS
CST10000 qm, FOT5000qm : 414 ton
SW/FW, PW, LOT : 93 ton
Total : 506 ton
ELECTRICAL &
INSTRUMENTATION
Power & Lighting Cables : 118 km
Control & Instrum. Cables : 213 km
Switchgears, UPS, Batteries
Control Systems, Instruments
HRSG
Steel Structure : 480 ton
Modules : 1666 ton
Drums & BDT : 136 ton
Casing, Ducting & Stac : 211 ton
Piping : 230 ton
Insulation : 75 ton
Others : 50 ton
Total : 2848 ton
SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
10. SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
SEVERNAYA 400 MW COMBINED CYCLE POWER PLANT
Shuvelan, REPUBLIC OF AZERBAIJAN
11. ANKARA OSB COMBINED CYCLE POWER PLANT
Ankara, TURKEY
Owner : Ankara Chamber of Industry, Organized Industrial
Zone Administration
EPC Contractor : ZORLU Enerji Electric Generation Auto producer
Group Co. Inc.
Supplier of HRSG : AALBORG Engineering A/S - Denmark
Contractor : EPRO Power and Industrial Plants Inc.
Date of Completion : October 2002
Description of work : Complete Mechanical, Electrical and Instrumentation
Erection Works of a Heat Recovery Steam generator and
associated equipment.
• 345 tons Mechanical Equipment
• 25 tons Piping including supports and valves
• Complete Electrical and Instrument Installation works including supply of
Electrical Heat Tracing System, Conduits and junction boxes
• Complete Inspection and Test (i.e. NDT, PWHT, HT, Blow-out)
AIOC Full Field Development Phase 1 Upgrade of SPS
Fabrication Yard Project
REPUBLIC OF AZERBAIJAN
Owner : Azerbaijan International Operating Company
Main Contractor : McDermott Caspian Contractors Inc.
Civil Works : TML – BOROVA
Mechanical Works S/C : EPRO Power and Industrial Plants, Inc
Date of Completion : August 2002
Description of work : Complete Mechanical Works within the scope of
Miscellaneous Civil Works Contract including;
• Design, supply, installation and commissioning of utility piping (water, fire water,
compressed air, propane, oxygen and underground sewer) systems
• Installation and commissioning of water and fire water pumps
• Chemical cleaning of gas piping systems in various parts of the SPS Fabrication Yard
• Fabrication of embedded steel items for pile caps
ACG Full Field Development Phase 1 Fabrication and
Erection of Dummy Drill Floor,
REPUBLIC OF AZERBAIJAN
Owner : Azerbaijan International Operating Company
Main Contractor : McDermott Caspian Contractors Inc.
Civil and Mech. Erection : TML – BOROVA
Works Subcontractor : EPRO Power and Industrial Plants, Inc.
Date of Completion : April 2003
Description of work : Fabrication and Erection of Dummy Drill Floor Steel
Structure including;
• Detail Design
• Supply and Fabrication of I1800x990x60x35 Built-Up Beams
• Supply and Fabrication of Dummy Drill Floor Beams and Deck Plates
• Erection of above
KARADAGH GAS COMPRESSOR STATION PROJECT
Karadagh, REPUBLIC OF AZERBAIJAN
Owner : Joint Stock Company AZERGAZ
Main Contractor : Toyo Engineering Corp.
Civil and M/E/I Erection : TML - BOROVA
Works Subcontractor : EPRO Power and Industrial Plants, Inc.
Date of Completion : August 2003
Description of work : Complete Mechanical/Electrical/Control &
Instrumentation Erection Works of Gas Compressor
Station also including;
• Supply of all structural steelwork for compressor building and pipe racks
• Design, supply and fabrication of fire works storage tank
• Supply and fabrication of vent stack
12. YAROSLAVL REFINERY MODERNIZATION PROJECT
(Yaroslavl, Russian Federation)
STRUCTURAL STEEL FABRICATION - İstanbul, TURKEY
Owner : OAO Slavneft - Yaroslavnefteorgsintez
Main Contractor : TOYO Engineering Corporation (Japan)
Fabrication Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : April 2004
Description of work : Supply and Fabrication of 550 metric tons of
structural steel for the Yaroslavl Refinery
Modernization Project. 72m height Reforming and
Regeneration Structure including;
• Detail Design
• Shop Drawings and Erection Drawings
• Supply of raw material
• Surface preparations and painting
• Fabrication of columns, girders, sub beams, staircase, ladders, handrails,
hoist rails and gratings
• Complete QC Service
BP EXPLORATION (SHAN DENIZ) LTD. / MCCI
MECHANICAL WORKS FOR INTEGRATED LOGISTICS PROJECT
(ILP) Phase 1A TANK FARM, Baku - AZERBAIJAN
Owner : Azerbaijan International Operating Company
Main Contractor : BP, Mc DERMOTT Caspian Contractors Inc.
Sub Contractor : TML (Civil works)
Mechanical Works : EPRO Power and Industrial Plants Inc.
Date of Completion : October 2004
Description of work : Complete Mechanical Works within the scope of;
external mechanical works, external fire and
safety works.
• Design, supply, fabrication, installation and commissioning of piping
(loading pipes to quayside and
rundown lines, main water supply lines, connection with diverting existing
main, process unit piping,
fire fighting pipes.
• Installation and commissioning of water and fire pumps, process unit,
treatment plant
• Design, supply, fabrication and installation of support systems
• NDT works.
Owner : Akenerji
Main Contractor : General Electric Energy Products Europe
HRSG Contractor : NEM BV, The Netherlands
Subcontractor : EPRO Power and Industrial Plants Inc.
Contract Date : 22.01.2004
Date of Completion : December 2004
Description of work : Complete Mechanical and Instrument Erection Works of
2 Heat Recovery Steam Generators and
associated equipment
• 32 Tons piping including supports and valves
• Instrument Installation
• Supply and installation of Insulation
• NDT, PWHT services
AKENERJİ KEMALPAŞA COMBINED CYCLE POWER PLANT
Kemalpaşa - İzmir, TURKEY
TÜPRAŞ DESULPHURIZATION PROJECT
Körfez, KOCAELİ
Owner : TÜPRAŞ, Turkish Petroleum Refineries Corp. İzmit Refinery
Consultant : Technicas Reunidas
Main Contractor : Technicas Reunidas - Alarko-Akfen Joint Venture Consorsium
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : December 2005 (1st Phase) – June 2006 (2nd Phase)
Description of work : Fabrication, Erection Testings and Cleaning Works of
Process and Utility. Piping Both Above and Underground
Inside and Outside Boundary Limits of
Desulphurization Project.
• Piping Materials; Carbon Steel, Alloy Steel and Stainless Steel
• Pipe diameters ranging from 1/4” to 72”
• Total pipe quantity 2,100 tons.
• Total support quantity 200 tons.
• Welding quantity :Shop 103,500 dia inch (38,400 joint)
• Field : 62,150 dia inch (20,330 joint)
13. SUMGAIT 500 MW COMBINED CYCLE POWER PLANT
MANUFACTURING & ERECTION OF 2 HRSG
REPUBLIC of AZERBAIJAN
Owner : AZERENERJI JSC.
Main Contractor : SIEMENS AG. Power Generation
Subcontractor : CMI Energy HRS – EPRO Power & Industrial Plants Inc.
Consortium
Date of Contract : August 2005
Date of Completion : May 2007
Description of work : Engineering, Supply, Manufacturing, Erection and
Commissioning of .2 Heat Recovery Steam Generators
CCPP22 430 MW COMBINED CYCLE POWER PLANT
MANUFACTURING & ERECTION OF 2 HRSG
Dubai / U.A.E
Owner : DUBAL Aluminium Company.
Main Contractor : ALSTOM Power Controllers - CMI Energy HRS
Subcontractor : EPRO Power & Industrial Plants Inc.
INCO International Fz. Co
Date of Contract : April 2006
Date of Completion : June 2007
Description of work : Engineering, Supply, Manufacturing, Erection and
Commissioning of 2 Heat Recovery Steam Generators
KUC PROJECTJ2 NORTHERN UTILITIES
KINGDOM OF SAUDI ARABIA
Owner : SAUDI ARAMCO
EPC Main Contractor : SNAMPROGETTI S.p.A - SAUDIA
Mechanical Works Contractor : TEKFEN İNŞAAT VE TESİSAT A.Ş.
Saudi Arabian Branch
Piping Subcontractor : EPRO Power and Industrial Plants
Inc.
Date of Completion : March 2009
Description of work : Erection of Utility Piping Systems and
Internal pipingof 4 nos. of HRSG units
• Installation, testing and commissioning of utility piping systems 41,200 Wdi
• Installation and testing of Internal piping of 4 HRSG Units under ASME S Code,
3,000 Wdi
2 x 338 MW MARITZA EAST1 POWER PLANT
Galabova, BULGARIA
Owner : AES Corporation
EPC : ALSTOM Power
Main Contractor : TGO Ltd.
Subcontractor : EPRO Power and Industrial Plants Inc.
Date of Completion : August 2009
Description of work : Fabrication, Erection Testings and Cleaning Works
of Piping Both Above and Underground Inside and
Outside Turbine Building
• Piping Materials; Carbon Steel, Alloy Steel and Stainless Steel
• Pipe diameters ranging from 1/4” to 72”
• Total pipe quantity 2,100 tons.
• Total support quantity 200 tons.
• Welding quantity Shop: 103,500 dia-inch (38,400 joint), Field: 50,000 dia-inch
14. VLORE 1 x 100 MW COMBINED CYCLE POWER PLANT
Vlore, ALBANIA
Owner : KESH Albanian Power Corporation
Main Contractor : MAIRE TECNIMONT S.p.A
Subcontractor : SOEPRO J.V. (EPRO Power and Industrial Plants Inc.
SOECO Engineering and Construction)
Date of Completion : September 2009
Description of work Complete Mechanical Erection, Piping,
Insulation and Painting Works of 100 MW Single-Shaft
Combined Cycle Power Plant.
• Gas Turbine, Steam Turbine, Generator and auxiliaries (Supplied by Ansaldo-Italy)
• HRSG (Supplied by Nooter Ericsen - Italy)
• Condenser (Supplied by Ofmeco - Italy)
• Piping and Supports (Fabrication, Erection, PWHT, NDT, Painting, Insulation, Testing)
• BOP Equipments and Systems i.e. Water Treatment Plant, Sea Water Pumps,
Fuel Oil Storage, etc.
• 4300 m. API 5L Fuel Oil Piping for Offshore connection between CBMS and Site
(Welding and NDE testing)
FABRICATION - STORAGE TANKS
VENT STACK
FUEL OIL STORAGE TANK CLEAN & DIRTY OIL STORAGE TANK
SERVICE WATER / FIRE WATER STORAGE TANK CONDANSATE WATER STORAGE TANK
FABRICATION - STELL STRUCTURES
PLANT STRUCTURE
WAREHOUSE / HANGERS
PIPERACKS
DUMMY DRILL FLOOR STRUCTURE
BUILDINGS
FABRICATION - HRSG
(Pressure Parts - Modules)
15. FABRICATION - HRSG
(Pressure Parts - Modules)
FABRICATION - HRSG
(Pressure Parts - Modules)
FABRICATION - HRSG
(Pipe Spools and Stacks)
FABRICATION - HRSG
(Non Pressure Parts - Steel Structures and Casings)
16. ADDRESSES & CONTACTS GENERAL COMPANY INFORMATION
EPRO A.Ş. - İstanbul, TURKEY
Adress : Fatih Sultan Mehmet Cad. No: 33 Kavacık 34810
Telephone : +90 (216) 413 33 39
Fax : +90 (216) 413 13 22
Contact Persons : Mr. Erdal Berkay
Chairman of the Board eberkay@epro.com.tr
: Mr. Niyazi Kuday
nkuday@epro.com.tr
mesigok@epro.com.tr
arkale@epro.com.tr
bababay@epro.com.tr
Quality Certificates : ISO 9001:2000 CERTIFICATE
ASME “S” and “U” Stamps (To be renewed for a new Fabrication Location)
Company Name : EPRO ENERJİ ve ENDÜSTRİ TESİSLERİ İNŞAAT SAN. TİC. A.Ş.
Type of Company : Corporation registered in Turkey
Date of Establishment : October 1997
Interested Work Areas : Europe, Eastern Europe, Caspian Region, Middle East, North Africa
Countries Worked : Albania, Azerbaijan, Bulgaria, Georgia, K. Saudi Arabia,
Russian Federation, Turkey, UAE (Dubai),
Quality Systems : ISO 9001 : 2000 , ASME “S & U”
18. Hatay-Erzin 900 MW CCGT Project / Erection Works of 2 HRSG Units - Erzin, TURKEY
Owner : EGEMER Electric Production A.Ş.
EPC Contractor : GAMA GÜÇ SİSTEMLERİ A.Ş.
Subcontractor : EPRO Power and Industrial Plants Inc.& BETA Eng. JV
Date of Completion : December 2013
Description of work : Complete Mechanical, Electrical and Instrumentation
Works of two (2) HRSGs for GE 209 TB MS type Gas
Turbine (Horizontal Draft, Triple Pressure + Reheat,
Manufactured by DOOSAN) including all External Piping
Works.
3