1. Taryn Mruk
Week Date Schedule Notes
1 9th –13th Start Storyboards Location not
Jan Treatment decided
Shooting script
Start Costume Design
Production logos
2 14th- 20th Finalise Storyboards Karen is the
Jan Finalise Location driver.
Crew and cast list (part of the crew)
Start/ finish Script Mel. Knapp
Finalise Costume Design/ Props makeup.
Shot List
Animatic Of Storyboard
3 21th – Finished Costumes
27th Jan Script Deadline
Equipment
(Lighting Plans)
4 28th – 3rd Test Shooting
Feb Risk Assessment
Sound and Video Check
5 4th – 10th Shooting
Feb Sound and Video Check
6 11th – Shooting
17th Feb Editing (Sound as well)
7 18th – Editing
27th Feb (shooting if necessary)
8 28th – Editing
11th Mar
9 11th Mar Deadline for Final Clip Everything
Finish Editing finished for this
date.
Key: Finished Items