COMMUNICATION
ON SITE
helpdesk@construction-productivity.co.uk
htt://www.construction-productivity.co.uk
COMMUNICATION
ON SITE-BRE GUIDE
Every year defects in the UK construction
industry cost at least £20 billion to repair
or rebuild
Some of the defects are as the result issues
such as:
 Poor communication;
 Poorly detailed drawing;
 Incorrect instructions or technical information
not being available on time;
COMMUNICATION
ON SITE
 Meeting types and frequencies;
 Method's of drawing transfer;
 Use and control of revised drawings, or
unconfirmed drawings;
 Reporting and tracking of defects;
 Lack of knowledge in detecting defects on
time.
COMMUNICATION
ON SITE-DEFERNT PHASES
Phase-1 Communication on site
 Who should accept and check deliveries of materials
to the site.
 Employment of a site engineers, clerk of work,
supervisors or securities.
 Setting their communication responsibilities and
methods.
 Setting the authority of the Clerk of Works to instruct
operatives.
 Communication with, and supervision of sub-
contractors.
COMMUNICATION
ON SITE
Drawing provision and distribution
 The role of accurate drawings in producing
good quality work.
 Careful attention must be paid as to:
 how drawings are going to be produced;
 Checked;
 distributed.
COMMUNICATION
ON SITE
The following points must be considered:
 provide drawings as complete as possible;
 at all relevant stages;
 with high accuracy;
 remove older version drawing immediately;
 make sure everyone involved with the project
knows about the new version.
COMMUNICATION
ON SITE
 ensure drawings are adequately detailed,
 and mistakes are all picked up before site
work starts.
 The drawings with high presentation-could
be produced to help building work
progress smoothly. Drawings such as:
 colour coded
 by trade or element
 laminated
 small or large sized.
COMMUNICATION
ON SITE
 The correct level of information is needed on
any drawing, for it to be successfully built
from.
 Where the drawings to be kept? It is going to
be in the site office?
 How to prepare and return amended
drawings back to site as quickly as possible.
 Is there a role for the manufacturers to help
prepare drawings?
COMMUNICATION
ON SITE
Single points of contact
 Consideration should be given to appointing
defined, single points of contact at suppliers,
design offices and contractors.
 This should help to avoid delays, confusion
and duplication of effort.
COMMUNICATION
ON SITE
Trade supervisors
 Assuming that the size of the project requires
a supervisor on site for each trade.
 This often brings benefits to the project
communication and the quality of build.
 Ensure that the role of the supervisor links
with the project requirements.
 Is the supervisor required only to schedule
work for the operatives?
COMMUNICATION
ON SITE
 Or is he/she directly involved with "setting
out", examination of drawings and quality of
build.
 To be effective, the trade supervisor must
have authoritarian style of management.
 May be a problem as the position can be
considered as not bering "operative" or
"management".
COMMUNICATION
ON SITE
Phase 2: Pre-start meeting
 The project manager should ensure that a pre-start or
"kick off" meeting is held.
 There are several benefits to site communication
which may arise from such a meeting,
Including the following:
 It allows people to get to know each other;
 This is likely to lead to better communication and less
confrontational attitudes as the work progresses.
COMMUNICATION
ON SITE
 It provides the opportunity to decide on how
communication will operate through out the
organization.
 It provides the opportunity to define points of contact
at each level.
 It can be used to ensure that all people have the
contact details for every person working on the
project.
 Ensuring all relevant people attend the kick off
meeting.
This may include:
 project management team;
 major suppliers.
COMMUNICATION
ON SITE
Technical literature and advice
 Large numbers of best practice information
and documents are accessible on the
internet on:
 Design
 material selection
 Construction
COMMUNICATION
ON SITE
 They are also available from a variety of
sources including the following:
 Manufacturers
 Construction site communication-guidance
 British Standards Institution
 BRE
 MCIOB
 RICS
 ETC
COMMUNICATION
ON SITE
Building regulatory authorities such
as:
Office of the Deputy Prime Minister,
Scottish Executive;
Trade associations;
Insurance companies (e.g. Housing
Association Property Mutual
(HAPM).
COMMUNICATION
ON SITE
National House Building Council
(NHBC));
Consultants and research
organisations (e.g. Building
Research Establishment;
(BRE), Construction Industry
Research and Information
Association (CIRIA)).
COMMUNICATION
ON SITE
Provision of technical advice
 Arrangements should be made to provide
technical advice to site operatives. In
circumstances such as:
 If there is a complex detailing to be built
 Operatives are inexperienced;
 New materials/products are in use;
 Providing the best practice information
including the following:
COMMUNICATION
ON SITE
 Introducing technical issues into the standard
induction procedures.
 Sample panels and mock-ups.
 Best practice posters on display (e.g. in the site
canteen, head office).
 Manufacturers visit the site to demonstrate best
practice or new products.
 Manufacturers visit design team to introduce new
products.
 Supply operatives with relevant parts of good practice
guidance.
COMMUNICATION
ON SITE
Upwards feedback
 Establish means by which
information can be effectively fed
back up through the formal
management structure.
 Two key areas where this can be
particularly important are as
follows:
COMMUNICATION
ON SITE
1. operatives to site office (e.g.
reporting on an incorrect drawing);
2. Site office to head office (e.g.
where an incorrect detail is
discovered;
3. this should be reported back to the
design office and the drawings
corrected).
COMMUNICATION
ON SITE
Project Meetings
 The success of formal meetings (e.g. the
monthly progress meeting) is helped by being
structured, including the following:
 Chairperson
 Agenda
 Set start and finish times
 Minutes recorded.
COMMUNICATION
ON SITE
Keep people informed at all time.
Advice all people involved across
the whole construction project.
Take care and time with
communication.
Communication must be
"supported" (i.e. ensure that
someone given an instruction).
COMMUNICATION
ON SITE
Has the back up, resources and
knowledge to complete the task
properly.
Make sure the method of
communication used is the most
appropriate.
COMMUNICATION
ON SITE
 Make sure the message is clear and all
people who need to know are informed.
 Provide instructions as early as possible,
 Do not assume that actions identified in a
memo, fax or e-mail will always have been
carried out.
 Always follow up to see if the message is
received and followed,
 Find a productive way to check if any one has
been forgotten to get the message,
COMMUNICATION
ON SITE
 Some sort of follow up or checking may
still be necessary.
 Learn from previous projects that you
have been involved with where the
communication was either particularly
good or bad.
 Learn from mistakes.
 Suggest improvement and follow up.
COMMUNICATION
ON SITE
New communication technology
 The use of new technology to help
communication should be considered.
Consider full benefits of items such as:
1. mobile phones
2. two way radios
3. digital cameras
4. on site internet- on site and at the head office
intranet
5. e-mail
COMMUNICATION
ON SITE
 For example, drawings can be e-mailed
between the site office and the architect, as
can digital photographs of defects and
progress.
 The internet can be used to access
information such as:
 Building Standards
 good practice guidance
 documentation.
COMMUNICATION
ON SITE
 On large scale construction projects the use
of project "intranet" systems has been shown
to be valuable.
 These systems are based on project wide
access via a network of personal computers
to electronic ("virtual") project documents
such as:
 Drawings
 Specifications
 correspondence.
016 communication in construction sector

More Related Content

Similar to 016 communication in construction sector

TOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdf
TOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdfTOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdf
TOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdf
Haikal658790
 
Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1
Rodi Murwisi
 
Why Do Accidents Still Occur On Modern Day Construction...
Why Do Accidents Still Occur On Modern Day Construction...Why Do Accidents Still Occur On Modern Day Construction...
Why Do Accidents Still Occur On Modern Day Construction...
Stephanie Clark
 
Stephen Cannoo CV 2013 ver 2
Stephen Cannoo CV 2013 ver 2Stephen Cannoo CV 2013 ver 2
Stephen Cannoo CV 2013 ver 2
Stephen Cannoo
 
Communications Management Plan
Communications Management PlanCommunications Management Plan
Communications Management Plan
Jonathan Reid
 

Similar to 016 communication in construction sector (20)

Communication Management
Communication ManagementCommunication Management
Communication Management
 
TOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdf
TOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdfTOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdf
TOPIC_4_TECH__COM_DEVELOPMENT_CONCEPT_IN_CIVIL_ENGINEERING_STUDENT NOTE (1).pdf
 
Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1
 
MDA csp
MDA cspMDA csp
MDA csp
 
Orientation Volumezero-1.pptx
Orientation Volumezero-1.pptxOrientation Volumezero-1.pptx
Orientation Volumezero-1.pptx
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning Phase
 
043 Integrating Risk Management
043 Integrating Risk Management043 Integrating Risk Management
043 Integrating Risk Management
 
043 integrating risk management
043 integrating risk management043 integrating risk management
043 integrating risk management
 
Communication management
Communication management Communication management
Communication management
 
Why Do Accidents Still Occur On Modern Day Construction...
Why Do Accidents Still Occur On Modern Day Construction...Why Do Accidents Still Occur On Modern Day Construction...
Why Do Accidents Still Occur On Modern Day Construction...
 
Technical report writing skills for civil engineers pdf
Technical report writing skills for civil engineers pdfTechnical report writing skills for civil engineers pdf
Technical report writing skills for civil engineers pdf
 
Stephen Cannoo CV 2013 ver 2
Stephen Cannoo CV 2013 ver 2Stephen Cannoo CV 2013 ver 2
Stephen Cannoo CV 2013 ver 2
 
Andrew Chalmers CV
Andrew Chalmers CVAndrew Chalmers CV
Andrew Chalmers CV
 
Communications Management Plan
Communications Management PlanCommunications Management Plan
Communications Management Plan
 
Edotco project body part
Edotco project body partEdotco project body part
Edotco project body part
 
Units 2, 3 Assignment Brief
Units 2, 3 Assignment BriefUnits 2, 3 Assignment Brief
Units 2, 3 Assignment Brief
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Empowerpack
EmpowerpackEmpowerpack
Empowerpack
 
Empowerpack
EmpowerpackEmpowerpack
Empowerpack
 
Empowerpack
EmpowerpackEmpowerpack
Empowerpack
 

More from DrFereydounDejahang

More from DrFereydounDejahang (20)

022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 construction productivity (2)
022 construction productivity (2)022 construction productivity (2)
022 construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 business planning process
012 business planning process012 business planning process
012 business planning process
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 business planning process
012 business planning process012 business planning process
012 business planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 
010 bmw tpm management training
010 bmw tpm management training010 bmw tpm management training
010 bmw tpm management training
 
009 benefits realization
009 benefits realization009 benefits realization
009 benefits realization
 
008 benefits management
008 benefits management 008 benefits management
008 benefits management
 

Recently uploaded

Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Recently uploaded (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 

016 communication in construction sector

  • 2. COMMUNICATION ON SITE-BRE GUIDE Every year defects in the UK construction industry cost at least £20 billion to repair or rebuild Some of the defects are as the result issues such as:  Poor communication;  Poorly detailed drawing;  Incorrect instructions or technical information not being available on time;
  • 3. COMMUNICATION ON SITE  Meeting types and frequencies;  Method's of drawing transfer;  Use and control of revised drawings, or unconfirmed drawings;  Reporting and tracking of defects;  Lack of knowledge in detecting defects on time.
  • 4. COMMUNICATION ON SITE-DEFERNT PHASES Phase-1 Communication on site  Who should accept and check deliveries of materials to the site.  Employment of a site engineers, clerk of work, supervisors or securities.  Setting their communication responsibilities and methods.  Setting the authority of the Clerk of Works to instruct operatives.  Communication with, and supervision of sub- contractors.
  • 5. COMMUNICATION ON SITE Drawing provision and distribution  The role of accurate drawings in producing good quality work.  Careful attention must be paid as to:  how drawings are going to be produced;  Checked;  distributed.
  • 6. COMMUNICATION ON SITE The following points must be considered:  provide drawings as complete as possible;  at all relevant stages;  with high accuracy;  remove older version drawing immediately;  make sure everyone involved with the project knows about the new version.
  • 7. COMMUNICATION ON SITE  ensure drawings are adequately detailed,  and mistakes are all picked up before site work starts.  The drawings with high presentation-could be produced to help building work progress smoothly. Drawings such as:  colour coded  by trade or element  laminated  small or large sized.
  • 8. COMMUNICATION ON SITE  The correct level of information is needed on any drawing, for it to be successfully built from.  Where the drawings to be kept? It is going to be in the site office?  How to prepare and return amended drawings back to site as quickly as possible.  Is there a role for the manufacturers to help prepare drawings?
  • 9. COMMUNICATION ON SITE Single points of contact  Consideration should be given to appointing defined, single points of contact at suppliers, design offices and contractors.  This should help to avoid delays, confusion and duplication of effort.
  • 10. COMMUNICATION ON SITE Trade supervisors  Assuming that the size of the project requires a supervisor on site for each trade.  This often brings benefits to the project communication and the quality of build.  Ensure that the role of the supervisor links with the project requirements.  Is the supervisor required only to schedule work for the operatives?
  • 11. COMMUNICATION ON SITE  Or is he/she directly involved with "setting out", examination of drawings and quality of build.  To be effective, the trade supervisor must have authoritarian style of management.  May be a problem as the position can be considered as not bering "operative" or "management".
  • 12. COMMUNICATION ON SITE Phase 2: Pre-start meeting  The project manager should ensure that a pre-start or "kick off" meeting is held.  There are several benefits to site communication which may arise from such a meeting, Including the following:  It allows people to get to know each other;  This is likely to lead to better communication and less confrontational attitudes as the work progresses.
  • 13. COMMUNICATION ON SITE  It provides the opportunity to decide on how communication will operate through out the organization.  It provides the opportunity to define points of contact at each level.  It can be used to ensure that all people have the contact details for every person working on the project.  Ensuring all relevant people attend the kick off meeting. This may include:  project management team;  major suppliers.
  • 14. COMMUNICATION ON SITE Technical literature and advice  Large numbers of best practice information and documents are accessible on the internet on:  Design  material selection  Construction
  • 15. COMMUNICATION ON SITE  They are also available from a variety of sources including the following:  Manufacturers  Construction site communication-guidance  British Standards Institution  BRE  MCIOB  RICS  ETC
  • 16. COMMUNICATION ON SITE Building regulatory authorities such as: Office of the Deputy Prime Minister, Scottish Executive; Trade associations; Insurance companies (e.g. Housing Association Property Mutual (HAPM).
  • 17. COMMUNICATION ON SITE National House Building Council (NHBC)); Consultants and research organisations (e.g. Building Research Establishment; (BRE), Construction Industry Research and Information Association (CIRIA)).
  • 18. COMMUNICATION ON SITE Provision of technical advice  Arrangements should be made to provide technical advice to site operatives. In circumstances such as:  If there is a complex detailing to be built  Operatives are inexperienced;  New materials/products are in use;  Providing the best practice information including the following:
  • 19. COMMUNICATION ON SITE  Introducing technical issues into the standard induction procedures.  Sample panels and mock-ups.  Best practice posters on display (e.g. in the site canteen, head office).  Manufacturers visit the site to demonstrate best practice or new products.  Manufacturers visit design team to introduce new products.  Supply operatives with relevant parts of good practice guidance.
  • 20. COMMUNICATION ON SITE Upwards feedback  Establish means by which information can be effectively fed back up through the formal management structure.  Two key areas where this can be particularly important are as follows:
  • 21. COMMUNICATION ON SITE 1. operatives to site office (e.g. reporting on an incorrect drawing); 2. Site office to head office (e.g. where an incorrect detail is discovered; 3. this should be reported back to the design office and the drawings corrected).
  • 22. COMMUNICATION ON SITE Project Meetings  The success of formal meetings (e.g. the monthly progress meeting) is helped by being structured, including the following:  Chairperson  Agenda  Set start and finish times  Minutes recorded.
  • 23. COMMUNICATION ON SITE Keep people informed at all time. Advice all people involved across the whole construction project. Take care and time with communication. Communication must be "supported" (i.e. ensure that someone given an instruction).
  • 24. COMMUNICATION ON SITE Has the back up, resources and knowledge to complete the task properly. Make sure the method of communication used is the most appropriate.
  • 25. COMMUNICATION ON SITE  Make sure the message is clear and all people who need to know are informed.  Provide instructions as early as possible,  Do not assume that actions identified in a memo, fax or e-mail will always have been carried out.  Always follow up to see if the message is received and followed,  Find a productive way to check if any one has been forgotten to get the message,
  • 26. COMMUNICATION ON SITE  Some sort of follow up or checking may still be necessary.  Learn from previous projects that you have been involved with where the communication was either particularly good or bad.  Learn from mistakes.  Suggest improvement and follow up.
  • 27. COMMUNICATION ON SITE New communication technology  The use of new technology to help communication should be considered. Consider full benefits of items such as: 1. mobile phones 2. two way radios 3. digital cameras 4. on site internet- on site and at the head office intranet 5. e-mail
  • 28. COMMUNICATION ON SITE  For example, drawings can be e-mailed between the site office and the architect, as can digital photographs of defects and progress.  The internet can be used to access information such as:  Building Standards  good practice guidance  documentation.
  • 29. COMMUNICATION ON SITE  On large scale construction projects the use of project "intranet" systems has been shown to be valuable.  These systems are based on project wide access via a network of personal computers to electronic ("virtual") project documents such as:  Drawings  Specifications  correspondence.