3. Design Objectives
• Primary cruise terminal – 3000 passengers
• Dry hire event space – 3000 people
• Place to welcome visitors & share our culture
• Retain & reveal character and heritage
• Contrast old & new to create drama
• Flexible open space for events and cruise
• Connect interior to sea, sky and city
• A sustainable place
4. Program
Jasmax engaged for Design December 2011
Concept Design for review End February 2012
Council approval of Business Case April 2012
LTP adopted 28 June 2012
Design complete July 2012
Construction tender issue July 2012
Consent September 2012
Main Building Works commence September 2012
Building Works Complete April 2013
Gangway & Fenders September 2013