1. Week Date Schedule Notes
1 9th –13th Storyboards Location not
Jan Treatment decided
Production logos
Start Costume Design
Shooting script
2 14th- Finalise Storyboards Karen. Knapp -
20th Jan Start/ finish Script driver.
Animatic of storyboard (part of the crew)
Finalise Costume Design/ Props Mel. Knapp -
Finalise Location makeup.
Crew and cast list
Shot List
3 21th – Finished Costumes
27th Jan Script Deadline
Equipment
(Lighting Plans)
4 28th – Risk Assessment
3rd Feb Test Shoots
5 4th – 10th Shooting
Feb
6 11th – Shooting Begin Sound and
17th Feb Sound Editing Video Checks
7 18th – Editing
27th Feb Sound Editing
(shooting if necessary)
8 28th – Editing
11th Mar
9 11th Deadline for Final Cut Everything
Mar Finish Editing finished for this
date!
= Completed work
Chris Knapp