Update on Pavement Smoothness in California
1. Update on Pavement Smoothness
In California
CalAPA Fall Asphalt Conference & Equipment Expo
October 27, 2016
Don Matthews, PE
Pavement Recycling Systems, Inc.
2. California’s Smoothness Transition
Before 2012, pavement
smoothness was measured
using a California
profilograph and straightedge
After 2012, pavement
smoothness is measured
using the inertial profiler and
straightedge
3. Ride Comfort – Depends On:
Road Roughness
Vehicle Response to the Road
Human Response to Vibration
Profilograph and Inertial Profiler
Inertial Profiler and Subsequent IRI
Calculation
Indirectly Considered via IRI
6. No One Debates the Benefits of
Smooth Pavements
Smoother roads:
Provide a comfortable ride
Last longer
Stay smoother longer
Are safer
Save money (pavement and vehicle
repairs and fuel economy)
Are better for the environment
10. To Help
Industry and Caltrans together
held a Smoothness Forum 9/28/15
A Smoothness Subtask Group Was Formed
• Working Group - Data Collection/Analyses, Design
Guidance and Specification
• Working Group - Best Paving Practices
• Working Group - ProVAL Training and Smoothness
Corrections
11. Profilograph Specification
• Profile Index of 2.5 inches per 0.1 mile
• Must Grinds – Localized roughness of 0.3 inch or more in 25 feet
Inertial Profiler with IRI Specification
• Mean Roughness Index (MRI) – 60 or 75 in/mi depending on depth of HMA
• Area of Localized Roughness (ALR) – 160 in/mi localized roughness based on a
25 feet sliding scale
They Seem Similar
What the Specification Numbers Meant
Determined That Few Understood:
Concept Maybe Numbers No!
12. Few Understood:
What it took to achieve the new smoothness requirements
during construction
What best paving practices are really required for
smoothness
The Killer Phrase -
“I am not worried about it. I have been paving for 30
years” Get out the checkbook!
13. Consistency - Head of Material on Screed
Consistency - Paving Speed
Consistency - Mix Temperature
Best Paving Practices = Consistency!!!
14. Screed Control – Referencing
What is referenced has a major impact on smoothness
Longer and smoother the reference, the smoother the
pavement
A smooth cold planed surface that was cut with an
averaging system could be a good reference surface as
opposed to a rougher shoulder or adjacent lane
However, if the cold planed surface delaminates another
surface should be used
Once a good reference line is set trust the equipment
.
16. Best Paving Practices Training Available
Joint Working Group on Best Paving Practices
Is nearly complete with training module
Expected out by end of the year
CalAPA’s ½ Day Training Class
PAVEMENT SMOOTHNESS ESSENTIALS -- NEW
SPECIFICATIONS, TECHNOLOGY & BEST PRACTICES
17. Also Realized Few Understood:
If smoothness could be achieved for a given roadway
condition using standard design strategies
No Consideration of Roadway Location or Type
Little Consideration to Existing Roughness
18. TYPES OF ROADS
Both Mill and Fill of 0.10’
Both Have a Final MRI Requirement of 75 in/mi
The roadway on the right will likely take much more pre-
paving correction and effort then the left
19. Existing Surface
MRI (in/mi)
New Surface
MRI (in/mi)
300 120
200 90
150 75
120 65
90 60
60 45
*Based Upon One Smoothness Opportunity
Using Best Paving Practices
As Part of the Smoothness Working Group
Industry Provided Reasonable Expected Improvement Values
For Caltran’s Consideration
Additional Rehabilitation Line Items Would Be Provided If Existing MRI “Too Rough” For
Primary Design Strategy
Existing Pavement Grinding or Cold Planing Corrections
Removals and Replacement
Leveling Course etc.
Least agreement on this number
20. Prepave Grinding (Corrections)
As a Strategy
Existing Asphalt Surface Prior to
Overlay
Existing Pavement Surface
Aggregate Base/Subgrade
Pre-pave Grinding or
Cold Planing is a
Smoothness
Opportunity
HMA OverlaySmoothness
Opportunity
21. CalTran’s Specification – Prepaving “Grinding”
Correct Areas of Localized Roughness HMA >180 in/mi
Currently Bid by Day with Extra Days Paid as Determined By RE. Any
Areas Not Corrected, Excluded From Final Smoothness Requirements
Should Come with Inertial Profiler Bid Item
Overlay’s Only. Not Provided for Cold Planing or CIR
In the Future Pre-construction Profiles with Electronic Files Provided and
Prepaving Corrections Bid by the Lump Sum?
Depending on Existing Roughness Corrections May be Necessary Even
Prior to Cold Planing
Some Concern Over Interpretations
24. Mill and Fill
Cold Planing As A Strategy
Existing Pavement Surface
Aggregate Base/Subgrade
Smoothness
Opportunity?
Filled HMA
Smoothness
Opportunity
25. Cold Planing a Smoothness Opportunity?
There is a Debate!
Do Agree That It is Not Effective if:
Mill depth must be at the specified depth and follow
existing surface
Paving operation does not use milled surface for control
Good paving practices are not utilized
26. Variable Depth Cold Planing Must be Used
Following an existing rough surface at constant depth will transfer the
roughness to the bottom of cold planed surface. Good control systems such
as an averaging system should be used on the existing surface
Variable Depth
27. Good Cold Planing Practices Must Be Followed:
Transitions must be smooth into and out of cuts
The milled surface must be cleaned well
The drum must not be stopped while still in the cut
The mill’s mechanical systems must be maintained
The cutting tools and blocks must be maintained and/or
replaced as needed
28. Appropriate Continuous Speeds Must be Maintained
Do not out run the pattern – It may not be about production
The texture changes as speed increases
31. If delamination occurs
the cut depth must be
deepened
Paving over a
delaminated surface
can result in deferential
compaction
A delaminated surface
will also provide a
rough reference line for
the paver
Delamination
32. Existing Pavement Surface
Aggregate Base/Subgrade
Cold In-place Recycling (CIR)
With Overlay as a Strategy
HMA Overlay Smoothness
Opportunity
CIR
Sort of a Smoothness
Opportunity
33. CIR as an Smoothness Opportunity:
Regardless of the existing roadway’s
roughness, using best practices should result
in smoothness of the CIR at about 90 in/mi
MRI
Using best practices, a 60 in/mi MRI should
then be attainable on the HMA overlay
The Smoothness Subtask Group has made
the recommendation to raise the CIR
smoothness from 75 in/mi MRI and 180
in/mi ALR to 90 in/mi MRI and 240 in/mi
ALR, with no change to the overlay
smoothness requirements
34. Finally, Apparently Few Understood:
How to correct the final paved surface for
smoothness
What equipment must be used
How to prepare effective grinding strategies
The benefits and limitations of ProVAL
The limitations as to the amount of corrections
that can be done by grinding
35. ProVAL Smoothness Assurance Model
(SAM)
Requires Experience
Only models in two dimensions which may cause impacts
in other locations. Grinding wheels not necessarily on
same profile as grinding head when large variations in
transverse profile exist - May not be able to just correct a
single wheel path
Must use the exact equipment modeled
In some instances overestimates correction areas and
tends to be slower
Corrects for ALR and not MRI
38. But Grinding or Cold Planing Corrections
Can Only Do So Much
Can only go deeper or wider
Can’t fix a pavement or subgrade
39. WORKING CRACKS – Respond Dynamically to
Vehicles, Including Inertial Profiler
Working – Not correctible
by grinding
Non Working – Likely
correctible by grinding
40. The Good News:
While it may be unreasonable to expect to obtain
smoothness with the design strategy specified,
there appears to be:
Better understanding of the
issues involved by
Contractors and the State
Better partnering to come to
an equitable solution before
construction begins
41. The Good News:
There is effective dialog occurring in the Smoothness
Subtask Group – With a joint effort trying to resolve
issues
Effective contractors have adapted and are raising the
bar
The cry was – “It cannot be achieved”
Now – “If the design strategy and existing roadway allows it,
we will get it”
Many look forward to pay incentives that will likely be available
in the future (Late 2017 projects?)