Submit Search
Upload
project-management-1.pptx
•
Download as PPTX, PDF
•
0 likes
•
8 views
A
AlmarieMaligonCompac
Follow
Project management
Read less
Read more
Business
Report
Share
Report
Share
1 of 83
Download now
Recommended
CMGT 410 Week 1 Supporting Activity
CMGT 410 Week 1 Supporting Activity
tmschaf
New projectplandefinition1
New projectplandefinition1
Jonathan Joyce
Lec#1
Lec#1
Yasir Khan
Project Management Process
Project Management Process
Adepitan Oluwasoro, PMP, CSM, MBA
Basics of Project Planning
Basics of Project Planning
Zilicus
Managing Project Success
Managing Project Success
Baker Khader Abdallah, PMP
PROJECT MANAGEMENT intro - Lecture 01.pptx
PROJECT MANAGEMENT intro - Lecture 01.pptx
BimsaraRotaract
Project and process engineering management industrial engineering management
Project and process engineering management industrial engineering management
Luis Cabrera
Recommended
CMGT 410 Week 1 Supporting Activity
CMGT 410 Week 1 Supporting Activity
tmschaf
New projectplandefinition1
New projectplandefinition1
Jonathan Joyce
Lec#1
Lec#1
Yasir Khan
Project Management Process
Project Management Process
Adepitan Oluwasoro, PMP, CSM, MBA
Basics of Project Planning
Basics of Project Planning
Zilicus
Managing Project Success
Managing Project Success
Baker Khader Abdallah, PMP
PROJECT MANAGEMENT intro - Lecture 01.pptx
PROJECT MANAGEMENT intro - Lecture 01.pptx
BimsaraRotaract
Project and process engineering management industrial engineering management
Project and process engineering management industrial engineering management
Luis Cabrera
Project Management Introduction
Project Management Introduction
Siliguri Institute of Technology ( A unit of Techno India Group)
10 critical factors for success of a project
10 critical factors for success of a project
Zilicus
Project Intro
Project Intro
Vibha Mittal
UNIT-1.pptx
UNIT-1.pptx
ArunSingh205872
PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
Project Management Overview
Project Management Overview
cford1973
Project Plan For A Project Management Project
Project Plan For A Project Management Project
Mary Stevenson
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
Md. Masudur Rahman, PMP
Project Manangement Introduction
Project Manangement Introduction
asim78
How to close a project
How to close a project
Emmanuel Mwagomba
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
GhulamQadirWaqar1
Assignment Help Moodle Monkey
Assignment Help Moodle Monkey
ZomakSoluion
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
saikumarmba2023
83 Chapter 5 PROJECT.docx
83 Chapter 5 PROJECT.docx
ransayo
Project Manager Primer
Project Manager Primer
Tom Cremins
Project Mangement
Project Mangement
Gaurav Shrivastava
U1 - S1 - Modern Project Management.pdf
U1 - S1 - Modern Project Management.pdf
Md. Masudur Rahman, PMP
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
Kate Pynn
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
tarifarmarie
Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project
Tehmas Saeed
Progress Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
Holger Mueller
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
lizamodels9
More Related Content
Similar to project-management-1.pptx
Project Management Introduction
Project Management Introduction
Siliguri Institute of Technology ( A unit of Techno India Group)
10 critical factors for success of a project
10 critical factors for success of a project
Zilicus
Project Intro
Project Intro
Vibha Mittal
UNIT-1.pptx
UNIT-1.pptx
ArunSingh205872
PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
Project Management Overview
Project Management Overview
cford1973
Project Plan For A Project Management Project
Project Plan For A Project Management Project
Mary Stevenson
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
Md. Masudur Rahman, PMP
Project Manangement Introduction
Project Manangement Introduction
asim78
How to close a project
How to close a project
Emmanuel Mwagomba
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
GhulamQadirWaqar1
Assignment Help Moodle Monkey
Assignment Help Moodle Monkey
ZomakSoluion
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
saikumarmba2023
83 Chapter 5 PROJECT.docx
83 Chapter 5 PROJECT.docx
ransayo
Project Manager Primer
Project Manager Primer
Tom Cremins
Project Mangement
Project Mangement
Gaurav Shrivastava
U1 - S1 - Modern Project Management.pdf
U1 - S1 - Modern Project Management.pdf
Md. Masudur Rahman, PMP
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
Kate Pynn
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
tarifarmarie
Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project
Tehmas Saeed
Similar to project-management-1.pptx
(20)
Project Management Introduction
Project Management Introduction
10 critical factors for success of a project
10 critical factors for success of a project
Project Intro
Project Intro
UNIT-1.pptx
UNIT-1.pptx
PMP assessment exam 1.1
PMP assessment exam 1.1
Project Management Overview
Project Management Overview
Project Plan For A Project Management Project
Project Plan For A Project Management Project
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
Project Manangement Introduction
Project Manangement Introduction
How to close a project
How to close a project
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
Assignment Help Moodle Monkey
Assignment Help Moodle Monkey
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
Impact of eLearning Scope Creep_ A Project Manager's Guide.pdf
83 Chapter 5 PROJECT.docx
83 Chapter 5 PROJECT.docx
Project Manager Primer
Project Manager Primer
Project Mangement
Project Mangement
U1 - S1 - Modern Project Management.pdf
U1 - S1 - Modern Project Management.pdf
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project
Recently uploaded
Progress Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
Holger Mueller
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
lizamodels9
GD Birla and his contribution in management
GD Birla and his contribution in management
chhavia330
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
noida100girls
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
Suhani Kapoor
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
Neil Kimberley
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
KeppelCorporation
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
soniya singh
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
lizamodels9
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Shawn Pang
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
Orient Homes
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
nakalysalcedo61
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
Renandantas16
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
Aggregage
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
noida100girls
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
discovermytutordmt
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
lizamodels9
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
muskan1121w
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
lizamodels9
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
MalviyaNagarCallGirl
Recently uploaded
(20)
Progress Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
GD Birla and his contribution in management
GD Birla and his contribution in management
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
project-management-1.pptx
1.
Project Management
2.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
3.
Project Definition An unique
set of co-oridinated activities, with definite starting and finishing points, undertaken by an individual or organization to meet specific objectives within defined schedule, cost and performance parameters’ $ € $ 1 2 3 4 5 6 7 8 9 1 0 1 1 12 13 14 1 5 1 6 1 7 1 8 19 2 0 21 22 23 24 2 5 26 2 7 28 28 30 31 Monday Tuesday Wednesd ay Thursday Friday Saturday Sunday Exa mple JANUARY 2010 1 2 3 4 5 6 7 8 9 10 1 1 1 2 1 3 1 4 1 5 16 17 18 1 9 2 0 2 1 2 2 23 2 4 25 26 27 28 Monday Tuesday Wednesd ay Thursday Friday Saturday Sunday Exa mple FEBRUARY 2010 Exa mple Copyright © 2008 - 2012
4.
Project ‘Triangle’ Cost Quality Performance Time S Safety Broadly
these objectives, which are usually defined as part of the business case and set out in the project brief, most meet three fundamental criteria: The project must be completed on time The project must be accomplished within the budgeted cost The project must meet the prescribed quality requirements Copyright © 2008 - 2012
5.
Project ‘Diamond’ Cost Safety Quality Performance Time Time-bound project A
score board for a prestigious tennis tournament must be finished in time for the opening match, even if it costs more than anticipated and the display of some secondary information, such as the speed of the service, has to be abandoned. In other words, cost and performance may have to be sacrificed to meet the unalterable starting date of the tournament Cost-bound project A local authority housing development may have to curtail the number of housing units and may even overrun the original construction program, but the project cost cannot be exceeded, because the housing grant allocated by central government for this type of development has been frozen at a fixed sum. Another solution to this problem would be to reduce the specification of the internal fittings instead of reducing the number of units Copyright © 2008 - 2012
6.
Project ‘Diamond’ Cost Safety Quality Performance Time Performance (quality)
– Bound Project An armaments manufacturer has been contracted to design and manufacture a new type of rocket launcher to meet the client’s performance specification in terms of range, accuracy and rate of fire. Even if the delivery has to be delayed to carry out more tests and the cost has increased, the specification must be met. Again if the weapons are required during the war, the specification might be relaxed to get the equipment into the field as quickly as possible Safety-bound Project A part from the obvious examples of public transport given previously, safety is a factor that is required by law and enshrined in the Health and safety at work act. Not only must safe practices be built into every project, but constant monitoring is an essential element of safety policy. A serious accident which may kill or injure people will not only cause anguish among the relatives, but, while not necessarily terminating the project, could very well destroy the company Copyright © 2008 - 2012
7.
Project Manager and
his Charter The individual who has the responsibility, authority and accountability assigned to him or her to achieve safely the project objectives within agreed time, cost and performance/quality criteria Charter Project Manager Name: _________ Appointment/Position________ Date of appointment_________ Project title: _______________________ Responsibility and Authority given to the Project Manager. The above named Project Manager has been given the authority, responsibility and accountability for _____________________________ Project Goals and deliverables are: A_____________, B_______________, C_______________ The project will be reviewed:______________________________________________ Copyright © 2008 - 2012
8.
Project Manager and
his Charter Charter Final authority The project manager’s delegated financial powers are:______________________ Intramural resources: The following resources have been/are to be made available________ Trade-offs: a._________%, b. Time_________, c. Performance___________ Charter review: No charter review is expected to take place for the duration of this project unless it becomes clear that the Project Manager cannot fulfil his/her duties or a reassessment of the trade- offs is required Approved Sponsor/Client/Customer/Programme Manager________________ Project Manager_____________ Line Manager___________ Distribution a) Sponsor b) Programme Manager c) Line Manager Copyright © 2008 - 2012
9.
The Project Environment The
Project Distributors Contracting Company Suppliers Competition Public End-users Clients Political Economic Socio- cultural Legal Environment Technological Copyright © 2008 - 2012
10.
Business Case Client Sponsor Before embarking
on a project it is clearly necessary to show that there will be benefit either in terms of money or service or both. The document which sets out the main advantages and parameters of the project is called the business case and is (or should be) produced by either the client or the sponsor of the project who in effect becomes the owner of the document Copyright © 2008 - 2012
11.
Business Case indications As
with all documents, a clear procedure for developing the business case is highly desirable and the following headings give some indication of the subjects to be included Why is Project required? What are we trying to achieve? What are the deliverables? What is the anticipated cost? How long it will take to complete? What qualify standards must be achieved? What are the performance criteria? What are Key Performance Indicators? What are the main risks? What are success criteria? Who are the main stakeholders? Copyright © 2008 - 2012
12.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
13.
Initial findings A clear
project definition and detailed objectives are critical to the success of the project. If the definition and objectives are ambiguous, unrealistic, not agreed upon, or not written down, the project is in serious trouble before it begins. What ever time and energy you need to define the project properly in the planning stage is much less than what it will cost to fix problems after the project is completed For example, if a project involves the construction of a new plant, the project manager needs • To know how the new plant will operate • To understand the needs of the users of the new plant • To understand why the client wants the new plant • A clear view of what is involved in constructing the plant and what is expected of him • To be sure the new plant will actually solve the problem at hand at hand or appropriately address the presenting opportunity. If the problem or opportunity has not been correctly identified, the plant, even if constructed successfully, would be a failure Copyright © 2008 - 2012
14.
The Project ‘SMART’ The
objectives must be so clear and well defined that anyone with a basic knowledge of project area can understand them. They must precisely define what the project will do and will not do SPECIFIC Objectives must be defined in measurable terms. If they cannot be measured, they are too ambiguous and fuzzy and you need to define them more clearly. To be successful, you must be able to measure and report on the progress MEASURABLE The Project Manager, clients, and customers must agree on the project objectives. There must be agreement that the end result will solve the problem or respond to the opportunity defined AGREED UPON The Project objectives must be possible to achieve, given that available resources, knowledge, skills and time. It might take some time and energy to negotiate project objectives that are realistic REALISTIC The objectives need to be framed within clear time (cost) goals. Define how much time (budget) is available and if there is any flexibility TIME (COST) LIMITED Copyright © 2008 - 2012
15.
The Project objectives
triangle Scope If the time is short, the resources (cost) must increase or scope must decrease, or both If funds or short, then time can be extended or scope must decrease, or both If the scope is large, the cost will be greater or the time must be extended, or both Time Cost Scope Funds Time Scope Scope Cost Time Copyright © 2008 - 2012
16.
Work breakdown structure After
designing the objectives of the project, the next step is to break the project down into manageable pieces in a work breakdown structure Let us see an example of work breakdown structure – Noah’s Ark Noah’s Ark Animals People Boat Gather Feed House Feed Design Boat Build Boat Get elephants 1M, 1F Get lions 1M, 1F Internal design External design Level 2 Level 3 Level 1 The work breakdown structure is the basis for time estimation, resource allocation, and cost estimating and collection. If the work breakdown structure is faulty, all further planning will also be faulty Copyright © 2008 - 2012
17.
Often overlooked activities
in Project Management Project Management Include the budget and resources needed to manage the project. Include costs for the project manager, support staff, project office, and computer support Documentation The documentation includes lessons learned, how the end product differd from the project plan (describe ‘as built’ condition), and how the end product functions Product Implementation Projects that deliver a great product or system can fail if they do not implement the product or system. This can include product delivery, user training, communication plans, or marketing plans End Product Evaluation Does the product perform as expected? Is the problem solved? Have you successfully taken advantage of the opportunity? Project Closure This includes the time, budget and reasons needed to close the project office, reassign project personnel, and close financial accounts Product retirement Include the plans to refine the product after its useful life Copyright © 2008 - 2012
18.
Estimating activities Project assumptions,
constraints, and excursions (a description of what is not included in the work package) Compliance with standards (governamental, institutional, international, and organizational) Technical specifications of the end products, such as performance, quality, reliability, survivability, operability and maintainability The work packages identify the specific activities that must be performed to complete the project. This explains how to estimate time and cost needed to complete each of the activities Copyright © 2008 - 2012
19.
Activity estimation sheet Activity
number: ______________ Title ______________ Team Responsible:______________ Team Leader:______________ Statement of Work:_______________ Describe completion condition:_____________________ Describe assumptions, exclusions, constraints:_______________ Time: No. of working days needed_____________ • Personnel ________ person hours of _____________________________ skill group ________ person hours of _____________________________ skill group ________ person hours of _____________________________ skill group • Direct Costs Item________________ cost$________________ needed at _____ ______ to pay Item________________ cost$________________ needed at _____ ______ to pay Item________________ cost$________________ needed at _____ ______ to pay • Predecessor steps This activity cannot begin until _____ % of activity#________ is complete _____ % of activity#________ is complete Define if less than 100% __________________________________ • Successor steps This activity cannot begin until _____ % of activity#________ is complete _____ % of activity#________ is complete Define if less than 100% __________________________________ Signature: ______________ Date: ______________ Copyright © 2008 - 2012
20.
Underestimating activities Managers often
underestimate activities, and projects run over budget and overschedule. The following are some common reasons Team members are usually optimistic and desire to please. They might say what they think the Project Manager wants to hear People might underestimate the amount of non-productive time in a day (such as personal distractions, fatigue, interruptions, meetings, administratibve tasks, sick, leave, vacations, training, crisis management, and so on) Workers might be overly optimistic about the number of calendar days it takes to complete the number of work hours estimated People tend to have incomplete recall of previous experience. They remember successes better than failures and tend to forget pain Team members might not be familiar with the complete scope of the project when they make their estimates Workers might have no experience with this activity to draw upon Copyright © 2008 - 2012
21.
Estimating Familiar work
vs. New work Familiar Technology New Technology Familiar Work New Work • Need accurate performance data • Draw on performance history and measure performance improvement • Easiest type of project work to plan • Performance history needs to be adjusted for the complexity of technology • Important issue is the similarity of activities • New activities required by the technology are difficult to estimate • Difficult to predict since activitiesmay be different • No performance history available or not useful • High profitability of estimates being understated • Needs frequent project review and estimate revisions • Use a group of experts to produce the estimate • Very short planning horizons • No performance history available or not useful • Needs close monitoring and frequent replanning Copyright © 2008 - 2012
22.
Activity relationships A dependency
between activities where one activity must finish before the other can finish Finish Start Activity A must finish before activity B can begin Start Start Activity A must begin before activity B can begin Start Finish Activity A must begin before activity B can finish Finish Finish Activity A must finish before activity B can finish Copyright © 2008 - 2012
23.
Geebold Manufacturing -
a case study Five months ago, the Board of Directors approved the building, a new facility to manufacture a new line of clothing. The company has already selected the Project Manager and the Project Team OBJECTIVES MEASURES TARGETS INITIATIVES 1 2 3 4 5 6 7 8 9 10 1 1 1 2 1 3 1 4 1 5 16 17 18 1 9 2 0 2 1 2 2 23 2 4 25 26 27 28 2 9 30 3 1 Monday Tuesday Wednesda y Thursday Friday Saturday Sunday Exam ple MARCH 2010 1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 13 14 15 1 6 1 7 1 8 1 9 20 2 1 22 23 24 25 2 6 27 2 8 29 30 Monday Tuesday Wednesda y Thursday Friday Saturday Sunday Exam ple APRIL 2010 Exam ple Ann, the Project Manager, has spent the past five months planning the project. She carefully defined the project in terms of cost, time and scope Ann Copyright © 2008 - 2012
24.
Geebold Manufacturing -
a case study Ann Ann obtained the approval of the Board of Directors on the statement of work Ann Working diligently, she created a work breakdown structure to the best of her knowledge. The diagram contains one hundred boxes in eight levels. Some of the work packages represent 150 hours of work. She then estimated each of the activities using an analogous approach, drawing on plans she discovered of a similar facility the company planned three years ago but never completed Copyright © 2008 - 2012
25.
Geebold Manufacturing -
a case study Ann Ann then drew a graphical network diagram including each of the work packages from the work-breakdown structure. The diagram showed the sequence of activities and their interrelationships. Ann is now ready to select the project team and get the project rolling What has Ann done correctly ? If you were the Project Manager, what would you do differently ? Copyright © 2008 - 2012
26.
Geebold Manufacturing -
a case study Ann Project Team In her enthusiasm, Ann spent five months planning and estimating the project all by herself. Although she may be complemented on her diligence, she appears to lack of common sense. She should have used those five months involving the Project Team from the beginning of the planning process. The team members would have helped to develop the work breakdown structure, provided the estimates, and given input on all phases of planning. Not only may Ann’s plans have serious faults, it may now be difficult for Ann to get the support of the Project Team when she represents the plans to them Copyright © 2008 - 2012
27.
Geebold Manufacturing -
a case study Ann It appears that she carefully defined the project objectives of cost, time and scope, and she wisely got the approval of the BOD on the scope statement Project objectives No mention is made of project reviews, such as a conceptual review, feasibility study, benefit-cost analysis, alternative course of action review, or risk assessment. These are critical in a large project Project reviews Ann The work break down structure appears to be imbalanced. Typically, the work package should represent to eighty hours of work. Ann’s package with two to three hours of work are probably too detailed to be scheduled and managed by the Project Manager. The package with 150 hours of work probably need to be broken down further Work breakdown structure Incomplete Copyright © 2008 - 2012
28.
Geebold Manufacturing -
a case study Ann estimated each of the activities using an analogous approach, drawing on plans she discovered of a similar project that company had planned three years ago but never completed. The time and costs in these three years old plans need to be verified in the current economy. Further, because this old plan was never executed, the assumptions in the plan should be carefully tested. She should have used skilled team members to create accurate plans and estimates. Parametric estimating may be more appropriate for this construction project, or even a bottom-up estimate because she has created a very detailed work breakdown structure Estimating Ann Time Costs Copyright © 2008 - 2012
29.
Geebold Manufacturing -
a case study Ann has drawn a network diagram showing the sequence of each activity and their interrelationships. As she invokes the project team in the planning process, she should verify the accuracy of the diagram with the team Sequencing the activities Ann If Ann has shared all these activities with Project Team from the beginning, rather than doing herself, Ann would have been done a great work on this mega project. Copyright © 2008 - 2012
30.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
31.
The Project Manager’s
role Recognizing and rewarding exceptional work Keeping key stakeholders informed Developing teams Protecting intellectual property Ensuring a paradigm shift from planning to implementation Once the project management plan has been formulated, and “debugged” in the Final Planning Review, it must be executed by the project manager. There are at least five major roles that the project manager plays during this phase Copyright © 2008 - 2012
32.
Ensuring a paradigm
shift PROJECT PLANNING TO IMPLEMENTATION During the planning phase there exists an appropriate mindset that what is being estimated is not yet fixed. However, once the transition from the planning phase to the execution phase takes place, a corresponding paradigm shift among project participants must also take place. The shift must be made from tentativeness to implementation This is often accomplished by conducting an execution “kick off” meeting which not only announces the transition but also attempts to get participants to now see the task at hand which is to be accomplished This is one of the project manager’s primary roles in the execution phase of the project Copyright © 2008 - 2012
33.
Keeping shareholders informed SHARE
HOLDERS MEETING • Another important role of the project manager in this phase is to keep the key stakeholders informed of the project’s status. The purpose of these briefings is show that the project manager understands key stakeholder interests and is successfully managing them • Using the communication plan, established in the initiation phase, the project manager provides pertinent status information at the appropriate level and scope • Key financial stakeholders are interested primarily in the cash flow aspects, and less interested in the technical details of the product design status • Project manager must customize these briefings to the interests of the individual stakeholders. Project managers must be careful not to overwhelm stakeholders with excessive esoteric technical jargon Project Manager Copyright © 2008 - 2012
34.
Protecting intellectual property Project Manager As
new design concepts develop it is vital that they be protected by the project manager. It is important for the project manager to find a qualified, experienced patent attorney early in the project, and to begin the protection process quickly. This begins by keeping detailed records of the new product development, including documentation, and properly labeling them as “proprietary” so that project personnel do not inadvertently expose them to competitors Copyright © 2008 - 2012
35.
Team Development Teams do
not grow into high-performance teams automatically. To assume so is naive on the part of the project manager. Teams must be developed quickly when they are formed to solve complex problems. Teams do not grow into high-performance teams automatically. To assume so is naive on the part of the project manager. Teams must be developed quickly when they are formed to solve complex problems Copyright © 2008 - 2012
36.
Example – Publication
process Planning and Project request Executive committee approval Budget Approval Project Planning Writing, editing, design Translation Printing Shipping Delivery to customer Copyright © 2008 - 2012
37.
Risk Management in
projects Make Risk Management Part of Your Project Identify Risks Early in Your Project Communicate About Risks Consider Both Threats and Opportunities Clarify Ownership Issues Prioritize risks Analyze Risks Plan and Implement Risk Responses Register Project Risks Track Risks and Associated Tasks Copyright © 2008 - 2012
38.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
39.
Scheduling One of the
primary features of Project Management is scheduling. Unfortunately, some people think the Project Management is nothing but scheduling. Scheduling is one of the tools used to manage jobs and should not be considered the primary one. People today tend to acquire scheduling software, of which there is abundance, and think that will make them instant project managers. But their idea is wrong. Infact, it is nearly impossible to use the software unless you understand Project Management. Copyright © 2008 - 2012
40.
Brief history of
Scheduling Until around 1958, the only tool used for scheduling projects was the bar chart. Henry Gantt developed a complete notational system for showing progress with bar charts, they are often called Gantt charts. Bar chart (Gantt charts) Bar charts have serious drawback – it is very difficult to determine the impact of a slip on one task on the rest of the project. To overcome this problem, two methods of scheduling were developed. One of these methods developed by Du Pont is called The other, developed by the U.S. Navy and the Booze Allen and Hamilton Consulting Group, is called Program Evaluation and Review Technique Critical Path Method PERT Copyright © 2008 - 2012
41.
Network diagram The network
in the next slide uses activity on arrow notation, in which the arrow represents the work being done and circle represents an event. An event is binary; that is, it has either occurred or it has not. An activity on the other hand, can ben partially complete. In scheduling terminology, an event is a specific point in time where something has just started or has just been finished. Copyright © 2008 - 2012
42.
Arrow diagram method An
activity-on-node network Activity A Activity B Activity D Activity C An activity-on-arrow network 1 3 2 4 Activity A Activity B Activity C Activity D Copyright © 2008 - 2012
43.
Arrow diagramming method
– a small example This common diagramming method is to represent the activities on arrows and connect them at nodes (circles) to show the dependencies. These are called arrow diagrams or activity on arrow Start Order Pipe Deliver Pipe Dig Trench Lay Pipe Finish A B C D Copyright © 2008 - 2012
44.
Reason for scheduling The
deadline has to be met for every projects. Since the Critical Path Method helps identify which activities will determine the end date, it also helps guide how the project should be managed. It is very easy to create schedules that look good on paper but don’t work in practice. The main reason is usually that resources are not available to do the work when it comes due. Unless the resources are allocated properly, schedules are next to useless. Additionally, there are 2 points worth considering here. One is that if scope is changing often in a project, not enough time is being spent doing up-front definition and planning scope changes most often occur because something is forgotten. Second, if priorities are changing often, management does not have its act together. Generally, the organization is trying to tackle too much work for the number of resources available. One company found, as an example, that when it stopped having people work on multiple projects, employee’s productivity doubled! Copyright © 2008 - 2012
45.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
46.
Achieving Team Member
Self-control Ultimately, the only way to control a project is for every member of the project team to be in control of his or her own work. A project manager can achieve control at the macro level only if it is achieved at the micro level. To achieve self-control, team members need: A clear definition of what they are supposed to be doing, with the purpose stated. A personal plan for how to do the required work Skills and resources adequate to the task Feedback on progress that comes directly from the work itself A clear definition of their authority to take corrective action when there is a deviation from plan Copyright © 2008 - 2012
47.
Characteristics of a
project control system The control system should focus on project objectives, with the aim of ensuring that the project mission is achieved. To do that, the control system should be designed with the following question in mind. What is important to the organization? What are we attempting to do? Which aspects of the work are most important to track and control? What are the critical paths in the process at which controls should be placed? Copyright © 2008 - 2012
48.
Taking corrective action A
control system should focus on response – if control data do not result in action, then the system is ineffective. That is, if a control system does not use deviation data to initiate corrective action, it is not really a control system but simply a monitoring system. If you are driving and realize that you have somehow got on the wrong road but do nothing to get back on the right road, you are not exercising control. Copyright © 2008 - 2012
49.
Timeliness of response If
actions occurs too late, it will be ineffective. Data on project status are sometimes delayed by 4 to 6 weeks, making them useless as a basis for taking corrective actions. When information collection is delayed for too long, the manager may end up making things worse, instead of better. The government’s attempts to control recessions and inflation sometimes involves long delays, as a result of which the government winds up doing the exact opposite of what should have been done, making situation worse. Copyright © 2008 - 2012
50.
Designing the right
system One system is not likely to be correct for all projects. It may need to be scaled down for small projects and beefed up for large ones. Generally, a control system adequate for a large project will overwhelm a small one with paperwork, while one that is good for small project won’t have enough “clout” for a big project. Copyright © 2008 - 2012
51.
Practicing the KISS
principle “KISS” stands for “Keep it Simple, Stupid!”. Any control data that are not essential should be eliminated. However, as was just mentioned, one common mistake is to try to control complex projects with systems that are too simple! To keep control simple, it is a good idea to check periodically that reports that are generated are actually being used for something by the people who receive them. We sometimes create reports because we believe the information in them should be useful to others, but if the recipients don’t actually use it, we kid ourselves Copyright © 2008 - 2012
52.
Project review meetings There
are 2 aspects to project control. One can be called maintenance, and the other aim at improvement of performance. The maintenance review just tries to keep the project on track. The improvement review tries to help project teams improve performance. There are 3 kinds of reviews: 1 Status reviews 2 Process reviews 3 Design reviews A status review is aimed at maintenance. It asks where the project stands. Design reviews, of course, are appropriate only if you are designing hardware, software, or some sort of campaign, such as marketing campaign. Process review means the way something is done, and you can be sure that process always affects task performance. Copyright © 2008 - 2012
53.
Project evaluation Evaluation Project evaluation
appraises the progress and performance of a job compared to what was originally planned. That evaluation provides the basis for management decisions on how to proceed with the project. The evaluation must be credible in the eyes of everyone affected, or decisions based on it will not be considered valid. Project process review is the primary tool for project evaluation. Copyright © 2008 - 2012
54.
Purpose of project
evaluation Following are some of the general reasons for conducting periodic project reviews. Improve project preference together with the management of the project. Ensure that quality of project work does not take a back seat to schedule and cost concerns. Reveal developing problems early so that action can be taken to deal with them. Identify areas where other project should be managed differently. Copyright © 2008 - 2012
55.
Conducting project process
review Two questions are asked in the review. The process review must be conducted in a spirit of learning, rather than in a climate of blame and punishment. If people are afraid that they will be “strung up” for problems, then they will hide those problems if at all possible. What have we done well so far? What do we want to improve in the future?. Finally, the results of the review should be published. Copyright © 2008 - 2012
56.
The process review
report The report should contain the following • Current project status • Future status • Status of critical tasks • Risk assessment • Information relevant to other project • Limitations of the process review Copyright © 2008 - 2012
57.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
58.
Stakeholder Analysis Stakeholders are
the people who support in your work and business. They may also block your business when they get affected by your plans. Stakeholder Analysis is the technique used to identify the key people who have to be won over. You then use Stakeholder Planning to build the support that helps you succeed. Some of the benefits of this approach is: • We can get opinions of powerful stakeholders regarding our projects at an early stage. • We can get more resources which implies that our project will be successful. • The stakeholders understand what you are doing and how the project is going to benefit them. • You can anticipate what people's reaction to your project may be, and build into your plan the actions that will win people's support. Copyright © 2008 - 2012
59.
Identify your stakeholders Stakeholders
are the people who support in your work and business. They may also block your business when they get affected by your plans. Stakeholder Analysis is the technique used to identify the key people who have to be won over. You then use Stakeholder Planning to build the support that helps you succeed. Your boss Shareholders Government Senior executives Alliance partners Trade associations Your co-workers Suppliers The press Your team Lenders Interest groups Customers Analysts The public Prospective customers Future recruits The community Copyright © 2008 - 2012
60.
Prioritize your stakeholders There
may be a long list of people or organizations who are affected by your project. Some may have power either to block the project or advance. Map out your stakeholders on a Power/Interest Grid as shown below, and classify them by their power over your work and by their interest in your work. Keep satisfied Manage closely Monitor (minimum effort) Keep informed POWER HIGH LOW LOW HIGH INTEREST Copyright © 2008 - 2012
61.
Understand your stakeholders Key
questions that can help you understand your stakeholders are: • What impact do they have from your work – Positive or Negative? • What information do they need from you? • What communication mode do they prefer? • What is their opinion about your work? • If they are not likely to be positive, what will win them around to support your project? • If you don't think you will be able to win them around, how will you manage their opposition? • Who else might be influenced by their opinions? Do these people become stake- holders in their own right? Copyright © 2008 - 2012
62.
Stakeholder management After Stakeholder
analysis is over, now you have to plan how to manage communication with your stakeholders. The next stage is to plan your communication so that you can win them around to support your projects. Stakeholder Planning is the process by which you do this. • Using the following steps, work through the planning exercise • Create a worksheet and update it with Power/Interest Grid information • Plan your approach to stakeholder management • Think what you want from the stakeholders • List out the messages you need to convey to the stakeholders • Identify actions and communications Copyright © 2008 - 2012
63.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
64.
A business tale
of what it takes to turn around troubled projects Jack is working as a Director of Customer Relationship Management at MintCo. One fine morning, Jack went to meet his boss, Brandon to discuss about one of the company’s troubled projects. Jack had substantial experience, but he has recently joined MintCo. He was still learning about some of the nuances of his current employer. Brandon and Jack got to the topic at hand. Brandon Jack “Jack, I’ll get straight to the point. I need to you to take over the Customer Master File project from Paul” “We hired you because of your significant project management expertise.” Copyright © 2008 - 2012
65.
Troubled waters Jack came
out of Brandon’s office and set out to learn more about the challenge that Brandon had posed on him. After a few weeks, Jack tool over the Customer Master File project, met with key project team members, and conducted interviews with key stakeholders. Jack was back in Brandon’s office to give a rather start update on the situation. Brandon Jack “Brandon, I’ve talked to the project team and to key stakeholders, and I know why this project is in trouble. If you want me to turn this project around, I need your support.” “What did you find out, Jack, and what can I do to help you?” Copyright © 2008 - 2012
66.
Troubled waters Jack “Brandon, as
you know, this project is already behind schedule and over budget. In talking to the key stakeholders, I don’t see the situation getting better without making significant changes” Brandon ???????? Jack’s experience helped him to quickly identify a number of critical issues with the project, which he carefully outlined for Brandon • The scope of the project is not well defined • The IT architects are sitting in their ivory towers and disagree with the project’s direction • The project team is not functioning as a team • There is a lack of clear executive sponsorship • Steve from marketing is trying to manipulate this project for his own political gain Copyright © 2008 - 2012
67.
Foundation for success Jack “Thanks
for working with me on this Brandon. Just to confirm, let me summarize the changes that we agreed to implement.” Brandon “I think, that’s a good idea!” Brandon knew what Jack said was true, and he also knew that changing the situation would be difficult, painful, and potentially costly. He reluctantly agreed with Jack, and together they laid out several key changes. • Stop the current project and recreate a clear and well-defined scope • Assign key IT architects to the project on a full time basis • We are going to form a special team and assign members to a full-time basis on the project • Active participation from all members to drive key decisions for the project • Finally, Brandon should have heart-to-heart with Steve and if necessary his boss to eliminate any political agendas that could derail the project Copyright © 2008 - 2012
68.
Celebrations Brandon Jack “Jack, Congratulations
on getting the Customer Master File project into pilot. By all accounts, it has been a resounding success.” Six months later . . . . . “Thank you. But you know it was pretty touch and go after we met in your office to plan and project turnaround. There were a lot of unhappy campers and several of them didn’t like the idea of being assigned 100% to the project if you recall.” Copyright © 2008 - 2012
69.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
70.
Team building Building an
effective team begins on the first day of the team’s existence. Failure to begin the team building process may result in a team that is more like a group than a team. In a group, members may be “involved” in but not “committed” to the activities of the majority. Copyright © 2008 - 2012
71.
Getting organized Decide what
must be done, using work breakdown structures, problems definitions, and other planning tools Determine staffing requirements to accomplish the tasks identified in the first step Recruit members for the project team Complete your project plan through participation of team members Here are the four major steps in organizing a project team Copyright © 2008 - 2012
72.
Clarifying the Team’s
mission, goals and objectives Imagine, as an example, a hockey team deciding to play cricket Excellent organizations “stick to their knitting”. They stick to what they are good at and do not go off on tangents, trying to do something they know nothing about. The same thing can happen to project teams if members are not clear on the team’s mission, they will take the team where they think it is supposed to go, and that may not be the direction intended by the organization Copyright © 2008 - 2012
73.
Conflict between individual
goals and team’s mission Sometimes members have what are called “hidden agendas”, personal objectives that they do not want anyone to know about, because they are afraid that other members will try to block them if their objectives are known. A manager should try to satisfy the needs of the organization, while simultaneously helping individuals satisfy their own needs through participation in the project. Copyright © 2008 - 2012
74.
Working out procedures Dealing
with how we do it comes next. The key word here is processes. The work must be done as efficiently and as effectively as possible, and improvement of work processes is very important issue today. It is commonly called re-engineering and is the analysis and improvement of work processes to make the organization more competitive. Copyright © 2008 - 2012
75.
Stages in team
development In the forming stage, people are concerned with how they will fit in and with who calls the shots, makes decisions, and so on. Forming The storming stage in frustrating for most people. When the team reaches this stage, people begin to question their goals. Storming At the norming stage, they are beginning to resolve their conflicts and settle down to work. Norming Finally, when the team reaches the performing stage, the leader’s job is easier. Members generally work well together now, enjoy doing so, and tend to produce high-quality results Performing Copyright © 2008 - 2012
76.
Developing commitment to
a project team Have team members interact frequently so that they gain a sense of being a team. Be sure that individual needs are being met through participation in the team. Let all members know why the project is important. People don’t like working on a ‘loser’. Make sure all members share the goals of the team. One bad apple can spoil the barrel. Copyright © 2008 - 2012
77.
Contents Overview of Project
Management Planning the Project Executing the Project Scheduling Project Work Project Control and Evaluation Building Support for your projects A Business tale Managing the Project Team How to make project management work in your company? Copyright © 2008 - 2012
78.
Making a project
work in your company Companies must build into performance appraisals items that evaluate a project manager’s use of the tools. They should reward people for practising the best methods and, if necessary, sanction them when they do not. After the training is completed, pick a project that already has a pretty high probability of success – don’t pick your hardest job; the probability of failure is too high. It helps to have the entire team trained in the basics. The project managers generally need a minimum of 3 or 4 days training in project management and team members need about 2 days. Plan small wins for the people. No sports team ranked number 10 would want to play the top-ranked team for its first game. It would prefer to play the 9th ranked team maybe, or even the 11th Copyright © 2008 - 2012
79.
Making a project
work in your company Practice a lot of MBWA (Management By Walking Around) as the project progresses, but do it to be helpful, not in the blame-and-punishment mode. Do process reviews to learn and to try to improve whenever possible. If you find you have a problem child in your team, deal with that person as soon as possible. Talk to someone who has the experience and who can help you. Be very proactive, not reactive. Take the lead. Break road- blocks for your team members Copyright © 2008 - 2012
80.
Making a project
work in your company Have team members make presentations to senior management on their part of the job. Give them credit for their contributions. For those tasks on the critical path of the project, you may find that you have to physically collocate the people doing those activities so that you don’t have them constantly pulled off to do other jobs. Benchmark other companies to find out what they do with project management. Have individual take responsibility for being champions of various parts of the project management process. Try to read management books and glean everything you can from them that will help you do your job better. Look at managing projects as a challenge or even as a game. If it doesn’t strike you that way, it probably won’t be very exciting. Experiment with new approaches. Find out what works and keeps it. Throw out what does not. Copyright © 2008 - 2012
81.
Effective Project closure
– Check list Have all activities in the project plan has been completed? Project – Checklist Have all work orders been completed? Have all contracts been comleted? Have all outstanding commitments been resolved? Has the client or customer accepted the final products? Are all deliverables completed? Has agreement been reached with the client on the disposition of any remaining deliverables? Have external certifications and authorizations been signed and approved? Have all audits been completed and issues resolved? Have ongoing maintenance procedures been activated? Copyright © 2008 - 2012
82.
Effective Project closure
– Check list Have all payments been made to vendors and contractors? Finances checklist Have all costs been charged to the project? Have project accounts have been closed? Have remaining project funds been returned? Have project plans and supporting documents been revised to reflect the ‘as-built’ condition? Documentation checklist Have final project reports have been prepared and distributed? Has the project plan been achieved with all supporting data? Have ‘lessons learned’ been documented, shared with appropriate people, and archieved with project plans? Copyright © 2008 - 2012
83.
Effective Project closure
– Check list Are all parties aware of the pending close-out? Personnel checklist Has effort been recognized and rewarded? Have project personnel been reassigned Has excess project material been dealt with? Resources checklist Have project facilities, equipment, and other resources been reallocated? Copyright © 2008 - 2012
Download now