This document summarizes changes made to the UK's Construction Act by the 2009 Construction Act. It outlines amendments to key provisions around adjudication and payment. For adjudication, additions include permitting adjudicators to correct errors and requiring contracts to allow this. For payment, new requirements are introduced for payment and pay less notices within 5 days of the payment due date, and provisions are strengthened around paying notified sums. Overall, the changes aim to improve adjudication and payment processes for construction contracts.
1. Construction Act Tracker
1996 Construction Act 2009 Construction Act
Housing Grants, Construction
and Regeneration Act 1996
Local Democracy, Economic Development and Construction Act
2009 (LDEDCA)
104 Definition of a
construction
contract
No change. The exclusions under the Construction Contracts
(England and Wales) Exclusion Order 1998 continue to apply e.g.
PFI, development and finance agreements.
105 Definition of
construction
operations
No change
106 Exclusion of
residential
occupiers
Amended by omitting subsection (1) paragraph (b) 138(2)
106A NEW “Power to disapply provisions of this Part
(1) The Secretary of State may by order provide that any
or all of the provisions of this Part, so far as extending
to England and Wales, shall not apply to any
description of construction contract relating to the
carrying out of construction operations (not being
operations in Wales) which is specified in the
order....”
1
138(3)
107 Only applicable to
agreements in
writing
Repealed
2
139(1)
108 Right to refer
disputes to
adjudication
Amended to read
(2) “The contract shall include provision in writing so as
to…”
(3) and (4) shall refer to “provide in writing”
3
139(2)
1
This power existed under s106(10(b) of the 1996 Act so the reason for the amendment is not clear. A
draft exclusion order indicates that contracts and sub-contracts under the private finance initiative may
be excluded.
2
According to the explanatory notes to the 2009 Act, from legislation.gov.uk, “As originally enacted,
section 107 of the 1996 Act provided that Part 2 of the 1996 Act only applied to contracts which were
“in writing”. This was interpreted restrictively by the courts such that all of the non-trivial terms of
construction contracts had to be “in writing” for Part 2 to apply. Section 139 removes this general
requirement, whilst prescribing that various matters must nonetheless be in writing.”
2. 1996 Construction Act 2009 Construction Act
108(3A) NEW Adjudicator’s power to make corrections
“(3A) the contract shall include provision in writing
permitting the adjudicator to correct his decision so as to
remove a clerical or typographical error arising by
accident or omission”
Note: if the contract does not provide for the stated
aspects in writing then in accordance with s108(5) of the
1996 Construction Act the Scheme for Construction
Contracts will apply.
140(2)
108A NEW “108A Adjudication costs: effectiveness of provision
(1) This section applies in relation to any contractual
provision made between the parties to a construction
contract which concerns the allocation as between
those parties of costs relating to the adjudication of a
dispute arising under the construction contract.
(2) The contractual provision referred to in subsection (1)
is ineffective unless—
(a) it is made in writing, is contained in the
construction contract and confers power on the
adjudicator to allocate his fees and expenses as
between the parties, or
(b) it is made in writing after the giving of notice of
intention to refer the dispute to adjudication.”
141
109 Entitlement to
stage payments
“… in subsection (4), for ‘under the contract’ substitute
‘provided for by the contract.’.”
143(1)
110 Dates for payment Determination of payments due
(1) In the Housing Grants, Construction and
Regeneration Act 1996, section 110 (dates for
payment) is amended as follows.
(2) After subsection (1) insert—
“(1A)The requirement in subsection (1)(a) to provide an
adequate mechanism for determining what payments
become due under the contract, or when, is not
satisfied where a construction contract makes
payment conditional on—
(a) the performance of obligations under another
contract, or
(b) a decision by any person as to whether
obligations under another contract have been
performed.
(1B)In subsection (1A)(a) and (b) the references to
obligations do not include obligations to make
payments (but see section 113).
142
3
These requirements and those introduced by s140 of the 2009 Construction Act become part of the
minimum requirements for a construction contract.
3. 1996 Construction Act 2009 Construction Act
(1C)Subsection (1A) does not apply where—
(a) the construction contract is an agreement
between the parties for the carrying out of
construction operations by another person,
whether under sub-contract or otherwise, and
(b) the obligations referred to in that subsection
are obligations on that other person to carry
out those operations.”
(3)After subsection (1C) (as inserted by subsection (2)
above) insert—
“(1D)The requirement in subsection (1)(a) to provide an
adequate mechanism for determining when
payments become due under the contract is not
satisfied where a construction contract provides for
the date on which a payment becomes due to be
determined by reference to the giving to the person
to whom the payment is due of a notice which relates
to what payments are due under the contract.”
4
110 110(2) on notices
of payment
(2) In section 110 of that Act (dates for payment), omit
the following—
(a) subsection (2), and
(b) in subsection (3), “or (2)”.
143(2)
110A Payment notices: contractual requirements
(1) A construction contract shall, in relation to every
payment provided for by the contract—
(a) require the payer or a specified person to give a
notice complying with subsection (2) to the
payee not later than five days after the
payment due date, or
(b) require the payee to give a notice complying
with subsection (3) to the payer or a specified
person not later than five days after the
payment due date.
(2) A notice complies with this subsection if it specifies—
(a) in a case where the notice is given by the
payer—
(i) the sum that the payer considers to be or
to have been due at the payment due date
in respect of the payment, and
(ii) the basis on which that sum is calculated;
(b) in a case where the notice is given by a
specified person—
(i) the sum that the payer or the specified
person considers to be or to have been due
at the payment due date in respect of the
payment, and
(ii) the basis on which that sum is calculated.
143(3)
4
The main effect of the new subsections s110(1A) – (1D) is to deprive pay when certified and conditional
clauses of any enforceable effect. The interpretation of s110(1C) is likely to prove complex and
controversial. Does it entitle the contractor to avoid paying its subcontractors? Mr Justice Coulson, in
‘Construction Adjudication’ (2011) comments on s110 (1A) and 110(1C): “it is thought that these
provisions are likely to fall to be considered by the courts sooner rather than later.”
4. 1996 Construction Act 2009 Construction Act
(3) A notice complies with this subsection if it specifies—
(a) the sum that the payee considers to be or to
have been due at the payment due date in
respect of the payment, and
(b) the basis on which that sum is calculated.
(4) For the purposes of this section, it is immaterial that
the sum referred to in subsection (2)(a) or (b) or (3)(a)
may be zero.
(5) If or to the extent that a contract does not comply
with subsection (1), the relevant provisions of the
Scheme for Construction Contracts apply.
(6) In this and the following sections, in relation to any
payment provided for by a construction contract—
“payee” means the person to whom the
payment is due;
“payer” means the person from whom the
payment is due;
“payment due date” means the date provided
for by the contract as the date on which the
payment is due;
“specified person” means a person specified in
or determined in accordance with the provisions
of the contract.
110B Payment notices: payee's notice in default of payer's
notice
(1) This section applies in a case where, in relation to
any payment provided for by a construction
contract—
(a) the contract requires the payer or a specified
person to give the payee a notice complying
with section 110A(2) not later than five days
after the payment due date, but
(b) notice is not given as so required.
(2) Subject to subsection (4), the payee may give to the
payer a notice complying with section 110A(3) at any
time after the date on which the notice referred to in
subsection (1)(a) was required by the contract to be
given.
(3) Where pursuant to subsection (2) the payee gives a
notice complying with section 110A(3), the final date
for payment of the sum specified in the notice shall
for all purposes be regarded as postponed by the
same number of days as the number of days after
the date referred to in subsection (2) that the notice
was given.
(4) If—
143(3)
5. 1996 Construction Act 2009 Construction Act
(a) the contract permits or requires the payee,
before the date on which the notice referred to
in subsection (1)(a) is required by the contract
to be given, to notify the payer or a specified
person of—
(i) the sum that the payee considers will
become due on the payment due date
in respect of the payment, and
(ii) the basis on which that sum is
calculated, and
(b) the payee gives such notification in accordance
with the contract,
that notification is to be regarded as a notice
complying with section 110A(3) given pursuant to
subsection (2) (and the payee may not give another
such notice pursuant to that subsection).”
111 Notice of intention
to withhold
payment
Substituted
Requirement to pay notified sum
(1) Subject as follows, where a payment is provided for
by a construction contract, the payer must pay the
notified sum (to the extent not already paid) on or
before the final date for payment.
(2) For the purposes of this section, the “notified sum” in
relation to any payment provided for by a
construction contract means—
(a) in a case where a notice complying with section
110A(2) has been given pursuant to and in
accordance with a requirement of the contract,
the amount specified in that notice;
(b) in a case where a notice complying with section
110A(3) has been given pursuant to and in
accordance with a requirement of the contract,
the amount specified in that notice;
(c) in a case where a notice complying with section
110A(3) has been given pursuant to and in
accordance with section 110B(2), the amount
specified in that notice.
(3) The payer or a specified person may in accordance
with this section give to the payee a notice of the
payer's intention to pay less than the notified sum.
(4) A notice under subsection (3) must specify—
(a) the sum that the payer considers to be due on
the date the notice is served, and
(b) the basis on which that sum is calculated.
It is immaterial for the purposes of this subsection
that the sum referred to in paragraph (a) or (b) may
be zero.
144(1)
6. 1996 Construction Act 2009 Construction Act
(5) A notice under subsection (3)—
(a) must be given not later than the prescribed
period before the final date for payment, and
(b) in a case referred to in subsection (2)(b) or (c),
may not be given before the notice by reference
to which the notified sum is determined.
(6) Where a notice is given under subsection (3),
subsection (1) applies only in respect of the sum
specified pursuant to subsection (4)(a).
(7) In subsection (5), “prescribed period” means—
(a) such period as the parties may agree, or
(b) in the absence of such agreement, the period
provided by the Scheme for Construction
Contracts.
(8) Subsection (9) applies where in respect of a
payment—
(a) a notice complying with section 110A(2) has
been given pursuant to and in accordance with
a requirement of the contract (and no notice
under subsection (3) is given), or
(b) a notice under subsection (3) is given in
accordance with this section,
but on the matter being referred to adjudication the
adjudicator decides that more than the sum specified
in the notice should be paid.
(9) In a case where this subsection applies, the decision
of the adjudicator referred to in subsection (8) shall
be construed as requiring payment of the additional
amount not later than—
(a) seven days from the date of the decision, or
(b) the date which apart from the notice would
have been the final date for payment,
whichever is the later.
(10)Subsection (1) does not apply in relation to a
payment provided for by a construction contract
where—
(a) the contract provides that, if the payee becomes
insolvent the payer need not pay any sum due in
respect of the payment, and
(b) the payee has become insolvent after the
prescribed period referred to in subsection
(5)(a).
(11) Subsections (2) to (5) of section 113 apply for the
purposes of subsection (10) of this section as they
apply for the purposes of that section.”
7. 1996 Construction Act 2009 Construction Act
112 Right to suspend
performance for
non-payment
“In section 112 of that Act (right to suspend
performance for non-payment)—
(a) in subsection (1), for the words from ‘Where’
to ‘given’ substitute ‘Where the requirement
in section 111(1) applies in relation to any sum
but is not complied with,’;
(b) in subsection (3), for ‘the amount due’
substitute ‘the sum referred to in subsection
(1)’.
“(2)In subsection (1), after ‘performance of’ insert ‘any
or all of’.
(3) After subsection (3) insert—
“(3A) Where the right conferred by this section is
exercised, the party in default shall be liable to
pay to the party exercising the right a
reasonable amount in respect of costs and
expenses reasonably incurred by that party as a
result of the exercise of the right.”
(4) In subsection (4), after ‘pursuance of’ insert ‘, or in
consequence of the exercise of,’.”
144(2)
145(2)-
(4)
113 Prohibition of
conditional
payment
provisions
No change
114 Scheme for
Construction
Contracts
No change to this provision although the Scheme has been
amended
8. Minimum Requirements under 1996 & 2009 Construction Acts
Adjudication Payment
• a right to refer disputes to
adjudication (s108(1))
• enable a party to given notice at any
time of intention to refer a dispute
to adjudication
• provide a timetable with object of
securing appointment of adjudicator
and referral within 7 days
• require adjudicator to reach a
decision within 28 days or such
longer period as later agreed by
parties
• allow adjudicator to extend period
by up to 14 days with consent of
referring party
• impose duty on adjudicator to act
impartially
• enable adjudicator to take initiative
in ascertaining facts and law
(s108(2)(a) to (f))
• decision of adjudicator is binding
until finally determined by
proceedings, arbitration or
agreement (s108(3))
• permitting adjudicator to correct
typos and slips (s108(3A) NEW)
• adjudicator not liable unless acts in
bad faith (s108(4))
(note see paragraph 2 Scheme 1998)
• payment by instalments, stage
payments or other periodic payments
for work in excess of 45 days;
contract should set out the amounts
of payments and the intervals at
which or circumstances in which they
become due (s109(1))
• an adequate mechanism for
determining what payments become
due under the contract & when
(s110(1)(a))5
• provide for a final date for payment
(s110(1)(b))
• require the payer to provide a
payment notice or the payee to
provide a default payment notice in
either case not later than 5 days after
the due date (s110A(1) NEW)
• the prescribed period under s111(7)
for the giving of the pay less notice
(NEW)
Author
Sarah Fox of 500 Words Ltd developed this note. She is a speaker and trainer who cuts
through the complexities of construction law. She provides confidence to those who use
construction contracts through workshops that clarify and simplify the law. She is also
author of the 500-Word Contract™.
To find out how Sarah can transform your technical training, contact her via: 07767 342747
or by email: sarah@500words.co.uk
5
NOTE under s110(1A) as introduced by LDEDCA this requirement for an adequate mechanism is not
satisfied when it makes payment conditional on performance of obligations under another contract, or
the decision by anyone as to whether those obligations under another contract have been performed;
under s110(1D) the requirement for determining when payments become due is not satisfied with a
notice to the payee.